Professional Documents
Culture Documents
Se 1 2 22
Se 1 2 22
net/publication/281348236
CITATION READS
1 480
3 authors, including:
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Almoataz Y. Abdelaziz on 30 August 2015.
1. INTRODUCTION
All rights reserved. No part of contents of this paper may be reproduced or transmitted in any form or by any
means without the written permission of ORIC Publications, www.oricpub.com.
Journal of Science and Engineering Vol. 1 (2), 2013, 121-132 P a g e | 122
The transient energy function method [7, 8] and extended equal-area criterion [9, 10] have also been
applied in power system transient stability assessment. However, these methods have some modeling
limitations and they still need a lot of computations to determine an index for transient stability [11].
Artificial intelligence has been also introduced in the out-of-step field. The K-means clustering pattern
recognition technique gives good results in detecting out-of-step conditions [12]. Another out-of-step
prediction approach based on neural networks has been also presented in [13].
Nowadays Phasor Measurement Units (PMUs) are capable of tracking the dynamics of an electric power
system in real time, and with modern telecommunication technologies, utilities are becoming able to
respond intelligently to an event in progress [14, 15]. By synchronized sampling of microprocessor-based
systems, phasor calculations can be placed on a common reference [16-18] to achieve Synchronized Phasor
Measurement Units (SPMUs). A new approach considering synchronized measurement data from both ends
of a transmission line to protect transmission line is presented in [19].
Synchro-phasor measurements of synchronized voltage and current are used by utilities to control and
stabilize the power network. The dependence of the machine on the position of the rotor makes it difficult
for the application of phasor measurements for stability control methods. Under transient conditions, it is not
easy to find solutions to obtain machine voltages, currents and flux linkages when expressed in phase
quantities. The time varying coefficients need to be stabilized to obtain stationary mechanical coefficients
[20, 21]. Phasor measurement units equipped with Global Positioning System (GPS) receivers and a
time-stamp device are placed at power plants to obtain power plant variables. The gathered data is then
transmitted to a central location where the data can be compared, analyzed and processed. With some local
processing power they can be used to determine the generator angles, speeds, accelerations and powers from
terminal voltages and currents [20, 22]. Prior knowledge of the system is necessary since the network
topology changes would influence proper machine identification. Lack of direct measurement of the plant
auxiliaries may result in phasor measurements not providing a real picture of rotor angles. Previously two
multi-layered feed-forward artificial neural networks have been used to estimate rotor angles and speed from
phasor measurements. This solution did not consider the lack of direct measurements as a source of
uncertainties. Selection of input variables was also not considered [23, 24]. The generator measurable
outputs with its electrical parameters have been used to estimate the state variables. The results did not use
the availability of the field voltage Efd, which provides additional insight into the internal machine flux
linkages [21].
This paper presents a modification on an existing algorithm in [18], which presents a study for power
oscillations with a laboratory model comprising a strong network, a transmission line and a generator, an
algorithm tested for a three phase short circuit fault for a single machine infinite bus system . An approach to
design power system transient stability assessment using direct methods for a multi-machine system that
uses measured values of the currents and voltages of the three phases of two buses (equivalent to PMU data)
is presented. The multi-machine system was reduced to a single machine infinite bus (SMIB) system using
system reduction. The measured data is transformed from time domain into phasor domain using Discrete
Fourier Transform (DFT) to predict whether the swing is a stable or an unstable one. The performance of the
method has been tested on a simulated multi-machine system using PSCAD and MATLAB software. The
proposed scheme can be used for the detection of out of step condition using an extension of the equal-area
criterion. A three phase fault was simulated at test system comprises 4-machine network for validating the
proposed algorithm.
Instead of using relays to detect Out-Of-Step events, new measurement systems are available where it is
possible to measure phase angles in the whole power system with the same time and angle reference. The
main device in such a system is called a phasor measurement unit, PMU. The value of data provided by
PMUs has been recognized, and installation of PMUs on power transmission networks of most major power
systems has become an important current activity.
The modern PMUs use one pulse per second signals provided by the Global positioning system (GPS)
satellite receivers. GPS system consists of 24 satellites in six orbits at an approximate altitude of 10,000
miles above the surface of the earth. The accuracy of the GPS timing pulse is better than 1μs, which for a 50
Hz system corresponds to about 0.018 degrees, this accuracy is more than enough to ensure that the
123 | P a g e A. Y. Abdelaziz, Amr M. Ibrahim, Zeinab G. Hasan
measurements obtained by such clocks will be simultaneous for the purpose of estimation and analysis of the
power system state [25]. PMUs are nowadays increasingly used to measure and monitor the state of the
power systems [26]. Successful commercialization of this technology now makes it possible to build wide
area measurements systems, which enable on-line control of power systems and implementation of new
protection schemes [27].The main advantage of PMU is that measured values have same time reference.
PMU uses GPS signals to time synchronizing and after calculating voltage and current phasors, using DFT,
PMU adds a time tag to sampled data and synchronize them with GPS signals [28].With the advancement in
technology, the micro-processor based instrumentation such as protection Relays and Disturbance Fault
Recorders (DFRs) incorporate the PMU module along with other existing functionalities as an extended
feature [29].
The synchronized phasor measurement technology is relatively new, and consequently several research
groups around the world are actively developing applications of this technology. It seems clear that many of
these applications can be conveniently grouped as follows:
4. PROBLEM FORMULATION
4.1. System
In stability assessment of multi-machine systems, the following simplifying assumptions are often made:
1. Each synchronous machine is represented by a constant internal voltage behind the transient
reactance.
2. The governor's actions may be neglected. It means that input mechanical power of turbine
generator remains constant during and after the disturbance.
3. During the transients, loads are modeled as constant admittances to ground.
By these assumptions discussed in [32] the system can be modeled using system reduction, and then the
proposed out-of-step detection algorithm can be applied. A multi-machine system was chosen for this study.
The assumption was made that voltages and current can be measured by synchronized phasor measurement
devices at the terminal of the generator. Additionally, the generator parameters were known. According to
[12], if the external bus voltage has a magnitude of V and phase θ, and , which are the components of
the bus voltage after they have been converted by Parks transformation; , can be calculated by:
( ) ( ) (1)
(2)
And be used in the swing equations to calculate the acceleration power of machines [33].
predetermined locations to maintain load generation balance, avoid equipment damage and power blackouts.
The Out-of-Step Trip function differentiates between stable and unstable power swings and initiate system
area separation at the predetermined network locations to maintain power system stability [34]. The
equal-area criterion can be used to calculate the maximum fault clearing time before the generator loses
synchronism. The equal-area criterion integrates the energy gained when the turbine-generator is
accelerating, during the fault (area A1, in Figure 1) and compares that area with the decelerating area, (area
A2, in Figure1) when the generator exports the energy stored during the fault.
Area A1 represents the total kinetic energy gained during the acceleration period. As soon as the fault is
cleared at angle δc the angle will continue to increase and the kinetic energy gained during the fault period
will expand into the power system, when area A2 is equal to area A1 angle δ has reached its maximum
value [18, 35].
The area under the power-angle curve can be calculated by:
c
A1 ( P0 P sin )d (3)
o max D
P
A2 (P sin P0 )d (4)
c max P
where
D= during fault
P= post fault
When area A1 < A2 the system will be stable and if A1 > A2 the system will be unstable.
For multi-machine system, we will reduce it to two machines system and then converted into an equivalent
single machine system. We will be able to use out-of-step detection algorithm in [36].
The area under the power-delta curve, assuming that the pre-fault and post-fault network conditions are
similar, can be calculated from the swing equation, with a three phase fault as follows:
(5)
where B is one group of machines that swing together and C represents another group.
(6)
(7)
d 2
Pa M (8)
dt 2
Pa P0 Pe (9)
where Pa is the accelerating power and P0 is the mechanical power.
No
Yes
Calculate area A and B
No
If area A1 > area A2
Yes
Print: OUT-OF-STEP
The proposed algorithm will be tested on 4-machine network used in [33]; system configuration is shown in
Figure 3. The four machine system was reduced to form a two machine system by combining the machines that
swing together, that is, G1+G2 and G3+G4 based on the swing curves in Figure 4. The two machine network
was further reduced into SMIB. The inertia constant, delta and the electrical power were calculated according
to equations (6), (7) and (8) respectively. The resulting SMIB is used in PSCAD program. The voltages and
currents measurements at the generator and at the infinite bus are the two required readings to operate the
algorithm. The system is simulated under several fault duration for three phase short circuit fault.
1000
Infinite bus voltage [kv]
500
-500
-1000
-1500
0.3 0.35 0.4 0.45 0.5 0.55 0.6 0.65
time [sec]
300
200
generator voltage [kv]
100
-100
-200
-300
-400
0.3 0.35 0.4 0.45 0.5 0.55 0.6 0.65
time [sec]
-13
x 10 Current versus time
1.5
0.5
-0.5
-1
-1.5
-2
0.3 0.35 0.4 0.45 0.5 0.55 0.6 0.65
time [sec]
3
generator current [A]
-1
-2
-3
0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.55 0.6 0.65
time [sec]
The proposed scheme is tested by calculating areas A1 and A2 for this fault and determines that the
generator will be out of step (unstable condition), this fault is tested by TDS and determines instability of the
system as shown in Figure 9.
Time versus angle
2000
1800
1600
1400
angle [degrees]
1200
1000
800
600
400
200
0
0 0.1 0.2 0.3 0.4 0.5
time [s]
It is concluded from Table 1 that duration of fault is directly related to the angle difference between the
generator and infinite bus (δ) which will affect the accelerating and decelerating area affecting the stability
of the system. When Df increases for the same tf the system will tend to be unstable. All cases are compared
by TDS and give identical results. This is the same for single machine infinite bus system discussed in [36].
6. CONCLUSIONS
This paper presents an approach to design power system transient stability assessment using direct methods
for a multi-machine system which uses measured values of the currents and voltages of the three phases of
two buses (equivalent to PMU data) to detect the out-of-step condition accurately. The multi-machine
system was reduced to a single machine infinite bus (SMIB) system using system reduction. The Discrete
Fourier Transform is used to transform the sampled data in phasor domain which is equivalent to PMU
readings. The EAC is used and proved that it is an efficient method for determining the transient stability of
a power system and detecting the out of step condition for multi-machine system as one machine against
infinite bus or two machine systems. Test results show that the proposed algorithm is able to detect transient
stability on a multi-machine system with a temporary fault, through PMU measurements and generator
parameters for different durations. It would be interesting to make simulations on larger networks that
include more generators and machines and to find possible nodes to implement PMUs.
REFERENCES
[1] Imhof, J., Berdy, J., Elmore, W., Goff, I., New, W., Parr, G., Summers, A. and Wagner, C. (1977).
Out-of-Step Relaying for Generators. IEEE Transactions on PAS., Vol. PAS-96, pp. 1556-1564.
[2] Taylor, C.W. (1983). A New Out-of-Step Relay with the Rate of Change of Apparent Resistance, IEEE
Transactions on PAS., Vol. PAS-102, pp. 631-639.
[3] Reomish, W.R. and Wall, E.T. (1985) A New Synchronous Generator Out-of-Step Relay Scheme, Parts
I &II, IEEE Transactions on PAS, PAS-104, pp. 563-582.
[4] Kundur P. (1994). Power System Stability and Control. McGraw-Hill.
[5] Pavella, M.; Murthy, P.G. (1994).Transient Stability of Power Systems: Theory and Practice. John
Wiley & Sons Ltd.
[6] Karami, A. (2011). Power System Transient Stability Margin Estimation using Neural Networks. Int. J.
Electrical Power and Energy Systems, Vol. 33, Issue 4, pp. 983-991.
[7] Pai, M. A., (1989). Energy Function Analysis for Power System Stability, Springer.
[8] Fouad A. A. and Vittal V.,(1992). Power System Transient Stability Analysis using the Transient
Energy Function Method. Prentice-Hall.
[9] Xue Y., Cutsem T. V. and Pavella M. A., (1989). Extended Equal-Area Criterion Justifications,
Generalizations, Applications. IEEE Transactions on Power Systems, Vol. 4, No. 1, pp. 44–52.
[10] Xue Y., Cutsem T. V. and Pavella M. A.,(1988).Simple direct method for fast transient stability
assessment of large power Systems. IEEE Transactions on Power Systems, Vol. 3, No. 2, pp. 400-412.
131 | P a g e A. Y. Abdelaziz, Amr M. Ibrahim, Zeinab G. Hasan
[11] Colvara L. D., (2009). Stability Analysis of Power Systems Described with Detailed Models by
Automatic Method. International Journal of Electrical Power and Energy Systems, Vol. 31, No. 4, pp.
139–145.
[12] El-Arabaty, A.M., Talaat, H.A., Mansour, M.M., and Abdelaziz, A.Y. (1994) Out-of-Step Detection
Based on Pattern Recognition’, Int. J. Electrical Power & Energy Systems 16 (4), pp. 269-275
[13] Abdelaziz, A.Y., Irving, M.R., El-Arabaty, A.M. and Mansour, M.M. (1995) Out-of-Step Prediction
Based on Artificial Neural Networks. Electric Power Systems Research 34(2), pp. 135-142.
[14] Phadke, A. G. and Thorp, J. S. (1988).Computer Relaying for Power Systems. John Wiley and Sons
Inc., New York.
[15] Phadke, A. G. (1993). Synchronized Phasor Measurements in Power Systems. IEEE Computer
Applications in Power, Volume. 6, No. 2, pp.10-15.
[16] Phadke, A. G. et al. (1993). Synchronized Sampling and Phasor Measurements for Relaying and
Control. IEEE PES Winter Meeting, Columbus, Ohio, USA.
[17] Yoon, Y. J. (2005). Study of the Utilization and Benefits of Phasor Measurement Units for Large Scale
Power System State Estimation. M.Sc. Thesis, Texas A&M University.
[18] Berkestedt, A. H. (2007). Phasor Measurement based Out-Of-Step Detection. M. Sc. Thesis, Division
of Electric Power Engineering, Department of Energy and Environment, Chalmers University of
Technology, Göteborg, Sweden.
[19] Zadeha, H. K. and Li, Z. (2011). Phasor Measurement Unit based Transmission Line Protection
Scheme Design. Electric Power Systems Research, Vol. 81, Issue 2, pp. 421-429.
[20] Ali, M. and Mansour, W. (2008). A Proposed Approach for Online Transient Stability of
Multi-machine Power Systems Using Parallel Microprocessors. Proceedings of the 6th International
Conference on Electrical Engineering, Military Technical College, Cairo, Egypy, pp. 901-910.
[21] Venkatasubramanian, V.; Kavasseri, G. (2004). Direct Computation of Generator Internal Dynamic
States from Terminal Measurements. IEEE Proceedings of the 37th Hawaii International Conference on
System Sciences.
[22] Vidalinc, A. (July 1997). On-Line Transient Stability Analysis of a Multi-Machine Power Systems, M.
Sc. Thesis, Virginia Polytechnic Institute and State University.
[23] Del Angel, A. (2003). Artificial Neural Networks to Estimate Rotor Angles and Speeds from Phasor
Measurements.
[24] Ali, M., Anis, W., Mansour, W. and Bendary, F. (2010). ANFIS Based Synchro-Phasors Measurements
for Real-Time Estimation of Critical Clearing Time. Proceedings of the 14th International Middle East
Power Systems Conference (MEPCON’10), Cairo University, Egypt, Paper ID 193, pp. 422-427.
[25] Phadke, A. G. and Thorp, J. S. (2006). History and Applications of Phasor Measurements. Virginia
Tech, Blacksburg, Virginia, USA, PSCE.
[26] Rauhala, T. And Järventausta, P. (2007). Testing the Quality of PMU Output Data based Sub
synchronous Damping Analysis in Real-Time Simulation Environment. International Conference on
Power Systems Transients (IPST’07), Lyon, France.
[27] Mariotto, L. ; Pinheiro, H. ; Cardoso, G. ; Morais, A.P. ; Muraro, M.R., (2010). Power Systems
Transient Stability Indices: An Algorithm based on Equivalent Clusters of Coherent Generators. IET
Generation, Transmission and Distribution, Vol. 4, Issue 11, pp. 1223-1235.
[28] Bozchalui M. C., Sanaye-Pasand M. (2006). Out of Step Relaying using Phasor Measurement Unit and
Equal-Area Criterion. IEEE Power India Conference.
[29] Singh, B., Sharma, N., Tiwari, A., Verma, K. and Singh, S. (2011). Applications of Phasor
Measurement Units (PMUs) in Electric Power System Networks Incorporated with FACTS Controllers.
International Journal of Engineering, Science and Technology, Vol. 3, No. 3, pp. 64-82.
[30] Hart D.G., Uy D., Gharpure V., Novosel D., Karlsson D. and Kaba M. (2001).PMUs - A New
Approach to Power Network Monitoring. ABB Review1.
[31] Thorp J. S., Phadke A. G., Horowitz S. H. and Ekgovic M. M.(May 1988). Some Applications of
Phasor Measurements to Adaptive Protection. IEEE Transactions on Power Systems, Vol. 3, No. 2, pp.
791-798.
[32] Mohammadi-Ivatloo, Shiroei, B. and Parniani, M. (2011). Online Small Signal Stability Analysis of
Multi-Machine Systems Based on Synchronized Phasor Measurements. Electric Power Systems
Research (81), 1887– 1896.
Journal of Science and Engineering Vol. 1 (2), 2013, 121-132 P a g e | 132
[33] Monchusi, B., Mitani, Y., Changsong, L. and Dechanupaprittha, S. (2008). Power System Transient
Stability Assessment Based on Synchronized Phasor Measurements. The IEEE 2nd International Power
and Energy Conference.
[34] Kundu, K., Rao, J., Nayak, P. and Pradhan, A. (2010). Wide Area Measurement Based Out-of-Step
Detection Technique. 2010 IEEE Joint International Conference on Power Electronics, Drives and
Energy Systems, India.
[35] Demetrios A. Tziouvaras, Daqing Hou. (2003).Out-Of-Step Protection Fundamentals and
Advancements. Schweitzer Engineering Laboratories, Inc. Vacaville, CA USA, Schweitzer
Engineering Laboratories, Inc.Boise, ID USA.
[36] Abdelaziz, A. Y., Ibrahim, A. M. and Hassan, Z. G. (2012). Phasor Measurement Units for Out of Step
Detection. Proceedings of the 8th International Conference on Electrical Engineering ICEENG-8,
Military Technical College, Cairo, Egypt.
[37] Kimbark, W.K. (1995). Power System Stability Volume 1 Elements of Stability Calculations. IEEE
Press Power Engineering Series, New York.
[38] Jha, A. Ralte, L., Kumar, A, and Pat, P. (2009).Transient Stability Analysis Using Equal Area Criterion
Using Simulink Model. (Thesis), Department of Electrical Engineering, National Institute of
Technology, Rourkela.
[39] Saadat, H. (2004). Power System Analysis. (Book), Second Edition, International Edition.
[40] Pavella, M.; Murthy, P.G. (1994). Transient Stability of Power Systems: Theory and Practice. John
Wiley & Sons Ltd.
Please cite this article as: A. Y. Abdelaziz, Amr M. Ibrahim, Zeinab G. Hasan, (2013), Phasor Measurement Units For Out-Of-Step Detection of A
Multi-Machine System Using System Reduction, Science and Engineering, Vol. 1(2), 121-132