Professional Documents
Culture Documents
ELECTRICAL SAFETY
Any questions or feedback about this Global Engineering Standard should be addressed to
the author:
J Officer, Head of Pharmaceutical Engineering, PSC Engineering and EHS
Section 7.4.4 Added the words “who are suitably qualified and
experienced with the type of switchgear and the supply
network”
“Authorised Person” replaced with “Senior Authorised
Person”
Section 7.4.5 Section re-written to be more specific,
Added text as close as possible to the point of work and to
HV work requirements,
Section 7.5.3 Precautions section re-written to be more specific,
Added text as close as possible to the point of work and to
LV work requirements,
Limited Work Certificate paragraph added,
Section 7.8 Added the words “Sections 7.3 to 7.8”
Section 7.9.1 General section added including requirement for risk
assessment; need to identify, isolate, prove dead and
earth; and reference to GES113 and SEHS standard 5.14
Section 7.9.2 Section renumbered from 7.9.1. Added requirement to
have up to date, accurate plans of cable and suitable
identification.
02 May-17 Section 7.9.3 Section added – Excavation
Section 7.9.4 Section added – Precautions
Section 7.9.5 Section added – Cable Spiking
Section 7.9.6 Section renumbered from 7.9.3
Section 7.10.1 Phasing Out paragraph re-written to include PPE
Section 7.11.2 Comments added regarding first responders and isolation
of HV substations before entry of
Emergency Response
Teams
Section 7.11.3 Comment added regarding need for sufficient oxygen
levels
Section 7.13 Cross reference updated.
Section 7.14 Cross references to SEHS standards updated
Section 7.14.1 Gauntlet details updated
Section 7.14.2 “Vacuum” added to text. Face visor added to list of PPE
Gauntlet details updated
Section 8.1.3 “Yellow phase” changed to “L2 phase”
Section 9 Updated references
Table of Contents
DOCUMENT REVISION HISTORY...................................................................................... 2
1 RATIONALE ............................................................................................... 5
2 POLICY ...................................................................................................... 5
3 PURPOSE .................................................................................................. 5
4 SCOPE ....................................................................................................... 5
4.1 Within Scope ............................................................................................................ 5
4.2 Excluded from Scope................................................................................................ 5
5 QUALITY COMPLIANCE REQUIREMENTS .............................................. 5
6 EHS COMPLIANCE REQUIREMENTS ...................................................... 6
7 ENGINEERING MANDATORY REQUIREMENTS ..................................... 6
7.1 Definitions ................................................................................................................. 6
7.2 Responsibilities and Duties ....................................................................................... 6
7.3 Hazard Identification, Risk Assessment and Management........................................ 8
7.4 General................................................................................................................... 11
7.5 High Voltage Equipment ......................................................................................... 14
7.6 Low Voltage Distribution Equipment........................................................................ 17
7.7 Plant Service Equipment ......................................................................................... 19
7.8 Work On or Near Live Conductors .......................................................................... 20
7.9 Generating Plant ..................................................................................................... 21
7.10 Cables and Overhead Lines .................................................................................... 21
7.11 Tests and Test Equipment ...................................................................................... 24
7.12 Fire Protection for Electrical Equipment .................................................................. 25
7.13 Temporary Installations Including Construction Sites .............................................. 25
7.14 Decommissioning ................................................................................................... 25
8 ENGINEERING BEST PRACTICE ............................................................ 26
8.1 Circuit and Cable Identification ............................................................................... 26
9 REFERENCES ......................................................................................... 28
APPENDIX 1 - DEFINITIONS ............................................................................................ 29
APPENDIX 2 – MODEL CERTIFICATE OF HV AUTHORISATION .................................. 33
APPENDIX 3 – HV PERMIT TO WORK ............................................................................ 34
APPENDIX 4 – LIMITED WORK / ACCESS CERTIFICATE ............................................. 36
APPENDIX 5 – HV SANCTION TO TEST ......................................................................... 38
APPENDIX 6 – HV CAUTION NOTICE ............................................................................. 40
APPENDIX 7 – MAIN HV CIRCUIT EARTH ...................................................................... 41
APPENDIX 8 – LIVE HV EQUIPMENT NOTICE................................................................ 42
APPENDIX 9 – EQUIPMENT UNDER HV ISOLATION ..................................................... 43
APPENDIX 10 – EQUIPMENT UNDER TEST “NO ACCESS” .......................................... 44
APPENDIX 11 – HV SWITCHING PROGRAM .................................................................. 45
APPENDIX 12 – EXAMPLE OF SWITCHBOARD, CIRCUIT and CABLE NUMBERING . 46
APPENDIX 13 - SAFE EXCAVATION PRACTICE ............................................................ 47
APPENDIX 14 - CABLE SPIKING ..................................................................................... 48
APPENDIX 15 – PREPARING FOR WORK ON HV EQUIPMENT .................................... 50
APPENDIX 16 - AUDIT CHECKLIST ................................................................................ 51
1 RATIONALE
The safe use and management of electricity and electrical equipment is a
fundamental requirement for all operations.
Effective electrical safety practices are essential in order to:
• ensure safe plant operation and minimise risks to the health and safety of
personnel, damage to the environment or damage to plant as a result of plant
failure
• comply with legal and regulatory requirements
2 POLICY
All electrical systems must be designed, constructed, installed, operated, maintained,
tested and inspected to prevent danger.
Only competent personnel, who have the necessary training and experience to make the
right judgments and decisions and the necessary skill and ability to carry them into
effect, must undertake work that impacts on electrical safety.
Sites must also comply with any relevant local legislation or regulatory requirements in
addition to the requirements defined in this Global Engineering Standard (GES)
3 PURPOSE
The purpose of this GES is to specify the minimum mandatory requirements and
engineering best practices relating to electrical safety at Pharma Supply Chain (PSC) and
Consumer Healthcare (CH) sites.
4 SCOPE
7.1 Definitions
A list of definitions is provided in Appendix 1. These definitions provide the sense in which
the expressions are used in this GES.
• Ensuring the GSK facility’s compliance with this Global Engineering Standard and
external regulatory requirements for electrical safety.
• Authorising individuals to work on GSK electrical systems.
This includes ensuring:
• All relevant electrical safety hazards are identified;
• Appropriate controls are selected;
• The integrity of the controls is monitored adequately;
• Continuous improvement is sought and applied.
To do this the Electrical Technical Authority must comply with requirements set out in GES
105 – Technical Authority.
ALARP (as low as reasonably practicable). To maximise their effectiveness and reliability,
controls should be selected according to the following hierarchy:
The risk assessment associated with the task must always address [as a minimum] the
following electrical risks associated with electrical related works and work in switchroom or
substation environments.
• Electric shock.
serves to provide a barrier between the wearer and the hazardous substance or reduce the
risk of exposure (e.g. static dissipative footwear).
In many cases the use of PPE to reduce exposures below local regulatory limits should only
be as an interim measure until more effective controls can be implemented”.
To comply with both EHS SG 2.01 and EHS SG 3.14, sites must risk assess all electrical
operations and where necessary specify where PPE is required. The degree of protection
provided by PPE must be commensurate with the degree of risk and must comply with local
regulations and standards.
For example, in US locations, OSHA standard 1910.335 – Safeguards for Personal
Protection sets a legal requirement for providing PPE for electrical operations. Guidelines
set out in NFPA 70E must be used to ensure compliance with OSHA Standard 1910.335.
The operation and testing of all HV equipment and LV distribution equipment must, as a
minimum, use the PPE described in the following sections.
7.4 General
• Sanction to Test
7.4.13 Contractors
All contractors whose employees are carrying out electrical work or using electrical
equipment must be provided with a copy of this standard or a Local SOP which aligns with
this Global Engineering Standard.
The contractor must ensure that his employees comply with these standards and any
local rules as a condition of the contract.
The site Electrical Engineer may forbid the use of any equipment, including test
equipment, provided and used by contractors if, in his/her professional opinion, it is
unsafe.
The person receiving the HV Permit to Work shall ensure that they and their work crew
fully understand what is written on the document, where all the Points of Isolation are and
where the Circuit Main Earths have been applied. They must also satisfy themselves that
they understand what equipment is safe to work on and what equipment is not.
At their discretion, the person receiving the permit may request a demonstration that the
equipment is safe to work on.
The person receiving the HV Permit to Work must sign the permit and its copy to
confirm that they fully understand the work to be done.
Refer to the Flow Chart of Appendix 15 for the process when preparing for work on HV
equipment.
The HV Permit to Work must define:
• the equipment on which it is safe to work
• where isolations have been made
• where earths have been fitted
• the limitations and extent of the work to be done
• the person in charge of or doing the work
• the lockout box number and key number
• further precautions to be taken
The HV Permit to Work must be retained at the work location while work is proceeding.
Where the duration of the work is more than one day, the precautions must be re-
confirmed each day before work starts to verify that the equipment is safe to work on.
An earth must be maintained on HV equipment while work is proceeding, unless the
equipment has been bodily removed from its normal live position or in cases where the
Senior Authorised Person has approved the omission of the earth for testing to be
undertaken.
HV equipment must not be made live after work until the following procedure has been
carried out:
• the authorised person in charge of or doing the work has
withdrawn their workers and signed the Clearance Section of the
HV Permit to Work to the effect that the workers have been
withdrawn, and all gear and tools are cleared from the work area
• the Senior Authorised or Authorised Person has examined the
work, has removed all earths and Caution/Safety notices applied
under the Permit and is fully satisfied that it is safe to make live
and has cancelled the HV Permit to Work
All HV Permits to Work must be retained for a minimum period of 3 years.
Limited Work/Access Certificate.
In approved cases where the work is concerned only with earthed metal parts of
equipment and no conductors are or can be exposed or where the equipment is
bodily removed from its normal live position, then there is no danger from the system and
the work can be undertaken under a Limitation of Access Document, (sometimes referred
to as a Limited Work Certificate).
The Senior Authorised Person must assess the work scope, equipment and environment
and specify when a Permit to Work is not required and a Limited Work Certificate can be
used.
purpose, the keys of which shall then be locked in a lock-out box. The lock- out
box must be locked using a suitable safety lock and the key to this lock retained
by the person issuing the Permit to Work. Individuals carrying out work on the
equipment must also apply their personal lock and personal danger tag to the
lock-out box. This follows the same process for Lock-Out / Tag-Out (LOTO) as
described in GES 110 – Machinery Safety.
• where the equipment could be charged by mutual inductance, earths must be
provided at the point of work.
An Authorised Person must ensure that all the above steps have been properly carried
out and that the equipment to be worked on is safe. The Authorised Person must also
ensure that danger notices have been prominently displayed on adjacent live equipment.
The Authorised Person must then issue a Permit to Work to the person in charge of or
doing the work.
All LV isolations must be demonstrated to the permit receiver(s) to prove the isolation is
secure. The person receiving the Permit to Work must sign the permit and its copy to
confirm that they fully understand the work to be done and on which equipment they are
permitted to work.
The Permit to Work must define:
• the equipment on which it is safe to work
• where isolations have been made
• where earths have been fitted, if any
• the limitation and extent of the work to be done
• the person in charge of the work
• the lockout box and key number
• further precautions to be taken
The Permit to Work must be retained at the work location while work is proceeding.
Where the duration of the work is more than one day, the precautions must be re-
confirmed each day before work starts to verify that the equipment is safe to work on.
All work areas must be checked at the start of any work activities to ensure conditions
have not changed from those identified on the permit.
LV distribution equipment must not be made live after work has been done until the
following procedure has been carried out:
• the person in charge of or doing the work has withdrawn their workers and
signed the Clearance/Complete section of the Permit to Work to the effect
that the workers have been withdrawn, and all gear and tools are clear
• an Authorised Person has examined the work, has removed all earths
(where fitted) and temporary notices and is fully satisfied that it is safe
to make live and has then cancelled the Permit to Work
7.8.1 General
Work must not be carried out on or near exposed live HV conductors forming part of the
electrical distribution system.
Work on or near any exposed live LV conductors must not be carried out unless it is
absolutely necessary.
Note:
Work on equipment protected to IP2X does not constitute live working.
Where necessary to prevent danger, suitably insulated barriers or screens must be used
during live working.
Approved insulating mats, tools and test equipment must be used as necessary to
prevent danger.
ELV systems (other than battery systems as defined by the Electrical Engineer) are
exempt from these live working procedures.
7.10.1 General
Before any intrusive work is undertaken on cables, a task specific written Risk Assessment
and Method Statement must be undertaken by the authorised person for the work to be
done.
Before any work is undertaken on cables they must be clearly identified, isolated, proved
dead and earthed at the remote ends by a suitably qualified Senior Authorised or Authorised
Person. All work on cables must be done under the site Permit to Work System.
The application of the Permit to Work shall be in accordance with the requirements of
GES113 and EHS SG 5.14 Permit to Work and Safe Systems of Work.
It is the responsibility of all sites to ensure that they have up to date, accurate plans and
drawings of buried and hidden electrical cable routes and that cable locations are suitably
identified along their route both internally and externally to buildings.
Before work involving the driving of any stake, rod or other earth penetrating object or
commencing any excavation, the position and depth of buried cables within the vicinity must
be established using a Cable Avoidance Tool and exploratory hand digs.
Before work involving the penetration of a permanent or temporary surface, such as drilling
or cutting a cable avoidance tool or cable locating devices must be used to ensure no
electrical cables are at risk of being hit.
When using plan drawings to identify cable routes and testing to establish underground
cable routes, care should be taken to ensure that ‘pull-pits’ or cable loops that extend outside
the direct route, have been correctly identified.
7.10.3 Excavation
Once the Risk Assessment has been completed and drawings/plans and a locator device
have been used to determine the position of underground services, excavation may
proceed.
NOTE: - Hand excavation only is allowed within the vicinity of buried cables. Mechanical
excavation is not permitted with 1.5m of electrical cables.
Excavation work should be carried out carefully, following recognised safe digging practices.
i.e. See Appendix 13 for guidance on cable excavation.
The site excavation permit procedure must be followed, and an excavation permit issued.
For further information on excavation permits, see:
EHS SG 5.14 Permit to Work and Safe Systems of Work – GES113
GES 606 – Construction and Demolition Works
No person shall in any way interfere with a cable or remove any cable cover, warning tile
or other protection unless specifically authorised to do so by a Senior Authorised Person.
7.10.4 Precautions
Work on cables must comply with Sections 7.3, 7.4 and 7.5 of this GES. In addition, the
following precautions must be taken:
• The cable in question must be shown to follow the precise route
identified on the cable location plan and must bear the appropriate
circuit or cable reference
• The cable must be physically traced from its source of supply to the
point of work, the remote ends of the cable must be identified using an
approved electrical method
• For non-faulted cables, using a n approved cable detector, the
appropriate cable must first be shown to be ‘Live’ and following isolation
of the circuit shown to be ‘Dead’. The detector must be tested both
before and after the cable identification. Detectors that rely on the
detection of the electromagnetic field generated by load current should
not be used as cables may be ‘Live’ but not carrying load current
• For faulted cables where it is not possible to make them ‘Live’ by use of
an approved signal injection device connected at the point of isolation
Note: -
1. Any cable that cannot be traced along its route e.g. underground services or
congested above ground routes must be spiked if the cable is to be
cut/removed/jointed,
2. Approved Cable Spiking equipment can be either Hydraulic or Explosive Charge
type, dependent upon the size and type of cable to be spiked,
3. Cable Spiking with either of the above equipment types should not be carried out
in areas designated as explosive atmosphere areas unless the area has been
tested using a gas meter and a hot work permit is issued.
The spiking device must be applied to the cable by or under the Personal Supervision of
the Senior Authorised Person issuing the Safety Document.
The spiking operation itself shall be carried out by the Senior Authorised Person or under
their Immediate Supervision.
A Permit to Work which may also include Hot Work Permit & HV Permit where necessary
shall be issued by the Senior Authorised Person for the Spiking operation to be undertaken.
On completion of the cable Spiking, the Permit to Work which may also include Hot Work
Permit & HV Permit shall be cancelled, earths will be applied to each end of the cut cable
and a new Permit for Work shall be issued to allow work on the cable(s) to proceed.
Where local statutory regulations do not exist, a risk assessment must be completed by a
person competent in the dangers associated with overhead lines.
7.11.1 General
This section covers the use of testing equipment where the testing equipment itself can
be dangerous or where the equipment to be tested can be in a dangerous condition
by virtue of the testing procedure.
Phasing out on live HV or LV distribution equipment must only be performed by an
Authorised Person using approved test equipment and wearing appropriate PPE and the
procedure in Section 7.10.3 need not apply. This activity requires an Accompanying
Person, who must also be wearing appropriate PPE if they are near the testing activity.
7.14 Decommissioning
All new or temporary electrical supplies within a decommissioning area must be installed on
clearly marked routes or use coloured sheathing to distinguish them from redundant cabling.
The Senior Authorised Person / Electrical Engineer / Project Manager must ensure that a
survey is carried out to identify redundant main cables within a decommissioning area. All
cables found must be clearly identified on the cable schedule, drawing or record.
Where redundant cables are spiked in accordance with Section 7.9.5, significant lengths
must be removed near their source and destination. The Electrical Engineer or Project
Manager must ensure that the associated cable schedule, drawing or other record is
updated to reflect any disconnection.
Where equipment is to be removed, cables must be cut within the switchroom or substation
so that the equipment is demonstrably disconnected from the system.
Where Plant Service Equipment is to be removed, it must be managed in accordance with
the approved site procedure for dealing with removal of cable from Plant Service Equipment
and sources.
In this example, the motor control centre is located in Building 168, it is operating on a three
phase supply and it is the second switchboard or distribution board in Building 168.
From this circuit number, we know that the MCC is in Building 168, it operates on a three
phase supply on the second switchboard, motor control centre or distribution board in
that building, and that the pump is supplied from circuit 1 on that MCC.
L2
In this example, the socket outlet circuit is supplied from a single phase distribution board
located in Building 169, it is the second switchboard, motor control centre or distribution
board in the building and the circuit supplying the socket outlets is on the ‘L2’ phase. Also,
it is the first way on the distribution board.
The Class of Cable is defined by a letter and is determined by the type of circuit as
follows:
• H High Voltage Distribution
• M Medium Voltage Distribution
• P Power
• C Control
• L Lighting
• T Trace Heating
The Cable Number is a consecutive number and depends on the number of cables in the
circuit.
An example can be seen in Appendix 12.
9 REFERENCES
9.1 EHS SG 2.01 Risk Assessment and Control
9.2 EHS SG 3.14 Physical Agents
9.3 EHS SG 5.14 Permit to Work and Safe Systems of Work
9.4 EHS SG 5.16 Machinery Safety
9.5 1 03 22 GUI WW Duty Holder – Electrical Safety
9.6 GES 103 Maintenance
9.7 GES 110 Machinery Safety
9.8 GES 113 Permit to Work
9.9 GES 402 High Voltage Equipment and Systems
9.10 GES 403 Portable Electrical Equipment
GES 404 Maintenance, Inspection and Testing of Electrical
9.11
Equipment
9.12 GES 405 Earthing
9.13 GES 606 Construction and Demolition Works
9.14 OSHA standard 1910.335 Safeguards for Personal Protection
9.15 UK Electricity at Work Regulations 1989
UK HSE Publication: Working Safely Near Overhead Electricity Power
9.16
Lines http://www.hse.gov.uk/pubns/ais8.htm
APPENDIX 1 - DEFINITIONS
Accompanying Person
An assistant who:
• is in attendance during work on a system when or where his/her presence
can substantially contribute to the safety of the work being carried out
• can summon and/or render prompt assistance in the event of an emergency
• has completed an emergency first aider course
• has been trained to recognise and take the appropriate action in the event of danger
Additional Earth
Earthing equipment of an approved type applied where necessary to a system or equipment
which is already earthed.
Approved
“Approved” as applied to electrical equipment means, that:
• a certification organisation accredited by a recognised Standards Council has
certified such equipment in accordance with the requirements of
(i) GMS Global Engineering Standards; or
(ii) Other recognized documents where such Global Engineering Standards do
not exist or are not applicable; or
• such equipment conforms to the requirements of the Local Regulatory Authority
Authorised Person
A suitably qualified and experienced person, appointed to carry out certain duties, as specified
on a certificate of appointment.
Caution Notice
An approved form of notice prominently displayed and secured on the electrical equipment at
the point of isolation warning against interference.
Competent Person/Competent Personnel
A suitably qualified and experienced person appointed to carry out certain duties. e.g. a
person may work for the original equipment manufacturer or hold accreditation to work on
certain types of equipment.
Danger Notice
An approved form of notice prominently displayed on live electrical equipment prohibiting work
on that equipment, or any part of the equipment.
Electrical Engineer
An engineer who is trained and has suitable experience and skill in electrical engineering
and is fully conversant with local electrical regulations and standards in the region. The
competent electrical engineer also understands the dangers of the electrical equipment and
systems on the site.
Electrical Work
Design, construction, installation, commissioning, maintenance, testing and operation of
electrical equipment and systems.
Electrical Technician
A technician formally trained in electrical systems and equipment. The formal electrical
training allows the technician to understand the dangers and make appropriate judgment to
ensure they do not endanger themselves or others.
Equipment
Includes anything intended to be used or installed for use to generate, provide, transmit,
transform, rectify, convert, conduct, distribute, control, store, measure or use electrical energy.
Extra Low Voltage (ELV)
Voltage in a system not normally exceeding 50 volts ac or 120 volts (ripple free) dc.
Functional Testing
The measurement of circuit parameters, observation of operational performance and the
adjustment of pre-set controls where no live conductors are exposed to touch.
High Voltage (HV)
Voltage in a system normally above 1000 volts ac or 1500 volts dc.
IP2X
In accordance with IEC 60529. Protection against hazardous parts by insertion of:
• a finger (a jointed test finger of 12mm diameter and 80mm length)
• a solid object of 12.5mm diameter
• a sphere of 12.5mm diameter
Isolation
Disconnection and separation of equipment from every source of electrical energy in such a
way that this disconnection and separation remains ‘effective, safe and secure’.
Live
Equipment connected to a source of electrical supply or subject to hazardous induced or
capacitive voltages. Generally, ‘live’ refers to a conductor or conductive part intended to be
energised in normal use, including a neutral conductor and conductive parts connected to a
neutral conductor.
Live Working
Work carried out on or near live conductors, where the ingress protection does not meet
IP2X (exposed to touch).
Lock-out Box
A lockable facility for holding keys, fuses etc. An example is: multi-lock box - a lock-out box
used in a multi-locking system.
Low Voltage (LV)
Means the voltage in a system normally above extra low voltage but not exceeding 1000
volts ac (or 1500 volts dc) between conductors, or 600 volts ac (or 900 volts dc) between
conductors and earth.
Multiskilled Technician
A technician possessing or trained in more than one skill or area of expertise.
NEMA
The National Electrical Manufacturers Association in the United States, which is responsible
for the development and management of the NEMA standards
NEMA Enclosure Type 1
Intended for indoor use primarily to provide a degree of protection against (hand) contact
with enclosed equipment.
Nominated Person
A person with sufficient knowledge and experience of electrical equipment, to carry out
specific duties, as specified on a certificate of appointment.
Permit to Test (Sanction to test)
A Safety Document signed by a Senior Authorised Person and given to the person doing
the testing for the purpose of making known the equipment which is to be tested and the
conditions under which such testing is to be carried out.
Permit to Work
A Safety Document signed by an Authorised Person and issued to the person in charge of or
doing the work for the purpose of making known the equipment on which it is safe to
work, specifying the work to be carried out and the actions taken to achieve Safety from the
System.
Plant Service Equipment
All LV and ELV equipment other than LV distribution equipment. This does not include any
equipment supplied from High Voltage.
Portable Electrical Equipment
Defined in GES 403 – Portable Electrical Equipment,
Equipment that is not part of a fixed installation but is intended to be connected to a fixed
installation, or generator, by means of a flexible cable and either a plug and socket, or a spur
box, or similar means. This includes equipment that is either hand-held or hand-operated
while connected to the supply, intended to be moved while connected to the supply, or likely
to be moved while connected to the supply. The electrical supply to the equipment is
assumed to be a voltage that can give a fatal shock to a person, i.e. more than 50 volts ac or
120 volts dc.
Prescribed Area
An area marked out by temporary or permanent barriers and danger notices to prevent
unauthorised access.
Project Manager
A project manager is a professional in the field of project management.
Qualified Person
A person who has the training, knowledge and ability to carry out a specific duty. Qualified is
also used to denote an academic qualification.
Safety Lock
A padlock, which has a single, unique key used to control a point of isolation.
Safe System of Work
A structured approach to carrying out jobs safely. It includes risk assessment, hazard
removal, precautions, supervision and auditing including PTWs.
Senior Authorised Person
A competent, formally trained person with adequate and suitable knowledge of site electrical
systems who is responsible for operation and administration of all electrical equipment
including High Voltage Apparatus. Responsibilities include writing and issuing and/or
verification and signature of Safety Documents for work directly on High Voltage Apparatus
and equipment or conductors.
Substation
A room/area where electricity is transformed for distribution.
Switching
Operation of circuit breakers, isolators, disconnectors and/or the application of earths.
Switching Off
The disconnection and separation of equipment from every source of electrical energy for the
purpose of work, which does not require access to exposed conductors, in such a way that this
disconnection and separation remains ‘effective, safe and secure’.
Switching programme
A schedule of switching operations on distribution equipment on which the date, time and
person carrying out the operation is recorded.
System
An electrical system in which all the electrical equipment is, or may be, electrically connected
to a common source of electrical energy, and includes such source and such equipment.
System includes circuits, cables, overhead and underground services, electrical and
electronic equipment, irrespective of the applied or produced voltage and whether battery
or mains powered.
CERTIFICATE OF HV AUTHORISATION
Part A: Details
Name: Date:
I acknowledge receipt of this certificate of HV Authorisation and hereby declare that I have read and fully
understood GES 406 Electrical Safety and associated documentation. I agree to carry out the duties as
specified defined in Parts C – E.
Signed: Date:
Part G: Issue
I hereby authorise [Insert Name] to carry out duties as [Level of Authorisation] in accordance with the GES 406
Electrical Safety and as specified defined in Parts C – E.
Signed: Date:
Key Number:
HV PERMIT TO WORK
I hereby declare that the following High Voltage Apparatus in the area specified is dead, Isolated
from all Live conductors and is connected to Earth:
SAFETY LOCKS and CAUTION NOTICES have been posted at all points of
isolation. Further Precautions:
1. RECEIPT: I accept responsibilities for carrying out the testing on the Apparatus detailed on
this Permit to Work and no attempt will be made by me or by people under my charge to
work on any other Apparatus or in any other areas.
Note: After signing the receipt, this Permit to Work shall be retained by the Person in charge
at the place where the work is being carried out until work is complete and the clearance
section is signed.
2. CLEARANCE
The work for which this Permit to Work was issued is now suspended* / completed* and
all people under my charge have been withdrawn and warned that it is no longer safe to work
on the Apparatus detailed on this Permit to Work
3. CANCELLATION
1. ISSUE: in
charge of the work.
Location:
2. RECEIPT: I accept responsibilities for carrying out the work on the Apparatus
detailed on this Access Certificate and no attempt will be made by me or by people
under my charge to work on any other Apparatus or in any other areas.
Note: After signing the receipt, this Access Certificate shall be retained by the Person in
charge at the place where the work is being carried out until work is complete and the
clearance section is signed.
1. CLEARANCE
The work for which this Access Certificate was issued is now suspended* / completed* and
all people under my charge have been withdrawn and warned that it is no longer safe to work
on the Apparatus detailed on this Access Certificate.
2. CANCELLATION
Key Number:
I hereby declare that the following High Voltage Apparatus in the area specified is dead, Isolated
from all Live conductors and is connected to Earth:
These Earths may be removed and reapplied as necessary while the sanction is in force
The points of isolation are:
SAFETY LOCKS and CAUTION NOTICES have been posted at all points of
isolation. The following testing has to be carried out:
1. RECEIPT: I accept responsibilities for carrying out the testing on the Apparatus detailed on
this Sanction to Test and no attempt will be made by me or by people under my charge to
work on any other Apparatus or in any other areas.
Note: After signing the receipt, this Sanction to Test shall be retained by the Person in charge
at the place where the work is being carried out until work is complete and the clearance
section is signed.
2. CLEARANCE
The work for which this Sanction to Test was issued is now suspended* / completed* and
all people under my charge have been withdrawn and warned that it is no longer safe to work
on the Apparatus detailed on this Sanction to Test
3. CANCELLATION
LIVE
HV EQUIPMENT
“Permit to Work”
“Sanction to Test”
LIVE
TESTING IN PROCESS
ACCESS ONLY TO
HV SWITCHING PROGRAMME
Sheet 1 of 2
ITEM LOCATION EQUIP. IDENTIFICATION OPERATION TOOLS & EQUIPMENT REQ’D TIME & DATE OPERATOR
Hydraulic excavating equipment and hand-held power tools are the main source of damage to cables
and danger to personnel and they should not be used close to underground services.
Trial holes should be dug as required using hand tools to confirm the position of any buried services.
Special care should be taken when digging above or close to the assumed lines of any cable routes.
Hand tools, incorrectly used, are a common cause of accidents. However, if they are used carefully
and if the approximate position of cables has been determined using plans and locators, these tools
provide a satisfactory method for exposing underground services.
• They should not be thrown or spiked into the ground. Rather, they
should be eased into the ground with gentle foot pressure.
• Picks, pins or forks may be used with care to free lumps of stone and
other materials and to break up hard layers.
• Picks should not be used in soft clay or other soft soils in areas close to
buried services.
If excavation work is being undertaken in the vicinity of live cables, then the use of insulated hand tools
is strongly recommended.
As a minimum, all tools and implements used for excavating cables must be fitted with insulated
handles
Note:-
1. Any cable that cannot be traced along its route e.g. underground services or
congested above ground routes must be spiked if the cable is to be
cut/removed/jointed,
2. Approved Cable Spiking equipment can be either Hydraulic or Explosive Charge
type, dependent upon the size and type of cable to be spiked.
3. Cable Spiking with either of the above equipment types should not be carried out in
areas designated as explosive atmosphere areas unless the area has been tested
using a gas meter and a hot work permit is issued.
As final verification of the cable being identified correctly and dead and, subject to the requirements
of (i) or (ii) below, the cable must be spiked using an approved spiking device at any point at which
the cable is to be cut.
The spiking device must be applied to the cable by or under the Personal Supervision of the Senior
Authorised Person issuing the Safety Document.
The spiking operation itself must be carried out by the Senior Authorised Person or by a suitably trained
and experienced Authorised person under their Immediate Supervision.
Exemption from Spiking: -
The cable may be cut without the requirement for the cable to be spiked, if it is established that there
can be no error in the identification of the cable by it being physically traced over its whole length from
the point of work to:
i. A termination where either an Earth is applied, or the terminal
switchgear/apparatus has been proved not Live; or
ii. A point on the cable which has previously been identified and the conductor
has been traced from its terminations to this point,
Procedure for Spiking of Cables: -
The purpose of cable spiking is to prove that the cable spiked is not ‘Live’.
While spiking provides evidence of the state of the cable, it shall not be taken as sole proof of the
identity of the cable.
Normally a Sanction to Test should be issued by the Senior Authorised Person for the Spiking operation
to be undertaken. The wording on the Safety Document must include all actions necessary to complete
the required tests, e.g. carry out cable identification, establish insulation conditions before and after
spiking, identify cable cores after cutting.
The spiking device shall be of an Approved type and shall be used in accordance with the relevant
manufacturer’s instructions.
1) Caution: Use of an explosive cartridge type of Spiking Gun shall only be undertaken by a Senior
Authorised Person trained in its use and the operation shall always be carried out remote from
the device using a lanyard.
2) Use of a Hydraulic type of Spiking Gun shall only be undertaken by a Senior Authorised Person
who is trained in its use and the operation must be carried out remote from the spiking device.
3) The insulation condition of the cable cores should be checked before carrying out the Spiking
exercise.
4) Primary earths should then be applied to each end of the identified cable prior to Spiking the
cable(s).
5) After spiking, the insulation conditions of the cable cores shall be re-checked to from the ends
of the cable to ensure that the cable to be worked on has been shorted to earth by the spike. If
no change of insulation conditions is evident, consideration shall be given to the possibility that
either:
a. The wrong cable has been spiked in which case the procedure shall be suspended
and consideration given to the possibility that the cable that has been spiked is
the wrong cable; or
b. The spike has not penetrated the cores of the cable, in which case a further spiking
operation with a second spiking device shall be undertaken. Insulation conditions
shall again be re-checked to ensure that the cable to be worked on has been
shorted to earth by the spike. If there is still no change in insulation conditions and
there is any doubt as to whether the cable is HV or LV, the spiking device and the
cable shall be treated as ‘Live’. The Primary Earths shall be re-applied. If the
spiked cable is assumed to be a low voltage cable, local network checks shall be
carried out to ascertain if any supplies have been lost due to tripped circuit
breakers or blown fuses.
6) Site Operations should be checked after the cable has been spiked to ensure that no protection
devices have operated, and no areas have been disconnected from supplies as a result of the
spiking
7) The Primary Earths must be re-applied to the cable ends and secured before the spiking device
is removed from the cable,
8) The cable may now be cut by the Senior Authorised Person, or by an Authorised Person under
the Personal Supervision of the Senior Authorised Person. The initial cut into the cable must be
carried out using a hydraulic cutter head with a foot pump or battery-operated unit to remove
the person cutting the cable as far from the location as is reasonably practicable.by, or under
the Personal Supervision of, the Senior Authorised Person issuing the Safety Document. This
also applies to the first cut into each core of a group of single core cables.
9) Subsequent cuts into the cable may be carried out by, or under the Personal Supervision of the
Safety Document recipient, providing that the cable can be physically traced from the proposed
cut to a point as per (i) or (ii) above.
Identification of cables or cores through visual tracing is not acceptable if the cable is hidden from view
for any distance, no matter how short.
The positively identified cable must be suitably marked by paint or tape or similar means at the point
of work by the Senior Authorised Person issuing the Permit to Work prior to work commencing on the
cable(s).
When single core cables which are part of the same circuit are to be worked on, every core to be
worked on must be spiked.
Once the cable spiking has been completed the Sanction to Test should be cancelled and a Permit to
Work shall be issued to allow work on the cable(s) to proceed.
YES
The work must be done under NO Can the risks be controlled under a
a Permit to Work document Limited Access Certificate or an SOP?
YES