1. General
The Contractor shall be responsible for the design, supply, and installation and commissioning of
all equipment such that the full functioning with the SAS and remote end SCADA systems are
guaranteed.
The communication gateways shall secure the control of the information flow to remote network
control centres.
The Gateway(s) shall be part of the Substation Automation System (SAS). It shall enable local
station control via Industrial PC, employing a human-machine interface (HMI) and control
212
software package, performing the necessary system control and data acquisition functions.
The Gateway(s) shall comprise full station control, monitoring and communication functions, as
2002
described in the SAS technical specification, from the National Power Control Centre (NPCC).
As the Gateway serves for interfacing the SAS with remote end SCADA systems, it shall be
correctly interfaced with one another and also with the existing facilities if any.
2-2-
The provided Gateway(s) shall be equipped with sufficient communication facilities to integrate
2R
into the SCADA Master Station at NPCC without interfering its operation.
The Gateway(s) also should have sufficient capacity for future expansions, and all the related
software with license and configurations, maintenance and user manuals shall be provided.
11
The Gateway protocols and hardware configurations to be supplied under this Contract shall be
compatible and shall be integrated into the existing SCADA systems at NPCC locations.
R-
212
IEC 61000-4-5-2005 Surge Immunity Level 4 ±4KV line-
toearth/±2KV line-to-line
2002
IEC 61000-4-6-2006 Conducted RF Immunity Level 3-10Vrms
IEC 61000-4-8-2001
2-2-
Magnetic Field Immunity Level 5- 100A/m 5min /
2R
1000A/m 1s
Substation
100%
3ms (cycle 3)
212
common/Differential
1.25KV for Substation
IEEE C37.90 Dielectric Strength 2000Vrms
2002
IEEE C37.90 Impulse Voltage 5000V
IEC 60870-2-1-1995
IEC 60870-2-1-1995 2-2-
DC Voltage Ranges
Voltage Ripple of DC
-20%~+15%
Level VR3- ≤5%
2R
IEEE C37.90 Nonoperational Temperature Range -40°C~+75°C
IEEE C37.90 Operational Temperature Range -30°C (Start-Up)~+65°C
11
R-
3. Environmental requirements
a Temperature (IEC 60068-2-1 Cold Temperature and IEC60068-2-2 Dry Heat Temperature)
O
212
The Firewalls shall be placed on network boundaries (places where traffic enters/leaves the SAS
network) before the Gateway(s) to protect the substation automation system perimeter.
2002
USB ports shall be deactivated; unused ports shall be closed, and periodic port scanning shall be
automatically configured with an option for manual configuration.
2-2-
All information points (signal, tele-measurement, command). The Data Points / Tele Information
Points list and grouping shall be prepared according to NTDC Standards. The Contractor shall
2R
obtain explicit approval of these documents from the Employer/Engineer.
The NPCC Signal List (comprising of Analog & Digital Signals from Substation to NPCC and
11
Remote Control Commands from NPCC to Substation) shall be jointly reviewed and approved
by the offices of General Manager (System Operation) NPCC, Chief Engineer (Protection &
Control), & Chief Engineer (Telecom) NTDC during the detailed design review stage.
R-
However, the signals to and from Local SAS HMI/BCU/Protection Relays/Fault Recorders,
Interlocking Scheme concerning the Substation shall be reviewed and verified by Office of Chief
O
212
and Fibre Optic Equipment Communication Ports:
o At least four (4) nos. of RS 232(V.24/V.28) serial ports
2002
o At least four (4) nos. of 10/100/1000Mbps Ethernet Ports (electrical & optical)
All the ports shall not be built in a single interface module and shall be of separate interface
4.2.
2-2-
modules for redundancy purposes. All the ports shall be protected against surges.
Mechanical Details of Equipment
2R
The Gateways shall be housed in SAS enclosed cabinets, which are insect and vermin proof.
All external cables shall pass through a cable gland plate, at base of the cabinet. Each cable shall
11
slots, or similar means, so that, modules cannot be plugged in the wrong position.
4.3. Schedule of the test at works
O
The following minimum tests shall be carried out in the presence of the Engineer and the
N
Employer. The tests shall comply with this Specification and approved documents by the
Employer/Engineer.
Gateway
a. Construction check
b. Insulation resistance measurement
c. Temperature rise test (Certification of type test may be accepted)
d. Power consumption measurement
e. Operation tests (both Simulation and actual operation)
f. Redundancy Verification Tests
g. Interoperability list for the Gateway shall be submitted with the test reports
h. End-To-End Test with NPCC: The testing related to the Telecommunication
Equipment, i.e. PLCs, SDH, Analogue/Digital signals at Gateways and their allied
equipment etc. shall be witnessed by the representatives of Office of Chief Engineer
(Telecom) NTDC. Moreover, local tests of SCADA signals list approved by GM (SO)
NTDC NPCC will be witnessed jointly by representatives of Protection & Control
Departments and Telecommunication Department of NTDC.
End-to-End Tests of SCADA signals list approved by GM (SO) NTDC NPCC, at
SCADA/EMS system at NPCC Islamabad shall be witnesses by representatives of Office
General Manager (System Operation) NPCC-NTDC in coordination with Telecom
Engineers and Protection & Control Engineers from NTDC available at the site.
However, the remaining Protection, Control & Automation related testing activities shall
be witnessed by protection & control engineers from NTDC.
212
No. Description Unit Required To be filled
2002
by Bidder
1 Manufacturer
2 Country of origin
3
4
Type – Model
Ordering Code 2-2-
2R
5 Operating system
6 CPU frequency GHz
7 RAM memory Gb Min 8 Gb
8 HDD SATA 10000 rpm or SSD Yes/No SSD
11
Nos >= 4
a. IEC 60870 – 5 – 101
Nos >= 4
b. IEC 60870 – 5 – 104
15 Ethernet ports 10/100/1000 Mb for separate Nos Min. x 1
connection in PRP according to topology Gb Ethernet
Ports (LC)
16 IEC 62439-3 PRP Network Yes/No
17 SNTP and (or) PTP Time Sync. over the Yes/No Yes
Network
18 Video ports: 1xDSUB + 1xDVI or HDMI Yes/No
19 TCO standard - 03
20 Power Supply cards/modules Yes/No Yes
Redundant Input Power Supply V DC 220
21 Overall Size (HxWxD) mm
22 Mounting: in rack 19’’ Yes/No Yes
23 Weight Kg
No. Description Unit Required To be filled
by Bidder
24 Temperature
a. Operating Deg C -10°C+55°C
b. Storage Deg C
25 Humidity ( non-condensing) % 5% - 95%
26 Enclosure Protection Class IP 40
27 Drawings, catalogues, manuals Yes/No
28 Reference list Yes/No
29 Test reports Yes/No
30 Specific software for IEC 61850 Yes/No
31 Software licenses Yes/No
32 Software installation kits Yes/No