Budget Bibitan

Sat Bibit 2019


120.000 Bbt PN
90% 108.000 Bbt MN
No Jenis Pekerjaan 90% 97.200 Bbt Siap Tnm
9 Area Buat (Ha)
Fisik Rp Rp/Bibit
20-01 PENETAPAN AREAL BIBITAN (SURVEY AWAL) Ha -
20-02 IMAS TUMBANG BIBITAN Ha 10.368.000 107
20-03 RUMPUK BIBITAN Ha 60.480.000 622
20-04 PEMBUATAN TAPAK BIBITAN Ha - -
20-04 PEMBUATAN JALAN BIBITAN Mtr 51.840.000 533
20-04 PEMBUATAN JEMBATAN BIBITAN Unit 25.920.000 267
20-04 PEMBUATAN PARIT BIBITAN Mtr 34.560.000 356
20-05 PEMBUATAN WADUK UNTUK BIBITAN Unit 15.000.000 154
20-06 PEMASANGAN INSTALASI AIR Ha 259.200.000 2.667
20-07 PEMBUATAN BANGUNAN Unit -
21-01 PEMBUATAN BEDENGAN DAN NAUNGAN - PN Unit 64.143.993 660
21-02 PENGUMPULAN TOP SOIL - PN - MN M3 56.138.192 578
PERSIAPAN LAHAN 577.650.185 5.943

▪ Jumlah Bibit
▪ Jenis Aktifitas
▪ Norma
Budget Bibitan

PRE- NURSERY
21-04 KECAMBAH Kcb 1.425.000.000 14.660
21-05 MENGISI TANAH - PN Bag 61.981.927 638
21-05 MENGATUR BABY BAG - PN Bag 14.192.429 146
21-04 SELEKSI KECAMBAH - PN Kcb 2.720.910 28
21-06 PENANAMAN KECAMBAH - PN Kcb 21.792.855 224
21-01 PEMBUATAN PAPAN NAMA BIBITAN (LABELLING) - PN Unit 1.345.202 14
21-03 PENYIRAMAN MANUAL - PN Bbt - -
21-03 PENYIRAMAN MEKANIS - PN Bbt 36.452.522 375
21-07 RAWAT PARIT BEDENGAN - PN Mtr 4.206.278 43
21-07 PEMELIHARAAN INSTALASI AIR - PN Ha 3.422.887 35
21-08 PEMUPUKAN PRE NURSERY Kg 40.759.979 419
21-10 PENGENDALIAN GULMA DI POLIBAG - PN Bbt 5.597.108 58
21-10 PENGENDALIAN GULMA DI LUAR POLIBAG - PN Bbt 5.925.523 61
21-09 PENGENDALIAN HAMA PENYAKIT TANAMAN - PN Bbt 80.639.620 830
21-11 SENSUS - PN Bbt 2.720.910 28
21-12 SELEKSI - PN Bbt 5.441.820 56
PRE NURSERY 1.712.199.970 17.615
Budget Bibitan
MAIN NURSERY
21-14 MENGISI TANAH - MN Bag 271.705.696 2.795
21-14 PENAMBAHAN TANAH - MN Bag 25.186.987 259
21-15 SPACING & SUSUN POLIBAG - MN Bag 18.007.866 185
21-16 LANGSIR POLIBAG - MN Bag 61.220.478 630
21-15 PEMBUATAN PAPAN NAMA BIBITAN (LABELLING) - MN Unit 342.324 4
21-13 MENCABUT & ANGKUT KE MN Bbt 26.627.363 274
21-17 MEMBUAT LUBANG TANAM (BOR) - MN Bag 30.610.239 315
21-18 TANAM BIBIT - MN Bag 62.967.468 648
21-03 PENYIRAMAN MANUAL - MN Bbt - -
21-03 PENYIRAMAN MEKANIS - MN Bbt 449.323.726 4.623
21-19 RAWAT PARIT - MN Mtr 73.617 1
21-19 PEMELIHARAAN INSTALASI AIR - MN Ha 33.342.487 343
21-20 PEMUPUKAN - MN Kg 238.260.485 2.451
21-22 PENGENDALIAN GULMA DI POLIBAG - MN Bbt 3.264.980 34
21-22 PENGENDALIAN GULMA DI LUAR POLIBAG - MN Bbt 3.801.960 39
21-21 PENGENDALIAN HAMA PENYAKIT TANAMAN - MN Bbt 115.442.344 1.188
21-23 SENSUS - MN Bbt 1.020.341 10
21-24 SELEKSI - MN Bbt 1.020.341 10
21-25 MENEGAKKAN POLIBAG DAN BIBIT - MN Bbt 306.102 3
21-25 PENGGANTIAN POLIBAG - MN Bag 21.146.152 218
MAIN NURSERY 1.363.670.956 14.030

TOTAL BIAYA 3.653.521.111 37.588


Budget TBM
TBM 0-1 TBM 2 TBM 3
NO ITEM PEKERJAAN
Rp Rp/Ha Rp Rp/Ha Rp Rp/Ha

01 LAND CLEARING
131.115.427 7.766.808 - - - -
02 PEMBUATAN INFRASTUKTUR JALAN DAN JEMBATAN
37.487.745 2.220.640 - - - -
03 PEMBUATAN PARIT, TPK KUDA DAN PLANTING POCKET
81.361.968 4.819.591 - - - -
04 PENANAMAN KACANGAN
44.613.928 2.642.769 - - - -
05 PENANAMAN
743.467.388 7.434.674 - - - -
06 MERUMPUT
119.436.134 1.194.361 166.161.838 1.438.225 28.055.086 1.714.859
07 PENGENDALIAN LALANG
18.180.423 181.804 20.506.558 177.496 2.833.348 173.188
08 PEMUPUKAN TANAMAN
175.272.785 1.752.728 395.432.128 3.422.689 60.236.947 3.681.965
09 PENGENDALIAN HAMA DAN PENYAKIT
47.509.186 475.092 59.789.533 517.512 9.655.006 590.159
10 MENUNAS / KASTRASI
- - 162.176.086 1.403.726 7.654.985 467.909
11 SENSUS DAN THINING OUT
1.948.955 19.490 2.251.678 19.490 571.783 34.950
12 SISIP DAN KONSOLIDASI
45.280.817 452.808 52.281.349 452.525 5.555.956 339.606
13 PEMELIHARAAN PARIT / TERESAN / TAPAK KUDA
- - 4.478.579 38.765 1.295.709 79.200
14 PEMELIHARAAN JALAN / JEMBATAN, TITI PANEN
10.617.960 106.180 308.150.769 2.667.220 81.661.994 4.991.564
15 SURVEY DAN PATOK
1.446.623 14.466 - - 179.212 10.954
17 SCOUT HARVESTING
- - - - 5.307.675 324.430
SUBTOTAL BIAYA TBM / TM 1.457.739.340 29.081.411 1.171.228.519 10.137.647 203.007.702 12.408.784
ALOKASI BTL
TOTAL BIAYA TBM 1.457.739.340 29.081.411 1.171.228.519 10.137.647 203.007.702 12.408.784