Professional Documents
Culture Documents
ALLOCATION
Objective :
to maximize the overall profitability of the resulting supply chain
network while providing customers with the appropriate
responsiveness
profit = revenue – costs
revenue from sale of the product/service
costs from facilities, labor, transportation, material, and
inventories
profits are impacted by taxes and tariffs
profits should mean profits after tariffs and taxes
Decision Phases
I. Location and capacity of facilities
(long-term)
II. Assignment of current demand to available facilities and
Identification of lanes of transportation
Kripa Shanker IIT Kanpur 1
(intermediate–term)
MODELS FOR FACILTY LOCATION AND CAPACITY
ALLOCATION
Inputs :
• location of supply sources and markets
• location of potential facility sites
• demand forecast by market
• facility, labor, and material costs site wise
• transportation costs between each pair of sites
• inventory costs by site as well as a function of quantity
• sales price of product in different regions
• taxes and tariffs as product is moved between locations
• desired response time and other service factors
Models :
I. Network Optimization Models
Kripa Shanker IIT Kanpur 2
II. Gravity Location Models
NETWORK OPTIMIZATION MODELS
COMPETITIVE STRATEGY
PHASE I
GLOBAL COMPETITION
INTERNAL CONSTRAINTS
Supply Chain
Capital, Growth Strategy,
Strategy TARIFFS AND
Existing Network
TAX INCENTIVES
PRODUCTION
TECHNOLOGIES REGIONAL DEMAND
PHASE II Size, Growth, Homogeneity,
Cost, Scale/Scope Impact,
Support Required, Flexibility Regional Local Specifications
Facility
Configuration
COMPETITIVE POLITICAL, EXCHANGE
ENVIRONMENT RATE, AND DEMAND
RISK
PHASE III
Desirable
Sites
►Phase II
Kripa Shanker IIT Kanpur 3
MODELS FOR FACILTY LOCATION AND CAPACITY
ALLOCATION
Phase II : Network Optimization Models
The Capacitated Plant Location Model
Objective:
To decide on a network design that maximizes profits after taxes and
meets all the demands
Inputs :
• n = number of potential plant location/capacity
(each capacity will count as a separate location)
• m = number of markets or demand points
• Dj = annual demand from market j
• Ki = potential capacity of plant i
• fi = annualized fixed cost of keeping factory i open
• cij = cost of producing and shipping one unit from factory i to
market j
Kripa Shanker IIT Kanpur 4
(cost includes production, inventory, transportation, and duties)
MODELS FOR FACILTY LOCATION AND CAPACITY ALLOCATION
Constraints :
• Demand on each market point j be satisfied.
n
x D for j 1,2,......, m (all market points)
i1 ij j
• No plant can supply more than its capacity.
m
xij Ki yi for i 1,2,......, n (all plants)
j1
• Each plant is either open or closed.
yi =0 if the plant i is closed
1 KripaiShanker
if the plant is openIIT Kanpur 6
MODELS FOR FACILTY LOCATION AND CAPACITY ALLOCATION
PHASE III
PRODUCTION METHODS AVAILABLE
Desirable
Skill Needs, Response Time INFRASTRUCTURE
Sites
Gravity location models are used to find locations that minimize the cost of
transportation of raw materials from suppliers and finished goods to the markets
served
INPUTS :
(xn, yn) : coordinate location of either a market or supply source n
Fn : cost of shipping one unit for one unit of distance between facility and either
market or supply source n
Dn : quantity to be shipped between facility and either market or supply source n
Supply source
(xn, yn)
(x, y)
Market
Facility
The distance dn between the facility at location (x,y) and the supply source or
market n is given by d ( x x ) 2 ( y y ) 2
n n n
Inputs :
• n = number of factory locations xij j
Factories
i
Markets
• m = number of markets or demand points
• Dj = annual demand from market j
• Ki = capacity of factory i n m
• cij = cost of producing and shipping one unit from factory i to market j
(cost includes production, inventory, and transportation)
Decision Variables : xij = quantity shipped from factory i to market j
Kripa Shanker IIT Kanpur 9
MODELS FOR FACILTY LOCATION AND CAPACITY
ALLOCATION
Objective Function
n m xij j
Factories
Min cij xij i
Markets
i1 j 1
Constraints :
•Demand on each market point j be satisfied.
n m
n
x D for j 1,2,......, m (all market points)
i1 ij j
•No plant can supply more than its capacity.
m
xij K for i 1,2,......, n (all factories)
j1 i
Inputs :
• n = number of factories
• m = number of markets or demand points
• Dj = annual demand from market j
• Ki = capacity of factory i
• fi = annualized fixed cost of keeping factory i open
• cij = cost of producing and shipping one unit from factory i to
market j (cost includes production, inventory, transportation, and duties)
Decision Variables :
• yi = 1 if factory is located at site i , 0 otherwise
Kripa Shanker IIT Kanpur 11
• xij = 1 if market j is supplied by factory i
MODELS FOR FACILTY LOCATION AND CAPACITY ALLOCATION
DECSION VARAIBLES
yi = 1 if factory is located at site i; 0 otherwise
ye = 1 if warehouse is located at site e; 0 otherwise
xej = quantity shipped from warehouse e to market j
xie = quantity shipped from factory site i to warehouse e
xhi = quantity shipped from supplier h to factory at site i
Objective :
To decide on plant and warehouse locations as well as quantities
shipped between various points that minimize the total fixed and
variable costs.
n t l n n t t m
Min fi yi f e ye chi xhi cie xie cej xej
i 1 e 1 h 1 i 1 i 1 e 1 e 1 j 1
Kripa Shanker IIT Kanpur 14
MODELS FOR FACILTY LOCATION AND CAPACITY ALLOCATION
Locating Plants and Warehouses Simultaneously
Constraints :
1. Total amount shipped from a supplier cannot exceed the supplier’s capacity
Supplier (h)
Capacity=Sh n
n xhi
xhi sh for h 1,2,....,l (all supliers) Number=[ l ]
i1
i1
2. Total amount shipped out of a factory cannot exceed the quantity of raw material received
l t Factory (i)
hi xie for i 1,2,....., n (all factories)
x
l t
h1 e1 xhi xi
h1 Capacity=Ki
e1
3. Total amount produced in the factory cannot exceed its capacity Number=[ n ]
t
xie Ki yi for i 1,2,....., n (all factories)
e1
i i y , x 0,1 Number=[ t ]
m
ejx W y
e e for e 1,2,....., t (all warehouse)
j1
Constraints :
• Total shipment to a market point should not exceed the demand
(Demand on each market point j be satisfied).
n
xij D j for j1,2,......,m (all market points)
i1
• No plant can supply more than its capacity.
m
xij Ki yi for i 1,2,......, n (all plants)
j1
• Each plant is either open or closed.
yi = 0 if the plantKripa
i is Shanker
closed; 1IIT
if Kanpur
the plant i is open. 17