Professional Documents
Culture Documents
Numerical Analysis and Field Monitoring On Deformation of The Semi-Top-down Excavation in Shangai
Numerical Analysis and Field Monitoring On Deformation of The Semi-Top-down Excavation in Shangai
Downloaded from ascelibrary.org by Universidad Militar Nueva Granada on 01/21/21. Copyright ASCE. For personal use only; all rights reserved.
1
Ph.D. student, Department of Civil Engineering, Shanghai Jiao Tong University.
Shanghai, China. E-mail: zhonghui_huang@live.cn
2
Graduate student, Department of Civil Engineering, Shanghai Jiao Tong
University. Shanghai, China. E-mail: dacymeng@126.com
3
Associate Professor, Department of Civil Engineering, Shanghai Jiao Tong
University. Shanghai, China. E-mail: chenjj29@sjtu.edu.cn.
4
Professor, Department of Civil Engineering, Shanghai Jiao Tong University.
Shanghai, China. E-mail: wjh417@sjtu.edu.cn
INTRODUCTION
The ground water level is about 0.5 m below the ground surface. The engineering
properties of the soil layers in-site are given in Table 1.
Fig. 1 shows the site layout. There are many buildings close to the location of
new station which must be protected rigorously, including ten high-rise buildings
with strip foundation and four buildings with box foundation. The shortest
distance between the diagram wall and the exiting foundation is just 4.5 m.
Downloaded from ascelibrary.org by Universidad Militar Nueva Granada on 01/21/21. Copyright ASCE. For personal use only; all rights reserved.
Moreover, the existing elevated station of Line 3 stands on the west of the new
underground station and the shortest distance between two stations is only 2.7 m.
Large deformation of underground structure or soil would be seriously harmful to
Line 3 and buildings nearby. Therefore, it is very important to control the
movement of station and existing structure within the allowable limit.
According to the site investigation report, the excavation is underlain by thick,
relatively soft, quaternary alluvial and marine deposits as shown in Table 1.
slab of deep excavation in this project, and the middle slab is also used as the
supporting structure during the semi-top-down construction.
Table 3 shows the contrast between the two methods. Compared with the
bottom-up method, the speed of excavation below the middle floor slab is
relatively slower, which could be overcome by some construction measures, while
the deformation of the surrounding environment is controlled within a small value.
Downloaded from ascelibrary.org by Universidad Militar Nueva Granada on 01/21/21. Copyright ASCE. For personal use only; all rights reserved.
Because of the effect of the middle floor slab, a large amount of foundation
enhancement is decreased significantly. Considering all factors, the
semi-top-down method would gain higher economic benefits.
entire 2D models consist of 16,531 elements and 16,926 nodes. To reduce the
computation load, all the elements are linear-order elements. The two side
boundary surfaces are fixed along the direction perpendicular to each surface. The
bottom boundary is constrained along all x and y directions. The diaphragm walls,
the steel columns, the RC piles of the foundation, and the floor slab is modeled as
isotropic linear-elastic materials. The Young’s modulus and the Poisson’s ratio of
Downloaded from ascelibrary.org by Universidad Militar Nueva Granada on 01/21/21. Copyright ASCE. For personal use only; all rights reserved.
the concrete are taken as 30 GPa and 0.2, respectively, while those of the steel are
taken as 211 GPa and 0.3, respectively. The Cam-clay model is adopted to
simulate the nonlinear behavior of soils. The parameters of soils are obtained
empirically from the soil investigation report. The node-to-surface contact model
in ABAQUS is applied to model the soil-wall interface so that the slippage and
separation could be considered if there is enough relative displacement.
0 0
bottom-up semi-top-down
7 7
14 14
Depth( m)
Depth( m)
Downloaded from ascelibrary.org by Universidad Militar Nueva Granada on 01/21/21. Copyright ASCE. For personal use only; all rights reserved.
21 21
1 1
2 2
28 28 3
3
4 4
35 35
0 5 10 15 20 25 30 0 5 10 15 20 25
Lateral displacement of the wall( mm) Lateral displacement of the wall( mm)
0 0
1 1
5 2 5 2
3 3
4 4
10 10
Depth( m)
Depth( m)
15 15
20 20
25 25
bottom-up
semi-top-down
30 30
-35 -28 -21 -14 -7 0 7 -25 -20 -15 -10 -5 0 5
Lateral displacement of the wall( mm) Lateral displacement of the wall( mm)
0
settlement of the ground( mm)
-3
-6
-9
bottom-up method
-12 semi-top-down method
-15
0 10 20 30 40 50 60
distance from the wall ( m)
MEASUREMENT ANALYSIS
nearest Point F184 is 0.4 m far from the enclosure wall, and Point F185 is 3.4m
far from the enclosure wall. Figure 4 indicates that after the construction of the
middle floor slab, the subsidence of all monitoring points trend to be mild. It
means that if the distance between the building and diaphragm walls does not
reach 1.0m, the deterrent effect from the middle floor slab is obvious.
Point F184: The maximum settlement of sidewall of is 9.76 mm, the settlement
difference is 7.09mm, and the ratio of differential is 0.25‰. Point F185: The
maximum settlement of sidewall of is 6.18mm, the settlements’ difference is 1.84
mm, and the differential settlement ratio is 0.07‰. The diagonal settlement
differences of Building A are 5.42 mm and 3.46 mm. Although the semi-top-down
method has some impact, it’s not enough to influence residents’ daily life. The
monitor result shows that the increase of building settlements trends to be mild
after the middle slab is constructed, which indicates that semi-top-down method
could reduce the deformation of surrounding buildings.
Fig. 6 shows the relationship between the deformation of diaphragm walls and
the settlement of building A. After the construction, the horizontal displacement of
the diaphragm walls near the building is 45.4 mm, and of the other side is 32.0
mm. The excavation depth of the foundation pit is about 16 m, and the wall’s
horizontal displacement is about 0.2-0.3% of the depth, it is reasonable for the
general rules of deep foundation pits’ deformation.
0
F184
F189
-4 F190
F185
Settlement(mm)
F186
-8 F187
constructing
F188
middle floor
slab
after
-12 construction constructing the
before the below middle bottom floor slab
construction of floor slab
middle floor slab
-16
11/1 11/16 12/1 12/16 12/31 1/15 1/30 2/14
Time(day)
Table 5 shows the contrast between the FEM and the measured data of wall and
soil. It shows that measured data are all larger than FEM data, but both sets of
data show the same regularity: δhml > δhmr, Hhml < Hhmr, and the difference of δvm
of FEM and measured data is less than 10%, the prediction is consistent well with
the measured data.
CONCLUSIONS
Since Station Yishan Road is close to some high-rise buildings and the exiting
station of Line 3, so that the bottom-up method might be harmful to the
surrounding environment, the paper suggests using the semi-top-down method
and does numerical analysis with ABAQUS. The result shows displacements of
the semi-top-down method are less than those of bottom-up method, which means
the semi-top-down method has the higher security. The monitored data indicates
that the proposed series of techniques is effective and the displacements of the
adjacent structures are similar to that predicted by numerical method. The
settlement observation of the high-rise building and the elevated metro station
shows that both the settlements and the differential settlement are within control.
Therefore, the new method can ensure the efficiency of deep excavation and
Downloaded from ascelibrary.org by Universidad Militar Nueva Granada on 01/21/21. Copyright ASCE. For personal use only; all rights reserved.
reduce the environment deformation, and the monitored data in the trend is
consistent well with FEM data.
ACKNOWLEDGMENTS
REFERENCES
Long, M. (2001). “Database for retaining wall and ground movements due to deep
excavations.” J. Geotech. Geoenviron. Eng., ASCE, 127 (3): 203-224.
Ou, C.Y, Teng, F.C, Wang, I.W. (2008). Analysis and design of partial ground
improvement in deep excavations. Computer and Geotechnics, 35 (4):
576-584.
Ou, C.Y., Liao, J.T., and Lin, H.D. (1998). “Performance of diaphragm wall
constructed using top-down method.” J. Geotech. Geoenviron. Eng., ASCE,
124(9): 798-808.
Paek, J.H., and Ockz, J.H. (1996). “Innovative building construction technique:
modified up/down method.” J. Constr. Engrg. And Mgmt., ASCE, 122(2):
141-146.
Wang, J.H., Xu, Z.H., and Wang, W.D. (2010). “Wall and ground movements due
to deep excavations in Shanghai soft soils.” J. Geotech. Geoenviron. Eng.,
ASCE, 136(7): 985–994.