a.
b.
= 8*60 mins
= 480 mins.
As 400 units must be manufactured per day, the required cycle time is
=480/400
= 1.2 min.
c.
The cycle time is determined by the time taken by C and D tasks. The total cycle time is as follows:
A+C+D+F+G+H
= 3.3 mins
The total time taken for all the tasks is 3.8 mins
= 3.8/3.3
=1.15
The efficiency can be calculated as (cycle time - idle time)/ cycle time
= 2.8/3.3 *100
= 84.84