Professional Documents
Culture Documents
2011 USRM Cave Mining-Back To The Basics - Moss
2011 USRM Cave Mining-Back To The Basics - Moss
Basics
Allan Moss,
General Manager
Rio Tinto Underground Technology
Theme: Back to the Basics What you
can’t measure you can’t manage
Wrap-up
Wrap -up
160000
140000
Palabora
Henderson
Homestake - S Dakota
Magma
Western Deeps
1000m
Kidd Creek
Open pits Super
120000
TONNES PER DAY
2000m
caves
3000m
100000
4000m
80000
Wrap -up
Shaft
Ore body
Draw bells
Haulage
system
Production tunnels
Expansion Void
(Air gap)
Caved
Zone
Yielded Zone
LHD
Grizzley
Block
Block
CaveCave
June 2011
1 March 2011 US Rock Mechanics Symposium 16
Increased Production, Higher Lifts
uncertainty
reduced knowledge
limited control
well established method
good control
more certainty
Escondida, Chile
IOZ
DOZ
Courtesy of PTFI
June 2011 US Rock Mechanics Symposium 18
Block Caving Concept
VALUE REALIZATION
CAPITAL INVESTMENT
100 %
Vyazmensky © 2007
CAVE DYNAMICS
SOURCES OF
UNCERTAINTY
TIME
CAVE MANAGEMENT
June 2011 US Rock Mechanics Symposium 19
Caving Process • Block cave mining is based on
the principle that, once a
sufficiently large area of a block
has been undercut by drilling
and blasting, the overlying
20 block of ore will start to cave
under the influence of gravity.
Progressive spalling • The process will continue until
caving propagates through the
entire block to surface or to the
open pit above
25 35 45
Fully Bulked
σ3
0 10
June 2011 US Rock Mechanics Symposium 21
Key Technical Issues
cave propagation
cave flow
June 2011
cave fragmentation
US Rock Mechanics Symposium 22
Critical dimensions to initiate caving
Primary
Index of Interruptions Frequency Fragmentation
(Salvador mine, draw point 04W20)
Secondary
fragmentation
HoD
Initial secondary
fragmentation
Blasting effect
Blasted undercut material
Flow Interruption Index Secondary
(events/tons x 1000) Fragmentation
expansion
Secondary
void
fragmentation
fragment
size
evolution
f(fragment size)
higher
mobility of
finer
fragments
within a
draw Coarse material
column
IDZ
30m
0.1 1 10
What do we draw?- the recovery issue
High grade ore Dilution entry
ORE BODY
$
WASTE ROCK WASTE ROCK
Vyazmensky
Vyazmensky ©
© 2008
2008 TIME
REPEAT
June 2011 US Rock Mechanics Symposium 29
Geometry of drawbells
DRAWBELLS
waste
Waste
Entry
waste ore
waste
ore
ore ore
HoD
IDZ ~ Ellipsoid of Motion
(extracted blocks)
June 2011 US Rock Mechanics Symposium 31
Rilling
32
Impacts of Fragmentation
IMPLICATIONS ON PRODUCTIVITY
RESOURCE RECOVERY
SECONDARY
BLASTING
VALUE
AT RISK
June 2011 US Rock Mechanics Symposium 33
Flow dictates Revenue Stream
WASTE ROCK
elliptical or frustum
shaped IEZ;
height equivalent
to~100-200 mean
EXTRACTED ORE fragment size
ORE BODY
$
WASTE ROCK WASTE ROCK
Vyazmensky
Vyazmensky ©
© 2008
2008 TIME
Wrap-up
$
Recovery Recovery Operations
Draw strategy
& control
Reserve
Production Forecast
Design &
planning
Orebody Knowledge
Monitor &
Measure
Design,
Production
value proposition
Plan,
Knowledge
Forecast
Design,
Production
Plan,
Knowledge
Forecast
Mapping
Design,
Production
Plan,
Knowledge
Production
Plan,
Knowledge
Forecast
Rock Mass
Properties
Design,
Production
Plan,
Knowledge
Forecast
200
180
Unconfined Compressive Strength (UCS)
160
NPM
140 PMC
Oyu Tolgoi
120
0.3
Statistics
Oyu Tolgoi
(avg. UCS = 133 MPa)
Experience
Range - 35 to 190 MPa
80 Number of Data Sets - 17
Empirical
0.25 Mean - 106.1 MPa
Median - 100 MPa
Relative Frequency
Methods
0.15
40 0.1
0.05
20
0
20 40 60 80 100 120 140 160 180 200 205
Uniaxial Com pressive Strength (MPa)
Mine
Numerical
Methods
Error in Estimate
Estimated vs. Actual Hydraulic Radius
50
30
(m )
20
Prediction of Cave 10
Performance 0
0 10 20 30 40
Estimated Hydraulic Radius (m)
Numerical Modeling
Design,
Production
Plan,
Knowledge
Forecast
50m
Cave propagation
arrest and crown
pillar collapse
Vyazmensky, 2008
Lesson learned Monitor &
Measure
Design,
Production
Plan,
Knowledge
Forecast
Palabora
successfully Orebody Learn &
Knowledge Modify
transitioned from an
open pit to a 30,000
tpd underground
block cave but…….
Experience wall
convergence as
fractured columns
of rock deform
(buckle) into panel
Immediate
abutment
Production
Initial
state
Constru
ction
Rock Behaviour Modes in σ - space
49
Behaviour
• Observations are:
– Brittle failure dominates
– Onset and propagation occurs generally in walls and lead
to gradual de-stabilisation of back
– Indications that failure involves a surface skin of around 1
to 2m fractured rock. This is the volume of ground to be
managed
• Drivers of failure are stress; not only the major principal stress
(loading) but the minor principal stress (relaxation). Require
support systems that deal with displacements
50
Where do we Obtain Production Monitor &
Measure
Information?
Design,
Production
Plan,
Knowledge
Forecast
Grade Convergence
Fragmentation Number of buckets drawn
Height of Draw
Location of Cave Back
Compliance to Plan
Grade and Performance Reconciliation
June 2011 US Rock Mechanics Symposium 51
Bucket factor: An imprecise Measure Design,
Monitor &
Measure
Production
Plan,
Knowledge
Forecast
and Fragmentation
Design,
Production
Plan,
Knowledge
Forecast
53
Monitor and Measure Design,
Monitor &
Measure
Production
Plan,
Knowledge
Forecast
30%
25000
20%
% Cu
0.40
10%
20000
0%
X/CUT 05
X/CUT 18
X/CUT 07
X/CUT 19
X/CUT 16
X/CUT 14
X/CUT 08
X/CUT 12
X/CUT 13
X/CUT 01
X/CUT 09
X/CUT 06
X/CUT 04
X/CUT 15
X/CUT 03
X/CUT 17
X/CUT 02
X/CUT 20
X/CUT 10
0.30
15000
0.20
10000
Variation (tons)
15 Average Tonnes Hoisted Hoisting Potential Planned Tonnes Measured Grade %Cu 0
Metal Balance -5,000 0 10 20 30 40 50 60
10
-10,000
Plan
5 -15,000 Something is
0
-20,000 happening
Week
-5
-10
1000
Higher than Shortfall realizations
-15 plan perceived Shortfall
against
perceived
05Q1
05Q2
05Q3
05Q4
06Q1
06Q2
06Q3
06Q4
07Q1
07Q2
07Q3
07Q4
08Q1
08Q2
08Q3
08Q4
09Q1
09Q2
09Q3
09Q4
GOOD plan
as BAD single
2005 2006 2007 2008 2009 realization
June 2011 US Rock Mechanics Symposium 54
IEZ = IEZ = IEZ = IEZ =
13m 12m 10m 8m
33 24 17 12
months months months months
IEZ = IEZ = IEZ = IEZ =
13m 12m 10m 8m
33 24 17 12
months months months months
Recovery? Design,
Monitor &
Measure
Production
Plan,
Knowledge
Forecast
57
Monitor &
Design,
Production
Plan,
Knowledge
with Statistics
Forecast
80%
70%
L H D A v a ila b ility
60%
50%
40% Care required when examining data in isolation
30%
20%
10%
0%
0 50 100 150 200 250 300 350 400
Average Tonnes Hoisted
June 2011 58
US Rock Mechanics Symposium
Monitor, Learn, React Monitor &
Measure
Design,
Production
Plan,
Knowledge
Forecast
Wrap -up
uncertainty. CONCRETE
DAMAGE
Required
Fragmentator
In Situ
Fragment Crushing
Size and Grinding
Energy
(Distance Traveled)
Reliable
Ore Flow
The Ore
The RockFactory
Factory
Summary
• Caving method relies on gravity to
break the rock sufficiently to allow
efficient transfer to surface
• Knowledge and planning is critical.
• Four steps in reliable production
forecasts:
1. Collect appropriate rock mass and
operating data
2. Turn data into information through
organising and visualising
3. Analyse and forecast
4. Monitor, reconcile and learn
33 24 17 12
months months months months
IEZ = IEZ = IEZ = IEZ =
13m 12m 10m 8m
33 24 17 12
months months months months
Uncertainty in Cash Flow over
Time
Stage 1: Initial Cave: 0 to 30% draw ( this will be include the
period of production build up)
Stage 2: Steady State Cave: 30 to 60% draw
Stage 3: Mature Cave: 60 to end of life draw (nominally 100%)
Base Case
Time
Uncertainty in Schedule
70
OPEN PIT CAVE MINING
VALUE
AT RISK
SECONDARY BLASTING
CONFIDENTIAL ©2009, Rio Tinto, All Rights Reserved 74
CAVE DYNAMICS: FLOW
Access:
Exploration shafts/drifts Tonnage:
(Resource) development draw rate, drawpoints
availability
Studies (Reserve) Layout:
bell construction rate
Grade
time
UNCERTAINTY IN CAVE MINING
CAVE FLOW:
UNCERTAINTY C
MINING INPUT:
undercutting,
material extraction rate OUTPUT - VALUE:
(stress, void) tonnage, grade
UNCERTAINTY D UNCERTAINTY f(time)=A*B*C*D
RILING ANIMATION
Caveability