You are on page 1of 79

Caving: Back to the

Basics
Allan Moss,
General Manager
Rio Tinto Underground Technology
Theme: Back to the Basics What you
can’t measure you can’t manage

• Measurement: A quantitatively expressed reduction of


uncertainty based on one or more observations (Hubbard: How to
Measure Anything, 2010

• The key measure in the mining industry is value, generally


expressed as NPV, and is a function of metal recovery. Indeed
considerations of value dictate the plan as much dictates as
pure technical requirements
• Technical work on caving in its infancy. Thus there is a paucity
of literature on caving, particularly around cave performance
• Acknowledge the thinking of Dennis Laubscher who laid the
foundation for modern cave design

June 2011 US Rock Mechanics Symposium 2


Ore grade and value

1. The resource grade; a


measure of the metal that is
Value is a function of in the ground

Run of Mine (ROM) 2. The reserve grade, a


measure of the effectiveness
grade which is an of the design
outcome of three inter-
3. The recovered grade, a
related factors measure of how the cave is
managed and cave dynamics

June 2011 US Rock Mechanics Symposium 3


Agenda

Context – why the interest in caving

How block caving works and key technical considerations

Back to basics: Robust data and measurement of performance

Wrap-up

June 2011 US Rock Mechanics Symposium 4


Agenda

Context – why the interest in caving

How block caving works and key technical considerations

Back to basics: Robust data and measurement of performance

Wrap -up

June 2011 US Rock Mechanics Symposium 5


Greater Depths of Mining

June 2011 US Rock Mechanics Symposium 6


Trends in Mining ~ to 2013

June 2011 US Rock Mechanics Symposium 7


Trends in Mining ~ after 2013

June 2011 US Rock Mechanics Symposium 8


Why Caving?
• Use of gravity to break the rock (instead of explosives), thus low
operating cost compared with other underground methods
• High production rates can be achieved allowing economies of
scale
• Allows high degree of mechanization
• Safe
However
• High initial capital costs
• Conceptually simple – let gravity do the work - but technically
very challenging
• Requires large design effort; high quality construction; and
rigorously managed operations
June 2011 US Rock Mechanics Symposium 9
Evolution of daily production rates

New generation Caves; under construction

160000

140000
Palabora

Henderson

Homestake - S Dakota
Magma

Western Deeps
1000m

Kidd Creek
Open pits Super
120000
TONNES PER DAY

2000m

caves
3000m

100000
4000m

80000

60000 San Manuel


Climax Henderson “Conventional”
40000
Andina underground
Kiruna Olympic Dam
Palabora
Malmberget
20000 Miami Premier
Freeport IOZ/DOZ
Ridgeway
Kidd Creek
Mount Isa Salvador
0
1880 1900 1920 1940 1960 1980 2000 2020 2040
YEAR (after Brown 2004a)

June 2011 US Rock Mechanics Symposium 10


Cave Mining ~ When is it Applicable?

• Orebodies with a substantial


vertical dimension; massive
or pipe like
• Rock strength not a
limitation but need sufficient
orebody dimensions
• Primarily used in copper
mining but also
molybdenum and diamonds,

June 2011 US Rock Mechanics Symposium 11


Agenda

Context – why the interest in caving

How block caving works and key technical considerations

Back to basics: Robust data and measurement of performance

Wrap -up

June 2011 US Rock Mechanics Symposium 12


Components of a Caving Operation
Plant
Crushed Ore

Shaft
Ore body

Draw bells

Haulage
system
Production tunnels

June 2011 US Rock Mechanics Symposium 13


Terminology

Zone of Stress Pre-mining


Fracturing Conditions
(seismogenic zone)

Expansion Void
(Air gap)

Caved
Zone
Yielded Zone

(Modified from Duplancic & Brady 1999)


Direction of Advancing Undercut

June 2011 US Rock Mechanics Symposium 14


Modernisation of an Old Method

LHD
Grizzley
Block
Block
CaveCave

June 2011 US Rock Mechanics Symposium 15


Scale

June 2011
1 March 2011 US Rock Mechanics Symposium 16
Increased Production, Higher Lifts

uncertainty

reduced knowledge

limited control

well established method

good control

more certainty

June 2011 US Rock Mechanics Symposium 17


Access and Extraction Complexity
DOZ Mine – Freeport, Indonesia

GBT Area I & II

Escondida, Chile
IOZ

DOZ

Courtesy of PTFI
June 2011 US Rock Mechanics Symposium 18
Block Caving Concept
VALUE REALIZATION
CAPITAL INVESTMENT

100 %

Vyazmensky © 2007
CAVE DYNAMICS
SOURCES OF 
UNCERTAINTY

TIME
CAVE MANAGEMENT
June 2011 US Rock Mechanics Symposium 19
Caving Process • Block cave mining is based on
the principle that, once a
sufficiently large area of a block
has been undercut by drilling
and blasting, the overlying
20 block of ore will start to cave
under the influence of gravity.
Progressive spalling • The process will continue until
caving propagates through the
entire block to surface or to the
open pit above

25 35 45

1. Develop undercut level 3. Drill and blast undercut rings


2. Develop production tunnels 4. Open troughs

June 2011 US Rock Mechanics Symposium 20


Mechanics of Caving
(Itasca, MMT, 2007)
In Situ Stress
Elastic Elastic
Damage Threshold Joint Slip
Seismogenic Crack Growth
Peak Strength
Cohesive/Tensile
Yield Weakening
Residual Strength Frictional
Strengthening
Air Gap
σ1
50
Dilation, Modulus
Bulking Softening
Caved

Fully Bulked

σ3
0 10
June 2011 US Rock Mechanics Symposium 21
Key Technical Issues

cave propagation

cave flow

June 2011
cave fragmentation
US Rock Mechanics Symposium 22
Critical dimensions to initiate caving

June 2011 US Rock Mechanics Symposium 23


Fragmentation: the key to a successful
operation

June 2011 US Rock Mechanics Symposium 24


Caving the block

Primary
Index of Interruptions Frequency Fragmentation
(Salvador mine, draw point 04W20)

Secondary 
fragmentation
HoD

Initial secondary
fragmentation

Blasting effect

Blasted undercut material

Flow Interruption Index  Secondary
(events/tons x 1000) Fragmentation

June 2011 US Rock Mechanics Symposium 25


Stress Drives Fragmentation
a) Fracturing Joint extension and
creation due to stress

Dependent on: Preconditioning of ground


by caving induced stresses
¾ Rock Quality
b) Shear ¾ Caving stress
stress

Increasing Shear and fracture generation in abutment arch


KEY DRIVERS IN REDUCING FRAGMENTATION
June 2011 US Rock Mechanics Symposium 26
Fragmentation is complex: risks!!!
Primary
zone of loosening fragmentation

expansion
Secondary
void
fragmentation

fragment
size
evolution
f(fragment size)

with draw Fine material

higher
mobility of
finer
fragments
within a
draw Coarse material
column
IDZ

June 2011 US Rock Mechanics Symposium 27


Primary fragmentation increase with higher stress level

In‐situ fragmentation 20% increase in stress 40% increase in stress

30m

0.1                                      1                                   10
What do we draw?- the recovery issue
High grade ore Dilution entry

ORE BODY

$
WASTE ROCK WASTE ROCK

Vyazmensky
Vyazmensky ©
© 2008
2008 TIME
REPEAT
June 2011 US Rock Mechanics Symposium 29
Geometry of drawbells

DRAWBELLS

June 2011 US Rock Mechanics Symposium 30


Cave Flow
Zone of Loosening
(blocks that were displaced
vertically at least once)

waste

Waste
Entry
waste ore

waste
ore
ore ore

HoD
IDZ ~ Ellipsoid of Motion
(extracted blocks)
June 2011 US Rock Mechanics Symposium 31
Rilling

32
Impacts of Fragmentation

IMPLICATIONS ON PRODUCTIVITY
RESOURCE RECOVERY
SECONDARY
BLASTING

VALUE
AT RISK
June 2011 US Rock Mechanics Symposium 33
Flow dictates Revenue Stream

WASTE ROCK

CAVED ORE WASTE


ENTRY
UNCAVED cylindrical IEZ
ORE

elliptical or frustum
shaped IEZ;
height equivalent
to~100-200 mean
EXTRACTED ORE fragment size

RILLING and MASS FLOW PREDOMINATLY MASS FLOW

June 2011 US Rock Mechanics Symposium 34


What do we draw?- the recovery issue
High grade ore Dilution entry

ORE BODY

$
WASTE ROCK WASTE ROCK

Vyazmensky
Vyazmensky ©
© 2008
2008 TIME

June 2011 US Rock Mechanics Symposium 35


Complexity of Caving
Agenda

Context – why the interest in caving

How block caving works and key technical considerations

Back to basics: Robust data and measurement of performance

Wrap-up

June 2011 US Rock Mechanics Symposium 37


Production Pyramid

$
Recovery Recovery Operations

Draw strategy
& control

Reserve
Production Forecast
Design &
planning

Resource Caving Analysis

Orebody Knowledge

June 2011 US Rock Mechanics Symposium 38


Fundamentals

Monitor &
Measure

Design, Plan, Production


Forecast Knowledge

Orebody Learn &


Knowledge Modify

June 2011 US Rock Mechanics Symposium 39


Rock mass performance dominates
Monitor &
Measure

Design,
Production

value proposition
Plan,
Knowledge
Forecast

Orebody Learn &


Knowledge Modify

June 2011 US Rock Mechanics Symposium 40


Monitor &

First Stop Information


Measure

Design,
Production
Plan,
Knowledge
Forecast

Acoustic Televiewer Orebody


Knowledge
Learn &
Modify

Rock strength testing


Core Logging

Mapping

June 2011 US Rock Mechanics Symposium 41


Differences in Orebody Knowledge
Monitor &
Measure

Design,
Production
Plan,
Knowledge

therefore differences in Uncertainty


Forecast

Orebody Learn &


Knowledge Modify

Initiation point close to


surface Substantial information
No geotechnical constraints

Ore drilled and typically sampled


as part of mining process – detailed
knowledge for short term planning

Initiation point remote from surface


Limited information Substantial
geotechnical constraints

Limited knowledge of ore- sampling after the fact

June 2011 US Rock Mechanics Symposium 42


Orebody Knowledge - Factors Design,
Monitor &
Measure

Production
Plan,
Knowledge
Forecast

Orebody Learn &


Knowledge Modify

Joint Orientation SRM suite of tests


(direct tension, UCS, triaxial)
Discrete Fracture
Network (DFN)

Joint Frequency &


Persistence

Rock Mass
Properties

Intact UCS, Primary


Tensile Strength, Fragmentation
Y. Modulus
& Poisson’s ratio
Induced Fracturing vs.
Cave-induced stresses microseismicity
June 2011 US Rock Mechanics Symposium 43
Cave Performance
Monitor &
Measure

Design,
Production
Plan,
Knowledge
Forecast

Orebody Learn &


Knowledge Modify

200

180
Unconfined Compressive Strength (UCS)

160
NPM
140 PMC
Oyu Tolgoi

120

100 DOZ 0.35

0.3
Statistics
Oyu Tolgoi
(avg. UCS = 133 MPa)
Experience
Range - 35 to 190 MPa
80 Number of Data Sets - 17

Empirical
0.25 Mean - 106.1 MPa
Median - 100 MPa
Relative Frequency

Std Dev. - 48.2


0.2
60

Methods
0.15

40 0.1

0.05

20
0
20 40 60 80 100 120 140 160 180 200 205
Uniaxial Com pressive Strength (MPa)

Mine

Numerical
Methods

Error in Estimate
Estimated vs. Actual Hydraulic Radius

50

Actual Hydraulic Radius


40

30

(m )
20

Prediction of Cave 10

Performance 0
0 10 20 30 40
Estimated Hydraulic Radius (m)

June 2011 US Rock Mechanics Symposium 44


Advanced Design –
Monitor &
Measure

Numerical Modeling
Design,
Production
Plan,
Knowledge
Forecast

ELFEN CAVE PROPAGATION AND SUBSIDENCE


Orebody
Knowledge
Learn &
Modify

Evolution of vertical displacements (0.1 – 1m)

50m

Cave propagation
arrest and crown
pillar collapse

Vyazmensky, 2008
Lesson learned Monitor &
Measure

Design,
Production
Plan,
Knowledge
Forecast

Palabora
successfully Orebody Learn &
Knowledge Modify

transitioned from an
open pit to a 30,000
tpd underground
block cave but…….

dilution of the ore


reserve and
subsequent
reduction in life of
mine
June 2011 US Rock Mechanics Symposium 46
Footprint Condition - Dynamic

Stresses change as undercut passes over and


drawbell developed
Stress concentrated
in walls
Back in “relaxed” state

Experience wall
convergence as
fractured columns
of rock deform
(buckle) into panel

Zone of Stress Induced


Brittle Fracture 1-2m
47
wide
Effect of cave front advance rate

Immediate
abutment

Production
Initial
state

Constru
ction
Rock Behaviour Modes in σ - space

At UCS/10 or >10MPa for UCS >100MPa

49
Behaviour
• Observations are:
– Brittle failure dominates
– Onset and propagation occurs generally in walls and lead
to gradual de-stabilisation of back
– Indications that failure involves a surface skin of around 1
to 2m fractured rock. This is the volume of ground to be
managed
• Drivers of failure are stress; not only the major principal stress
(loading) but the minor principal stress (relaxation). Require
support systems that deal with displacements

50
Where do we Obtain Production Monitor &
Measure

Information?
Design,
Production
Plan,
Knowledge
Forecast

Orebody Learn &


Knowledge Modify

Grade Convergence
Fragmentation Number of buckets drawn

Height of Draw
Location of Cave Back
Compliance to Plan
Grade and Performance Reconciliation
June 2011 US Rock Mechanics Symposium 51
Bucket factor: An imprecise Measure Design,
Monitor &
Measure

Production
Plan,
Knowledge
Forecast

Orebody Learn &


Knowledge Modify

The LHD: One of the primary


cave management and
measuring tools!!!!!

A measure of how full a


bucket is with solid
material: Mostly a
function of material type
High bucket factor Low bucket factor
possibly > 1 likely < 1
June 2011 US Rock Mechanics Symposium 52
Monitor and Measure: Height of Draw Monitor &
Measure

and Fragmentation
Design,
Production
Plan,
Knowledge
Forecast

Orebody Learn &


Knowledge Modify

53
Monitor and Measure Design,
Monitor &
Measure

Production
Plan,
Knowledge
Forecast

Underground Tonnage Hoisted


Average Drawpoint Availability
45000
MTD Average % Cu = 0.67
0.80 100%
MTD Average = 33,546
90% Orebody Learn &
40000 Knowledge Modify
0.70 80%
70%
35000 60%
0.60
50%
30000 40%
0.50
Tonnes Hoisted

30%
25000
20%

% Cu
0.40
10%
20000
0%

X/CUT 05
X/CUT 18

X/CUT 07
X/CUT 19

X/CUT 16

X/CUT 14

X/CUT 08
X/CUT 12
X/CUT 13

X/CUT 01
X/CUT 09

X/CUT 06

X/CUT 04
X/CUT 15

X/CUT 03
X/CUT 17

X/CUT 02
X/CUT 20

X/CUT 10
0.30
15000

0.20
10000

5000 0.10 Variation from Business Plan


0 0.00
10,000
01-May-11
02-May-11
03-May-11
04-May-11
05-May-11
06-May-11
07-May-11
08-May-11
09-May-11
10-May-11
11-May-11
12-May-11
13-May-11
14-May-11
15-May-11
16-May-11
17-May-11
18-May-11
19-May-11
20-May-11
21-May-11
22-May-11
23-May-11
24-May-11
25-May-11
26-May-11
27-May-11
28-May-11
29-May-11
30-May-11
31-May-11
5,000

Variation (tons)
15 Average Tonnes Hoisted Hoisting Potential Planned Tonnes Measured Grade %Cu 0
Metal Balance -5,000 0 10 20 30 40 50 60
10
-10,000
Plan
5 -15,000 Something is
0
-20,000 happening
Week
-5

-10
1000
Higher than Shortfall realizations
-15 plan perceived Shortfall
against
perceived
05Q1
05Q2
05Q3
05Q4
06Q1
06Q2
06Q3
06Q4
07Q1
07Q2
07Q3
07Q4
08Q1
08Q2
08Q3
08Q4
09Q1
09Q2
09Q3
09Q4

GOOD plan
as BAD single
2005 2006 2007 2008 2009 realization
June 2011 US Rock Mechanics Symposium 54
IEZ = IEZ = IEZ = IEZ =
13m 12m 10m 8m

33 24 17 12
months months months months
IEZ = IEZ = IEZ = IEZ =
13m 12m 10m 8m

33 24 17 12
months months months months
Recovery? Design,
Monitor &
Measure

Production
Plan,
Knowledge
Forecast

Orebody Learn &


Knowledge Modify

Material actually recovered


due to over pulling

Material “planned” to be recovered

57
Monitor &

Must be very careful


Measure

Design,
Production
Plan,
Knowledge

with Statistics
Forecast

Orebody Learn &


Knowledge Modify

LHD availability vs. Tons Hoisted

80%
70%
L H D A v a ila b ility

60%
50%
40% Care required when examining data in isolation
30%
20%
10%
0%
0 50 100 150 200 250 300 350 400
Average Tonnes Hoisted
June 2011 58
US Rock Mechanics Symposium
Monitor, Learn, React Monitor &
Measure

Design,
Production
Plan,
Knowledge
Forecast

Orebody Learn &


Knowledge Modify

June 2011 US Rock Mechanics Symposium 59


Implications of Time to Construct Monitor &
Measure

No Feedback loop Design,


Plan,
Forecast
Production
Knowledge

Orebody Learn &


Knowledge Modify

June 2011 US Rock Mechanics Symposium 60


Agenda

Context – why the interest in caving

How block caving works and key technical considerations

Back to basics: Robust data and measurement of performance

Wrap -up

June 2011 US Rock Mechanics Symposium 61


Can’t define risk - Can’t define
value
Characterisation – the resource; understanding the size of the prize
Design – resource to reserve; time for imagination

Construction – the big spend and first taste of reality


Operation – recovery and payback

Paper (Design) Value vs. Actual Value


ƒComplete knowledge of the future is an
impossibility
ƒThe question then becomes “how
representative is the information we have on
hand?”
ƒThis information is used to develop a robust
enough plan to cater for the inherent 1,5 m

uncertainty. CONCRETE
DAMAGE

ƒUncertainty translates to risk (Flexibility CONCRETE

costs money) DAMAGE

Block caving is not for marginal projects


June 2011 US Rock Mechanics Symposium 62
The Vision – an Ore Factory

Required
Fragmentator

In Situ

Fragment Crushing
Size and Grinding

Energy
(Distance Traveled)

Reliable
Ore Flow

Predictable Ore Transport


Fragmentation and Sizing
(+ grade)

The Ore
The RockFactory
Factory

June 2011 US Rock Mechanics Symposium 63


Light at the End of the Tunnel

Summary
• Caving method relies on gravity to
break the rock sufficiently to allow
efficient transfer to surface
• Knowledge and planning is critical.
• Four steps in reliable production
forecasts:
1. Collect appropriate rock mass and
operating data
2. Turn data into information through
organising and visualising
3. Analyse and forecast
4. Monitor, reconcile and learn

Thank you for your Attention


64
IEZ = IEZ = IEZ = IEZ =
13m 12m 10m 8m
IEZ = IEZ = IEZ = IEZ =
13m 12m 10m 8m

33 24 17 12
months months months months
IEZ = IEZ = IEZ = IEZ =
13m 12m 10m 8m

33 24 17 12
months months months months
Uncertainty in Cash Flow over
Time
Stage 1: Initial Cave: 0 to 30% draw ( this will be include the
period of production build up)
Stage 2: Steady State Cave: 30 to 60% draw
Stage 3: Mature Cave: 60 to end of life draw (nominally 100%)

Stage 3 Uncertainty in Performance


Stage 2
Stage 1
Cash Flow

Base Case

Time

Uncertainty in Schedule

Stage 0 Stage 1 Stage 2 Stage 3

2 March 2010 SME March 2010 68


2 March 2010 SME March 2010 69
Case Study - Palabora mine

70
OPEN PIT CAVE MINING

• better control • reduced knowledge


• more certainty • poor control
• high uncertainty

Need for a better technology


COMPLEXITY OF CAVE MINING

KEY RISKS ARE IN


CAVE DYNAMICS
AND CAVE
MANAGEMENT
CAVE DYNAMICS: FRAGMENTATION
IMPLICATIONS ON PRODUCTION LEVEL LOGISTICS:
RESOURCE RECOVERY EQUIPMENT, MUCKING SPEED

VALUE
AT RISK

SECONDARY BLASTING
CONFIDENTIAL ©2009, Rio Tinto, All Rights Reserved 74
CAVE DYNAMICS: FLOW

BLOCK CAVE PANEL CAVE

EARLY DILUTION – POTENTIALLY LOWER AVERAGE GR


UNCERTAINTY Rock mass Cave
Uncertainty
Ore reserves &
response performance
Risk

Orebody Cave TARGET


Construction
knowledge management VALUE
PROCESS

Access:
Exploration shafts/drifts Tonnage:
(Resource) development draw rate, drawpoints
availability
Studies (Reserve) Layout:
bell construction rate
Grade

Cave ramp-up to full


production
CASH FLOW

time
UNCERTAINTY IN CAVE MINING

IN-SITU VALUE: grade ROCK MASS RESPONSE:


UNCERTAINTY A caving, fragmentation, subsidence
UNCERTAINTY B

CAVE FLOW:
UNCERTAINTY C

MINING INPUT:
undercutting,
material extraction rate OUTPUT - VALUE:
(stress, void) tonnage, grade
UNCERTAINTY D UNCERTAINTY f(time)=A*B*C*D
RILING ANIMATION
Caveability

Notes: mines in database


1.Palabora
2.North Parkes
3.Premier
4.Esmerelda
5.Andina
6.Salvador
7.Henderson
8. DOZ
Bingham
9.Finsch
10.Blanco
11.Magma

You might also like