CANTIDADES DE OBRA

FECHA
OBRA: ZONA:

ELEMENTO ESTRUCTURAL: UBICACIÓN:

# # W (kg/m) W (kg/m)
ELEMENTO CANT. LONG (m) ESQUEMA DIMENSION(m) OBSERVACIONES INSPECIONADO POR:
ELEM VARILLA Unitario Total
A=
B=
1 101 4 6 5,28 0,994 31,48992 C=
D=
E=

A=
B=
2 101 3 34 0,88 0,560 16,7552 C=
D=
E=

A=
B=
3 102 4 3 4,34 0,994 12,94188 C=
D=
E=

A=
B=
4 102 4 3 4,15 0,994 12,3753 C=
D=
E=

A=
B=
5 102 4 3 2,69 0,994 8,02158 C=
D=
E=

A=
B=
6 102 4 3 2,31 0,994 6,88842 C=
D=
E=

A=
B=
7 102 4 3 4 0,994 11,928 C=
D=
E=

A=
B=
8 102 3 49 0,88 0,560 24,1472 C=
D=
E=

A=
B=
9 103 4 6 5,28 0,994 31,48992 C=
D=
E=

A=
B=
10 103 3 34 0,88 0,560 16,7552 C=
D=
E=

A=
B=
11 104 4 3 5,83 0,994 17,38506 C=
D=
E=

A=
B=
12 104 4 3 8,02 0,994 23,91564 C=
D=
E=

A=
B=
13 104 4 3 2,69 0,994 8,02158 C=
D=
E=

A=
B=
14 104 4 3 2,22 0,994 6,62004 C=
D=
E=

A=
B=
15 104 4 3 9,35 0,994 27,8817 C=