Professional Documents
Culture Documents
School of Engineering
OR
Getting what we planned.
“It’s not just doing the right thing, it’s about doing
the thing right.”
Lecture number 4a
Agenda
• Project control
− Project monitoring
− Tracking earned value
4
The Project Management Life Cycle
Process
and Scope/ Project
product
Define it brief
knowledge
Monitoring progress
Managing quality
6
What to monitor?
Matters that could
• Time elapsed and time left
affect tasks: • Effort (hours) consumed and left
• Risks materialising Time • Estimated time and effort required to complete
• Unexpected events • Milestone status – on time?
• Scope creep • Validity of assumptions – to complete on time
• Imposed changes
• The News
• Communications
Cost Specification
• Planned costs versus actual costs • Milestone outputs achieved
• Estimated costs to complete • Quality control, performance
• Expenditure by cost type • Quality assurance
• Validity of assumptions re. future costs • Realism of milestone targets left
• Cash flow situation
7
Project monitoring and control
“The project control cycle is continuous”
Updating documents
and records as Setting a goal
required
Making
controlled
Taking action and Measuring progress
changes to
recycling the
reduce or
process
eliminate
variations
Comparing
Understanding actual and
causes of variations planned
and possible Identifying variations Pinto (2007),
remedies against current plan p411
8
Project monitoring and control advice
• You can only manage forward –
you cannot re-manage the past
• Good monitoring enables you to
anticipate problems before they
arise
• Be aware that some information
you receive may be wrong
• People may hide problems in
the hope they can fix them
Budget Specification
10
Agenda
• Project control
− Project monitoring
− Tracking earned value
11
Project control
12
Monitoring progress – costs and time
Cumulative
cost
Baseline plan
Estimated
expenditure
to completion
Time
TODAY
13
Monitoring progress – Earned Value
Analysis
• Controlling time and cost is extremely importance. They
can make or break a project !
14
Earned Value Analysis – what is it?
15
Earned Value Management
- Determine Earned Value.
‘Value’ is ‘earned’ by completing tasks. The budget for each task is the value earned.
5 105 1 £14,000 O
TODAY £46,000 £36,000 £32,000
6 106 1 £10,000
7 107 1 £13,000 Maylor, H
Project
8 108 1 £11,000 manage-
ment 3rd ed.
9 109 1 £16,000 Harlow:
Pearson,
10 110 1 £4,000 p278
TOTAL 10 £100,000 16
This is about where we are TODAY,
compared with where we planned to be.
Project Task Planned Budgeted Tasks Actual Earned
week no. duration cost done cost value
(weeks)
1-5 101-105 £46,000 101-104 £36,000 £32,000
Consider cost performance (Cost Variance), i.e. after completing tasks 101
to 104: Earned Value is £4,000 less than actual spend. This is NOT good.
Understanding the true situation
Project Task Planned Budgeted Tasks Actual Earned
week no. duration cost done cost value
(weeks) BCWS ACWP BCWP
1-5 101-105 £46,000 101-104 £36,000 £32,000
VARIANCES
Cost Variance (CV) = BCWP – ACWP = £32,000 - £36,000
(the difference between Earned value and the actual cost for the # of tasks
completed by this stage)
Schedule Variance (SV) = BCWP – BCWS = £32,000 - £46,000
(the difference between Earned value and what was budgeted for the expected # of tasks
that should have been completed by this stage)
VARIANCES
Cost Variance (CV) = BCWP – ACWP = £32,000 - £36,000
Schedule Variance (SV) = BCWP – BCWS = £32,000 - £46,000
VARIANCES
Cost Variance (CV) = BCWP – ACWP = £32,000 - £36,000 = - £4,000 +ve good
-ve bad
Schedule Variance (SV) = BCWP – BCWS = £32,000 - £46,000 = - £14,000
EFFICIENCY INDICES
Cost Performance Index (CPI) = BCWP = £32,000 = 0.889
ACWP £36,000 >1 = good
<1 = bad
Schedule Performance Index (SPI) = BCWP = £32,000 = 0.696
BCWS £46,000
21
Predicting what the TOTAL project will
cost and how long it will take.
Project Task Planned Budgeted Tasks Actual Earned
week no. duration cost done cost value
(weeks) BCWS ACWP BCWP
1-5 101-105 £46,000 101-104 £36,000 £32,000
FORECASTS:
Estimated Cost at Completion = Original Budget
CPI
22
Predicting what the TOTAL project will
cost and how long it will take. Project Task no. Planned Budgeted Tasks Actual Earned
week duration cost done cost value
(weeks)
7 107 1 £13,000
Estimated Cost at Completion = Original Budget
8 108 1 £11,000
CPI
9 109 1 £16,000
10 110 1 £4,000
= £100,000 / 0.889 = £112,500 TOTAL 10 £100,000
FORECASTS:
Estimated Cost at Completion = Original Budget
CPI
28
1. Definitions of quality
• Something that satisfies me at a price I can afford
(most customers)
• Conformance to specifications
(everyday reality in manufacturing)
29
Quality control and quality assurance
Quality control: the part of Quality assurance: the part of
quality management quality management focussed on
focussed on fulfilling quality providing confidence that quality
requirements – that is the requirements will be fulfilled.
quality of the output defined
in the specification. The
project QA:
QC: output • evaluates project performance
• monitors specific project regularly (how things are being
results against defined The project done - methods)
requirements
• focuses on preventing defects
• focuses on identifying and by assessing process used to
correcting defects make the product.
30
Remember: Quality in = Quality out
“Quality: The degree to which a set of inherent characteristics fulfills
requirements."
PMI, Guide to the Project Management Book of Knowledge
Desired timescale
Right people
Desired cost
PROJECT
Right methods
ACTIVITIES
Desired quality
Right standards
Satisfied customer
31
Example of quality tool - Cause and effect diagram for
problem identification
Cause Cause Cause
Effect
Effect
Debris
Worn parts Fuel level incorrect ENGINE CSC
Manufacturing
PUMPS Handbook, 1996,
p 6.12
34
2. Project communication
Why?
• Report, inform, advise
• Conform (to process or standard), create record
• Request or solicit information
• Inspire, recognise, and thank people
• Prove, demonstrate
• Convince
Who?
Who provides communication, who receives it?
What?
What is the information required? In what format?
When?
What are the dates and frequency of communications?
How?
Is communication in person or through what media?
Where?
Does communication have to be in specific places? 35
Have a communication plan
Team leaders Weekly Every Monday Oral Teams meeting Project manager
Etc …..
36
Project communication – getting the
message across
37
Use a common language for better understanding
C3H8
propane
5,000
words
Everyday
Tort language
5,000 10,000 Lawyer
words words
Chemist
Cooper, B. (1964),
Writing Technical
Reports, Penguin, p18.
38
Types of communication (1)
• One-to-one Meetings: You still have to prepare for any one-to-
one meeting. No meeting is entirely routine.
o Phone
o Online
o In-person
39
Types of communication (2)
• Electronic messages: - Keep them short. Key information only.
Key recipients only. Caution - electronic is forever.
40