AVIDA VERGE TOWER 2

Inspection & Test Plan FORM NO.: FR-01-QAQC-GF-016-rev.1

Reinforcement Bar Installation for Column/Slab/Beam/Girder


and Shearwall
by DCMS

Document Review
Activity Company Name Title Signature Date
Reviewed by MDC Edgardo Amigo Jr QAQC Supervisor/ Officer 12-21-2021
Reviewed by MDC Mary Jane Carreon Project Trade Supvr/ Supt
Recommended by MDC Project In-Charge
Approved by MDC Rufino Malonjao III Project Manager

Makati Development Corporation ITP DIVISION NO. Rev.


REBAR WORKS Page 1 of 2 M S - I T P - D I V 0 3 - 0 1 1
Revision: June 2021
AVIDA VERGE TOWER 2
Inspection & Test Plan FORM NO.: FR-01-QAQC-GF-016-rev.1

RECORDS / TESTED / INSPECTED / REVIEWED BY


REFERENCE
CHECK POINT TEST / INSPECTION FREQUENCY DOCUMENTS
SPECIFICATIONS SUBCON FOG QAQC
REQUIRED
1. WORK ACTIVITY SUBMITTALS
1.1 Pre-Construction - Method Statement Review Method Project Specification, Approved Method
Per Type X R R
Statement Contract Agreement Statement
1.2 Pre-Construction - Shop Drawing Approved Shop
Review FCD/ IFC/ RFA Approved Shop Drawing Per Type X/R R R
Drawing
1.3 Pre-Construction - Materials
1.3.1 RSB Project Specification,
Approved material
Review Product Data, Mill Per Type X/R R R
submittal
Certificate
2. WORK IN-PROGRESS
2.1 Materials Delivery Inspection Approved Submittals, Mill
Visual Inspection Per Delivery MDI Form X R/W R/W
Certificate
2.2 Tensile/ Compressive Testing
Visual & Physical Test Result/Reports/
Inspection (Accredited Project Specification Per delivery Rebar Test Result X R/W R/W
by MDC testing Center) Monitoring

2.3 Survey
Survey Request Approved Drawings/ IFC Per area per scope Work Requests X R/W R/W

2.4 Rebar Installation


Work Activity Permit/
Inspection Approved Cutting List Per area per scope X R/W R/W
Work Activity Permit

3. WORK ACTIVITY COMPLETION


3.1 Post-Construction Inspection Per requirements/per
Punchlist
Inspection/Visual drawing/ Approved Per area per scope X R/W R/W
Form/Checklist
submittals
3.2 Handover Closed
Visual Inspection Per Requirements Per Area X R/W R/W
Punchlist/Handover
3.3 As-Built Survey As Built Plan/ Survey
Survey Report Per drawing Per area per scope X R R
Data
LEGENDS: X - Initiated R- Review W-Witness H- Hold Point
Makati Development Corporation ITP DIVISION NO. Rev.
REBAR WORKS Page 2 of 2 M S - I T P - D I V 0 3 - 0 1 1
Revision: June 2021