Professional Documents
Culture Documents
MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 1 of 28
Rev. X
This document has been revised as indicated below and described in the revision record on the following
page. Please destroy all previous revisions.
gar19
Digitally signed
by gar19098
Discipline Lead José I. García Date:
098 2020.06.02
23:14:33 -04'00'
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 2 of 28
Rev. X
Record of Revisions
X 02-Jun-2020 VOID
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 3 of 28
Rev. X
Contents
Section
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 4 of 28
Rev. X
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 5 of 28
Rev. X
1.0 GENERAL
1.1. Scope
These design criteria establish the engineering standards and practices to be followed in the
design of the fresh water pipeline for the Quellaveco Project, owned by Anglo American
Quellaveco S.A. (AAQSA). This document will be applied to the design of the pipeline
pump stations and valve selection. It also defines the coating to be applied to the pipe,
avoid corrosion. The pipeline will be used to transport fresh water from sources at the
Vizcachas and Titire rivers to the storage ponds located at Caracoles hill – approximately
3,850 meters above sea level (m.a.s.l.) which eventually will feed the Papujune fresh water
tank (TAG 3930-TK-001).
These design criteria do not apply to control systems, electrical and construction systems.
The design of the piping systems shall conform to generally accepted engineering practices,
codes and standards, in their latest version, issued by the following institutions:
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 6 of 28
Rev. X
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 7 of 28
Rev. X
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 8 of 28
Rev. X
1.5. Drawings
1.6. Studies
AA REQ 100 Quality Requirements for Suppliers of Critical and Major Equipment.
AA REQ 110 Owners Team Quality Activities.
AA REQ 120 Purchaser Quality Activities.
AA REQ 130 Contract Inspection Requirements.
1.8. Others
United States Department of Interior, Water and Power Resources Service, “Engineering
Monograph N° 41 Air-Water Flow in Hydraulic Structures”.
All of the foregoing documents are referred to in their latest version / revision to date
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 9 of 28
Rev. X
2.1. General
The fresh water transport system will consider two feed sources – the Vizcachas and Titire
rivers.
Independent pumping systems will extract water from both of these sources. These
independent feed pipes will then join at a common header 15 km from the Titire intake.
This main will then transport a flow of water to the transfer tank located at Pelluta hill,
located 21 km downstream the Titire intake and at an approximate elevation of 4.820
m.a.s.l. From this tank (TAG 1140-TK-001), water will gravitationally flow to the fresh
water transfer tank (TAG 1140-TK-002) at km 88,6 from Titire intake and at 3.899,0
m.a.s.l.. This transfer tank location will allow the use of the 30” polyethylene pipe currently
used for construction water transport. This aforementioned existing pipeline ends at the
storage ponds at Caracoles hill and the Quellaveco water tank. The total distance of the
flow is approximately 88,6 km and crosses the peak of the of Pelluta hill at a peak altitude
of 4.820 m.a.s.l.
The fresh water system will be permanently fed by the Titire while flow is available. The
use of water from the Vizcachas river (reservoired during wet season) will be reserved for
periods when the Titire source is not sufficient.
The Titire intake (designed by third party) will be located at approximately 4.342 m.a.s.l.
The feed system will consist of a pump station (Titire river Fresh water Pumps TAG 1120-
PU-001@005). At km 15 this pipe will connect with the pipe coming from the other fresh
water source (Vizcachas river).
A dam for the Vizcachas river (by third party) is at an approximate elevation of 4.343
m.a.s.l. An intake from the output at the river bottom will feed the pump station (Vizcachas
river Pumps TAG 1130-PU-001@008).
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 21-Jul-2015
Contract Q1CO Page 10 of 28
Rev. B
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 11 of 28
Rev. X
The following design critieria have been established for the Titire and Vizcachas
pipelines:
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 12 of 28
Rev. X
The active protection design for corrosion must be coordinated by the piping
discipline.
3.1. General
Design of the facility contemplates the characteristics of the pipeline itself as well as the
other equipment and systems which, together, provide acceptable operative results.
Control systems applicable to pipeline operation will be the subject of study by the
instrumentation discipline. Control equipment and systems specifications are outside the
scope of this document.
Dual purpose air valves will be used at all elevated points and at others determined in the
hydraulic transient analysis.
Air valves will be located and selected in accordance with the AWWA M51 Air Release,
Air / Vacuum & Combination Air Valves.
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 13 of 28
Rev. X
Air and drainage valve internals in contact with the fluid must be made of a material that is
suitable for withstanding the aggressiveness of said fluid.
Both air and drainage valves will be installed within a chamber for protection from freezing
and. Access to these chambers will be restricted.
For air valves located in sections of pipe working like closed conduit, the valves shall be
calculated in accordance with a Sikora expression that reasoned that the mean air velocity
could not exceed the mean water velocity. This leads to the expression for the maximum
possible airflow rate in a closed conduit, wich is:
𝑄 𝐴
1
𝑄 𝐴
Where:
Aerial supports will be used in the pump stations, pig stations and valve chambers.
Stress calculations will be conducted for the design of pipe supports and anchoring blocks.
These calculations will then be provided to the Structural Discipline.
Concrete blocks will be placed at the platform access zones and next to valve chambers.
Steel materials used for the fabrication of the supports will have a tensile strength greater
than or equal to 165 MPa (24.000 psi).
A thermal stress analysis will be conducted as indicated in ASME B31.4. This analysis is
required due to temperature variations that may exist in the facilities location.
Pressurized metallic sections of the pipeline will include pig stations distributed along its
routing. These operations will consider a launching station wherein a scrubbing and
gauging pig may be inserted. This instrument will then be pushed along by the water flow.
The pipe will be designed to permit the uninterrupted passage of this tool to the receiving
station (“pig receiver”).
Each station will be designed according to ASME BPVC Section III Boiler and Pressure
Vessel Code.
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 14 of 28
Rev. X
Pig launchers and receivers stations will be designed to accommodate internal inspection
instruments for gauging dirt buildup and evaluating the levels of internal corrosion and
wear of the lining.
Pig launchers and receiver must have a flange connection class according to pressure level
required, a full bore API 6D shut off valve and a quick open end enclosure.
Each station will include a reception tray used for collecting the dirt eliminated from the
inside of the pipe. This tray will facilitate natural drying of the wastes or mechanical
removal thereof.
For launcher stations in gravity sections of pipeline, perforated disc butterfly valves (like
Monovar valves) shall be used to allow the pressure drop necessary for pig launching. This
ensure that the flow mainline cannot be blocked.
Pump stations will be located next to water intake areas of the Vizcachas and Titire rivers.
These pump stations will include the following elements:
The Titire intake is a civil work that collects water from the river and conducts it to
the pumping area. The design criteria for this facility is by others.
3.5.2. Pumps
The pumps for the Vizcachas river will consist of multistage split case horizontal
pumps. Titire river pumps will consist of vertical turbine multistage pumps.
The pump materials shall be defined by the supplier based on the water quality
information obtained from study MQ09-09-RE-0000-GA0009 “Fresh water
Corrosiveness Analysis / Pipe and Lining Test Analysis” conducted by a third party
in conjunction with Anglo American.
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 15 of 28
Rev. X
The pump stations will also consider one pump on standby with the others in
operation. The number of pumps will be defined based on the type of pump, the
size of the motor and the flexibility required. A control system must be provided
that regulates the flows between sections of pipe.
The discharge manifold will be constructed with a collector pipe and a system of
cutoff and check valves that direct the water to the main pipeline. The head will
include a recirculation system and filling system. Special attention must be given to
the design of the drainage system, considering that the pumping systems are
situated at the lower sector of the Pelluta hill.
Given the complexity of the discharge manifold design, this considers branches,
reductions, valve connections and instrumentation connections, the internal FBE
lining is therefore also complex. Given the foregoing, discharge manifold materials
will be stainless steel quality 316/316L (ASTM A312 TP316/316L).
The tank for the transfer of water located at Pelluta hill will work like a transfer chamber.
The water tanks will be constructed of carbon steel with interior corrosion protection and a
conical roof. The design will be as indicated in AWWA D100 or API 650. The necessity of
tank insulation to avoid freezing needs to be verified by heat transfer methods.
The fresh water transfer tank, approximate location at km 3+786 (3.923,4 m.a.s.l.) of the
route of the existing construction water pipeline, will have a capacity equal to the
aforementioned charge tank and it will work like a transfer chamber too.
The water tank will be carbon steel with internal corrosion protection coating and without
roof. The design will as indicated in AWWA D100 or API 650.
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 16 of 28
Rev. X
4.1. General
The pipeline design will consider diverse aspects that require the most adequate solutions
to fresh water transport problems. Every aspect must be correctly referenced in accordance
with the appropriate codes and standards for each case. Below are the important aspects to
be considered for designing the pipeline:
Hydraulic design
Mechanical design codes and standards
Route and slopes
Pipe fittings and materials
Possibility of fluid freeze.
Calculation methodology
Transient analysis (i.e. waterhammer)
Pipe flexibility analysis
Valve selection
Pump stations
Pressure dissipation stations
Interior and exterior coating
Cathodic protection
Pigging
Manufacturing process
Draining
Emergency system
Use of intelligent tools (PIGS) for inspection and cleaning
Use of robotics for interior FBE coating of welded joints.
Pipeline design must consider a minimum 92% availability.
The design and calculations for the pipeline must match the route defined in the project
drawings. Likewise, definitions for above-ground or buried sections of pipe, changes in
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 17 of 28
Rev. X
direction or elevations of the pipeline must be in accordance with the definitions indicated
in the project drawings.
Where the electrical lines cross over the pipeline route, the distance of the towers to the
axis of the pipeline shall be no less than 11 m.
When a pipe section a run over supports, the height of these supports will be calculated
while considering the possibility of flooding over the soil surface. Therefore, a minimum
400 mm distance from the base of the pipe to the soil surface must be considered.
When the pipeline runs directly supported over the soil surface, lateral movements of the
pipe will be restricted using proper supports.
When the pipe will not be buried, the pipe bending and the distance to the high voltage
overhead lines will be the same for case of buried pipe.
A detailed trench preparation design shall be submitted by the civil discipline and must
take into consideration the soil mechanics along the pipeline route; thereby facilitating the
generation of proper slopes during the construction phase. The design must include backfill
quality and preparation of the bedding where the pipe will be placed.
Aerial supports will be used in the areas where the pipeline runs above ground such as in
the cases of high slopes or rocky areas.
Areas where the pipeline crosses roads, railway lines and there the line surfaces above
ground will consider concrete anchor blocks to ensure restricted movement of the buried
pipe.
Stress calculations will be conducted for the design of pipe supports and anchoring blocks.
These calculations will then be provided to the Structural Discipline.
Concrete blocks will be placed at the platform access zones and next to valve chambers.
Steel materials used for the fabrication of the supports will have a tensile strength greater
there or equal to than 165 MPa (24.000 psi).
Sections of the pipeline running above ground will have supports along the entire span.
Design of these supports will consider a standard minimum yield stress (SMYS) not
exceeding 66%.
A thermal stress analysis will be conducted as indicated in ASME B31.4. This analysis is
required due to temperature variations that may exist along the route of the pipeline.
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 18 of 28
Rev. X
Flow pressure losses in the pipe will be calculated using the Darcy-Weisbach equation and
the friction factor estimated using the Colebrook expression.
An additional 5 – 10 % must be added to the head loss value due to friction, considering the
aging of the pipe, diameter differences or any other abnormal condition of the internal
surface of the pipe. The additional head loss factor must not be added to pressure losses due
to elevation changes or acceleration. Velocities under 2.0 m/s are considered acceptable
under special conditions such as in the case of long spans of pipeline.
Another important aspect to keep in mind is the geographical variety. This allows a gravity
flow with mixed behavior (pressurized and free surface channel) and if important savings
can be obtained , this configuration may be adopted (i.e. use of HDPE runs). In summary,
the pipeline needs to be verified by head loss, pressure and velocity, taking into account the
economical factor.
Parameter values and type of piping to be selected will be as indicated in Section 2.2.1. The
fabrication process data, materials, welding and linings, as offered, will be openly reported
by the manufacturer.
Drainage must be calculated considering pressure values existing at selected points and the
volumes to be drained. Each case must also consider risk control for personnel associated
with the operation of drainage devices.
Venting and combination air/vacuum valves will be designed and calculated using the
AWWA M51 manual as a reference. The position and quantity of these valves will be
defined based on the definitive route of the pipeline and must be established in the pipeline
layout drawings. These draining points will be directed towards adjacent ravines/gulleys.
Civil works will be considered at these locations to dissipate energy and to avoid
undercutting/erosion.
Hydraulic calculations of closed conduit or free surface pipeline sections must consider the
requirements indicated in points 3.3 of the Hydraulic Design Criteria document No. MQ11-
02-DC-0000-PD0002.
For sections working hydraulically like closed conduit, vents valves will be used to permit
the air feed to the interior of pipes. This valves shall be calculated for admit the air flow
according to Sikora expression indicated in equation n° 78 of United States Department of
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 19 of 28
Rev. X
Interior, Water and Power Resources Service, “Engineering Monograph N° 41 Air-Water Flow in
Hydraulic Structures”.
The pipeline will be designed in accordance with ASME code B31.4 for all buried
and above ground pipe sections. The same code will be used for designing the
pump stations.
It will be understood that the design involves all integral components of the
pipeline (i.e.: pipe, fittings, flanges and separate components forming one element
by means of welding and bolting).
The mechanical design will consider all types of stress that may occur during the
pipeline’s operation; permanent stress from operation, occasional loads due to
seismic activity and transient loads due to infrequent operations such as abrupt
opening or closing of valves, starting or shutting down pumps, etc.).
Heating of the empty pipe (due to the effects of solar radiation) and subsequent
cooling thereof (due to temperature drops in the field) must be considered as a
special case, only in sections running above ground.
The design shall consider the natural movements of the pipe while in operation.
The buried portions of the pipe will have restricted movement while movement of
the sections above ground will not be restricted and will consider adequate support.
The proper elements needed for accommodating expansion and contraction of the
pipeline must be considered for its correct operation.
Fittings must comply with MSS SP75 standard for fittings from 3” up to 30”.
Directional changes for angles up to 1.5° will be made with fabricated curves on a
single pipe.
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 20 of 28
Rev. X
Thermal expansion (α): for carbon steel pipe, an thermal expansion coefficient of
11.7 x 10-6 °C-1 will be considered for temperatures up to 120° C. HDPE pipe will
consider a thermal expansion coefficient of 0.2x10-3 °C-1.
Poisson's ratio (ν): 0.3 for carbon steel and 0,46 for HDPE.
t = wall thickness, mm
Do = External diameter, mm
Plastic pipes with SDR >21 are forbidden. For Plastic pipe of SDR21, it shall be
calculated for vacuum pressure collapse.
Road and railway line crossing calculations must be carried out in accordance with
API RP1102 ‘Steel Pipelines Crossing Railroads and Highways’.
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 21 of 28
Rev. X
All valves must be ASME class for maximum operation pressure and maximum
testing pressure as indicated in ASME B16.34 and API 6D.
Specifications will be as listed in tables 423.1-1 (for materials) and 426.1-1 (for
dimensions) in ASME code B31.4. Exceptions to the foregoing must be approved
by the engineering department.
Materials that those parts of the valves in contact with the water must be made of
stainless steel class 316L or greater.
Gate valves will be selected in accordance with API 600. When these valves are
used for isolating sections of the pipeline, they must be “full port” type, however,
this is not necessary when the gate valves are used for drains.
All flanges will comply with MSS SP-44 and will be the same steel grade as the
pipe.
Threaded joints shall not be permitted. All joints will be butt-welded, socket
welded or flanged.
Gaskets shall comply with ASME B16.20 (spirometallic) or ASME B16.21 (non
metallic) as required.
Machine bolts for ASME class 150 will be as specified in ASTM A307 Gr. B,
whereas the bolts will be as specified in ASTM A 194 Gr. 2H. For ASME class
300 and 600, studs will be as specified in ASTM A 193 Gr. B7 with bolts as
specified in ASTM A194 Gr.2H.
Metallic piping material will be API 5L, type PSL2 with longitudinal seams.
Variable thicknesses will be considered depending on the maximum pressure
values at different sections of the pipeline. The pipe will be grade X60 (minimum
yield strength of 60.000 psi) for the pumped section (between the stations an
Pelluta hill) and grade X42 for the metallic gravitational sections from the line
(from Pelluta hill to the Caracoles ponds).
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 22 of 28
Rev. X
All fittings will be fabricated with materials of the same class used for the main
pipe. All welds will be type butt-welds. The materials for metallic fittings will be
as defined in specification MSS SP-75. HDPE fittings must be the same material
used for the pipe (PE4710) and with a standard dimension ratio (SDR) that
withstands nominal pressure to the same degree as full pressure rated pipe. Elbows,
not molded, must be fabricated with a minimum of 5 miter joints.
The minimum allowable curvature for a metallic fitting use in the pipeline must be
equal or greater than 5D (given that the minimum radius to permits the passage of a
cleaning and inspection tool) and as shown in Table 4.2. The minimum allowable
curvature for fitting use in sections that will not need the passage of pig, must be at
least 1,5D.
Piping and fittings that are unlined on the interior and in contact with water must be
stainless steel 316L or greater.
The minimum radius of curvature for HDPE pipe will be recommended by the
manufacturer. Typically, the natural radius of curvature for HDPE pipe is as shown
in Table 4.3 below:
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 23 of 28
Rev. X
5.0 CONSTRUCTION
5.1. General
For sections of pipeline routed above 4.000 m.a.s.l., buried and above ground, the risk of
freezing shall be evaluated using the heat transfer rules. In those sectors without risk of
freezing, the depth will depend on the surface loads. A minimum 0,61 meter depth over the
top of the pipe will be considered for normal loads. For heavy loads that include crossings
under roads, railways etc., the minimum depth over the top of the pipe will be 1,2 m.
Furthermore, such crossings will comply with requirements set out in API 1102.
Procedures for cold bending metallic pipe on site will be required when the pipe must
adjust to the horizontal or vertical alignment of the pipe for the radius of curvature between
40D and 503D (for API 5L X60), and between 40D and 719D (for API 5L X42).
Care must be taken so that the diameter/thickness correlation of the pipe never exceeds 96
times. If the wall thickness reduction from bending exceeds the aforementioned value, the
resistance of the deformed wall may be lower than the minimum limit. A deformation study
will be conducted prior to any bending decisions. If bending is required, an additional
thickness will be added to the section to be bent.
The pieces to be bent will be cut from sections of pipe and will not have branch
connections nor will it be formed from 2 or more pieces with circumferential joints – even
if the joints have been approved.
Metallic pipe lined on the interior with a FBE coating must have the minimum radius of
curvature indicated in ASME code B31.4 section 404.2.2. This section specifies that the
minimum acceptable radius of curvature must not be less than 30 times the diameter of the
pipe. However, for this Project, given that the use of a robotic tool for the application of
internal FBE lining for the welded joints has a 38D limit (where 38D is equivalent to 1.5°
of the curve per diameter inch of the pipe) a minimum radius of curve of 40D has been
adopted.
5.3. Elbow or Bend Restrictions (cast or hot bent fittings) of the Line Pipe
Given the use of pigging tools on the pipeline and the restrictions for coating welded joints,
the use of bends or elbows consider the following design restrictions:
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 24 of 28
Rev. X
Bends with a radius of curvature lower than 40D must be flanged in both ends.
5.4. Restrictions on Pipe located at the Installations
Given the restrictions of the application of internal FBE, all connection branches used
along the pipeline must be equal to or greater than 3”. Moreover, all spools to be installed
at the pump stations (discharge and suction manifolds) and at the reducing, vents and
drains, must be shop fabricated as a special piece with flanged ends.
Given the restrictions of the application of internal FBE, all pipe joints located in areas
with a slope exceeding 15% must be with welded neck flanges and must be completely
coated in the shop (from face to face on both sides of the flange).
The pipe production process will be carried out exclusively by qualified welders with the
qualified procedure, according to API 1104. The ends to be welded will be correctly cut
and cleaned of any impurities or damage that may affect the final results.
6.0 SINGULARITIES
6.1. Drains
The discharge pipe will be calculated so that the water output velocity does not exceed 5.0
m/s in the drainage pipe and 0,6 m/s in mainline.
The drainage system shall consist of a shut-off gate valves and a group of orifice plate-
type, fluid pressure reduction disks.
Discharge openings along the entire drainage system must always point to an open location
where there is no risk of damage to persons and/or equipment.
Pipe sections between the pump stations and the peak of Pelluta hill will drain into the
bilge to the pump stations. Pipe sections from the peak of Pelluta hill to Papujune will drain
into the Caracoles ponds or to the appropriate ravines.
Pipe protection must be suitable for ensuring a minimum life of 29 years. The coating is valid
only for carbon steel pipe.
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 25 of 28
Rev. X
Internal coating of the pipe to prevent corrosion will be FBE as recommended in report MQ09-
09-RE-000-GA0009 “Analysis of Fresh water Corrosivity/Pipe and Lining Test Analysis” by
AguaMarina and defined in MQ11-02-TE-0000-PD0008 “FBE Internal Pipeline Protection
System”, based on API 5L7 “Recommended Practice for Unprimed Internal Fusion Bonded
Epoxy Coating of Line Pipe”. The thickness of the cured coating must be not less than 500
microns.
External coating of buried pipe will be coal-tar enamel, fabricated as stipulated in MQ11-02-TE-
1000-PD0007 “Coal-Tar External Pipeline Protection System” based on AWWA C203 “Coal-Tar
Protective Coatings and Linings for Steel Water Pipelines – Enamel and Tape Hot Applied”. The
thickness of the dry coating must not be less than 2,5 mm.
Buried fittings such as bends and elbows must be as indicated in section 4.5.3 of this document.
Moreover, these fittings must be externally coated with the same external protection as the pipe as
indicated in MQ11-02-TE-0000-PD0007 “Coal-Tar External Pipeline Protection System” (coal-
tar as per AWWA C203), and internally shop-coated in accordance with MQ11-02-TE-0000-
PD0008 “FBE Internal Pipeline Protection System”.
Pipe running above ground will only require an epoxy coating. The exterior coating will only be
applicable if the pipe is partially submerged in water when laying it directly over the ground.
During operation, there is a possibility that the fresh water from the Titire or Vizcachas
may introduce a certain quantity of dirt to the pipe interior. Pig launching stations will be
used as mechanical cleaners for pressurized metallic sections of the line.
Sections of plastic pipe and / or where the flow is free surface, will not be cleaned or
inspected.
The quantity of pigging stations will be defined in accordance with the route and
characteristics of the pipeline. There will be at least 1 pigging station for each section of the
line between pump stations.
When the pipe section includes internal FBE protection, the pig design must take into
consideration such protective lining so as to avoid damaging the surface.
A1 – External protection
It is mandatory for buried pipe to have a cathodic protection system (as well as a coal-
tar enamel exterior protection) which must be defined at the onset of the corrosivity
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 26 of 28
Rev. X
analysis of the soil. Corrosion control must be based on the guidelines defined in
NACE RP 0169.
The pipe must also have a system of electrical isolation to protect it from:
Cathodic protection systems will be designed by third parties – reviewed and approved
by the electrical discipline.
The existence of other protection methods on nearby metallic structures may create
electrical interference on the pipeline. Likewise, pipeline protection methods may also
create interference with these external structures. Proper isolation methods shall be
designed to avoid such interferences.
The buried pipe sections will not consider thermal insulation. These sections must be
buried at a sufficient depth to avoid freeing at the surface, as calculated by the
Berggren method.
A2 – Interior Protection
B1 - External protection
Above-ground pipe sections without thermal insulation and mounted on supports shall
be externally protected using a coating of liquid epoxy in accordance with AWWA
C210. Additional UV protection will be required for outer layers of the coating. The
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 27 of 28
Rev. X
Pipe that includes thermal insulation will be protected in accordance with the
guidelines set out in NACE RP 0198. These sections must always run over supports
that isolate them from contact with soil and moisture. Moreover, they must be coated
with an anticorrosive epoxy beneath the insulation.
Cathodic protection using impressed current, combined with sacrificial anodes, will be
required on installations with piping that doesn’t have thermal insulation, where the
climate is sufficiently humid and where there is a possibility of electrical storms.
A covering placed over the insulation, made of steel or tin sheeting must be electrically
isolated (as described for pipe without insulation) using epoxy paint and the appropriate
cathodic protection. Moreover, the isolating layer must ensure an effective barrier from
rainwater or environmental moisture.
Pipe sections resting directly over the ground will not consider thermal insulation and
protection with cathodic protection by impressed current. Sacrificial anodes will be
installed if the soil resistance is abnormally high.
B2 - Internal protection
C - Tanks
Tanks will be painted on the interior and exterior in accordance with MQ11-02-TE-
0000-GA0001 Especificación Técnica de Pinturas, with P6-A scheme.
The following matrix shows the protection scheme summary for pipes:
Piping
Anglo American Quellaveco S.A. MQ11-02-DC-1100-PD0004
Project Quellaveco Date 02-Jun-2020
Contract Q1CO Page 28 of 28
Rev. X
8.1. General
This section refers to certain aspects related to inspection, testing, start-up and maintenance
of the pipeline during commissioning and the commencement of regular operations,
including the following:
Pipe installation
Initial fill
Leak detection
Pressure tests
Controlled draining
Specific repairs
Combination and vent valve operation.
Pipe installation and the aforementioned operations will be part of the technical
specification MQ11-02-TE-000-PD0006 - Fresh water Pipeline Fabrication and
Installation, and are therefore not included in this document.
END OF DOCUMENT
Piping