Professional Documents
Culture Documents
bit.ly/manupom
LECTURE 6:
PROJECT CRASHING
(USING TIME COST TRADEOFF AND
USING LEAST COST METHOD)
COST SLOPE
Normal
500
NC
t
CT 4 NT 7
`ATIAH ABDULLAH SIDEK MANU 3314 PROJECT & OPERATION MANAGEMENT
1. Find CP in project network
CRASHING 2. Calculate crash cost per period
for all activities*
ACTIVITY 3. Select the activity on the critical
TIMES path with the smallest crash
cost per period and crash this
activity to the maximum extent
▪ How much each possible or to the point at
activity can be crashed which your desired deadline
has been reached.
▪ How much the 4. Check to be sure that the
crashing process costs critical path you were crashing
is still critical. If the critical path
is still the longest path through
the network, return to step 3. If
not, find the new critical path
and return to step 2.
`ATIAH ABDULLAH SIDEK MANU 3314 PROJECT & OPERATION MANAGEMENT
2 Calculate Crash Cost Per Period
COST SLOPE
Do the rest…
Activity
Times
per week
Thus, you will need to check the critical path in the revised
network and perhaps either identify additional activities to
crash or modify your initial crashing decision
A 0 3 C 3 13 G 19 25
Start End
3 0 3 10 4 14 6 19 25
F 14 19
5 14 19
D 3 14
11 3 14
Critical Path= A-D-F-G
Project Duration=25
Total Direct Cost=$450
A 3 2 1 50 70 20
B 6 4 2 80 160 40
C 10 9 1 60 90 30
D 11 7 4 50 150 25
E 8 6 2 100 160 30
F 5 4 1 40 70 30
G 6 6 0 70 70 0
Total Direct Cost= $ 450
A C G
Start End
2x 10 6
F
5
D
11
Critical Path= A-D-F-G
Duration=24
Total Direct Cost=$470
A C G
Start End
2x 10 6
F
5
D
10
Critical Path= A-D-F-G
and A-C-F-G
Duration=23
Total Direct Cost=$495
A C G
Start End
2x 10 6
F
4x
D
10
Critical Path= A-D-F-G and
A-C-F-G and A-B-E-G
Duration=22
Is further reduction possible? Total Direct Cost=$525
`ATIAH ABDULLAH SIDEK MANU 3314 PROJECT & OPERATION MANAGEMENT
B 2 8 E 8 16
6 2 8 8 8 16
A 0 2 C 2 12 G 16 22
Start End
2x 0 2 10 2 12 6 16 22
F 12 16
4x 12 16
D 2 12
10 10 12
A C G
Start End
2x 10 6
F
4x
D
10
Critical Path= A-D-F-G and
Is further reduction possible? A-C-F-G and A-B-E-G
Let us look at other possibility Duration=22
Total Direct Cost=$525
`ATIAH ABDULLAH SIDEK MANU 3314 PROJECT & OPERATION MANAGEMENT
B E
6 8
A C G
Start End
2x 10 6
F
4x
D
10
A C G
Start End
2x 9x 6
F
4x
D
9
Duration=22-1=21
Total Direct Cost=$525 +
$30 +$25 +$30= $610
24 470 350
23 495 300
22 525 250
21 610 200