You are on page 1of 1

SCHEDULE "Q" CONTRACT NO.

6600041347

SCHEDULE "Q"

QUALITY REQUIREMENTS FOR CIVIL WORKS

1 GENERAL

1.1 This Schedule describes COMPANY's minimum requirements for


CONTRACTOR's Quality Management System

1.2 CONTRACTOR shall be totally responsible for the quality of WORK


required by th is Contract.

1.3 CONTRACTOR shall inspect, test and verify all parts of the WORK as
defined in hedule "S" nd individual Purchase Order where applicable,
including Subcontra ors' WORK, in conformance with the Job
Specification, and all drawings, specifications and standards applicable to
the WORK .

1.4 COMPANY shall be entitled to have the Company Representative or his


nominee present at all locations where CONTRACTOR or its
Subcontractors or Vendors are engaged in the performance of the WORK,
at any and all times, to review all aspects of CONTRACTOR's Quality
activities and to witness whatever inspection and testing is required by this
Contract. COMPANY retains the right to conduct whatever additional tests
or inspections it deems necessary to assure that the Materials and
personnel performing the activities meet the requirements of the Contract.
CONTRACTOR shall not refuse access to technical or other data which
CONTRACTOR considers proprietary or confidential, but which is
reasonably required to inspect CONTRACTOR's performance of the
WORK. Where the nominee of Company Representative is a competitor of
CONTRACTOR in the sale, engineering, or installation of systems similar
to the FACILITIES or is related to or affiliated with such a firm, the Company
Representative may nominate an alternate.

1.5 COMPANY will complete its review of CONTRACTOR's Quality documents


(Qualit~ Plan and Inspectio & Test s) and Rersonnel gUflljficatiQlls no
More t an thirty calendar days after submittal of a document or its
subsequent modifications . Following its initial review, COMPANY will
approve or provisionally approve the submitted document or personnel
qualification, or it will reject the document with comments.

1.6 The foregoing or any other provisions elsewhere in this Contract


notwithstanding, in no event shall CONTRACTOR commence WORK
directly related to the actual physical installation of the FACILITIES prior to
obtaining COMPANY's written approval of CONTRACTOR's Quality Plan.