The present deposits - aging rust, oil, grease - are not blocking the internal pipes,
and this finding is confirmed upon our discussion, where circulation of water in your
closed system was possible.
Our principle of cleaning your equipment is setup in flushing with alkaline solution.
The alkaline solution is basically NALCO 8900 (with effective inhibitor).The use of
NALCO specialty product (inhibitor - NALCO 8900) has a good effect for the
protection of the metals, and it will be very safe on the equipment.
• Cleaning procedure
First step
1. Fill the unit with fresh water and recirculate for three hours
2. Drain the unit
3. Remove and clean the strainers
4. Blow off the low points
1. Before starting the cleaning procedure make sure you have a vent for disposing
gases
2. Fill the unit with 5% solution of NALCO 8900 and recirculate for 48 hours
3. Maintain pH above 12 to ensure removal of rust layer on the metals
4. pH should be monitored, throughout the cleaning process to evaluate the
efficiency of the cleaning, as it will decrease in the recirculating solution and
reach a steady value which will give us indication when the process should be
terminated
5. Iron should be monitored throughout the cleaning process to evaluate also the
cleaning effect of the chemicals
6. Drain the unit
7. Remove and clean the strainers
8. Blow off the low points to ensure full removal of the alkaline solution
9. Fill the unit with fresh water and recirculate for half an hour
10. Drain the unit
11. Remove and clean the strainers
12. Blow off the low points
• Guaranty
The cleaning work for your equipment can be accomplished safely. The corrosion
effect will be minimized by the use of inhibitor.
If the equipment does not have any existing deep pitting corrosion - covered by
rust deposits - or any weak welds, then no damage to the equipment will be made.
• Pump (Qty 1):Operational pressure 1 bar. It will be used to pump the chemicals
from the tank to the closed system.
• Flexible Hoses (Qty 2): To suit the arranged setup from the tank to the
network. Flexible Hoses will be also used to drain the different solution.
• Tank (Qty 1): It will be used for the preparation of the solution.
• Needed material
NALCO 8900
• Lab Equipment
HACH pH meter
DR 2010 Spectrophotometer
• Safety equipment
Mask / Gloves
First aid kit
All mechanical work will be executed by your staff. Our joint efforts
will allow us to bring the maximum targeted results, satisfy your needs. Please
note that the following should be provided from your side:
• Engineer: One engineer available all time during the cleaning job.
• Workers: Persons available all time during the cleaning job.
• Water: Make sure that supply of water will be available all times.
• Follow up
PROBLEM DESCRIPTION
Corrosion
• pH
• Anaerobic bacteria (SRB)
• Temperature
• Galvanic Corrosion
• Dissolved O2 and CO2
Fouling
• Corrosion by products
• Microbiological deposits (Slime Former)
The initial dosage rate is based on your total volume of the closed system and is
verified by analyzing and maintaining 1000ppm of nitrite in the system.
Nalco 77352 should be shock dosed every three months at 200ppm each time;
based on system volume through the feeding equipment.
TREATMENT BENEFITS