The activity relationships are given in the table below

immediate Duration Cost in Resource


Activity predecessors in days 1000 INR per day
A 6 24 4
B 4 12 5
C A 5 20 2
D A 7 29 3
E B 6 26 4
F B 8 34 3
G C,E 10 27 6
H D,F 9 34 5

a. Draw the Activity on Arrow and Activity at Node Network (5+5 = 10)

b. Show the critical path and compute maximum time to complete the work (5)

c. Draw a time vs cost diagram for the above problem to find out the minimum cost (30)

d. Show how much resource need to be allocated daily for the final network. (15)