Professional Documents
Culture Documents
Distribution
Distribution
SEATWORK 3
1. A 3-phase transmission line has a per-phase series impedance of
(0.05+j0.45)ohm per km and a per-phase shunt admittance of
y=(j3.4x10−6 ) Siemens per km. The line is 80km long. The line
delivers 306MW at unity power factor at 220kV. Assume nominal pi
equivalent circuit. Determine the:
a. sending-end voltage
b. Sending-end current
c. Voltage regulation
d. Sending-end power
e. Transmission efficiency
• Z = 0.05 + j0.45 80 = 4 + j36 ohm
• Y = j 3.4x10−6 80 = j0.000272 siemens
YZ (j0.000272)(4+j36)
• A=D=1+ =1+ = 0.9951 + j0.000544
2 2
• B = Z = 4 + j36
YZ j0.000272 4+j36
• C=Y 1+ 4
= j0.000272 1 + 4
=
j0.0002713
220,000
• ER = = 127,017.06V/phase
3
PR 306x106
• IR = = = 803.04A
3ER pfR 3(220,000)(1)
• ES = AER + BIR = 0.9951 + j0.000544 127,017.06∠0 +
4 + j36 803.04∠0 = 𝟏𝟑𝟐, 𝟖𝟎𝟕. 𝟒𝟖𝟎𝟗∠ 𝟏𝟐. 𝟔 𝐕/𝐩𝐡𝐚𝐬𝐞
• IS = CER + DIR = j0.0002713 127,017.06∠0 + (0.9951 +
j0.000544) 803.04∠0 = 𝟕𝟗𝟗. 𝟖𝟐𝟔𝟗∠𝟐. 𝟓 𝐀
ES 132.8
−ER 0.9951+j0.000544
−127
A
• %VR = = ∗ 100% = 5.0818%
ER 127
• SS
= 3ES IS∗ =
3 132,807.4809∠ 12.6 799.8269∠ − 2.5 =
𝟑𝟏𝟑. 𝟕𝟑𝐌𝐖 + 𝐣𝟓𝟓. 𝟖𝟖𝐌𝐕𝐀𝐑 = 𝟑𝟏𝟖. 𝟔𝟔𝟗∠𝟏𝟎. 𝟏 𝐌𝐕𝐀
PR 306
•𝛈 = = ∗ 100% = 𝟗𝟕. 𝟓𝟑𝟔%
PS 313.73
3. A 3-phase, 765kV, 60Hz transposed line has a line inductance
of 0.89mH/km per phase and a shunt capacitance of
12.668nF/km per phase. The line is 400km long. Assuming the
line is lossless, determine the following:
a) Surge impedance
b) Phase constant
c) Wavelength
d) Surge impedance loading
L 0.89x10−3
• ZC = = = 𝟐𝟔𝟓. 𝟎𝟓𝟖𝐨𝐡𝐦𝐬
C 12.668x10−9
•β = 2πf LC = 2π 60 0.89x10−3 12.668x10−9 =
𝟏. 𝟐𝟔𝟔𝐱𝟏𝟎−𝟑 𝐫𝐚𝐝/𝐤𝐦
2π 2π
•𝝺 = = = 𝟒𝟗𝟔𝟑. 𝟎𝟐𝟐𝐤𝐦
β 0.001266
𝐸𝑅 𝑙𝑖𝑛𝑒 2 7652
• SIL = = = 𝟐𝟐𝟎𝟕. 𝟗𝟏𝟐𝐌𝐖
𝑍𝑐 265.058
2. A single-circuit, 60Hz, three-phase transmission line is 230mi long. It has a series impedance
of (0.1603+j0.8277)ohm/mi and a shunt admittance of j5.105 microSiemens/mi. The load on the
line is 125MW at 215kV with unity pf. Determine
a. Sending-end line voltage
b. Sending-end line current
c. Total sending-end power
d. Voltage regulation
e. Transmission efficiency
f. Wavelength
g. Velocity of propagation
• 𝛾𝑙 = 𝑧𝑦 ∗ 𝑙 = 230 0.1603 + 𝑗0.8277 𝑗5.105𝑥10−6
arg( 0.1603+𝑗0.8277 𝑗5.105𝑥10−6 )
• 𝛾𝑙 = 230 0.1603 + 𝑗0.8277 𝑗5.105𝑥10−6 ∠
2
169.039
• 𝛾𝑙 = 230 4.3039𝑥10−6 ∠ = 0.4772∠84.5195 = 0.045576 + 𝑗0.47502
2
𝑧 0.1603+𝑗0.8277 −10.9607
• 𝑍𝑐 = = = 165147.8354∠ = 406.3839∠ − 5.48
𝑦 𝑗5.105𝑥10−6 2
PTR 1
1 2
BREAKER
FAILURE
PTR 2
3 4
Sectionalized Bus
• Anextension of the single bus configuration is the
sectionalized bus arrangement. This arrangement is
basically two or more single bus schemes, each tied
together with bus sectionalizing breakers.
PTR 1
1 2
BREAKER
FAILURE
5 MAINTENANCE
PTR 2
3 4
Ring Bus
•A ring bus configuration is an extension of the
sectionalized bus arrangement and is accomplished by
interconnecting the two open ends of the buses through
another sectionalizing breaker.
1 2 3
BREAKER
FAILURE
4
MAINTENANCE
BREAKER
FAILURE
PTR 1 PTR 2
Breaker and a half
• The breaker-and-a-half configuration consists of two
main buses, each normally energized. Electrically
connected between the buses are three circuit breakers
and, between each two breakers, a circuit.
BUS BUS
1 1 2 3 2
BREAKER
MAINTENANCE
FAILURE
4 5 6
7 8 9
PTR 1 PTR 2
Double Breaker – Double Bus
• The double breaker-double bus configuration consists of
two main buses, each normally energized. Electrically
connected between the buses are two circuit breakers
and, between the breakers, one circuit.
1 2
3 4
5 6
BUS BUS
1 PTR 1 2
Load Characteristics
• Connected load – sum of all continuous ratings of all loads which
are connected to the system under consideration.
• Demand – is the load that is drawn from the source of supply,
averaged over a suitable and specified interval of time.
• Average load – the mean or average of all the power demands that
have occurred during a specified time.
Example
• A customer has the following average daily load schedule as
follows: 6AM to 12NN = 20kW; 12NN to 6PM = 12kW; 6PM to 11PM
= 25kW; 11PM to 6AM = 4kW. Solve the average load of the
customer for the day.
σ(𝑘𝑤ℎ) 20 6 +12 6 +25 5 +4(7)
• 𝐴𝐿𝑑𝑎𝑦 = = = 14.375𝑘𝑊
24 24
Load Characteristics
• Maximum demand or Peak load – is the greatest of all demands that
have occurred during a given period of time.
• Demand Factor – is the ratio of the maximum demand of the system to
the total connected load of the system.
𝑃𝐿
• 𝐷𝐹 =
𝐶𝐿
• Load Factor – is the ratio of the average power to the maximum
demand.
𝐴𝐿
• 𝐿𝐹 = 𝑃𝐿
• Diversity Factor – ratio of the sum of individual maximum demands of
the subdivisions of the system to the maximum demand of the whole
system.
𝑠𝑢𝑚 𝑜𝑓 𝑖𝑛𝑑𝑖𝑣𝑖𝑑𝑢𝑎𝑙 𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑑𝑒𝑚𝑎𝑛𝑑𝑠
• 𝑑𝐹 =
𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑑𝑒𝑚𝑎𝑛𝑑 𝑜𝑓 𝑒𝑛𝑡𝑖𝑟𝑒 𝑔𝑟𝑜𝑢𝑝
Load Characteristics
• Utilization factor – is the ratio of the maximum generator demand to the
generator capacity.
𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑑𝑒𝑚𝑎𝑛𝑑 𝑜𝑓 𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟
• 𝑈𝐹 = 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑔𝑒𝑛𝑒𝑟𝑎𝑡𝑜𝑟
• Installed capacity of the station – sum of all the ratings of the generators
installed in the station.
• Plant capacity factor – it is the ratio of the energy delivered in kWh in a given
period to the maximum possible energy that could have been produced during
the same periods.
𝑘𝑊ℎ 𝑑𝑒𝑙𝑖𝑣𝑒𝑟𝑒𝑑 𝑖𝑛 𝑎 𝑔𝑖𝑣𝑒𝑛 𝑝𝑒𝑟𝑖𝑜𝑑 t – number of hours in the given period
• 𝑃𝐶𝐹 = 𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑒𝑑 𝑘𝑊 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑝𝑙𝑎𝑛𝑡∗𝑡
• Plant use factor – it is the ratio of the energy delivered in kWh in a given period
to the actual energy that have been produced during the same periods.
𝑘𝑊ℎ 𝑑𝑒𝑙𝑖𝑣𝑒𝑟𝑒𝑑 𝑖𝑛 𝑎 𝑔𝑖𝑣𝑒𝑛 𝑝𝑒𝑟𝑖𝑜𝑑
• 𝑃𝑈𝐹 = 𝐼𝑛𝑠𝑡𝑎𝑙𝑙𝑒𝑑 𝑘𝑊 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑝𝑙𝑎𝑛𝑡∗𝑛 n – actual number of hours in the
plant has been in operation