Professional Documents
Culture Documents
3 Unit
Topic Weeks
Process services 6
Material handling 8
Revision 13
1
1
1 Chapter 1
What is Engineering? It better to ask these two precursor questions. What is Science? and What is
Technology?
Design is a creative activity, and as such can be one of the most rewarding and satisfying activities
undertaken by an engineer. It is the synthesis, the putting together, of ideas to achieve a desired
purpose. The design does not exist at the commencement of the project. The designer starts with
a specific objective in mind, a need, and by developing and evaluating possible designs, arrives at
what he considers the best way of achieving that objective; be it a better chair, a new bridge, or for
the chemical engineer, a new chemical product or a stage in the design of a production process.
In other for an engineer to create/design a solution he/she must go through basic design process
shown in Figure 1.1 and guided by constraints in Figure 1.2.
(1.1 )
Figure 1.1 The design processes.
Figure 1.2 Design constraints
Before a process design can be started, the design problem must be formulated. Formulation of the
design problem requires a product specification. If a well-defined chemical product is to be
manufactured, then the specification of the product might appear straight forward (e.g., A purity
specification). However, if a specialty product is to be manufactured, it is the functional properties
that are important, rather than the chemical properties, and this might require a product design
stage to specify the product (Seideretal.,2010; Cussler and Moggridge, 2011).
Many times, the failure of a process design project is ill defined problem. For example, in the
expansion of bio-hydrogen production. The question is do you expand the biomass drying unit or
do you purchase dry feedstock and eliminate the cost of drying.
Thus, from the initial ill-defined problem, the design team must create a series of very specific
options and these should then be compared on the basis of a common set of assumptions regarding,
for example, raw materials and product prices. Having specified an option, this gives the design
team a well-defined problem to which the methods of engineering and economic analysis can be
applied.
After formulating a well-defined formulated and clear objective, the designer must collect all the
relevant facts and data required. This includes existing design and solutions, for process designer
the process equipment performance, physical and chemical properties of chemicals involve. A
thorough search and collection of the information needed creates a foundation for successful
design. Remember progress is more rapid when there is foundation.
1.1.3 Synthesis and simulation
After the gathering of all the necessary information, the process of synthesizing and simulating the
solution(s) begins with sorting the available information. The sorting separates identifies existing
solutions which can readily be commission or deployed. Why change it if it is not broken? The
sorting can stimulate fresh ideas resulting in the synthesis of new design(s). But rarely is any design
novel, therefore, the best could be a hybrid design that improves on an old design by combining
with fresh ideas.
In a chemical process, the transformation of raw materials into desired chemical products usually
cannot be achieved in a single step. Instead, the overall transformation is broken down into several
steps that provide intermediate transformations. These are carried out through reaction,
separation, mixing, heating, cooling, pressure change, particle size reduction or enlargement for
solids. Once individual steps have been selected, they must be interconnected to carry out the
overall transformation. Thus, the synthesis of a chemical process involves two broad activities.
First, individual transformation steps are selected. Second, these individual transformations are
interconnected to form a complete process that achieves the required overall transformation. A
flowsheet or process flow diagram (PFD) is a diagrammatic representation of the process steps with
their interconnections.
The three (3) sorted and synthesized categories of solutions are subject to constraints for selection.
The designs that fail the constraints are sent back to the drawing board specifically for collection of
more information to fix the identified area of failure then they are run through the cycle again.
Design is a continuous cycle.
The designs that pass the constraints are final or feasible designs. Sometimes the many designs
could pass the initial constraint. In other to get the final design more and/or stringent constraints
could be introduced.
The development of a complete plant design requires consideration of many different factors such
as:
This is the diagrammatic representation of the unit operation and their interconnection in the
production of the chemical.
The geographical location of the final plant can have strong influence on the success of an industrial
venture. Considerable care must be exercised in selecting the plant site, and many different factors
must be considered. Primarily, the plant should be located where the minimum cost of production
and distribution can be obtained, but other factors, such as room for expansion and safe living
conditions for plant operation as well as the surrounding community, are also important.
i. Marketing Area
ii. Raw Materials
iii. Transportation Facilities
iv. Availability of Labors
v. Water supply
vi. Energy Availability (power and fuel)
vii. Climate
The process units and ancillary buildings should be laid out to give the most economical flow of
materials and personnel around the site. Hazardous processes must be located at a safe distance
from other buildings. Consideration must also be given to the future expansion of the site.
In the design of an industrial plant, the methods which will be used for plant operation and control
help determine many of the design variables. For example, the extent of instrumentation can be a
factor in choosing the type of process and setting the labor requirements.
1.2.5 Utilities
The word utility is used for the ancillary services needed in the operation of any production process.
These services are normally supplied from a central site facility and include:
i. Electricity.
ii. Steam, for process heating.
iii. Cooling water.
iv. Water for general use.
v. Demineralized water.
vi. Refrigeration.
vii. Compressed air.
viii. Inert-gas supplies;
1.2.6 Storage
i. Raw materials
ii. Intermediate products
iii. Final products
iv. Recycle materials.
v. Off-grade materials
vi. Fuels
Adequate plan must be made from the design stage of a plant on the disposal of waste generated
during the chemical production. Waste may be hazardous or non-hazardous but generally they are
nuisance. It could be through third party agent or a department setup internally.
Health and safety is paramount for the process plant community this include plant personnel,
people, animals and vegetation living around the process plant and the process plant (facility) itself.
The design team should give priority for health and safety in site location, identify possible hazard
units and develop programs and training to highlight importance. Furthermore, regular assessment
of risk should be carried out.
i. Fire
ii. Explosion
iii. Toxic release
The process design team should consider all the flow of materials in, within and out of the process
plant and review subject to:
i. Toxicity
ii. Flammability
iii. Reactivity
iv. Transportation
2
2
2 Chapter 2
1.3 Introduction
• Material balance
• Sizing of equipment
• Energy balance
• Service requirement
• Manual calculation
• Computer-aided (Aspen Plus, Hysys, PRO-II)
• Hybrid computation
Flow-sheet is the working document of a process engineer, therefore, the presentation must be
clear, comprehensive, accurate and complete.
• Block diagram
• Pictorial representation
• Presentation of stream flow-rates
1.5.1.1 Block Diagram
We will use Workout or Class activity 2.1 to demonstrate Mass and Energy balance of a Process
Flow Diagram.
In the production of Acetic-anhydride two reactors were used. Acetone (1035K, 1.6 atm) achieved
75% conversion to Ketene and Methane in a plug flow reactor (operates adiabatically, length 3m,
diameter 1m) and the outlets stream was further separated in a rectifier to remove excess acetone
follow by a distillation column to separate ketene from methane. The ketene (25oC, 1 bar) was feed
into the second CSTR reactor (50oC, 0.2 bar, volume 20m3) where acetic acid (25oC, 1 bar) reacts
with Ketene to form the desired product. Assume all acetone are recycled back to the feed.
Question
Compt1 Compt…N
Name
Formulae
MW
BP
Hf
CP A
B
C
D
4. Draw the flow sheet with stream labeled with numbers for the process described.
5. Draw the table and guess the components in each stream from the description.
6. Write and balance the chemical reaction(s) in the plug flow reactor.
7. Write and balance the chemical reaction(s) in the CSTR reactor.
8. Carryout material balance on the plug flow reactor.
9. Carryout material balance on the CSTR reactor.
10. Draw the stream material balance table in kmol and kg.
11. Determine the heat of reaction for the reactions.
12. Carryout energy balance for the CSTR reactor.
13. Calculate the amount of steam or water to maintain the heat in the CSTR.
Solution
1. Acetic anhydride
2. Acetone
3. Ketene
4. Methane
5. Acetic acid
1.6.4 Tabulate the Formulae, Molecular Weight, Boiling Point, Heat of formation, Heat capacity
(A, B, C & D) of the components present in the process.
1.6.6 Draw the table and guess the components in each stream from the description.
Acetone C3H6O 1 1 1
Ketene C2H2O 1 1 1 1
Methane CH4 1 1 1
Acetic Acid C2H4O2 1 1
Acetic anhydride C4H6O 1
1.6.7 Reactions
1.6.7.1 Write and balance the chemical reaction(s) in the plug flow reactor.
1.6.7.2 Write and balance the chemical reaction(s) in the CSTR reactor.
1.6.8.3 Draw the stream material balance table in kmol and kg.
(1) (2) (3) (4) (5) (6) (7) (8)
km k km k km k km k km k km k km k km k
ol g ol g ol g ol g ol g ol g ol g ol g
C3H6 100 25 25
O
C2H2 75 75 75
O
CH4 75 75 75
C2H4 75
O2
C4H6 75
O
𝑄𝑝 = 𝐻2 − 𝐻1 − 𝑄𝑠
H1 = 0 kJ/kmol
H2 = 193661.084 kJ/kmol
Qs = 5988 kJ/kmol
Qp = 187673.08 kJ/kmol
1.6.9.3 Calculate the amount of steam or water to maintain the heat in the CSTR.
𝑄𝑝 = 𝑚𝐶𝑝 ∆𝑇 𝑘𝐽/ℎ
m = 1489.47 kg
1.7 Computer-Aided Flow-Sheeting
To present the process flow sheet problem to the computer, the basic process flow diagram,
showing the sequence of unit operations and the interconnected streams must be transformed into
an information flow diagram. Each block in an information flow diagram represents a calculation
module.
The split fraction concept allow the information flow diagram be converted into calculation module
of system of linear equations that relate the outlet stream component flows to the inlet flows.
Example 2.1
1 2 3 4 5 𝜆 g
Simplify
1 2 3 4 5 𝜆 g
1 1 0 0 0 0 𝜆1𝑘 𝑔10𝑘
j 3 0 −∝32𝑘 1 0 0 𝜆3𝑘 = 0
Acetic acid 4 0 0 0 0 0 0 75 0
Acetic Anhydride 5 0 0 0 0 0 0 0 75
Let’s solve manually for Acetone.
3
3
3 Chapter 3
The geographical location of the final plant can have strong influence on the success of an industrial
venture. Considerable care must be exercised in selecting the plant site, and many different factors
must be considered. Primarily, the plant should be located where the minimum cost of production
and distribution can be obtained, but other factors, such as room for expansion and safe living
conditions for plant operation as well as the surrounding community, are also important.
For materials that are produced in bulk quantities, such as cement, mineral acids, and fertilizers,
where the cost of the product per metric ton is relatively low and the cost of transport is a significant
fraction of the sales price, the plant should be located close to the primary market. This
consideration is much less important for low-volume production and high-priced products, such as
pharmaceuticals.
The availability and price of suitable raw materials will often determine the site location. Plants that
produce bulk chemicals are best located close to the source of the major raw material, as long as
the costs of shipping product are not greater than the cost of shipping feed. For example, at the
time of writing much of the new ethylene capacity that is being added worldwide is being built in
the Middle East, close to supplies of cheap ethane from natural gas. Oil refineries, on the other
hand, tend to be located close to major population centers, as an oil refinery produces many grades
of fuel, which are expensive to ship separately.
The transport of materials and products to and from the plant can be an overriding consideration
in site selection. If practicable, a site should be selected that is close to at least two major forms of
transport: road, rail, waterway (canal or river), or a sea port. Road transport is increasingly used
and is suitable for local distribution from a central warehouse. Rail transport is usually cheaper for
the long-distance transport of bulk chemicals. Air transport is convenient and efficient for the
movement of personnel and essential equipment and supplies, and the proximity of the site to a
major airport should be considered.
Labor will be needed for construction of the plant and its operation. Skilled construction workers
are usually brought in from outside the site area, but there should be an adequate pool of unskilled
labor available locally, and labor suitable for training to operate the plant. Skilled craft workers such
as electricians, welders, and pipe fitters will be needed for plant maintenance. Local labor laws,
trade union customs, and restrictive practices must be considered when assessing the availability
and suitability of the local labor for recruitment and training.
Chemical processes invariably require large quantities of water for cooling, washing, steam
generation, and as a raw material, and the plant must be located near a source of water of suitable
quality. Process water may be drawn from a river, from wells, or purchased from a local authority.
Power and steam requirements are high in most industrial plants, and fuel is ordinarily required to
supply these utilities. Consequently, power and fuel can be combined as one major factor in the
choice of a plant site. If the plant requires large quantities of coal or oil, location near a source of
fuel supply may be essential for economic operation. The local cost of power can help determine
whether power should be purchased or self-generated.
Electrical power is needed at all sites. Electrochemical processes (for example, chlorine
manufacture or aluminum smelting) require large quantities of power and must be located close to
a cheap source of power.
A competitively priced fuel must be available on site for steam and power generation.
1.8.7 Climate
Adverse climatic conditions at a site will increase costs. Abnormally low temperatures require the
provision of additional insulation and special heating for equipment and pipe runs. Stronger
structures are needed at locations subject to high winds (cyclone/ hurricane areas) or earthquakes.
Corrosive environments will need strong protection for the plant equipment.
4
4
4 Chapter 4
1.9
5
5
5 Chapter 5
Process Services
1.10
Mid Semester Assessment
6
6
6 Chapter 6
Material Handling
1.11
Material handling 8
7
7
7 Chapter 7
1.12
8
8
8 Chapter 8
1.13
9
9
9 Chapter 9
1.14
10
10
10 Chapter 10
1.15
Revision 13