Professional Documents
Culture Documents
Uts Manpro
Uts Manpro
In the program evaluation and review technique (PERT), the most-likely scenario is
given a weight of 4 as compared to the weight of 1 for each of the pessimistic and
optimistic scenarios. The pessimistic estimate for an activity is 20 days, the optimistic
estimate is 10 days, and most-likely estimate is 15 days. Calculate the expected
estimate using the PERT technique.
Describe how assumptions and constraints, e.g., in the project scope statement,
can affect the schedule, as well as what you can do about it.
Lora Nirvana is the project manager for Sequence DNA of a Buffalo (SDB) project.
Match each item in the first column of the following table to the correct item in the
second column.
How can the assumptions log and risk register project documents be updated as
a result of this process?
The pessimistic cost estimate for an activity is $5,000, the optimistic estimate is
$3,000, and most-likely estimate is $4,000. Calculate the expected estimate by
using the PERT technique, where the most-likely scenario is given a weight of 4 as
compared to the weight of 1 for each of the pessimistic and optimistic scenarios.
Rajinder, the project manager, is now working on procurement planning for a portion
of the project. She is looking at the following options for procuring different pieces.
Match each consideration in the first column with the corresponding contract type in
the second column of the following table.