You are on page 1of 6

FEATURE ARTICLE

2011 Transit Center construction,


near Millennium Tower (left rear)

Soil Mixing Evolution in San Francisco


“San Francisco is 49 square miles Seiko. This pioneering company was methods. Typically, groundwater is
surrounded by reality.” So said Paul based in the East Bay and some of its within 15 to 20 ft (5 to 6 m) of grade,
Kantner of the local ’60s icons, Jefferson early employees still work at the eight requiring cutoff walls for deep excava-
Airplane, and his words have still held soil mixing contractors now operating in tions. The Old Bay Clay unit, present at
true. The rate, scale and complexity of the area. approximately 100 ft (30 m) below the
recent construction in this city has Second, subsurface conditions here downtown Transbay district, is an
been remarkable, even compared to the are well suited to soil mixing methods. effective groundwater control layer, and
Gold Rush or reconstruction after the The stratigraphy at city sites typically cutoff walls are frequently keyed into
1906 earthquake. This article will comprises urban fill, dune sand, young this strata, or at least constructed with a
address developments in soil mixing in marine or marsh soils, Colma sand, and deep toe within the Colma unit.
San Francisco since 2011, and how the Old Bay Clay. The fill and dune sand are Third, the active seismicity of this
marked settlement of a downtown high predominantly granular, forming well- region generates geotechnical chal-
rise has influenced this booming blended soil cement. Although the lenges such as static settlement and
construction market. young marine and marsh soils are liquefaction. Soil mixing offers efficient
mainly cohesive, their low strength and cost-effective solutions for these
Local Soil Mixing allows for effective mixing, creating a situations. Finally, market demand has
Deep soil mixing has gained prominence reasonably consistent product. The enabled contractors and consultants to
in San Francisco for four reasons. First is stronger Colma formation, while rapidly evolve their expertise, as each
the regional concentration of expertise. predominantly dense well-graded sand, successful project sets a new bar for
Japanese deep mixing technology was contains some silt and clay, which is complex support of excavation in tight,
introduced to the U.S. in 1987 by S.M.W. mixable using shaft and end mixing constrained urban sites. Although in

AUTHOR Rob Jameson, Malcolm Drilling Company

DEEP FOUNDATIONS • JAN/FEB 2022 • 71


2012, 50 ft (15 m) was considered deep,
San Francisco’s Mission Bay, downtown in 2006
by 2020, multiple excavations had
extended over 70 ft (20 m), while being
directly adjacent to existing buildings.

Approaches in Early 2000s


Back in 2011, the local soil mixing
market predominantly involved multi-
axis deep soil mixing (DSM) rigs
operated by U.S. subsidiaries of
Japanese companies, or single-axis
mixing rigs operated by Malcolm
Drilling Company and Condon-Johnson
& Associates. San Francisco had seen
limited new building since the 1980s.
Construction projects were mainly
infrastructure, structural retrofits, or
relatively shallow excavations con-
structed with conventional pile and
lagging or underpinning methods. Jet
mixing had gained ground as being very
fast and efficient; however, equipment Constructed Mission Bay district in 2019, and Transbay District towers near downtown
constraints had limited this approach
to about 70 ft (20 m) of total drilling
depth. One unique project was the
Sunset Reservoir, where multiple tiered
soil mix cells provided slope stabiliza-
tion and liquefaction mitigation. This
project was constructed by Raito using
a multi-axis rig. Cutter soil mixing
(CSM) had not yet been used in San
Francisco.

The Last Decade


After the Great Recession of 2008 and
2009, the city began a rapid growth
trajectory fueled by the technology
sector. Strong demand for state-of-
practice soil mixing further con-
centrated local expertise among
designers and contractors. Millennium
Tower, completed and opened in 2009,
b e c a m e i n f a m o u s fo r i t s p o s t-
construction settlement, resetting the complex excavations in an increasingly Millennium Tower Impact
risk perspective of many in the deep risk-focused environment led to Millennium Tower is a 58-story luxury
foundation industry. widespread adoption of CSM as a condominium whose opening in 2009
Soil mixing has followed three tracks preferred construction method. Within provided the first new downtown tower
of development since 2011. An increased this heated, but maturing market, in almost 20 years. Its concrete frame
application of DSM grid systems has construction demands have also construction is founded on up to 90 ft
occurred for combined bearing support encouraged refinement and optimiza- (27 m) long concrete piles driven into
and liquefaction mitigation; secondly, tion of more conventional methods, such the Colma formation. The site is directly
the demand for larger, deeper, more as single- and multi-axis and jet mixing. adjacent to the Transbay Transit Center,

72 • DEEP FOUNDATIONS • JAN/FEB 2022


whose construction from 2011 through order of $300 million (€260 million). compressible soils or on any other sites
2018 included a secant pile buttress Heightened sensitivity to potential as directed by DBI. Specific considera-
designed to limit deformation of construction impacts on nearby struc- tions the peer reviewer addresses
Millennium Tower during excavation tures has also occurred nationally, include ground improvement, effects of
of the adjacent 60 ft (18 m) deep station. further emphasized by the recent dewatering on site and nearby, and
The buttress was keyed into the 250 ft Champlain Towers collapse in South effects of construction-related activities
(75 m) deep Franciscan bedrock, with Florida. One outcome is an increased on neighboring foundations.
installation costs exceeding $50 million focus on contractual risk management In essence, Millennium has in-
(€44 million). for all parties, notably the design creased the focus on liability and risk
In 2016, it was publicly disclosed professionals and specialist subcon- transfer between parties engaged in
that Millennium Tower had settled 16 in tractors, as has certainly occurred in geotechnical construction and created a
(40 cm) in 7 years, compared to the San Francisco construction “Post- new requirement for third-party peer
predicted 20-year settlement of only Millennium.” review of support of excavation (SOE)
5.5 in (14 cm). The Transit Authority Another related impact of the and bearing support for critical projects.
reported that 10 in (25 cm) of that Millennium has been an increase in This means that design-build projects
settlement had occurred in the two regulation of geotechnical aspects of require earlier contractor engagement to
years before their adjacent work started; construction by San Francisco’s Depart- determine the optimal construction
by 2018, Millennium’s total settlement ment of Building Inspection (DBI). In approach and steer projects through
was 18 in (45 cm). The residents, city, 2017, Interim Guidelines for Structural, permit approvals. Often, the peer review
developer, Transit Authority and others Geotechnical and Seismic Hazard requires enhanced analysis, including
initiated legal claims and counterclaims. Design Review for Tall Buildings were finite element modelling of the geotech-
Settlements were reached without i s s u e d , a n d t h e n fo r m a l i z e d i n nical construction process, supple-
allocation or admission of fault. The November 2018. mental to the soil structure interaction
Millennium Tower fallout has still Although permitting previously studies that are conventionally run for
impacted most contractors and con- relied solely on geotechnical engineer of completed structures under seismic
sultants in San Francisco. In particular, record recommendations, the new loading. In consequence, complex
the project highlighted the potential guidelines require geotechnical peer projects now often have lead times of 6
scale of liabilities surrounding deep review of projects over 240 ft (75 m) to 18 months to break ground after a geo-
foundation and excavation support high. This requirement also applies to technical construction team is selected.
work. Some repair schemes that were buildings constructed in seismic zones These changes have afforded
considered had estimated costs on the with soft soils, on sites overlying soft or specialty contractors with an increased
role in project development and
participation in evaluating applicable
solutions for risks. Another upside is
that contractors are more frequently
selected based on expertise, rather than
solely on a low bid and potential
willingness to accept challenging
contract terms.

Post-Recession Challenges
Construction of 350 Mission Tower
kicked off the new, post-recession era in
San Francisco. Its 50 ft (15 m) deep
basement excavation was supported
with internally braced CSM walls that
extended through the Colma sands into
the Old Bay Clay. Since this project’s
successful completion, increasingly
deep, complex excavations have
occurred in direct proximity to
established structures. Several sites
A cutter soil mix tool

DEEP FOUNDATIONS • JAN/FEB 2022 • 73


have been excavated to over 70 ft (20 m) the SOE wall can further stiffen shoring Malcolm constructed a 140 ft (43 m)
in the Transbay District, with shoring systems to manage deformation and deep, 3.3 ft (1 m) thick, continuous peri-
walls extending deeper than 100 ft effects on adjacent properties. meter wall. To minimize deformation
(30 m); this depth allowed for structural effects, heavy W30 and W33 steel
embedment and sealing into the clay Project Example sections were placed at 4 ft (1.2 m)
unit for groundwater control. Some- Malcolm Drilling constructed SOE and centers around the site perimeter.
times, walls have exceeded 130 ft (40 m) deep foundations for Oceanwide Center, Structural beam lengths and other
to seal off and depressurize confined an L-shaped site that has a 61-level factors meant “over-the-hole” mech-
aquifers for blowout mitigation, and for tower and a 53-level tower, over anical splices were employed during
basal heave control in the underlying multilevel basements. The complex site wet set placement of the reinforcement.
clay layers. Bedrock is too deep to footprint wraps around six adjacent Two of the six structures adjacent to
contribute strength or stability. structures, and required an SOE scheme Oceanwide were high-rise towers
Although traditional SOE schemes that could allow tower excavation to founded on piles driven into the Colma
in San Francisco used the dense Colma progress without schedule constraints. formation. The planned excavation
sand to provide toe stability for shoring Overall, the mass excavation depth extended below pile tip of those
walls, the current, deeper excavations extended to 72 ft (22 m) depth, structures. To further stiffen the SOE
effectively remove this competent soil, penetrating into the top of the Old Bay wall at these critical locations, soil
and walls embed into the weaker, Clay. This uncharacteristic depth was cement buttresses were installed
underlying clay. This increases the further complicated by a thick sand lens perpendicular to the perimeter align-
potential for basal heave effects that within the underlying clay soils that ment. The buttresses were constructed
escalate the already significant ground required cut-off and depressurization. from original site grade by overlapping
movements predicted for these deep Due to the large depth and extensive nominally reinforced soil cement
excavations. The CSM method has removal of the Colma, the excavation panels end to end. They were removed
provided an effective solution to stiffen had a relatively low factor of safety in lifts as excavation progressed and
SOE systems by allowing thicker walls against basal heave. bracing levels were installed, with the
to accommodate larger, heavier steel The selected SOE approach was an remaining length below final subgrade
sections than in traditional multi-axis internally braced, combined shoring acting as a shear-key to resist lateral
soil mixing layouts. Also, buttress and cutoff wall. Using a steerable, movement and basal heave. Finite
elements constructed perpendicular to instrumented CSM mixing tool, element modelling of the shoring
The 72 ft (22 m) deep Oceanwide Center basement excavation

74 • DEEP FOUNDATIONS • JAN/FEB 2022


the Colma or on soil cement grids that
transfer load down to this soil unit. The
12-story mixed use building at 1066
Market has three basement levels and
imposes a peak load demand of 7 ksf
(335 kPa). The site abuts double-
stacked transit tunnels and multiple
existing buildings. Its stratigraphy is
comprised of undocumented fill
materials and compressible marsh
deposits overlying the Colma. Analysis
p r e d i c t e d u p to 3 i n ( 8 c m ) o f
liquefaction-induced settlement and
up to 5.5 in (14 cm) of seismic densifi-
cation of the fill.
Malcolm Drilling developed its
bearing support design using 3 and 7 ft
(0.9 and 2.1 m) diameter overlapped soil
cement columns to create a combined
bearing support and liquefaction
Soil mix buttress elements exposed during excavation
mitigation grid extending through the
system provided deformation and Deep Mixing meeting paper in 2012 fill and marsh soils, and 5 ft (1.5 m) into
e s t i m a t e s , a n d t h e p ro j e c t w a s by Filz and colleagues, and a 2013 the underlying dense Colma formation.
completed with actual movements FHWA deep mixing design manual. Also For the peak bearing pressure noted
within the predicted 0.1% to 0.2% of the Boulanger and Shao keynote from above, a 100% area replacement ratio
excavation depth. DFI’s 2021 Deep Mixing Conference (ARR) was used, with reduced coverage
presents a comprehensive review of of 45-55% ARR elsewhere. Soil mix
Liquefaction and Bearing recent developments in this field. walls constructed around the site
Capacity perimeter and to accommodate site
DSM use for liquefaction mitigation in Market Street Example grade changes were incorporated into
the U.S. dates back to Jackson Lake Dam Three blocks of San Francisco’s arterial the liquefaction grid pattern.
in 1987, with multiple projects since Market Street (5th to 8th) have seen 10 In a 2013 ASCE Journal of Geotechnical
then relying on its ability to construct soil mixing projects this past decade. and Geoenvironmental Engineering article,
below-grade shear structures to These mid-rise structures have used Nguyen and colleagues shared the basis
enhance slope stability and mitigate soil-mixed SOE walls for basement of the grid design, with predicted
lateral spreading. These civil structures excavation, and are either founded on performance based on ARR, strength of
include dams, wharfs and reservoirs. soil cement, depth of
However, the last decade has seen the mixed columns,
rapid adoption of these methods for cyclic stress ratio and
building projects, combining soil cyclic resistance ratio.
mixing grids for seismic mitigation and The grid configuration
permanent bearing capacity support. reduces the shear
Since soil mixing is often used for the strain imposed on
perimeter SOE of these projects too, enclosed soil and
efficient combined systems have provides a barrier to
offered commercial advantages that excess pore pressure
have accelerated DSM grid adoption in migrating from sur-
San Francisco. The development of rounding unimproved
industry-wide design standards has soils. The overlapped
also assisted nationally in applying this soil cement grid
approach. Key references include a 2011 elements are con-
USACE design guide for levees and Market St. soil mix grid layout and applied loads of approximately 1 ksf figured to remain in
floodwall stability, an ASCE Grouting (50 kPa, in blue) to over 7 ksf (335 kPa, in red) compression, in
DEEP FOUNDATIONS • JAN/FEB 2022 • 75
contrast to the bending and cracking
induced in individual elements subject
to the same loading. The selected grid
layout was integrated with the
perimeter soil cement SOE walls for the
Market Street project to provide
completed enclosed cell elements.

Conclusion
Since 2011, San Francisco has experi-
enced a massive surge in commercial
Excavated Market Street site
and residential development. Millen-
nium Tower issues and legal fallout
triggered changes to business practices, mixing systems, CSM’s combination of for soil mixing with conventional tools
local code and the review of geotech- direct down-hole monitoring, operator (multi- and single- axis and jet mixing)
nical requirements. control and variable wall thickness has continued to thrive.
As developers continued to pursue provides significant technical advan-
larger, deeper and more complex tages for most challenging SOE projects.
Rob Jameson has 30 years of geotechnical
excavations in an increasingly dense, The use of soil mix grid systems for
experience. Based in San Francisco, he oversees
constrained environment, CSM has combined bearing support and lique- engineering and technical risk management
become the preferred system to faction mitigation has become more throughout the U.S. for Malcolm Drilling
successfully execute these works. widespread, as new industry standard Company, which celebrates its 60th anniversary
Although typically costlier than references provide an accepted design this year.
conventional vertical multi-axis soil basis. In addition, the existing market

76 • DEEP FOUNDATIONS • JAN/FEB 2022

You might also like