You are on page 1of 7

Status of draw control

practice and waste Management


at Cullinan diamond mine
Gert van Hout, De Beers Consolidated Mines, Technical Support Services, Operations Geotechnical
Stephen Allen, Mark Breed, John Singleton, De Beers Consolidated Mines, Cullinan Diamond Mine

Abstract
Cullinan Diamond Mine (previously known as Premier Mine) currently employs two mechanized block caves and plans
another extraction level at approximately 900 m below surface. As with all major block cave operations, challenging
situations and difficult events occurred during the implementation phase, unforeseen throughout the project feasibility
study. The panel caves in the kimberlite pipe have experienced problems of various types that caused deviations from the
original planned mining sequences. In combination with (the traditional) production pressures, numerous problems
resulted in not achieving good Draw Control practice. A drastic change to the weekly Draw Control planning was
introduced with the buy-in from production personnel and mine management. In conjunction with the improved Draw
Control practice, an innovative but simple waste determination process has been developed and implemented. Both the
Draw Control and the Waste Management at Cullinan Diamond Mine are currently based on ‘back to basics’ principles,
straightforward and not controlled (yet) by impressive computer programs. This paper describes some of the geotechnical
and practical related difficulties that were encountered during the implementation phase and how those were tackled with
varying degrees of success. The importance and impact of Draw Control and Waste Management on the overall mine
performance is illustrated.

1 INTRODUCTION risks dictating Draw Control at many other sites are not
discussed.
Cullinan Diamond Mine (previously called Premier Mine)
started mining diamonds in 1903. The kimberlite pipe, the 2.1. Avoid premature gabbro dilution
largest in South Africa is cut by a flat dipping 75 m thick Draw Control is very crucial in avoiding early ingress of
gabbro sill at approximately 400 m below surface, shown in the overlying gabbro waste as this premature dilution would
figure 1, together with the position of current mining blocks. reduce the overall ore recovery and shorten the life of cave.
Mining above the sill was initially open cast mining, later Right from the Feasibility Study stage for BA5 and BB1E
long hole benching (early 60’s) and block caving (late 60’s). onwards, fragmentation of the kimberlite was predicted to
Below the sill, resources in the BA5 and BB1E mining blocks be coarse and that of the overlying gabbro sill to be fine
are currently exploited by retreat panel caving. BA5 and (Rood and Bartlett, 1994).
BB1E presently have a combined production of At Cullinan Diamond Mine, it is anticipated that a recovery of
approximately 13,000 tons per day. In BA5, mining started 85 percent of the in situ ore can be achieved if proper Draw
in 1988; 130 m below the gabbro sill and this mining block Control is exercised. Poor draw practice results in a much lower
has a current life of mine until 2005. It is anticipated that the ore recovery rate as drawpoints will be forced to close earlier
BB1E, where production started in 1996 approximately 230 than anticipated for two possible reasons. Firstly, cut-offs due
m below the sill, will cease operations in 2009. In 2005, the the influx of gabbro into the drawpoints adjacent to ‘overdrawn’
mine plans to start producing kimberlite ore from the BB1E drawpoints occurs much earlier than planned. Secondly,
Advanced Undercut Cave providing interim tons until the inconsistent draw practice stimulates migration of material over
Centenary Cut (previously referred to as C-Cut) commences considerable vertical and horizontal distances, inducing the
mining at approximately 900 m below surface and starts premature mixing of waste with ore, especially as gabbro
production in 2009. fragments are fine and would thus move through the column
Draw Control in the current block caves BA5 and BB1E quickly, (Bartlett, 1998). To compound matters, it was found that
has always been regarded as strategic (Rood & Bartlett, the kimberlite fines percentage (a function of kimberlite
1994, Bartlett & Nesbitt, 2000, Nesbitt & Vorster, 2000). A accelerated weathering) was underestimated at the time of
great deal of effort and capital have been spent over the initial block cave feasibilities in the mid 80’s (BA5) and early
years on infrastructure, computer programs and other tools 90’s (BB1E).
to monitor the drawn volumes from the cave blocks. There
are several reasons to understand why Draw Control is 2.2. Minimise gabbro into plant headfeed
considered important, not only at Cullinan Diamond Mine The gabbro not only sterilises the drawn ore but also
but also at most caving operations worldwide. causes problems at the Dense Media Separator in the
diamond recovery plant due to its high specific density.
2 VITAL REASONS FOR DRAW CONTROL
2.3. Reduce risk of ore recompaction
Cullinan Diamond Mine hasn’t experienced serious mud Lack of good Draw Control results in static columns of
rushes or seismicity and therefore these two supplementary cave rock, resulting in ore re-compaction, generating point

Massmin 2004 Santiago Chile, 22-25 August 2004 491


2.5. Optimal ore fragmentation
Uneven draw or drawing at too rapid a rate may lead to
very coarse fragmentation, poor grade control and severe
waste dilution. As mentioned before, coarse ore
fragmentation and fine waste fragments induce rapid
gabbro waste movement from the top, through the column,
to the drawpoints, thereby sterilising the drawpoint
prematurely and creating problems at the recovery plant.
It has often been observed that drawpoints with coarse
fragmentation were subjected to draw, far above the call
allowed by the maturity rules. If material is drawn too
quickly, there is not enough ‘residence time’ for the
kimberlite material: there is a lack of mechanical interaction
between the ore fragments and insufficient communition of
primary fragments as material gravitates down the cave
column.

Figure 1: Diagrammatic plan and section of the kimberlite


pipe showing geology and mining blocks.

loads on the extraction level that damage the production


infrastructure. In kimberlite, if the draw of ore occurs more
than three months after the undercut has taken place, the
material in the drawbell and above the major apex may
compact. This ore re-compaction creates uneven loading
conditions on the extraction level or excessive localised
stresses that adversely affect tunnels. This becomes
apparent as support integrity worsens or when tunnels
collapse. Experience in the BA5 and BB1E caves shows
localised re-compaction of kimberlite becoming a major
issue when the drawpoint was closed for rehabilitation for
more than six weeks. Re-opening of compacted drawpoints
requires a high level of secondary blasting, further
damaging the brow area and in some cases it has taken as
long as eight weeks to re-open a drawpoint.

2.4. Maximum Draw Zone Interaction


In both the BA5 and BB1E, the offset herringbone
drawpoint layout (figure 2) was used with the drawpoint Figure 2: Interaction modes (a: isolated, b: interaction within
spacing across the major apex ranging between 24.2m to drawbell and c: interaction across minor apex)
24.7m, possibly creating interaction problems across the
major apex in some areas as the Isolated Draw Zone (IDZ)
varies from 9m to 11m, depending on the kimberlite rock Large blocks cause high hang-up frequencies in the
type. drawpoints, create problems in the ore handling system
Figure 2 shows the zones of draw at the three different and have a negative effect on the productivity as well as
draw interaction modes according to Laubscher (2000). If on the operating costs. Removal of drawpoint hang-ups
drawpoints draw in isolation, (the horizontal section of) the may result in long down-time and are costly because of
zone of material affected by this draw can be approximated the secondary breaking requirements. Oversized ore
by a circle with a diameter equal to the IDZ. If there is even blocks in the drawpoints must be reduced to reasonable
draw between the two drawpoints within the same drawbell, sizes that can be handled by the load-haul-dump (LHD)
the affected area has an elliptical footprint, one and a half machines.
times larger than the IDZ. When there is interaction between Back analysis of hang-up data during the period between
adjacent drawbells, the zone of influence enlarges another July 1998 and May 2000 (Rahal and Smith, 2000) revealed
one and half times. that in any given shift, 34 percent of the available

492 Santiago Chile, 22-25 August 2004 Massmin 2004


drawpoints are hung up and that the vast majority of these such as LHD availability, ore pass capacity, haulage and
hang-ups were cleared within one day. hoisting capability. The next draw control related concept
established was that of the ‘ideal depletion surface’. A
3 THE HISTORY OF DRAW CONTROL SYSTEMS predetermined ideal depletion sequence up until the life of
EMPLOYED AT CULLINAN DIAMOND MINE draw determines the short-term (week) draw schedule in
that the plan attempts to come as near to the ideal depletion
To impose Draw Control on the current mining blocks, state as possible. At any stage, mining is in function of the
various systems and software packages were implemented. ideal depletion profile and the call per drawpoint is
Some systems had more success than others. influenced by its draw history (corrective call when there
A comprehensive Draw Control system should at least was poor draw in the past).
consist of an integrated system of three major components: Planning on a monthly and weekly basis was also carried
an accurate and dynamically updated ore resource out using spreadsheets. These files produced satisfactory
database, a reliable vehicle monitoring system and a output as it catered for the input of all parties involved in
planning system. Draw Control. It was rather cumbersome to use but has
served its purpose to stimulate interaction between
3.1. Ore Resource database geotechnical, mining and mineral resource management
The very first version of PC-BC, developed for Cullinan departments. Regular meetings were held between these
Diamond Mine in 1988, was cumbersome to use: it took a departments to agree upon the monthly production plan
long time (2 to 3 hours) to deplete all drawpoint loads on a produced by these excel files but adherence to this plan
daily basis and it did not have the fine graphics displayed by could be improved.
the present version. After some time, mine personnel moved
towards spreadsheet type applications to store daily 4 DISCUSSION OF CURRENT
production data from the drawpoints. Later, a Microsoft DRAW CONTROL PRACTICE
Access database was employed to store the drawn volumes
in combination with the status of each drawpoint. A user 4.1. The Integrated Draw Control System
interface was then developed to present this data in a In 1999, the ‘Integrated Draw Control System’ (IDCS) with
graphical format and to allow management to extract a Mixed Integer Linear Programming (MILP) component
comprehensive summary reports. This application called described by Guest et al , 2000 was introduced on mine.
BLOCINFO, also permitted the user also to reconcile the The long and medium term schedule program based on
drawpoint production figures with the tons recorded by the the MILP was originally developed at Koffiefontein Mine for
treatment plant. its Front Cave (Hannweg and van Hout, 2001), and is
In 1999, MinRAS an SQL based product that also currently being used in the BB1E Advanced Undercut at
contained the mixing algorithms, enabling the Mineral Cullinan Diamond Mine. This scheduling module is the first
Resource Manager to derive a more accurate and auditable planning optimisation tool in block cave operations that is
ore reserve statement (Guest et al, 2000). able to optimise over the life of mine as well as over multi-
time periods. It incorporates all geotechnical, mining and
3.2. Vehicle Monitoring System financial constraints, in a unique way.
Reconciling tons, calculated from the loads that are Long term production planning for the older BA5 and
recorded by the vehicle monitoring system (VMS) with the BB1E blocks is still done by the use of spreadsheets and
tons from the weightometers at the plant is essential in any does not incorporate all ore flow constraints or geotechnical
good planning or effective Draw Control program to obtain a rules, except for the draw rate limits. The reason for the
correct and representative mineral resource database. implementation of the excel files instead of MILP is
Various VMS options have been trialled at Premier threefold. Firstly, those panel caves are considered too
including a beacon system using micro-wave technology depleted to optimise according to the principles within the
(Nesbitt & Vorster, 2000) followed by a gyroscopic based MILP. Secondly, the main focus of those caves currently is
monitoring system. None of the systems were a hundred avoiding tunnel collapses occurring from vertical loading
percent satisfactory due to technical problems, as well as and keeping porosity in the areas that hasn’t experienced
resistance from production personnel who saw it as a destructive stress levels. And lastly, the MILP version
management policing tool. allowing remote access only became available late 2003.
A combination of the radio-based voice communication The current Draw Control system at Cullinan does not
(utilising the leaky feeder to establish contact between cater for planning based on maximising NPV as the grades
control room at surface and underground) and a manual in the ore columns are set to an average column value and
recording based information system, currently in use, yields the mixing algorithms do not cater for vertical mixing within
the best results. However, it requires production crews to an ore column. The choice of an average column grade is
buy into Draw Control. justified, as there is generally very little resolution in the
As Cullinan Diamond Mine has different size LHD units, assumed grade profile vertically across the massive
there is an issue with the average bucket factor applied to orebody.
derive ‘tons mined’ from ‘buckets loaded’ at each drawpoint An optimal (and in South Africa legally prescribed) plan for
and until recently, the total tons hoisted were consistently all mining operations should be based on maximum ore
larger than the value based on the recorded buckets. recovery, thus maximising tons instead of maximising NPV,
the last being a method relying rather on grade and revenue
3.3. Planning System per carat. Block cave mining is a massive mining operation
Up until 1998, Production planning at Cullinan Diamond where principles of selective mine planning, based on
Mine was founded on empirical geotechnical guidelines financial parameters, cannot determine the production plan.
(Bartlett and Nesbitt, 2000) and did not take into account the These principles may constrain the schedule but an optimal
full effect of resource and equipment availabilities. The plan is primarily based on geotechnical considerations.
empirical guidelines were derived from extensive block cave The mixing algorithms mentioned in section 3.1 were
experience at Cullinan Diamond Mine and have been developed on site to simulate the ore movements within the
described by Bartlett, 1998. cave and the parameters were calibrated successfully: the
A more pro-active approach was initiated in 1998 when predicted time of drawpoint closure in the BA5 cave was
the weekly planning also incorporated mining constraints within one month from the actual date of closure. These

Massmin 2004 Santiago Chile, 22-25 August 2004 493


mixing algorithms are still being used but it is expected that system daily (Bartlett & Nesbitt, 2000). This information, in
REBOP,(Pierce et al, 2004), will be used as the standard combination with daily production data, enables the Draw
tool to update the ore resource database. This tool should Control engineer to analyse the effect of the draw rates and
then also provide an accurate production waste ingress and draw history on the frequency and type of hang-up as well
grade profile (or carat production graph). as waste entry parameters.
Extraction rate limits at Cullinan Diamond Mine have
4.2. The back to basics approach hence been determined in terms of tonnage per day using a
Towards the end of 2002, a major drive from maturity classification, based on the accumulative
management, the ‘back to basics’ principle occurred, not production or life of draw from a drawpoint. Four classes
only in terms of ‘keeping it simple’ but of increased were established and the associated draw rates increased
adherence to the basic Draw Control rules outlined in the from a maximum of 50 tons per day for a new drawpoint to
Cullinan Diamond Mine Code of Practice, (Bartlett, 2003) a maximum of 200 tons per day for a mature drawpoint.
and ameliorating interaction between Draw Control and As can be seen in figure 4, since the end of 2002, adherence
Production Departments. Some of the simple but critical to Draw Control has improved significantly (the average
procedures for a successful Draw Control Practice are deviation in 2000 was approximately 73%). The graph displays
discussed in this section. With issues of interaction being the deviation (actual production - planned), averaged over all
inherited from design (see section 2), the main aim of the BB1E drawpoints with the weighting factor being the planned
current BA5 and BB1E Draw Control system is to draw tons. A value around 10% is considered to be very good. A
equally throughout the caves with all drawpoints in Production Factor (van Hout & Guest, 2000), based on this
production at one time and to minimise dilution from the data has not been implemented at the mine as it is felt that
gabbro sill. Future optimising codes such as the MILP are average weighted deviation is adequate enough to
seen to be not applicable simply due to the maturity status communicate how well Draw Control is adhered to.
of the BA5 and the BB1E and past Draw Control practices.
The key to the whole short-term Draw Control process
(figure 3) is the accumulation, storage, processing and
presentation of data. The key relationship is between Draw
Control and Production. The culmination of the whole
process is presented at the weekly meetings that are held
where all parties "strategise" key loading and tunnel or
drawpoint rehabilitation patterns around Draw Control.
Production and short-term planning understand that Draw
Control needs alignment to the official annual production
plan, therefore by applying correct Draw Control principles
long-term cave management and production targets can be
achieved.

Figure 4: Weighted Average Deviation (datapoints and


trendline) from the weekly Draw Control plan for BB1E cave.

Cullinan Diamond Mine personnel are confident that the


present recording, storage and presentation of actual mined
tonnages in the MinRAS is satisfactory. Initially, the actual
production per drawpoint was entered into the system on a
weekly basis. This data is now imported on a shift to shift
basis, in combination with other information associated with
the drawpoint status (produced volume, hang-up type,
waste content, remedial support status, etc.).
Presentation of the draw data is usually in graphical
format, accessible for all people involved in Draw Control to
get a clear idea of the mined tonnage profile over a user
defined period as well as of the actual drawpoint status.
Figure 5 shows an example of the weekly Draw Control plan
that has been derived on a Friday afternoon, after
consultation between Draw Control and Production. Copies
of this sheet are given to the Draw Control Officers (who
enter it into MinRAS) and Production Mine Overseers (who
distribute it to the Shift Bosses). The Mine Overseers also
write this information onto ‘Draw Control loading’
whiteboards and compare the planned tons with the actual
Figure 3: Process flow chart on Draw Control at Cullinan production data on a shift to shift basis.
Diamond Mine. Listed below are some of the more important Draw
Control production principles developed with the "back to
Draw Control Observers gather the occurrence and type basics approach" that are vigorously implemented with the
of drawpoint hang-ups and record it into the Draw Control aim of achieve correct block cave management:

494 Santiago Chile, 22-25 August 2004 Massmin 2004


• Drawpoints closest to the orebody perimeter (highly 5 WASTE CALCULATION ON SURFACE
depleted or not), are continually loaded, at a reduced rate
if necessary. This allows for porosity in the caves and 5.1. Current practice
prevents the movement of groundwater from the contact For the last five years the official measurement of global
areas to the centre of the ore body. waste percentage has been determined by taking a sample
• A strict minimum (120 tons) and maximum (1,200 tons) of approximately 50 kilograms with a plough sampler per
weekly call per drawpoint is implemented with a maximum shift on the Sortex tailings stream. The size fraction on this
daily call of 300 tons. This prevents the loading of all belt is -65mm, +32mm. The sample is washed and hand-
planned production from a drawpoint in a single shift, with sorted into three different piles: internal waste, external
no loading during the remainder of the week. waste and kimberlite. The piles are then weighed and their
• A target for the weighted average deviation (figure 4) has relative percentages calculated. Different tests have been
currently been fixed at ten percent with acceptance from carried out to ascertain that this process of waste
both production crews and senior management. determination is appropriate as the following underlying
• It is strived to achieve equal draw across the major apex assumptions could be questioned:
and continuous production per drawpoint throughout the • The waste percentage in the -65mm to +32mm range is
week. This ensures achieving a maximum zone of representative for the total size distribution of the
influence (as in figure 2c). headfeed.
• Frequent interactions between Draw Control and • One sample of 50kg material per shift is an adequate
production to communicate clearly the availability, waste representation of the entire volume fed into the plant
content and status of drawpoints to anticipate correct during that shift.
loading calls. • The waste percentage does not depend on the person
• Reducing the closure/maintenance time from six to three who performs the test.
weeks where possible, to avoid re-compaction.
The first test involved the waste analysis in the +4mm size
distribution classes. It is impossible to quickly and
accurately recognise rock types in fragments smaller than
4mm by manual visual methods. Results for this analysis
were very similar to those of the -65mm to +32mm range. It
can therefore be concluded that waste is evenly distributed
across the different size fractions and the current fragment
size range is adequate.
During the second test, samples were taken every 15
minutes from the -65mm +32mm stream. The results from
this test did not indicate that the current practice of one
sample per shift needed to be adjusted.
The last test consisted of an identical series of samples
given to four different laboratory assistants. As can be seen
in figure 6, results may vary depending on the lab assistant
but would not justify the extra cost of additional personnel.

Figure 5: Weekly Draw Plan for the BB1E block cave.

The implementation of above principles should


dramatically improve fragmentation across the caves,
creating further reductions in secondary blasting and the
possible achievement of monthly "production" targets at
acceptable waste percentage.
A secondary function of Draw Control was developed in
Feb 2002 and consists of a qualitative assessment of the
physical state of drawpoints. The system involved a monthly
rating of each drawpoint on the basis of condition, stress
damage, water and LHD damage. The ratings are
transferred onto mine plans for future analysis.
Fragmentation data in line with Laubscher’s, (2000), Rock
Mass Rating classification were added to the data Figure 6: Analytical bias due to different lab assistants
collection. The data is currently used in back analysis for the
fragmentation analysis programs in order to model future 5.2. Research and future technologies
block caves within the same ore body. Research was undertaken to identify technology that
Another Draw Control function is to maintain waste levels could recognise waste accurately in - and possibly remove
at twelve percent or below. Past sampling practices did not it from - the ore flow within a short time span. Providers of
record levels of gabbro in each drawpoint. A waste technology based on Microwave Attenuation, Infra red,
management system developed by the Mineral Resource Laser Induced Fluorescence, Natural Gamma Emission
Management department assists in the prediction of waste were approached and three different optical sorters
tons and is discussed below. underwent testing and extensive assessments.

Massmin 2004 Santiago Chile, 22-25 August 2004 495


All applications were successful in differentiating between which the plant recovery would be less optimal. Waste at
waste and kimberlite to some degree on surface (conveyor Cullinan Diamond Mine has become increasing challenging
belts) but none were suitable for underground application. over the last few years, as the current block caves become
Optical sorter technology, widely used in the food and glass older and the reserves in the block are depleting fast.
industries, proved to be the most effective method in Keeping the average waste content below a threshold has
recognising and ejecting waste from an ore stream. The historically been addressed by stopping underground
ability to eject waste from an ore stream offers obvious, drawpoints with waste content higher than 15% but this has
additional advantages in ore processing, allowing improved sterilised large portions of the kimberlite resource. Waste
flexibility, an increased ore extraction ratio by recovering problems can be controlled to some degree by blending, ore
more diamonds from previously considered non payable from various sources underground and on surface can
drawpoints, lower crushing costs and ultimately improved assist to draw higher waste drawpoints longer, thereby
revenues. maximising extraction.
Prediction and control of waste tons is a task performed
6 WASTE CALCULATION UNDERGROUND by Draw Control. Multiplying drawn tons per drawpoint with
a waste percentage and adding this for all drawpoints
To manage waste effectively, an accurate means of across the two caves represents a value that indicates the
measuring the waste percentage in each drawpoint must be expected waste tons. Initially (2002) there was an extremely
established but the following factors complicate this close match between the predicted waste tons and the
process: actual recorded waste tons. But of late, differences of 4% -
• Dust, generated by LHD’s, makes visual observations 5% have been observed, with the predicted values based
extremely difficult. on the underground results always exceeding the on
• Washing the ore in the drawpoint with water to get rid of surface determined results.
the dust settled on the muckpile can result in rapid Benefits of the current waste management system are
disintegration of the ore, thereby biasing the sample taken listed below:
to determine the waste content. • The greatest benefit from a mineral resource perspective
• There are different types of waste and different is that more accurate forecasts and estimates can be
percentages of waste within different size fractions of ore, made. Financial contribution of drawpoints can be
making the derivation of an average waste value rather established and assist in the decision making process,
difficult. together with geotechnical factors, whether or not
• The finer the fragment size the more difficult it is to drawpoints or tunnels need to be closed.
differentiate between the different waste and kimberlite • When production planning is done, the expected waste
types. The ore fragment sizes depend largely on the rock tons can be calculated for each draw scenario. On the
type and the maturity of the cave. basis thereof, optimal draw and waste percentage can be
derived. The estimated waste percentage is of great value
At Cullinan Diamond Mine waste is classified as either to the metallurgical department as unexpected and
internal or external waste. Internal waste is that which excessive high density waste negatively affects recovery
slumped back into the pipe during volcanic emplacement of efficiencies.
the kimberlite pipe and consists mainly of felsite, Waterberg • A third benefit lies in the improved understanding of the
quartzite, norite and metasediments. The internal waste migration of gabbro sill material as the cave depletes. The
also includes barren late stage carbonatite dykes. In the drawpoint waste data recorded since 2002 is still too
metallurgical process these "floats" are separated from the scarce but correlation between the column depletion
ore stream via a process of dense media separation, as status and waste percentage will be analysed to
these rock types have a lower specific gravity. determine waste ingress curves that can be used in future
External waste consists of the country rock norite and the ore depletion planning.
gabbro sill. These two rock types are mineralogically similar
and can differ only slightly in texture. The norite enters the 8 SUMMARY AND CONCLUSIONS
cave through the boundary drawpoints when country rock
blocks detach, slump down, and cuts off or sterilizes parts of Cullinan Diamond Mine has experienced Draw Control
the resource It also enters the ore flow through the tipping challenges, resulting in early waste ingress and serious
of waste development into ore passes. External waste loading onto production tunnels. After a drive from senior
fragments are known in the metallurgical process as "sinks". management for ‘back to basics’, Draw Control adherence
Their specific gravity is similar to that of diamond bearing and ground conditions have improved drastically. Several
kimberlite, and it therefore reports to the concentrate of the Draw Control procedures are outlined in this paper.
dense media separation. Waste is and always will be a mining and treatment
Before 2002, the waste content was measured by visually constraint requiring constant management to ensure
estimating the waste in each drawpoint on a daily basis. Loss optimum extraction of ore.
of historical waste data combined with the inaccuracy of visual The introduction of a system that recognises and can
estimates made it impossible to compare waste estimates from eject waste from the ore flow will reduce the constraint of
underground with the surface measurement of waste. waste on Draw Control and treatment efficiencies. Cullinan
The test work described in section 5 showed that the Diamond Mine and the greater De Beers Group are
sampling methodology used on surface yields adequate vigorously pursuing the implementation of optical sorting
waste percentage values. It was therefore decided to technology, having completed extensive testing. A full
change the underground waste determination process from feasibility study of the project is being undertaken.
the visual estimation to one similar as applied on surface.
This involves samples taken from a drawpoint, transported ACKNOWLEDGEMENTS
to a lab analysed and results are entered into a database.
The authors are grateful to all their colleagues who helped
7 WASTE MANAGEMENT UNDERGROUND and supported them during the development and
AND BENIFTS THEREOF implementation of this work, in particular AR Guest, M
As mentioned above, the waste percentage of the Preece, C Baltus, HP Grobler and PJ Bartlett. The authors
headfeed needs to be kept below a critical level, above acknowledge the permission of the Director Operations and

496 Santiago Chile, 22-25 August 2004 Massmin 2004


the Cullinan Diamond Mine, General Manager to publish • Nesbitt, K & Vorster, J.A. 2000. Premier mine Draw
this technical paper. Control and underground vehicle monitoring and control
system. Proc. VIth International Symposium on Mine
REFERENCES Mechanisation and Automation, SAIMM, 2000, Vol 1:pp,
93-96.
• Bartlett, P.J. 1998. Planning a mechanised cave with • Pierce, M., van Hout, G.J. & Singleton J 2004. Draw
coarse fragmentation in kimberlite. PhD. Thesis. Control of the BA5 cave Cullinan Diamond Mine: Back
University of Pretoria, South Africa. Analysis with REBOP. Proc. MassMin2004, Santiago.
• Bartlett, P.J. & Nesbitt, K. 2000. Draw Control at Premier • Rahal, D.C. & Smith, M.L. 2000. De Beers Site Visit,
Mine. Proc. MassMin200, Brisbane. Vol 1: pp, 485-493. unpublished internal report. Corporate Head Quarters, De
• Bartlett, P.J. 2003. Block Cave Code of Practice for Beers Consolidated Mines.
Cullinan Diamond Mine. • Rood, H.R. & Bartlett, P.J. 1994. Mechanized Caving at
• Guest, A.R., van Hout, G.J., von Johannedis, A & Premier Mine. Proc. XVth CMMI Congress,
Scheepers, L.F. 2000. An application of linear Johannesburg, SAIMM, 1994, Vol 1: pp, 219-225.
programming for block cave Draw Control. Proc. • van Hout, G.J. & Guest A.R. 2000. Production Factor and
MassMin2000, Brisbane. Vol 1: pp, 461-468. Draw Control Factor, presentation to the International
• Hannweg, L.A. & van Hout, G.J 2001. Draw Control at Caving Study.
Koffiefontein Mine. Proc. VIth International Symposium on • Malope, P. 2001, Waste distribution in different size
Mine Mechanisation and Automation, SAIMM, 2000, Vol fractions of the kimberlite ore at Premier Mine,
1:pp, 93-96. unpublished internal report, Premier Mine, De Beers
• Laubscher, D.H.L 2000. Block Cave Manual. Consolidated Mines.

Massmin 2004 Santiago Chile, 22-25 August 2004 497

You might also like