S/N WORK DESCRIPTION S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 site clearance 1 2 Geophysical survey 1 3 setting up of rig 5 4 Construction of mud pit 2 5 Drilling of Pilot Hole 10 6 Drilling of 550mm Dia Hole 2 7 Installation of loss casing 2 8 Drilling of 350mm Dia. hole 20 9 Drilling of 300mm Dia. Hole 14 10 Logging of Horehole 1 11 Analysis of Drill Cutting Samples 1 12 Installation of screen 2 13 Casing of borehole 2 14 Grouting of angular space of surface casing 2 15 Gravel packing of well 2 16 Well Development 2 17 Borehole Yield and Constant rate Test 2 18 Installation of submersible Pump with riser pipe 2 19 installation of control panel 5 20 Water quality analysis 3 21 Installation of pipe for water level measurement 1 22 Submission of Borehole Report 1