Professional Documents
Culture Documents
2020
S.No Description Civil Dwg Panel location DWG Remarks
Mech Location GA dwg not received for
1 RAW MILL HYDRAULIC PANEL ROOM Received Done Lubrication & grease spray system
2 COOLER HYDRAULIC PANEL ROOM Not released
Mech Location GA dwg not received for
3 CEMENT MILL HYDRAULIC PANEL ROOM Received Done Lubrication & grease spray system
4 GAS ANALYSIER (SOx+NOx) - CEM ANALYSER - 97.6 mtr level Not released
5 GAS ANALYSERS (CO+O2) AT PH-1 OUTLET - 97.6 mtr level Not released
6 GAS ANALYSERS (CO+O2+NOx) AT PC-1 OUTLET - 59.8 mtr level Received Done
7 GAS ANALYSERS (CO+O2+NOx) AT KILN INLET 461 KL1 - 13 mtr level Received Done
8 CABINET FOR CO+O2 GAS ANALYSIS BAG FILTER L41 BF3 Not released
9 COAL MILL CO2 SYSTEM ROOM Not released
Tower dwg not
10 CABINET FOR KILN SHELL SCANNER
released
We sent mail to FLS for tower design