Nov-20 Dec-20 Jan-21 Feb-21

S.No Description
1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk
PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL

1 MRSS 22 0 32 0 39 0 31 0 17 0 10 0 10 0 4 0
2 CRUSHER 4 0 14 0 42 0 26 0 36 0 22 0 2 0 0 0
3 RMBH LC 18 0 30 0 63 0 79 0 78 0 70 0 64 0 48 0 11 0 11 0 8 0 8 0 4 0 4 0 0 0 0 0
4 COOLER LC 56 0 56 0 76 0 80 0 92 0 96 0 82 0 84 0 16 0 4 0 4 0 4 0
5 CEMENT MILL LC 18 0 24 0 60 0 84 0 70 0 60 0 56 0 56 0 56 0 64 0 28 0 14 0 12 0 14 0 4 0 0 0
6 CCR & ROBO LAB 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 6 0 6 0 6 0

7 SCS ROOMS 0 0 8 0 32 0 14 0 4 0 0 0 0 0 0 0 4 0 0 0 0 0 0 0
Total 36 0 54 0 123 0 163 0 216 0 206 0 240 0 210 0 201 0 229 0 211 0 175 0 101 0 60 0 26 0 14 0
E&I ERECTION SCHEDULE- MRSS
Jan-21 Feb-21
S.NO DESCRIPTION OF ACTIVITY
1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk

MRSS TO ALL LOAD CENTERS PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL
TRAY ERECTION
1 MRSS CELLAR TRAY 4
2 PANELS ERECTION 6 6
3 MRSS INSIDE CABLE LAYING 4
4 ERECTION OF PTR & NGR 5 5
5 BUS DUCT ERECTION 5
6 ROUTE A MRSS TO CEMENT MILL BUILDING ( COMMON ROUTE FOR ALL LCs) - 30 MTRS 4
7 ROUTE B & A1 FROM ROUTE A TO CEMENT MILL LOAD CENTER - 70 MTRS 4 4
8 ROUTE C FROM ROUTE A TO COOLER LC (COOMON FOR COOLER LC, RMBH,& CRUSHER LC) - 25 MTRS 4
9 ROUTE K FROM ROUTE A TO COOLER LC (COOMON FOR COOLER LC, RMBH,& CRUSHER LC) - 65 MTRS 4 4
10 ROUTE X FROM ROUTE A TO COOLER LC (COOMON FOR COOLER LC, RMBH,& CRUSHER LC) - 25 MTRS 4
11 ROUTE Y FROM ROUTE A TO COOLER LC (COOMON FOR COOLER LC, RMBH,& CRUSHER LC) - 55 MTRS 4 4
12 PIPE RACK FROM ROUTE A TO COOLER LC (COOMON FOR COOLER LC, RMBH,& CRUSHER LC) - 75 MTRS 4
13 PIPE RACK COOLER LC TO RMBH LC (COMMON FOR RMBH LC & CRUSHER LC) - 35 MTRS 4 4
14 PIPE RACK COOLER LC TO RMBH LC (COMMON FOR RMBH LC & CRUSHER LC) - 35 MTRS 4
15 ROUTE COOLER LC TO RMBH LC (COMMON FOR RMBH LC & CRUSHER LC) - 30 MTRS 4
16 ROUTE RMBH LC TO CRUSHER LC - 35 MTRS 4
17 ROUTE RMBH LC TO CRUSHER LC - 225 MTRS 4 6 6 4
18 RMBH LC TO CRUSHER LC - 100 MTRS 6
19 POWER CABLE LAYING 4 4 4 4 4 4
19 POWER CABLE TERMINATION 2 2 2 2 2 2
20 TESTING AND COMMISSIONG 4 4
22 0 32 0 39 0 31 0 17 0 10 0 10 0 4 0
E&I ERECTION SCHEDULE- CRUSHER LC
Jan-21 Feb-21
S.NO DESCRIPTION OF ACTIVITY
1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk

RMBH (RAW MILL, B.SILO,PH & KILN) PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL
1 CRUSHER LC CELLAR CABLE TRAY 4 4 4
2 PANEL ERECTION 4 4
3 LOAD CENTER INSIDE CABLE LAYING 4
4 LOAD CENTER INSIDE CABLE TERMINATION 4
5 LC TO CRUSHER BUILDING CABLE TRAY ERECTION 6 6 6
6 CRUSHER BUILDING TRAY ERECTION 4 4 4
7 LPB / LCS / DJB/IJB Installation 4
8 Power Cables Laying from MCC to MOTORS etc ` 4 4 4 4
9 Control,Signal and Load Cell Cable Laying from MCC / VFD / RIO to LPB/LCS/DJB/IJB 4 4 4 4
10 Communication cable laying from RIO Panel to PLC Panel and Testing 4
11 Field Instruments Erection and impulse line erection 4
12 Glanding and Termination of Power Cables 2 2 2 2
13 Glanding and Termination of Control and Signal Cables 2 2 2 2 2
14 Earth pits to be re erected 4
15 Fixing and wiring of lighting 4 4
16 Commissioning of VFD Panels 2
17 MCC to RI/0 Panel and RIO to Field 2 2
18 Individual Trials from HMI and Group trial 4 4
4 0 14 0 42 0 26 0 36 0 22 0 2 0 0 0
E&I ERECTION SCHEDULE- RMBC LC ( RAW MILL, B.SILO, PH & KILN SECTION)
Nov-20 Dec-20 Jan-21 Feb-21

S.NO DESCRIPTION OF ACTIVITY 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk

RMBH (RAW MILL, B.SILO,PH & KILN) PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL
1 1.5 METER LEVEL LC CELLAR CABLE TRAYS
2 5.5 METER LEVEL LC CELLAR CABLE TRAYS
3 10.75 METER LEVEL LC CELLAR CABLE TRAYS
4 1.5 METER LEVEL PANEL ERECTION 6 6 6 6
5 5.5 METER LEVEL PANEL ERECTION 6 6 6 6
6 10.75 METER LEVEL PANEL ERECTION 6 6 6 6
7 LOAD CENTER 1.5 MTR INSIDE CABLE LAYING 4 4 4
8 LOAD CENTER 5.5 MTR INSIDE CABLE LAYING 4 4 4
9 LOAD CENTER 10.75 MTR INSIDE CABLE LAYING 4 4 4
10 LOAD CENTER 1.5 MTR INSIDE CABLE TERMINATION 2 2 2 2
11 LOAD CENTER 5.5 MTR INSIDE CABLE TERMINATION 2 2 2 2
12 LOAD CENTER 10.75 MTR INSIDE CABLE TERMINATION 2 2 2 2
13 CABLE TRAY TRENCH FROM RABH LC TO RAW MILL BUILDING 6 6 6 6 6 6 6
14 CABLE TRAY FROM ROUTE A TO RAWMILL BUILDING AREA 6 6 6 6 6 6 6
15 CABLE TRAY FOR B.SILO AREA 4 4 4 4
16 CABLE TRAY FOR HOT DUST SILO AREA 4 4 4 4
17 CABLE TRAY FOR PRE HEATER AREA 4 4 4 4 4 4
18 CABLE TRAY FOR KILN AREA 4 4 4 4 4
19 ALL LOOP TRAYS IN BUILDINGS 4 4 4 4 4 4
20 LPB / LCS / DJB/IJB Installation for All RM,B.Silo,PH,Kiln sections) 8 8 8 8 8
21 Power Cables Laying from MCC to MOTORS etc 6 6 6 6
22 Control,Signal and Load Cell Cable Laying from MCC / VFD / RIO to LPB/LCS/DJB/IJB 6 6 6 6
23 Communication cable laying from RIO Panel to PLC Panel and Testing 3 3
24 Field Instruments Erection and impulse line erection 4
25 Glanding and Termination of Power Cables 2 2 2 2 2 2
26 Glanding and Termination of Control and Signal Cables 2 2 2 2 2 2
27 Earth pits to be re erected 4 4
28 Fixing and wiring of lighting 4 4 4
29 Commissioning of VFD Panels 3 3
30 MCC to RI/0 Panel and RIO to Field loop checking 4 4 4 4
31 Individual Trials from HMI and Group trial 4 4 4 4
18 0 30 0 63 0 79 0 78 0 70 0 64 0 48 0 11 0 11 0 8 0 8 0 4 0 4 0 0 0 0 0
E&I ERECTION SCHEDULE- CEMENT MILL LC ( CEMENT MILL & PACKING PLANT SECTION)
Nov-20 Dec-20 Jan-21 Feb-21

S.NO DESCRIPTION OF ACTIVITY 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk

RMBH (RAW MILL, B.SILO,PH & KILN) PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL
1 CELLAR CABLE TRAYS 12 12 12 12
2 PANEL ERECTION 6 12 6 6 6
3 LOAD CENTER INSIDE CABLE LAYING 6 6 6
4 LOAD CENTER INSIDE CABLE GLANDING & TERMINATION 4 4 4
5 CABLE TRAY CEMENT MILL LC TO CEMENT MILL BUILDING 8 8 8 8 8 8 8 8
6 CABLE TRAY FOR CEMENT MILL BUILDING 8 8 8 8 8 8 8 8
7 CABLE TRAY FOR PACKING PLANT BUILDING 8 8 8 8 8 8 8 8
8 ALL LOOP TRAYS IN BUILDINGS 8 8 8 8 8 8 8 8
9 LPB / LCS / DJB/IJB Installation 4 4 4 4 4 4 4
10 Power Cables Laying from MCC to MOTORS etc 6 6 6 6 6 6 6 6
11 Control,Signal and Load Cell Cable Laying from MCC / VFD / RIO to LPB/LCS/DJB/IJB 4 4 4 4 4 4 4 4
12 Communication cable laying from RIO Panel to PLC Panel and Testing 4 4 4
13 Field Instruments Erection and impulse line erection 4 4 4 4 4 4 4 4
14 Glanding and Termination of Power Cables 4 4 4 4 4 4 4 4 4
15 Glanding and Termination of Control and Signal Cables 2 2 2 2 2 2 2 2 2
16 Earth pits to be re erected 4 4
17 Fixing and wiring of lighting 4 4 4 4
18 Commissioning of VFD Panels 4 4
19 MCC to RI/0 Panel and RIO to Field 4 4 4
20 Individual Trials from HMI and Group trial 6
18 0 24 0 60 0 84 0 76 0 60 0 56 0 56 0 56 0 64 0 28 0 14 0 12 0 14 0 4 0 0 0
E&I ERECTION SCHEDULE- COOLER LC ( COOLER / TG BUILDINGSECTION)
Dec-20 Jan-21 Feb-21
S.NO DESCRIPTION OF ACTIVITY
1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk

COOLER LC PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL
1 CELLAR CABLE TRAYS 8 8 8
2 PANEL ERECTION 4 4 4
3 LOAD CENTER INSIDE CABLE LAYING 4
4 LOAD CENTER INSIDE CABLE TERMINATION 4
5 CABLE TRAY FROM COOLER LC TO COOLER BUILDING 8 8 8 8 8 8 4 4
6 CABLE TRAY FOR COOLER BUILDING 8 8 8 8 8 8 4 4
6 CABLE TRAY FOR TG BUILDING 8 8 8 8 8 8 4 4
6 CABLE TRAY FORPH BOILER BUILDING 8 8 8 8 8 8 8 8
6 CABLE TRAY FOR AQC BOILER BUILDING 8 8 8 8 8 8 4 4
CABLE TRAY FOR WTP BUILDING 8 8 8 8 8 8 4 4
7 ALL LOOP TRAYS IN BUILDINGS 8 8 8 8 8 8 4 8
8 LPB / LCS / DJB/IJB Installation 8 8 4 4 4 4
9 Power Cables Laying from MCC to MOTORS etc 4 4 4 4 4 4 4
10 Control,Signal and Load Cell Cable Laying from MCC / VFD / RIO to LPB/LCS/DJB/IJB 4 4 4 4 4 4 4
11 Communication cable laying from RIO Panel to PLC Panel and Testing 4 4
12 Field Instruments Erection and impulse line erection 4 4 4 4 4
13 Glanding and Termination of Power Cables 4 4 4 4
14 Glanding and Termination of Control and Signal Cables 4 4 4 4
15 Earth pits to be re erected 4 4
16 Fixing and wiring of lighting 4 4 4 4
17 Commissioning of VFD Panels 2
18 MCC to RI/0 Panel and RIO to Field 4 4 4
19 Individual Trials from HMI and Group trial 4 4 4 4
56 0 56 0 76 0 80 0 92 0 96 0 82 0 84 0 16 0 4 0 4 0 4 0
E&I ERECTION SCHEDULE- CCR & ROBO LAB
Dec-20 Jan-21 Feb-21

S.NO DESCRIPTION OF ACTIVITY STATUS 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk

RMBH (RAW MILL, B.SILO,PH & KILN) PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL
1 CCR & ROBO LAB WORKS C 12 12 12 12 12 12 12 12 12 6 6 6
2
12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 12 0 6 0 6 0 6 0
E&I ERECTION SCHEDULE- OTHER ROOMS
Dec-20 Jan-21 Feb-21
S.NO DESCRIPTION OF ACTIVITY
1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk 1-Wk 2-Wk 3-Wk 4-Wk

TRAY, PANEL ERECTION & CABLE LAYING AND TERMINATION PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL PLAN ACTL
1 RAW MILL HYDRAULIC PANEL ROOM 0 4 6
2 COOLER HYDRAULIC PANEL ROOM 0 4 6
3 CEMENT MILL HYDRAULIC PANEL ROOM 4 6
4 CABINET FOR GAS ANALYSIER (SOx+NOx) - CEM ANALYSER 4
5 CABINET FOR GAS ANALYSERS (CO+O2) AT PH-1 OUTLET 4
6 CABINET FOR GAS ANALYSERS (CO+O2+NOx) AT PC-1 OUTLET 4
7 CABINET FOR GAS ANALYSERS (CO+O2+NOx) AT KILN INLET 461 KL1 4 4
8 CONTROL CABINET FOR CO+O2 GAS ANALYSIS BAG FILTER L41 BF3 4
9 CABINET FOR KILN SHELL SCANNER 4
10 AAQMS 4
0 0 8 0 32 0 14 0 4 0 0 0 0 0 0 0 4 0 0 0 0 0 0 0