3rd Week YOSEF TEZAZU
3rd Week YOSEF TEZAZU
ID:-1000945
Departement advisor:-Abdulbasit
3rd week report
Monday
As our ameche site engineer told us our site will be a little less
active due to material shortage he allow us the access to see
finishing and other works to be done in the megenaga site.
The finishing work of the megenagna site was being
constructed the ceramic of the 3rd floor was being worked and
the plastering of the 4th floor was being worked