WEEK-1 WEEK-2 WEEK-3 WEEK-4

S/N WORK DESCRIPTION S M T W T F S S M T W T F S S M T W T F S S M T W T F S


1 site clearance 1
2 Geophysical survey 1
3 setting up of rig 5
4 Construction of mud pit 2
5 Drilling of Pilot Hole 10
6 Drilling of 550mm Dia Hole 2
7 Installation of loss casing 2
8 Drilling of 350mm Dia. hole 20
9 Drilling of 300mm Dia. Hole 14
10 Logging of Horehole 1
11 Analysis of Drill Cutting Samples 1
12 Installation of screen 2
13 Casing of borehole 2
14 Grouting of angular space of surface casing 2
15 Gravel packing of well 2
16 Well Development 2
17 Borehole Yield and Constant rate Test 2
18 Installation of submersible Pump with riser pipe 2
19 installation of control panel 5
20 Water quality analysis 3
21 Installation of pipe for water level measurement 1
22 Submission of Borehole Report 1