Professional Documents
Culture Documents
22/2022 Page 1 of 29
No.N/140/2022
___________________________________________________________________________
Dated:19.10.2022
Present
OP No.22/2022
BETWEEN:
AND
1. Gulbarga Electricity Supply Company Limited
(GESCOM),
Station Main Road
Kalaburagi–585 102.
(Represented by its Managing Director)
2. The Karnataka Renewable Energy Development Limited,
No. 39, “Shanthi Gruha”,
Bharath Scouts & Guides Building,
Opp. The Chief Post Master General Office, Palace Road,
Bengaluru-560 001.
(Represented by its Managing Director)
O.P.No.22/2022 Page 2 of 29
ORDERS
1. The petitioner has filed this petition under Section 86(1)(f) of the Electricity
2. From the documents produced and the averments made in the petition, the
a) The petitioner is the Special Purpose Vehicles (SPV) of M/s Ekialde Solar
Private Limited.
nodal agency for facilitation and implementation of the Solar Policy of the
O.P.No.22/2022 Page 3 of 29
c) Messrs Ekilalde Solar Private Limited, submitted its technical and financial
bids for the development and implementation of the solar power projects
in some of the taluks of the State of Karnataka. The bid submitted for 20
d) That M/s Ekialde Solar Private Limited, incorporated the petitioner as SPV,
and perform the obligations and exercise the rights of single business entity
including the obligation to enter into the PPA pursuant to issuance of LoA.
The 1st respondent (GESCOM) also accepted the petitioner as SPV of the
e) That the petitioner and 1st respondent (GESCOM) entered into Power
f) As per Article 3.1 of the PPA the agreement come into effect from the
date of getting concurrence from KERC on the PPA and such date shall
be referred to as the Effective Date. Article 3.2 of PPA provided that the
project was fixed as 18 months from the Effective Date. The KERC adopted
the bid discovered tariff and approved the PPA vide letter dated
g) Article 5.8.1 of the PPA, provides that the Developer, shall commence the
from the effective date and delay beyond 22 months from SCD is one of
the grounds for ‘Default by Developer’ (Article 5.8.3 of the PPA). As per
Article 16.1 (a), of the PPA, if the developer fails to achieve the
commercial operation beyond twenty two (22) months from the date of
getting concurrence from KERC on the PPA for power project for any
h) The petitioner stated that it was not able to commission the project
within 22 months stipulated under PPA for reasons beyond its control
the penalty stipulated under the PPA. The petitioner followed up the
respectively).
Precedent as per Article 4.3 of the PPA along with GST at 18% on
j) The petitioner has not complied with the intimation to pay the
the balance Rs.36 lakhs towards 18% GST on Rs.2 crores, for processing
to the 1st respondent (GESCOM) stating that the balance of Rs.36 lakhs
“We would like to intimate you that we are unable and not
willing to commission 20 MW project that was allocated to
under vide reference No.2 due to certain inevitable
circumstances that have been an obstacle for the process
of the project resulting to the situation wherein we would
not be able to submit commission certificate, or any further
progress related to completion of the project by SCOD or
under period liquidated damages also.”
petitioner in the last sentence of para 10 of the petition has stated that
on 28.03.2018.’ This clearly goes to show that even the 1st respondent
commissioning the plant as per the terms of the PPA within 22 months
the petitioner, the 1st respondent (GESCOM) has terminated the PPA
of the project developer M/s Max Plancks Solar Farms Private Limited,
that all the equipments are available at site and ready for
before the 2nd respondent (KREDL), for allotment of solar power plant
has acquired all the shares of the parent company of the petitioner,
i.e., M/s Ekialde Solar Private Limited as per Board Resolution dated
and modules has been made by M/s Sunsource Energy Private Limited
c) M/s Sunsource Energy Private Limited has also entered into Power
huge penalty under the PSA. Copies of the Power Supply and Off take
petitioner.
d) It could be seen that the entity that has now invested and applied for
Group Captive approval is totally a different one and that the capital
and arbitrary.
the said WP. The 1st respondent (GESCOM) challenged the said interim
O.P.No.22/2022 Page 10 of 29
WP on 25.07.2022.
counsel. The 3rd respondent (GoK) remained absent. The 2nd respondent
(KREDL) has not filed any written statement of objections. The 1st
a) The execution of the PPA and the exchange of several letters between
b) That the petitioner had fulfilled the Conditions Precedent as per Article
4.2 of the PPA affirming the same vide its letters dated 02.05.2019
required in Article 4.2 of the PPA the Conditions Precedent were fulfilled
d) The petitioner had filed OP. No 70/2019 before this Commission seeking
provision contained in the PPA. That this would establish that the
No.70/2019 on 05.03.2020.
Rs.36 lakhs (18% GST) for processing the termination of PPA dated
the PPA. That staying true to its content of letter dated 08.04.2021
During the site inspection it was found that the equipment which
respondent denied the request for termination of the PPA vide its letter
months from the date of getting concurrence from the KERC on the
O.P.No.22/2022 Page 12 of 29
PPA for Power Project, for any reason whatsoever, would constitute the
terminate the PPA. The PPA does not contain any term or situation
show that the petitioner is not entitled to plead the principle of estoppel
liquidated damages.
respondent.
i) The measures adopted by the petitioner are against the sanctity of the
contract entered between the parties. The petitioner could not have
PPA.
shares and Solar Pack India LLP having 0.01% share in the petitioner’s
than its shareholders and the transfer of shares from one to another
Limited by its own fund with a view to establish Group Captive Project,
is untenable and in no way relieve the petitioner from its liability under
PPA.
prayed that this Commission to dismiss the instant frivolous petition in its
6. The petitioner filed rejoinder reiterating the earlier grounds stated in the
petition with some more additional facts in support of it. In the rejoinder
the petitioner has admitted that the damages payable for non-fulfilment
Conditions Precedent and the same was accepted by the 1st respondent
(GESCOM) and that the petitioner’s earlier assertion in the petition that it
7. Sri G.S. Kannur, Senior Counsel, argued on behalf of the petitioner and
submitted that:
O.P.No.22/2022 Page 14 of 29
position to establish the Solar Power Project for the reasons stated by it
and requested the 1st respondent (GESCOM) to put an end to the PPA.
“We would like to intimate you that we are unable and not willing to
commission 20 MW project that was allotted to under vide reference
No.1, due to certain inevitable circumstances that have been an
obstacle for the progress of the project resulting to the situation
wherein we would not be able to submit Commissioning Certificate,
or any further progress related to completion of the project by SCOD
or under period liquidated damages also.”
made the same request for accepting the request for abandoning the
5.8 of the PPA with applicable GST. He has also pointed out that after
realising the Bank guarantee to the extent of Rs.2 crores, the 1st
Taluk for which the parent company of the petitioner was declared
as selected bidder.
pay Rs.36 lakhs towards the GST payable “for processing the
under the contract. PPA does not provide for automatic termination
to terminate this agreement and the developer does not have the
(GESCOM) event of default that the developer can terminate the PPA.
It is not the case of the developer that the 1st respondent (GESCOM)
has defaulted;
O.P.No.22/2022 Page 17 of 29
b) The case of the petitioner cannot be compared with the case of M/s
Max Plancks Solar Farms Private Limited (Annexure-P) and case of solar
HESCOM. It is pointed out that the above two projects have been
c) The conditions precedent as per Clause 4.0 of the PPA has been
fulfilled by the petitioner and the 1st respondent (GESCOM) has also
d) It is not the case of the petitioner that they are abandoning the project
and not able to do the construction of the project, but the intention of
the petitioner is to commission the project but not supply to the 1st
the petitioner for termination is to come out of the PPA and supply the
e) The legitimate expectation does not arise when there is contract, and
9. In response to the fact that the Project being ready for commissioning as on
the date of spot inspection on 04.03.2022, the petitioner has stated in para
17 of the petition that one Sunsource Energy Private Limited, which had
establishment of the Solar Power Project on the Project Site by investing its
own fund by borrowing the same from others. It is also stated that the said
Sunsource Energy Private Limited had entered into power supply agreement
dated 24.09.2021 with one OA consumer namely; A-One Steel and Alloys
10. From the pleadings and documents of the parties and the rival submissions
made during the arguments, the following issues arise for our consideration:
Issue No.1: Whether the 1st respondent (GESCOM) was bound to terminate
the PPA dated 28.03.2018 (Annexure-C) on the principles of
legitimate expectation, as contended by the petitioner?
Issue No.2: Whether the petitioner proves that the 1st respondent (GESCOM)
is estopped from refusing to terminate the PPA dated
28.03.2018 (Annexure-C)?
Issue No.3: Whether the communication dated 23.03.2022 (Annexure-S)
issued by the 1st respondent (GESCOM) requires to be set
aside?
Issue No.4: To which reliefs, the petitioner is entitled to?
11. After considering the submissions and the records our findings on the above
12. Issue No.1: Whether the 1st respondent (GESCOM) was bound to terminate
the PPA dated 28.03.2018 (Annexure-C) on the principles of
legitimate expectation, as contended by the petitioner?
a) Before dealing this issue on facts, it is necessary to deal with the question
of law raised by the learned counsel for the respondents, that while
legitimate expectation does not arise. The learned counsel for the
petitioner negated such contention. The parties had not placed any
Vs. Isaac Peter (1994) 4 SCC 104, in somewhat similar facts as in the
present case, has dealt with the plea of legitimate expectation while
The contract had been entered into subject to The Kerala Abkari Act,
the mutual rights and liabilities of the parties are governed by the
terms of the contracts (which may be statutory in some cases) and
the laws relating to contracts. It must be remembered that these
contracts are entered into pursuant to public auction, floating of
tenders or by negotiation. There is no compulsion on anyone to enter
into these contracts. It is voluntary on both sides. There can be no
question of the State power being involved in such contracts. It bears
repetition to say that the State does not guarantee profit to the
licensees in such contracts. There is no warranty against incurring
losses. It is a business for the licensees. Whether they make profit or
incur loss is no concern of the State. In law, it is entitled to its money
under the contract. It is not as if the licensees are going to pay more
to the State in case they make substantial profits. We reiterate that
what we have said hereinabove is in the context of contracts entered
into between the State and its citizens pursuant to public auction,
floating of tenders or by negotiation. It is not necessary to say more
than this for the purpose of these cases. What would be the position
in the case of contracts entered into otherwise than by public
auction, floating of tender or negotiation, we need not express any
opinion herein.”
c) The PPA in question has been entered into between parties in respect
accepted.
the parties.
e) The facts are already narrated and the close scrutiny of facts would
reveal that the previous instances or cases where PPAs were terminated
O.P.No.22/2022 Page 21 of 29
petitioner are not similar or comparable with the facts of the present
they could not do the construction. But on the other hand in the present
case, on the date of joint spot inspection, the 1st respondent (GESCOM)
found that the Solar Power Project was ready for commissioning at
Sub-Station Site, were fully installed. This one fact made the 1st
f) The petitioner contended that there was delay of more than two years
from taking any action by the 1st respondent (GESCOM) on the request
Power Project at the Project Site and that 3rd party viz., Sunsource
Solar panels and other equipment and material for installation of the
g) The above submission of the petitioner is not well founded. Though the
two reminders and the payment was intimated to the 1st respondent
few months but not a delay of more than two years as contended by
the petitioner.
Energy Private Limited had invested its own fund to purchase Solar
the transfer of shares in its favour which had taken place on 21.01.2022
material for establishment of the Solar Power Project. One cannot say
that the solar panels and other material installed at Project site belong
plant owner, disentitles it to contend that the solar plant belongs to the
third party. The 1st respondent (GESCOM) has nothing to do with the
transactions with the third party investor as the terms of PPA are
the petitioner cannot resile from its assurance in supplying the energy
shows that the petitioner wants to commission the project but not supply
O.P.No.22/2022 Page 24 of 29
power to the 1st respondent (GESCOM) as per the contract but supply
to a third party.
l) The petitioner has fulfilled the conditions precedent based on the PPA
obtained all permission for procuring the land, based on the PPA. Having
obtained all clearances based on the PPA, now the petitioner cannot
be allowed to cancel the PPA and continue with the construction and
from termination of the PPA. Article 4.3 provides that in the event, the
developer fails to fulfil the conditions precedent within the time allowed,
Similarly, Article 5.8 provides that the developer shall pay liquidated
damages for delay in supply of power by the SCD to the 1st respondent
(GESCOM) is entitled to make the demand for the same and the
for the petitioner to avoid such payments. On the other hand, the
Event of Default as the case may be, is only a discretion allowed to the
13. Issue No.2: Whether the petitioner proves that the 1st respondent (GESCOM)
is estopped from refusing to terminate the PPA dated
28.03.2018 (Annexure-C)?
b) Section 115 of The Indian Evidence Act, dealing with Estoppel reads as
follows:
“S. 115 Estoppel - When one person has, by his declaration, act or
omission, intentionally caused or permitted another
person to believe a thing to be true and to act upon
such belief, neither he nor his representative shall be
allowed, in any suit or proceeding between himself
and such person or his representatives, to deny the
truth of that thing.”
(2) The representation must have been of the existence of a fact and
not of promises de futuro or intention which might or might not be
enforceable in contract.
O.P.No.22/2022 Page 26 of 29
(3) The representation must have meant to be relied upon, i.e., it must
have been made under circumstances which amounted to an
intentioned causing or permitting belief in another. The proof of the
intent may be direct or circumstantial, e.g., by conduct. It is not
necessary that there should be a design to mislead, or any
fraudulent intention or that the representation should be false to the
knowledge of the maker. Representation even when made
innocently or mistakenly may operate as an estoppel.
(4) There must have been belief on the part of the other party in its truth.
(5) There must have been action on the faith of that declaration, act
or omission, that is to say, the declaration, act or omission must have
actually caused another to act on the faith of it, and to alter his
former position to his prejudice or detriment.
(7) The person claiming the benefit of an estoppel must show that he
was not aware of the true state of things. If he was aware of the real
state of affairs or had means of knowledge, there can be no
estoppel.”
following facts:
(i) That the petitioner made written request that it was not in
(iii) Pursuant to it, the petitioner has paid Rs.36 lakhs through
and the facts of the present case noted above, we have to examine
Estoppel and the facts of the present case, the Commission is of the
considered view that the petitioner has failed to make out a case that
the principle of estoppel would apply in its favour for the following
reasons:
ii) It can also be seen that the above said letters of the 1st
However, the factual position was contrary as the petitioner had not
abandoned the project but had established the project and intended
to convert it into a group captive category unit, solely for the purpose
of higher gains.
g) The PPA executed between the parties provides for termination of PPA
in PPA for its termination at will of any one of the parties. The PPA can
be terminated before the expiry of its term, only with the consent of
a) In view of the findings on Issue No.1 & Issue No.2, the question of setting
arise.
For the foregoing reasons, the petitioner is not entitled to any of the
ORDER