# Activity ID Activity Name Original Planned Start Planned Finish Actual Start Actual Finish May 2022 June 2022 July 2022 August 2022 September 2022 October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025
Duration
W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W1 W2 W3 W4 W5 W6 W7
1 OT3499 Modification of Purified Phosphoric Acid SX Plant Project in Ain Sokhna 800.63 17-May-22 30-Dec-24 17-May-22 30-Dec-24, OT3499 Modification of Purified Phosphoric Acid SX Plant Project in Ain Sok
39 OT3499.2.A Transport -Train 36 63.00 26-Nov-22 09-Feb-23 09-Feb-23, OT3499.2.A Transport -Train 36
40 OT3499.2.A.1 FRP internals/piping - Train 36 63.00 26-Nov-22 09-Feb-23 09-Feb-23, OT3499.2.A.1 FRP internals/piping - Train 36
41 A1250 Customer Clearance in Egypt for the entry of supply 60.00 26-Nov-22 06-Feb-23 Customer Clearance in Egypt for the entry of supply
42 A1140 Transfer of Supply to Sousse port 3.00 21-Jan-23 25-Jan-23 Transfer of Supply to Sousse port
43 A1220 Maritim Transport of Supply to Egyptian Port 10.00 25-Jan-23 06-Feb-23 Maritim Transport of Supply to Egyptian Port
44 A1230 Transport of Supply From Egyptia n Port to Plant 3.00 07-Feb-23 09-Feb-23 Transport of Supply From Egyptia n Port to Plant
45 OT3499.2.B Site Works -Train 36 285.00 30-Nov-22 03-Nov-23 03-Nov-23, OT3499.2.B Site Works -Train 36
46 OT3499.2.B.2 Dismantling Works -Train 36 46.00 30-Nov-22 24-Jan-23 24-Jan-23, OT3499.2.B.2 Dismantling Works -Train 36
47 OT3499.2.B.2.1 1st Batch -TRAIN 36 (16 pcs) Dismantling 38.00 30-Nov-22 13-Jan-23 13-Jan-23, OT3499.2.B.2.1 1st Batch -TRAIN 36 (16 pcs) Dismantling
48 A1030 B-1Cutting of interconnecting pipes 7.00 30-Nov-22 08-Dec-22 B-1Cutting of interconnecting pipes
49 A1010 B-1Dismantling Of settlers 16.00 08-Dec-22 27-Dec-22 B-1Dismantling Of settlers
50 A1080 B-1Loading, Transport & Unloading of settlers to Storage Area 7.00 27-Dec-22 04-Jan-23 B-1Loading, Transport & Unloading of settlers to Storage Area
51 A1290 B-1Dismantiling of SPIROK Unit 8.00 04-Jan-23 13-Jan-23 B-1Dismantiling of SPIROK Unit
52 A1300 B-1Dismantiling of AQ Launder Outlet Boxes 8.00 04-Jan-23 13-Jan-23 B-1Dismantiling of AQ Launder Outlet Boxes
53 A1410 B-1Dismantiling of ORG Launder Outlet Boxes 8.00 04-Jan-23 13-Jan-23 B-1Dismantiling of ORG Launder Outlet Boxes
54 OT3499.2.B.2.2 2nd Batch - TRAIN 36 (17 pcs) Dismantling 39.00 08-Dec-22 24-Jan-23 24-Jan-23, OT3499.2.B.2.2 2nd Batch - TRAIN 36 (17 pcs) Dismantling
55 A2600 B-2Cutting of interconnecting pipes 8.00 08-Dec-22 17-Dec-22 B-2Cutting of interconnecting pipes
56 A2610 B-2Dismantling Of settlers 16.00 17-Dec-22 05-Jan-23 B-2Dismantling Of settlers
57 A2620 B-2Loading, Transport & Unloading of settlers to Storage Area 7.00 05-Jan-23 13-Jan-23 B-2Loading, Transport & Unloading of settlers to Storage Area
58 A2650 B-2Dismantiling of SPIROK Unit 8.00 13-Jan-23 24-Jan-23 B-2Dismantiling of SPIROK Unit
59 A2640 B-2Dismantiling of AQ Launder Outlet Boxes 8.00 13-Jan-23 24-Jan-23 B-2Dismantiling of AQ Launder Outlet Boxes
60 A2630 B-2Dismantiling of ORG Launder Outlet Boxes 7.00 13-Jan-23 23-Jan-23 B-2Dismantiling of ORG Launder Outlet Boxes
61 OT3499.2.B.2.3 DOP Tanks 1st Batch (17 Pcs) Dismantling 15.00 04-Jan-23 23-Jan-23 23-Jan-23, OT3499.2.B.2.3 DOP Tanks 1st Batch (17 Pcs) Dismantling
62 A1050 B-1Dismantiling of DOP Unit 15.00 04-Jan-23 23-Jan-23 B-1Dismantiling of DOP Unit
63 OT3499.2.B.3 Installation Works -Train 36 247.81 13-Jan-23 03-Nov-23 03-Nov-23, OT3499.2.B.3 Installation Works -Train 36
64 OT3499.2.B.3.1 1st Batch - TRAIN 36 (16 pcs) Installation 245.81 13-Jan-23 02-Nov-23 02-Nov-23, OT3499.2.B.3.1 1st Batch - TRAIN 36 (16 pcs) Installation
65 A1210 B-1Installation of new settlers 27.00 13-Jan-23 14-Feb-23 B-1Installation of new settlers
66 A1330 B-1Installation of Repaired SPIROK Unit 16.00 19-Apr-23 09-May-23 B-1Installation of Repaired SPIROK Unit
67 A1340 B-1Installaion of Repaired AQ Launder Outlet Boxes 11.00 11-Aug-23 24-Aug-23 B-1Installaion of Repaired AQ Launder Outlet Boxes
68 A1420 B-1Installaion of Repaired ORG Launder Outlet Boxes 11.00 14-Sep-23 27-Sep-23 B-1Installaion of Repaired ORG Launder Outlet Boxes
69 A1310 B-1Interconnecting piping works 19.00 27-Sep-23 19-Oct-23 B-1Interconnecting piping works
70 A1740 B-1Commissionning and Testing 11.00 19-Oct-23 02-Nov-23 B-1Commissionning and Testing
71 OT3499.2.B.3.2 2nd Batch - TRAIN 36 (17 pcs) Installation 230.19 03-Feb-23 03-Nov-23 03-Nov-23, OT3499.2.B.3.2 2nd Batch - TRAIN 36 (17 pcs) Installation
72 A2740 B-2Installation of new settlers 27.00 03-Feb-23 07-Mar-23 B-2Installation of new settlers
73 A2770 B-2Installation of Repaired SPIROK Unit 16.00 19-Apr-23 09-May-23 B-2Installation of Repaired SPIROK Unit
74 A2780 B-2Installaion of Repaired AQ Launder Outlet Boxes 11.00 11-Aug-23 24-Aug-23 B-2Installaion of Repaired AQ Launder Outlet Boxes
75 A2790 B-2Installaion of Repaired ORG Launder Outlet Boxes 11.00 14-Sep-23 27-Sep-23 B-2Installaion of Repaired ORG Launder Outlet Boxes
76 A2750 B-2Interconnecting piping works 19.00 27-Sep-23 19-Oct-23 B-2Interconnecting piping works
77 A2800 B-2Commissionning and Testing 13.00 19-Oct-23 03-Nov-23 B-2Commissionning and Testing
78 OT3499.2.B.3.3 DOP Tanks 1st Batch (17 Pcs) Installation 15.00 22-Feb-23 11-Mar-23 11-Mar-23, OT3499.2.B.3.3 DOP Tanks 1st Batch (17 Pcs) Installation
79 A1320 B-1Installation of New DOP Unit 15.00 22-Feb-23 11-Mar-23 B-1Installation of New DOP Unit
80 OT3499.2.B.1 Reparation Works -Train 36 196.00 24-Jan-23 14-Sep-23 14-Sep-23, OT3499.2.B.1 Reparation Works -Train 36
81 OT3499.2.B.1.7 SPIROK Unit Reparation (x17) -Train 36 72.00 24-Jan-23 19-Apr-23 19-Apr-23, OT3499.2.B.1.7 SPIROK Unit Reparation (x17) -Train 36
82 A1490 Dismantling of SPIROK Roof (shaft+Steel) 9.00 24-Jan-23 03-Feb-23 Dismantling of SPIROK Roof (shaft+Steel)
83 A1500 Preparation activities (cleaning..) 8.00 03-Feb-23 13-Feb-23 Preparation activities (cleaning..)
84 A1450 Reparation of Liner (x17) 30.00 13-Feb-23 21-Mar-23 Reparation of Liner (x17)
85 A1470 Installation of new nozzles and internals (x17) 19.00 21-Mar-23 12-Apr-23 Installation of new nozzles and internals (x17)
86 A1480 Post-curing (x17) 6.00 12-Apr-23 19-Apr-23 Post-curing (x17)
87 OT3499.2.B.1.6 Reparation of Strip & Raffinate After Settlers, Concentrator Feed & loaded organic Tanks -Train 36 68.00 19-Apr-23 10-Jul-23 10-Jul-23, OT3499.2.B.1.6 Reparation of Strip & Raffinate After Settlers, Concentrator Feed & loaded organic Tanks -Train 36
88 A1650 Preparation activities (cleaning...) 3.00 19-Apr-23 22-Apr-23 Preparation activities (cleaning...)
89 A1630 Removing of nozzles and internals 3.00 22-Apr-23 26-Apr-23 Removing of nozzles and internals
90 A1040 Reparation of liner 26.00 26-Apr-23 27-May-23 Reparation of liner
91 A1640 Installation of new nozzles and internals 16.00 27-May-23 15-Jun-23 Installation of new nozzles and internals
92 A1610 Post-curing 9.00 15-Jun-23 26-Jun-23 Post-curing
93 A1060 Hydrotest 11.00 27-Jun-23 10-Jul-23 Hydrotest
94 OT3499.2.B.1.8 AQ Launder Outlet Boxes Reparation (x17) -Train 36 28.00 10-Jul-23 11-Aug-23 11-Aug-23, OT3499.2.B.1.8 AQ Launder Outlet Boxes Reparation (x17) -Train 36
95 A1550 Preparation activities (Cleaning...) 3.00 10-Jul-23 13-Jul-23 Preparation activities (Cleaning...)
96 A1520 Removing of nozzles 2.00 13-Jul-23 14-Jul-23 Removing of nozzles
97 A1510 Reparation of Liner (x17) 12.00 15-Jul-23 29-Jul-23 Reparation of Liner (x17)
98 A1530 Installation of new nozzles (x17) 7.00 29-Jul-23 07-Aug-23 Installation of new nozzles (x17)
99 A1540 Post-curing (x17) 4.00 07-Aug-23 11-Aug-23 Post-curing (x17)
100 OT3499.2.B.1.9 ORG Launder Outlet Boxes Reparation (x17) -Train 36 28.00 11-Aug-23 14-Sep-23 14-Sep-23, OT3499.2.B.1.9 ORG Launder Outlet Boxes Reparation (x17) -Train 36
101 A1620 Preparation activities (Cleaning...) 3.00 11-Aug-23 15-Aug-23 Preparation activities (Cleaning...)
102 A1580 Removing of nozzles 2.00 15-Aug-23 17-Aug-23 Removing of nozzles
103 A1570 Reparation of Liner (x17) 12.00 17-Aug-23 31-Aug-23 Reparation of Liner (x17)
104 A1590 Installation of new nozzles (x17) 7.00 31-Aug-23 08-Sep-23 Installation of new nozzles (x17)
105 A1600 Post-curing (x17) 4.00 09-Sep-23 14-Sep-23 Post-curing (x17)
106 OT3499.2.C Workshop Activities -Train 36 73.00 27-Oct-22 21-Jan-23 21-Jan-23, OT3499.2.C Workshop Activities -Train 36
107 OT3499.2.C.1 FRP Supply -Train 36 73.00 27-Oct-22 21-Jan-23 21-Jan-23, OT3499.2.C.1 FRP Supply -Train 36
108 A1070 Piping Fabrication 16.00 27-Oct-22 15-Nov-22 Piping Fabrication
109 A1350 Fittings Fabrication 25.00 27-Oct-22 25-Nov-22 Fittings Fabrication
110 A1460 Internals Fabrication 16.00 27-Oct-22 15-Nov-22 Internals Fabrication
111 A1360 Pre-fabrication of spools 20.00 25-Nov-22 20-Dec-22 Pre-fabrication of spools
112 A1370 Post-curing 17.00 20-Dec-22 09-Jan-23 Post-curing
113 A1380 Painting 11.00 09-Jan-23 21-Jan-23 Painting
114 OT3499.3 Phase 3B - Mixer Settler Area (Existing Modules, Unit 34) 560.06 27-Oct-22 23-Aug-24 23-Aug-24, OT3499.3 Phase 3B - Mixer Settler Area (Existing Modules, Unit 34)
115 OT3499.3.A Transport -Train 34 63.00 26-Nov-22 09-Feb-23 09-Feb-23, OT3499.3.A Transport -Train 34
116 OT3499.3.A.1 FRP internals/piping - Train 34 63.00 26-Nov-22 09-Feb-23 09-Feb-23, OT3499.3.A.1 FRP internals/piping - Train 34
117 A1950 Customer Clearance in Egypt for the entry of Supply 60.00 26-Nov-22 06-Feb-23 Customer Clearance in Egypt for the entry of Supply
118 A1910 Transfer of Supply to Sousse port 3.00 21-Jan-23 25-Jan-23 Transfer of Supply to Sousse port
119 A1920 Maritim Transport of Supply to Egyptian Port 10.00 25-Jan-23 06-Feb-23 Maritim Transport of Supply to Egyptian Port
120 A1930 Transport of Supply From Egyptia n Port to Plant 3.00 07-Feb-23 09-Feb-23 Transport of Supply From Egyptia n Port to Plant
121 OT3499.3.B Site Works -Train 34 309.56 22-Aug-23 23-Aug-24 23-Aug-24, OT3499.3.B Site Works -Train 34
122 OT3499.3.B.1 Liquid Pumping from Train 34 to train 36 8.00 22-Aug-23 30-Aug-23 30-Aug-23, OT3499.3.B.1 Liquid Pumping from Train 34 to train 36
123 A3230 Liquid Pumping from Train 34 to train 36 8.00 22-Aug-23 30-Aug-23 Liquid Pumping from Train 34 to train 36
124 OT3499.3.B.2 Dismantling Works -Train 34 46.00 20-Sep-23 14-Nov-23 14-Nov-23, OT3499.3.B.2 Dismantling Works -Train 34
125 OT3499.3.B.2.1 5th Batch - TRAIN 34 (16 pcs) Dismantling 38.00 20-Sep-23 03-Nov-23 03-Nov-23, OT3499.3.B.2.1 5th Batch - TRAIN 34 (16 pcs) Dismantling
126 A2880 B-5Cutting of interconnecting pipes 7.00 20-Sep-23 28-Sep-23 B-5Cutting of interconnecting pipes
127 A2890 B-5Dismantling Of settlers 16.00 28-Sep-23 17-Oct-23 B-5Dismantling Of settlers
128 A2900 B-5Loading, Transport & Unloading of settlers to Storage Area (By Client) 7.00 17-Oct-23 25-Oct-23 B-5Loading, Transport & Unloading of settlers to Storage Area (By Client)
129 A2930 B-5Dismantiling of SPIROK Unit 8.00 25-Oct-23 03-Nov-23 B-5Dismantiling of SPIROK Unit
130 A2920 B-5Dismantiling of AQ Launder Outlet Boxes 8.00 25-Oct-23 03-Nov-23 B-5Dismantiling of AQ Launder Outlet Boxes
131 A2910 B-5Dismantiling of ORG Launder Outlet Boxes 8.00 25-Oct-23 03-Nov-23 B-5Dismantiling of ORG Launder Outlet Boxes
132 OT3499.3.B.2.2 6th Batch - TRAIN 34 (17 pcs) Dismantling 39.00 28-Sep-23 14-Nov-23 14-Nov-23, OT3499.3.B.2.2 6th Batch - TRAIN 34 (17 pcs) Dismantling
133 A2950 B-6Cutting of interconnecting pipes 8.00 28-Sep-23 07-Oct-23 B-6Cutting of interconnecting pipes
134 A2960 B-6Dismantling Of settlers 16.00 07-Oct-23 26-Oct-23 B-6Dismantling Of settlers
135 A2970 B-6Loading, Transport & Unloading of settlers to Storage Area (By Client) 7.00 26-Oct-23 03-Nov-23 B-6Loading, Transport & Unloading of settlers to Storage Area (By Client)
136 A3000 B-6Dismantiling of SPIROK Unit 8.00 03-Nov-23 14-Nov-23 B-6Dismantiling of SPIROK Unit
137 A2990 B-6Dismantiling of AQ Launder Outlet Boxes 8.00 03-Nov-23 14-Nov-23 B-6Dismantiling of AQ Launder Outlet Boxes
138 A2980 B-6Dismantiling of ORG Launder Outlet Boxes 7.00 03-Nov-23 13-Nov-23 B-6Dismantiling of ORG Launder Outlet Boxes
139 OT3499.3.B.2.3 DOP Tanks 2nd Batch (17 Pcs) Dismantling 15.00 25-Oct-23 13-Nov-23 13-Nov-23, OT3499.3.B.2.3 DOP Tanks 2nd Batch (17 Pcs) Dismantling
140 A2940 B-2Dismantiling of DOP Unit 15.00 25-Oct-23 13-Nov-23 B-2Dismantiling of DOP Unit
141 OT3499.3.B.3 Installation Works -Train 34 255.00 25-Oct-23 23-Aug-24 23-Aug-24, OT3499.3.B.3 Installation Works -Train 34
142 OT3499.3.B.3.1 5th Batch - TRAIN 34 (16 pcs) Installation 253.00 25-Oct-23 21-Aug-24 21-Aug-24, OT3499.3.B.3.1 5th Batch - TRAIN 34 (16 pcs) Installation
143 A3130 B-5Installation of new settlers 27.00 25-Oct-23 27-Nov-23 B-5Installation of new settlers
144 A3090 B-5Installation of Repaired SPIROK Unit 16.00 07-Feb-24 26-Feb-24 B-5Installation of Repaired SPIROK Unit
145 A3100 B-5Installaion of Repaired AQ Launder Outlet Boxes 11.00 31-May-24 13-Jun-24 B-5Installaion of Repaired AQ Launder Outlet Boxes
146 A3110 B-5Installaion of Repaired ORG Launder Outlet Boxes 11.00 04-Jul-24 17-Jul-24 B-5Installaion of Repaired ORG Launder Outlet Boxes
147 A3150 B-5Interconnecting piping works 19.00 17-Jul-24 08-Aug-24 B-5Interconnecting piping works
148 A3120 B-5Commissionning and Testing 11.00 08-Aug-24 21-Aug-24 B-5Commissionning and Testing
149 OT3499.3.B.3.2 6th Batch - TRAIN 34 (17 pcs) Installation 247.00 03-Nov-23 23-Aug-24 23-Aug-24, OT3499.3.B.3.2 6th Batch - TRAIN 34 (17 pcs) Installation
150 A3200 B-6Installation of new settlers 27.00 03-Nov-23 06-Dec-23 B-6Installation of new settlers
151 A3160 B-6Installation of Repaired SPIROK Unit 16.00 07-Feb-24 26-Feb-24 B-6Installation of Repaired SPIROK Unit
152 A3170 B-6Installaion of Repaired AQ Launder Outlet Boxes 11.00 31-May-24 13-Jun-24 B-6Installaion of Repaired AQ Launder Outlet Boxes
153 A3180 B-6Installaion of Repaired ORG Launder Outlet Boxes 11.00 04-Jul-24 17-Jul-24 B-6Installaion of Repaired ORG Launder Outlet Boxes
154 A3220 B-6Interconnecting piping works 19.00 17-Jul-24 08-Aug-24 B-6Interconnecting piping works
155 A3190 B-6Commissionning and Testing 13.00 08-Aug-24 23-Aug-24 B-6Commissionning and Testing
156 OT3499.3.B.3.3 DOP Tanks 2nd Batch (17 Pcs) Installation 15.00 13-Nov-23 30-Nov-23 30-Nov-23, OT3499.3.B.3.3 DOP Tanks 2nd Batch (17 Pcs) Installation
157 A3140 B-2Installation of New DOP Unit 15.00 13-Nov-23 30-Nov-23 B-2Installation of New DOP Unit
158 OT3499.3.B.4 Reparation Works -Train 34 196.00 14-Nov-23 04-Jul-24 04-Jul-24, OT3499.3.B.4 Reparation Works -Train 34
159 OT3499.3.B.4.7 SPIROK Unit Reparation (x17) -Train 34 72.00 14-Nov-23 07-Feb-24 07-Feb-24, OT3499.3.B.4.7 SPIROK Unit Reparation (x17) -Train 34
160 A2160 Dismantling of SPIROK Roof (shaft+Steel) 9.00 14-Nov-23 23-Nov-23 Dismantling of SPIROK Roof (shaft+Steel)
161 A2190 Preparation activities (cleaning..) 8.00 24-Nov-23 04-Dec-23 Preparation activities (cleaning..)
162 A2150 Reparation of Liner (x17 30.00 04-Dec-23 09-Jan-24 Reparation of Liner (x17
163 A2170 Installation of new nozzles and internals (x17) 19.00 09-Jan-24 31-Jan-24 Installation of new nozzles and internals (x17)
164 A2180 Post-curing (x17) 6.00 31-Jan-24 07-Feb-24 Post-curing (x17)
165 OT3499.3.B.4.6 Reparation of Strip & Raffinate After Settlers, Concentrator Feed & loaded organic Tanks -Train 34 68.00 07-Feb-24 29-Apr-24 29-Apr-24, OT3499.3.B.4.6 Reparation of Strip & Raffinate After Settlers, Concentrator Feed & loaded organic Tanks -Train 34
166 A2390 Preparation activities (cleaning..) 3.00 07-Feb-24 10-Feb-24 Preparation activities (cleaning..)
167 A2360 Removing of nozzles and internals 3.00 10-Feb-24 14-Feb-24 Removing of nozzles and internals
168 A2380 Reparation of liner 26.00 14-Feb-24 15-Mar-24 Reparation of liner
169 A2370 Installation of new nozzles and internals 16.00 15-Mar-24 04-Apr-24 Installation of new nozzles and internals
170 A2340 Post-curing 9.00 04-Apr-24 15-Apr-24 Post-curing
171 A2350 Hydrotest 11.00 15-Apr-24 29-Apr-24 Hydrotest
172 OT3499.3.B.4.8 AQ Launder Outlet Boxes Reparation (x17) -Train 34 28.00 29-Apr-24 31-May-24 31-May-24, OT3499.3.B.4.8 AQ Launder Outlet Boxes Reparation (x17) -Train 34
173 A2220 Preparation activities (cleaning..) 3.00 29-Apr-24 01-May-24 Preparation activities (cleaning..)
174 A2250 Removing of nozzles 2.00 01-May-24 03-May-24 Removing of nozzles
175 A2210 Reparation of Liner (x17) 12.00 03-May-24 18-May-24 Reparation of Liner (x17)
176 A2230 Installation of new nozzles (x17) 7.00 18-May-24 27-May-24 Installation of new nozzles (x17)
177 A2240 Post-curing (x17) 4.00 27-May-24 31-May-24 Post-curing (x17)
178 OT3499.3.B.4.9 ORG Launder Outlet Boxes Reparation (x17) -Train 34 28.00 31-May-24 04-Jul-24 04-Jul-24, OT3499.3.B.4.9 ORG Launder Outlet Boxes Reparation (x17) -Train 34
179 A2280 Preparation activities (cleaning..) 3.00 31-May-24 04-Jun-24 Preparation activities (cleaning..)
180 A2310 Removing of nozzles 2.00 04-Jun-24 06-Jun-24 Removing of nozzles
181 A2270 Reparation of Liner (x17) 12.00 06-Jun-24 20-Jun-24 Reparation of Liner (x17)
182 A2290 Installation of new nozzles (x17) 7.00 20-Jun-24 28-Jun-24 Installation of new nozzles (x17)
183 A2300 Post-curing (x17) 4.00 28-Jun-24 04-Jul-24 Post-curing (x17)
184 OT3499.3.C Workshop Activities -Train 34 73.00 27-Oct-22 21-Jan-23 21-Jan-23, OT3499.3.C Workshop Activities -Train 34
185 OT3499.3.C.1 FRP Supply -Train 34 73.00 27-Oct-22 21-Jan-23 21-Jan-23, OT3499.3.C.1 FRP Supply -Train 34
186 A1770 Piping Fabrication 16.00 27-Oct-22 15-Nov-22 Piping Fabrication
187 A2070 Fittings Fabrication 25.00 27-Oct-22 25-Nov-22 Fittings Fabrication
188 A2110 Internal Fabrication 16.00 27-Oct-22 15-Nov-22 Internal Fabrication
189 A2080 Pre-fabrication of spools 20.00 25-Nov-22 20-Dec-22 Pre-fabrication of spools
190 A2090 Post-curing 17.00 20-Dec-22 09-Jan-23 Post-curing
191 A2100 Painting 11.00 09-Jan-23 21-Jan-23 Painting
Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: All Activities