Professional Documents
Culture Documents
Author Profile:
Page 1 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
A INTRODUCTION
A.1 GENERAL
Cranes are designed for a finite lifetime duty, which is specified in load cycles and load
spectrum and is not principally related to calendar working time. Classification of crane duty
provides the crane owner a means to specify the intended duty in order to achieve the
intended useful operational lifetime of the crane.
Typically the operational period for industrial cranes is from 10 to 20 years. However, a
specified crane classification may be related to any calendar time depending on the
application, e.g. 5 to 10 years for a special limited use or 40 years for a long-term
investment.
Monitoring of crane use does not in any way change requirements for periodic inspections
of the cranes, independent of whatever type of instruments are used for the monitoring.
Neither does it remove the requirement for regular maintenance of cranes. Inspections and
monitoring of use are methods, which complete each other, giving different information of
the condition.
The design working period (DWP) calculation in in this report is based on the ISO
12482:2014, and is derived from the design classification of cranes and is not to be
considered as a guaranteed operational period in any respect. Due to the probabilistic nature
of metal fatigue and other influencing factors, premature failures during the DWP cannot be
ruled out. However, the DWP represents a reliable estimate of a safe operational period of
the crane, with due consideration to specified design regulations and standardized design
safety factors.
The purpose of the assessment of DWP is to estimate accumulated duty of the crane and
assess its remaining life. The DWP calculation shall cover both the crane as a whole
(structures) and the mechanisms.
It is assumed that:
--- all periodic inspections scheduled for the crane have been carried out,
--- any damage suffered during the operation is recorded and appropriately repaired, and
--- maintenance work, as well as replacement of worn parts, is carried out in accordance
with the manufacturer’s instructions.
The applied DWP calculation method should follow the specification and classification of
the original design Standard, as closely as possible. ISO 12482-1 give DWP calculation
methods for cranes classified and designed in accordance with ISO 4301-1.
Page 2 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
m
Vh = Hoisting Speed Vh ≔ 2.0 ――
min
length ((N))
Ca ≔ ∑ N = 3.154 ⋅ 10 3
i
i=1
P T = [[ 0 8 16 24 32 40 ]] tonne
Page 3 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
B.1 GENERAL
Two basic duty factors and the crane classification as a combination of the two duty factors
are given in the applicable Part of FEM 1.001, as follows:
The two duty factors are of equal relevance. The DWP of the crane is reached when any
criterion reaches its design value. It is then an issue for the special assessment to find out
which of the crane components are critical in respect to each duty factor.
In cases where the manufacturer has specified the class of utilization for the crane, the
design limit for the number of work cycles, DN , shall be taken from Table A.1, ISO
12482-1.
The DWP of the crane is reached — i.e. the actual duty has reached the design limit in
respect of the total number of working cycles — when:
f1 ⋅ Ca = DN
Page 4 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
A starting point of this clause is that design limits for the parameters, number of work cycles
and load spectrum factor, are specified separately.
In cases where the manufacturer has specified the load spectrum class for the crane, the
design value for the load spectrum factor, Kp , shall be taken from Table A.2, ISO 12482.
For calculation of the load spectrum class from the actual operation history, values of
payloads from each working cycle must be recorded or estimated.
The DWP of the crane is reached — i.e. the actual duty has reached the design limit in
respect of cumulative loading — when:
Ca
⎛ Pi ⎞ 3
f1 ⋅ ∑ ⎜―⎟ = KP ⋅ DN
i=1 ⎝ P ⎠
Page 5 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
This clause applies to cases where the basic duty factors or their classes are not specified
separately and the crane classification only is known. In the DWP calculation, the load
spectrum and the number of work cycles are combined and converted to correspond to the
state of loading, KP = 1 .
The DWP of the crane is reached, that is the actual duty has reached the design limit in
respect to crane classification, when:
Ca
⎛ Pi ⎞ 3
f1 ⋅ ∑ ⎜―⎟ = DC
i=1 ⎝ P ⎠
Page 6 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
length ((N))
⎛ P ⎞3 length ((N))
⎛ P ⎞3
⎜ i ⎟ ⎜ i ⎟
f1 ⋅ ∑ N ⋅ ⎜―― ⎟ = KP ⋅ DN f1 ⋅ ∑ α ⋅ AN ⋅ ⎜―― ⎟ = KP ⋅ DN
i=1
i
⎝ Pmax ⎠ i=1
i
⎝ Pmax ⎠
AN = 2.444 ⋅ 10 4
Page 7 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
C.1 GENERAL
Two basic duty factors and the class of mechanism as a combination of the two duty factors
are dealt with as follows:
In cases where the manufacturer has specified the state of loading through the L-class of the
load spectrum factor, the design value for this shall be taken from Table B.1, ISO 12482
Otherwise a crane-specific value of KmD shall be used.
In cases where the manufacturer has specified the total duration of use through the
classification, the design limit for the total duration of use, DT , shall be taken from Table
B.2., ISO 12482 Otherwise, a crane-specific value of DT shall be used.
Page 8 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
For calculation of the cumulative loading for a hoist mechanism, values of total hoisted
loads from each work cycle must be recorded or estimated. Both the effective, working part
of the load cycle and the return part of the work cycle shall be considered.
The DWP of the hoist mechanism is reached — i.e. the actual duty has reached the design
limit — when:
⎛ 3 ⎞
Ca
⎜ ⎛ Pi + PA ⎞ ⎛ PA ⎞3 ⎟
f1 ⋅ ∑ t ⎜―――― ⎟ + tRi ⎜―――― ⎟ ⎟ = KmD ⋅ DT
⎜i
i=1 ⎝ ⎝ Pmax + PA ⎠ ⎝ Pmax + PA ⎠ ⎠
Pmax is the rated value of the payload for the Pmax = 40 tonne
crane
Page 9 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
ti = 3 min
KmD is the design value for the load spectrum KmD = 0.25
factor of the mechanism, see Table B.1.
This clause applies to cases where the basic duty factors or their classes are not separately
specified and the mechanism classification only is known. In the DWP calculation, the load
spectrum and the total operation time are combined and converted to correspond the state of
loading, Km = 1 .
The DWP of the hoist mechanism is reached — i.e. the actual duty has reached the design
classification— when:
⎛ 3 ⎞
Ca
⎜ ⎛ Pi + PA ⎞ ⎛ PA ⎞3 ⎟
f1 ⋅ ∑ t ⎜―――― ⎟ + tRi ⎜―――― ⎟ ⎟ = DM
⎜i
i=1 ⎝ P
⎝ max + P P + P
A⎠ ⎝ max ⎠ ⎠
A
DM is the design limit for converted number of the total operation time according to Table B.3,
ISO 12482:
Page 10 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
⎛ 3 ⎞
⎜ ⎛ P + PA ⎞ 3⎟
Ca
⎜ i ⎟ ⎛ PA ⎞
f1 ⋅ ∑ ⎜t ――――
⎜P ⎟ + tRi ⎜―――― ⎟ ⎟ = KmD ⋅ DT
i=1 ⎜
⎝i ⎝ max + PA ⎠ ⎝ Pmax + PA ⎠ ⎟⎠
ti = αi ⋅ Tactual tRi = 0
⎛ 3⎞
Tactual is the actual length ((N)) ⎜
⎛ P + PA ⎞ ⎟
⎜α ⎜―――― ⎟ ⎟
i
limit for the total f1 ⋅ Tactual. ∑ = KmD ⋅ DT
operation time. i=1 ⎜⎝ i ⎝ Pmax + PA ⎟⎠ ⎠⎟
⎜
KmD ⋅ DT
Tactual ≔ ――――――――― = ⎛⎝5.853 ⋅ 10 3 ⎞⎠ hr
⎛ 3 ⎞
length ((N)) ⎜
⎛ P + PA ⎞ ⎟
⎜ i ⎟ ⎟
f1 ∑ ⎜α ⎜――――
i=1 ⎜⎝ i ⎝ Pmax + PA ⎟⎠ ⎟⎠
Tactual = ⎛⎝5.853 ⋅ 10 3 ⎞⎠ hr
Tremaining = ⎛⎝5.695 ⋅ 10 3 ⎞⎠ hr
General overhaul (GO) is a set of repair, replacement and maintenance actions, which are
necessary for the safety of the further use of the crane. Some issues may require immediate
actions; some may be postponed, in which the case these actions shall be scheduled
according to the future duty of the crane.
Page 11 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
INDEX
m
Vh = hoisting speed [m/min] Vh = 2 ――
min
Page 12 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
Appliances as a whole are classified in eight groups, designated by the symbol A1, A2, ...,
A8 respectively (see section 2.1.2.4.), on the basis of ten classes of utilization and four load
spectra.
r
⎛ n ⎞ ⎛ P ⎞3
⎜ i ⎟ ⎜ i ⎟
The Load Spectrum Factor Kp = ∑ ⎜―― ⎟ ⋅ ⎜―― ⎟
i=1 ⎝ nmax ⎠ ⎝ Pmax ⎠
r
⎛ P ⎞3
⎜ i ⎟
Kp = ∑ αi ⋅ ⎜―― ⎟
i=1 ⎝ Pmax ⎠
The relative Percentages of T
working cycles for each load α ≔ [[ 0 60 0 30 10 0 ]]
Page 13 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
Class of Utilization: U is determined according to number of hoisting cycles (n) during the
life time of crane. Crane lifetime can be determined according to customer's requirements.
Dw = Working days/week Dw ≔ 5
Wy ≔ 48 = Working weeks/years Wy ≔ 48
nmax_d = 1.344 ⋅ 10 5
Crane Group:
Page 14 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
r
⎛ t ⎞ ⎛ P ⎞3
⎜ i ⎟ ⎜ i ⎟
Load Spectrum Class Km = ∑ ⎜―― ⎟ ⋅ ⎜―― ⎟
i=1 ⎝ tmax ⎠ ⎝ Pmax ⎠
r
⎛ P ⎞3
⎜ i ⎟
Kp = ∑ αm ⋅ ⎜―― ⎟
i=1
i
⎝ Pmax ⎠
Page 15 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
Dw = Working days/week Dw ≔ 5
Wy ≔ 48 = Working weeks/years Wy ≔ 48
m
Vh = hoisting speed [m/min] Vh ≔ 2 ――
min
2 ⋅ H ⋅ N ⋅ T ⋅ Dw ⋅ Wy ⋅ Lm_yrs
Total life time [h] Tmax ≔ ―――――――――
Vh
Tmax = ⎛⎝6.72 ⋅ 10 3 ⎞⎠ hr
Page 16 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
Individual Classification
Page 17 of 18
CRANE SAFETY ASSESSMENT OF DESIGN CRANE RISK
ASSESSMENT WORKING PERIOD (DWP) ASSESSMENT
REFERENCES:
Site Inspection
Page 18 of 18