Professional Documents
Culture Documents
Cronograma Valorizado
Cronograma Valorizado
CONSULTOR: V°B°
ING. FRYDA
"CONSTRUCCIÓN DE PAVIMENTO; EN EL (LA) AV. SAN MARTIN ENTRE LA AV. ATAHUALPA Y AV. HÉROES DEL CENEPA SECTOR 13 - SAN MARTIN DISTRITO DE CAJAMARCA,
MARIA DEL
PROVINCIA CAJAMARCA, DEPARTAMENTO CAJAMARCA", CÓDIGO ÚNICO DE INVERSIONES N° 2486765 MP. DE CAJMARCA
CARMEN GYGLI
REINA
DISTRITO:CAJAMARCA CIUDAD:CAJAMARCA CALLE:AV. SAN MARTIN ENTRE AV. ATAHUALPA Y AV. CENEPA
CRONOGRAMA FISICO - FINANCIERO (VALORIZADO)
MES Nº 01 MES Nº 02 MES Nº 03
MET. COSTO
ITEM DESCRIPCION UND PARCIAL COSTO COSTO COSTO TOTAL
TOTAL UNITARIO % AVANC % AVANC % AVANC
PROGR. PROGR. PROGR.
01 PAVIMENTO ASFALTICO, MEZCLA EN CALIENTE 1,783,277.07
01.01 OBRAS PROVISIONALES 93,635.14
CARTEL DE IDENTIFICACION DE OBRA CON VINIL
01.01.01 und 2.00 1,584.98 3,169.96 100.00% S/ 3,169.96 S/ - S/ - S/ 3,169.96
ADHESIVO (4.80 x 3.60 m)
01.01.02 MANTENIMIENTO DE TRANSITO GLB 1.00 5,842.20 5,842.20 100.00% S/ 5,842.20 S/ - S/ - S/ 5,842.20
01.01.03 CASETA DE GUARDIANIA Y ALMACEN m2 100.00 84.20 8,420.00 100.00% S/ 8,420.00 S/ - S/ - S/ 8,420.00
01.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 37,412.86 37,412.86 100.00% S/ 37,412.86 S/ - S/ - S/ 37,412.86
01.01.05 SERVICIOS DE BAÑOS PORTATILES mes 3.00 1,661.02 4,983.06 100.00% S/ 4,983.06 S/ - S/ - S/ 4,983.06
01.01.06 TRAZO Y REPLANTEO m2 31,893.45 1.06 33,807.06 100.00% S/ 33,807.06 S/ - S/ - S/ 33,807.06
01.02 MOVIMIENTO DE TIERRAS 77,479.90
01.02.01 DEMOLICION DE LOSAS DE CONCRETO m3 98.28 94.59 9,296.31 100.00% S/ 9,296.31 S/ - S/ - S/ 9,296.31
01.02.02 EXCAVACION DE BASE GRANULAR EXISTENTE m3 109.20 54.44 5,944.85 100.00% S/ 5,944.85 S/ - S/ - S/ 5,944.85
01.02.03 NIVELACION Y COMPACTACION DE SUB RASANTE m2 545.98 8.82 4,815.54 100.00% S/ 4,815.54 S/ - S/ - S/ 4,815.54
01.02.04 LIMPIEZA Y DESCOLMATACION DE CUNETAS m 826.95 23.87 19,739.30 100.00% S/ 19,739.30 S/ - S/ - S/ 19,739.30
01.04.02.04 CARPETA ASFALTICA EN CALIENTE E=3" m2 22,809.30 52.02 1,186,539.79 S/ - 75.00% S/ 889,904.84 25.00% S/ 296,634.95 S/ 1,186,539.79
01.05 OTROS 32,570.16
01.05.01 NIVELACION DE TAPA DE BUZON und 53.00 430.11 22,795.83 100.00% S/ 22,795.83 S/ - S/ - S/ 22,795.83
01.05.02 SELLADO DE JUNTAS DE DILATACION EN PAVIMENTO RIGIDOm 587.14 9.66 5,671.77 100.00% S/ 5,671.77 S/ - S/ - S/ 5,671.77
02.05 SELLADO DE JUNTAS DE DILATACION EN SARDINELES m 16.70 9.66 161.32 100.00% S/ 161.32 S/ - S/ - S/ 161.32
03 SEÑALIZACION 93,265.05
03.01 SEÑALIZACION HORIZONTAL 57,486.25
03.01.01 PINTURA LINEA DE EJE DE VIA m 1,320.00 5.79 7,642.80 S/ - S/ - 100.00% S/ 7,642.80 S/ 7,642.80
03.01.02 PINTURA EN SARDINELES m2 1,890.85 13.94 26,358.45 S/ - S/ - 100.00% S/ 26,358.45 S/ 26,358.45
03.01.03 PINTURA SEÑALIZACION CRUCE PEATONAL m2 1,215.25 13.94 16,940.59 S/ - S/ - 100.00% S/ 16,940.59 S/ 16,940.59
03.01.04 PINTURA SIMBOLOS Y LETRAS m2 469.47 13.94 6,544.41 S/ - S/ - 100.00% S/ 6,544.41 S/ 6,544.41
03.02 SEÑALIZACION VERTICAL 35,778.80
03.02.01 SEÑALIZACION TIPO R-1 und 10.00 498.98 4,989.80 S/ - S/ - 100.00% S/ 4,989.80 S/ 4,989.80
03.02.02 SEÑALIZACION TIPO R-14A und 44.00 699.75 30,789.00 S/ - S/ - 100.00% S/ 30,789.00 S/ 30,789.00
04 EQUIPAMIENTO 54,907.70
04.01 PARADERO DE 3.60M x 1.60M und 10.00 3,519.79 35,197.90 S/ - S/ - 100.00% S/ 35,197.90 S/ 35,197.90
04.02 REJILLA METALICA 0.70X1.50M und 55.00 358.36 19,709.80 S/ - S/ - 100.00% S/ 19,709.80 S/ 19,709.80
05 SEGURIDAD, SALUD DURANTE EL TRABAJO 37,293.94
05.01 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 346.03 346.03 100.00% S/ 346.03 S/ - S/ - S/ 346.03
05.02 EQUIPOS DE PROTECCION INDIVIDUAL GLB 1.00 3,509.79 3,509.79 100.00% S/ 3,509.79 S/ - S/ - S/ 3,509.79
05.03 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 416.92 416.92 100.00% S/ 416.92 S/ - S/ - S/ 416.92
05.04 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00 491.53 491.53 100.00% S/ 491.53 S/ - S/ - S/ 491.53
06.01 REGADIO DE VIA Y ELIMINACION DE DESMONTE DIARIO m2 22,809.30 0.31 7,070.88 33.33% S/ 2,356.96 33.33% S/ 2,356.96 33.33% S/ 2,356.96 S/ 7,070.88