Professional Documents
Culture Documents
العاصمة الإدارية- كود المعدات الكهربائية
العاصمة الإدارية- كود المعدات الكهربائية
ELECTRICAL WORKS
SECTION DESCRIPTION
16050 General Provisions For Electrical Work.
16060 Earthing System.
16120 Wires And Cables.
16130 Raceways, Boxes And Fittings.
16131 Cable Tray.
16132 Cable Trunking.
16140 Wiring Devices.
16150 Miscellaneous Control Equipment.
16170 Safety And Motor Isolators (Disconnects).
16075 Electrical Identification.
16270 Distribution Transformer.
16290 Instruments and Metering.
16320 Distribution Transformer Kiosk.
16330 Primary Medium Voltage Switchgear and Ring Main Units.
16430 Low Voltage Switchgear Assemblies Main Distribution Board
16440 Distribution Boards (Power and Lighting Panel Boards).
16490 Air Circuit Breakers.
16491 Miniature Circuit Breakers.
16492 Moulded Case Circuit Breakers.
16493 Residual Current Devices.
16495 Contactors.
16496 Automatic Reactive Power Compensation (Power Factor Capacitors
Correction) Assembly.
16500 Lighting.
16950 Testing And Commissioning.
16999 List Of Recommended Manufacturers.
Page 1 of 1
SECTION 16050
PART 1 - GENERAL
B. It’s the Contractor responsibility to be fully aware of and comply with all of
the requirements of the above.
D. Light and power and system riser diagrams and schematic diagrams
generally indicate equipment connections to be used for various systems.
Provide system raceway and wiring as required for actual systems installed
on this project. Provide all work shown on diagrams whether or not it is
duplicated on the plans.
I. Install the work in accordance with the diagrammatic intent expressed on the
electrical and mechanical drawings, and in conformity with the dimensions
indicated on final architectural and structural working drawings and on
equipment shop drawings.
J. Certain details appear on the drawings which are specific with regard to the
dimensioning and positioning of the work. These details are intended only
for the purpose of establishing general feasibility. They do not obviate field
coordination for the indicated work.
PART 2 - DEFINITIONS
A. The following initials, words and phrases shall have the following meanings:
BS - British Standards.
EN - European Standards.
UL - Underwriters Laboratories.
FM - Factory Mutual.
ii) when given in respect of drawings, documents or schemes called for by the
contract Documents or proposed by the Contractor, is only for conformance
with the design intent and information given in the Contract Documents or
contained in subsequent Instructions.
A. The definitions for words and phrased commonly associated with the design,
manufacture and site work for public health, mechanical and electrical
installations shall be those of the IEE Regulations, the IOP, plumbing
Services Design Guide, CIBSE Guides, BS, CP and associated Statutory
Acts.
D. Any reference to H.V. shall be for voltages in excess of 1000V a.c. or 15V
d.c. between conductors, or 600V a.c. or 900V, d.c. between any conductor
and earth.
I. Words in the documents importing the singular only, also include the plural,
and vice versa where the context requires.
J. Where any possible doubt exists as to the meaning of words or terms used in
the Contract Documents the matter shall be referred by the Contractor to the
Owner's authorized representative for clarification.
A. All publications referred to shall be the latest edition thereof together with
any amendments current ten days before the date of issue of contract
Rev.01 August, 2018 General Provisions For Electrical Work
Section 16050
Page 5 of 30
documents.
2.6 SYMBOLS
A. The symbol notation for all drawings to be produced by the Contractor shall
be in accordance with applicable standards and regulations and shall be
agreed by the consultant and shown on a separate drawing.
A. The Contractor shall verify the accuracy of all dimensions abstracted from
the consultant's drawings, including verifying the accuracy by taking
dimensions on site, in the preparation of any drawings by the Contractor and
before the relevant work proceeds.
A. Should any differences exist between the drawings or should there be any
discrepancy in the figures, scale or the respects, the Contractor shall refer the
same to the Owner's authorized representative for clarification before
proceeding with the work.
A. Shall mean the drawings, based on the Contract Drawings showing details of
the Contractor's proposals for the execution of the Works. The drawings
shall be to such scales, in such detail and with all necessary dimensions as to
enable the Work to be installed and shall indicate all pipe layouts, bends, tees
flanges, valves, connections etc., necessary for installation and also
particular installation methods to be applied in certain instances, e.g. where
connecting to existing services. These drawings shall also relate to builder's
work drawings confirming relationships to valve pits, cable intakes .. etc.
B. In respect of drainage drawings, shall take account of the exact location and
type of sanitary ware scheduled by the consultant , and all manholes and
access points shall be shown and dimensioned to take account of walls,
paving and other adjacent permanent work.
ii) General layout drawings of all plant and equipment included in the
Contract.
iv) Cabling and wiring connections showing cable types, sizes and loads.
v) Trunking and cable tray routes with details of sizes, fixings, cables
carried and terminations.
vi) Conduit routes with conduit sizes, methods of installation and details
of cables, loads and terminations, and all junction and pull-in boxes
A. Shall mean the drawings and Schedules prepared to show requirements for
architectural or structural provisions necessary to facilitate the execution of
the Works and allow their integration into the project.
A. Shall mean the drawings produced for the purpose of explaining how the
components of the designed works are to be fabricated and assembled.
ii) The item conforms to the specific description given in the Documents,
quoting the reference numbers from the Contract Document;
iii) The item is shown complete and entire as it will be supplied for the
works and no extraneous or alternative parts are indicated;
E. All wiring diagrams shall indicate clearly that wiring which forms part of or
is connected to the equipment as delivered and shall include the following
minimum information to enable the site connections and wiring to be
completed:
A. Shall mean the drawings and schematics of plant and equipment showing the
control layout with each item uniquely identified, and including a brief
description of controls operation and any associated interlocking.
A. Shall mean the drawings showing the general arrangement, the construction,
the external and internal layout of panels, and wiring diagrams comprising
internal wiring and external wiring diagrams, for the complete systems in the
panels. The drawings shall also indicate all pipe work and capillary
connections from the panels to external equipment.
A. Before commencing work, provide complete set of black and white prints of
Contract Drawings.
D. Make drawings available for the Architect’s periodic inspection and submit
for review with As-Built Drawings.
A. Prepare and submit before the relevant work proceeds, all drawings
necessary to install the Works. Drawings shall be based on the Contract
Drawings and must be fully coordinated with the architectural works and
other disciplines and shall take into account any modifications either to the
building or the installation which may have taken place, incorporating details
of the actual items of plant and equipment to be installed.
B. Prepare and submit all necessary Schedules of Equipment and devices with
the relevant drawings.
ii) The drawing does not contain any variations other than those
authorized by the Owner's authorized representative instruction.
iii) On re-submittal, all alterations made since initial submission have been
clearly annotated on the drawing and listed separately down the right
hand side of the drawing.
6.1 GENERAL
C. Provide two copies of all such guarantees, one of which shall be included in
the Operation and Maintenance Manual.
ii) Circuit breaker and cable schedules in the form of typewritten sheets
showing the number, type, location, application, service and symbol,
and normal operating position of each protection installed.
iv) Schedules of plant, equipment, valves, etc., by system, stating their locations
within the building, duties and performance figures, together with anticipated
life exp.
v) A unique code for each item of plant, equipment, valves, etc., installed
number cross-referenced to the rend diagrammatic drawings and Schedules.
The name, address and telephone number of the manufacturer of every item
of equipment and plant shall be listed together with catalogue list numbers.
vii) A copy of all test certificates including those for all plant, equipment, valves,
etc., used in the installations, including (but not limited to) electrical circuit
tests, corrosion testes, type testes, works tests, start-up and commissioning
tests, including those for air and water balancing.
i) Starting up, operating and shutting down instructions for all equipment and
systems installed.
ii) Control sequences for all systems installed.
iii) Scheduled details of all equipment settings, and actual values maintained in
controlled variables during commissioning.
A. Provide the Owner's authorized representative with one original and three
copies of the final Operation and Maintenance Manual.
C. Make two sets of temporary manuals (with provisional Record Drawings and
preliminary performance data) available at commencement of
commissioning to enable Owner's staff to familiarize themselves with the
installation.
These should be of the same format as the final manuals with temporary
insertions for items which cannot be finalized until the works are
commissioned and performance tested.
8.1 GENERAL
A. Prepare and submit a master plan for drawing production covering the
following:
A. The final draft of the Operation and Maintenance Manual shall be submitted
in due time, and in any case not less than four weeks prior to Practical
Completion, so that at least one copy of the complete final version is in the
possession of the Owner at Practical Completion.
B. the Operation and Maintenance Manual is an essential part of the works. The
works will not be accepted as complete and payment will be withheld until
the required number of copies of the complete final document have been
received by the Owner's Authorized representative.
A. If the contractor fails to produce and submit the record drawings as required
during the progress of the works, or other information for the operation and
Maintenance Manual by the due dates.
10.1 GENERAL
C. In addition, the contractor shall execute the following in connection with the
applicable statutory Undertaken and other Authorities.
A. Take responsibility for and complete any application made by the Owner in
respect of any matter related to the works.
10.4 SAMPLES
A. Examine and check the contract Documents for compliance with the Statutory
Requirements so that written notice of any divergence the contractor may find
between the contract Documents and the Statuary Requirements, can be
issued to the Owner's Authorized representative by the contractor in due time
so as not to delay the progress of the works.
A. Give all notices in accordance with BY-Laws and regulations and pay all
fees and charges legally demandable. Provisional Sums are included in the
Bill of Quantities for fees and charges payable to Statutory Undertakings and
other Authorities.
A. Obtain details of any builders work required, and provide the Owner's
Authorized representative with all necessary details of same.
10.9 AMENDMENTS
10.10 FORMALITIES
B. Prepare installation Drawings for sprinkler system, fire main, pumps, alarms,
fire prevention systems and the like, together with related calculations and
technical information in a suitable form and submit same to the local
Authorities and Fire Insurers as required by the Owner's Authorized
representative.
A. The contractor shall be responsible for any cost changes for re-connections,
re-visits, re-, etc., except for such charges arising from any direction of the
Owner's Authorized representative arising from any direction in respect of
defective work.
A. Arrange for facilities to be provided for the purpose of laying new mains and
services and adjusting existing equipment.
B. Notify the owner's Authorized representative that the work of the Statutory
Undertakings and other Authorities is complete in order that the owner's
Authorized representative can issue directions in respect of covering up of
the permanent works by other contractors.
A. Unless otherwise specified all materials, plant and equipment, and the use
and installation thereof, shall comply with the material, test and other
requirements of the relevant. IEE wiring regulations 16th edition, IEC
standards and BS standard.
D. Allow for proper packing and safe delivery of all equipment and materials
and for returning re-usable packaging to the suppliers as appropriate
E. Include for obtaining materials from any source whatsoever to complete the
works within the contract period and no claim will be allowed for materials
ex-stock or from any other source in the event of difficulty of supply.
E. Completely cover valve ports and ends of pipes or plug to prevent the ingress
of foreign matter, and additionally protect flanges against damage to the
flange surface.
F. Examine all materials and equipment supplied under this contract on delivery
to site and immediately prior to installation. Any material or equipment
which is damaged or faulty shall be replaced.
A. The contractor shall be responsible for the true and proper setting out of the
works and for the correctness of position, levels, dimensions and alignment
for all parts of the works and for the provision of all necessary instruments,
appliances and labor in connection therewith. If any error shall appear or
arise in the position, levels, dimensions or alignment of any part of the works
the setting out for which the contractor was responsible, the contractor shall
at his own expense rectify such error.
B. The checking of any setting out or of any line or level by the Owner's
authorized representative shall not in any way relieve the contractor of his
responsibility for the correctness thereof. The contractor shall carefully
protection preserve all bench-marks, sight rails, pegs and other things used in
setting out the works.
C. Take all necessary dimensions on site, check runs and levels and mark out
for builder's work.
A. The contractor shall be entirely responsible for ensuring that all his work is
adequately protected. Protection shall be by the contractor at the completion
of each day and during periods of inclement weather, and all work exposed
to view on completion in the works shall be protected from spillage, stains
and other damage. All systems shall be kept in a fully drained condition prior
to commissioning.
B. Test water shall be disposed of so as not to damage any part of the temporary
or permanent works, or any adjoining land or property.
A. Agree procedures for notices, witnessing, reporting and recording tests with
all parties involved including local authorities and statutory undertakings,
prior to the commencement of the works.
A. Re-test or carry out at no extra cost any additional tests required to establish
acceptability of the works following failure of any part thereof or any item
therein to meet the required standard or functional performance.
B. All such instruments and equipment shall be adequate for the purpose and
shall satisfy the purposes and accuracy’s required by the contract documents.
C. All instruments and equipment shall remain the property of the contractor.
A. Provide all necessary staff with the relevant skills and competence for all
inspection, testing, commissioning and performance testing.
12.1 GENERAL
13.1 PROCEDURES
B. Where appropriate all materials delivered to the site shall bear the
manufacturer's name, brand name and any other data that may be required to
verify their exact nature and relate it to the requirement of the contract
documents.
B. All records shall be retained on site and made available to the Owner's
authorized representative on request. On completion of the works all records
shall be handed over to the Owner's authorized representative unless
otherwise directed.
C. These records shall include, as appropriate, but not be limited to, project title,
contractor's name, the identification of the element, item, batch or lot, the
nature and number of the observations and tests, the dates of testing, the
name and signature of the person responsible for the testing, the number and
type of deficiencies found, and details of any corrective action taken.
D. Any record which indicates that any part of the works inspected or tested
does not comply with the contract documents shall be submitted without
A. Defective work, and the opening up of the works to ascertain same, shall be
dealt with strictly in accordance with the requirements detailed elsewhere in
the contract document.
B. Replace defective work with materials, goods or work in accordance with the
contract documents. Alternatively submit proposals for any treatment or
making good that is considered will bring the defective work to the standard
required by the contract documents. Such proposals shall not relieve the
contractor of his responsibility to execute the works to the full intent of the
contract documents.
C. The costs as defined in the contract conditions shall include the cost of any
related delay or disruption in the progress of the works, or any other
A. The contractor shall not execute any work when it is likely to be adversely
affected by inclement weather and he shall make good any damage so caused
at his own expense.
A. The contractor shall pay any costs incurred by the Owner, Owner's
authorized representative or the consultant in connection with unsuccessful
tests, including costs incurred due to the inability of the contractor to make
or complete a test, having given the notice required above.
The form of the records shall be agreed with the Owner's authorized
representative in advance of commissioning and the record for each
complete commissioning procedure shall be dated and signed by the
person whom the contractor has appointed to be formally in charge of
commissioning.
B. Only when this written certification has been received by the Owner's
authorized representative will performance tests be allowed to commence.
Unless otherwise agreed by the Owner's authorized representative in writing,
where engineering systems involve the works of more than one works
contractor, performance tests will only be allowed to commence when
written certification from all the relevant works contractors has been
received.
C. Carry out during this period full tests on the complete works to demonstrate
that the works meet the requirements of the contract documents.
D. The Owner's authorized representative may at his discretion waive any part
of the full test procedure if he considers it has been satisfactorily
demonstrated, recorded and properly certified at any earlier time but the
contractor shall however allow in his costs for carrying out all of the
provisions in this clause.
A. Test the performance of the whole of the works in both summer and winter
design conditions and allow for any special visits to site and provide any
necessary attendant during the defects liability period to set up, monitor and
remove test and recording equipment.
A. No part of the permanent services installations shall be used by the cofor his
own benefit without the written agreement of the Owner's authorized
representative.
B. Should any part of the works be operated during the period of the contract
for the benefit of the contractor and/or the Owner's authorized representative,
all consumable spares, including light bulbs and tubes which have been so
put to use shall be replaced by new not more than seven days prior to
practical completion.
A. Defects, s’s or other faults appearing at any time during the defects liability
period which have led, or, in the opinion of the Engineer, are likely to lead to
failure or malfunction of any part of the works shall be made good
immediately upon receipt of any instruction or direction of the Owner's
authorized representative.
B. Prepare and submit a record of any failure or malfunction of any part of the
works, the remedial action taken, subsequent re-testing and the results
thereof.
D. Inform the Owner's authorized representative in writing when all defects are
finally rectified so that an inspection may be carried out prior to the issue of
the final certificate.
B. Take all the necessary precautions to ensure the safety of all site personnel,
and the general public, and in respect of the contract works provide for the
safety, health and welfare of work-people employed on the site to comply
with the requirements of the following and of all other relevant statutes,
statutory instruments, statutory regulations or industrial agreements.
A. Conduct operations in such a manner that nuisance shall not be caused to the
general public, adjoining residents and users of adjacent buildings.
If such nuisance is being caused the contractor shall immediately make such
arrangements as will prevent a recurrence of the same and indemnify the
Owner against any claims arising there from.
ii. The laser should be turned off or shuttered when not in use or
unattended.
iii. The laser should be set well above or below the heads of employees
when possible.
iv. Employees should never stare directly into the laser beam or point the
laser at another person.
v. all laser equipment must bear a label indicating the maximum beam
output, which must not exceed 5 milli watts.
A. Carefully protect and maintain all trees, hedges, shrubs, etc., in proximity to
the works and which are to be retained in the permanent works.
The contractor shall include for providing assistance to the Owner's staff
during the course of the installation to explain the purpose and function of
the works.
A. Fuel and power for commissioning and performance testing the works
B. Fuel, water and power for running the contract heating system to dry out the
building including payment of statutory undertakings for same.
A. All temporary works required for the proper and safe construction of the
permanent works and for the protection of personnel on site.
A. The contractor shall provide and maintain in full working order all necessary
safety equipment for access and inspection purposes for use by the contractor
and for use by other personnel on site as instructed by the Owner's
authorized representative. Such equipment shall include, but not be limited
to, protective clothing, safety harness, gas detection and emergency
breathing apparatus for inspection of confined spaces.
A. The works covered by this contract are the design, selection, manufacturing,
works testing, supplying delivery to site, erecting, connecting up, testing,
commissioning, performance testing and handing over in working order the
complete engineering services installations described in the contract
document.
There will be other Contract Works associated with and related to this Contract.
The contractor is responsible for getting approval from Electricity Authority for
risers and distribution.
The Contractor shall make himself fully aware of the interfaces between and the
requirements of his Works and the works of other.
C. Once the Contractor has demonstrated the operation of the Works to the
satisfaction of the Owner's Authorized Representative the complete
integration of the Contractors Works with the Works of others will be the
responsibility of others.
D. Not withstanding this, the Contractor's Works will not be deemed complete
E. The Contractor shall allow for full attendance to the Owner's Authorized
Representative and others in order that the whole of the Works under this
contract can be successfully demonstrated to be functioning and operating
with all other associated works to the satisfaction of the Owner's Authorized
Representative.
F. This shall not relieve the contractor in any way of his responsibilities under
the Contract.
SUBSTATION EARTHING
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16010, applies to work of this
section.
1.4 SUBMITTALS
PART 2 - PRODUCTS
2.1 ELECTRODES
A. Earth rods shall be of circular cross-section copper bond type Sections shall be
jointed with purpose made couplings and a suitable driving cap and tip shall be
fitted to the rod extremities. Couplings shall not exceed the diameter of the rod.
B. Rod section couplings, driving cap and tip shall be bronze or other material
which exhibits mechanical strength, electrical continuity between sections and
does not give rise to electrolytic or corrosive action. All coupling units shall be
the same length of threaded length of the rod.
C. Earth rods shall be a minimum length of 3 meters and shall be driven into the
ground using a suitable mechanical hammer. The tops of the rods shall be
driven below ground level to suit the inspection pit.
D. The top of each rod electrode shall be housed in a purpose made concrete pit to
facilitate inspection. The pit shall be provided with a lid and the assembly shall
be flush with ground level.
E. All copper cables shall be connected 120 mm from the top of the earth rod with
a purpose made of thermo weld.
G. Copper stranded cable may be installed in the same trenches as LV cables but
shall be separated from all other cables and services by a distance not less than
300 mm.
H. The resistance to earth of the electrode system shall not exceed five ohm. Site
testes shall be made to ascertain that the electrode system resistance meets this
requirement. If the resistance exceeds this figure the contractor shall submit his
proposals to reduce the system resistance to the specified level.
A. Earthing conductors connecting the main earthing terminal or bar and electrode
system shall be green/yellow PVC insulated, stranded copper cable. A
A. The main earthing terminal shall consist of hard drawn copper to IEC,
DIN/VDE Standards BS 1432 formed into a bar having minimum dimensions
as detailed in the earthing schematic.
B. Each earthing bar shall be mounted not less than 450 mm above the finished
floor level and spaced by means of insulators not less than 50 mm from the
fixing surface.
C. The diameter of fixing holes shall not exceed one third of earthing bar width.
Where this is not possible then the connection shall be made to a copper flag
welded to the earthing bar.
B. Where a number of protective conductors follow the same route these shall be
green/yellow PVC covered and installed on a galvanized cable tray and fixed
with purpose made cleats.
D. Sockets lugs, bolts, nuts, washers, screws, rivets, clamps, cleats or other items
which come into direct contact with copper protective conductors bars, strips,
cables etc, shall be non-ferrous and manufactured from brass, bronze or other
suitable conducting material which will not cause electrolytic or other
corrosion. Where connections occur between copper and galvanized structures,
contact surfaces shall, additionally, be tinned and after completion compounded
The joints shall be made using zinc free brazing material with a melting point of
at least 600 oC. The amount of overlap between the two strips to be jointed shall
not be less than the width of the larger conductor.
PART 3 - EXECUTION
3.1 EXAMINATION
3.2 INSTALLATION
C. Earth the electrical installation including, but not limited to, the following:
Underground distribution, substation service equipment, electrical service
system neutral switchgear housings, cabinets, housings and neutrals of
transformers lighting protection system, emergency distribution systems,
busway enclosures, motor control centers, individual starters and other non-
current carrying metal parts of electrical equipment.
D. Wherever flexible metal conduit or cable are used for part of a raceway run,
provide an earthing conductor in the raceway or cable and connect to earthing
bushings at each end of run.
E. Where pull boxes contain barriers, provide an earth lug in each section.
J. Bond all conductive piping system in the building to the electrical system earth.
Make bonding connections as close as practical to the water pipe or service
equipment earthing bar.
K. Where expansion fittings occur, provide internal code size earth conductor
terminating in adjacent pulling points with earthing bushings.
3.3 EARTH TESTS
After installation of the individual earthing systems in accordance with the above for
the various parts of the works and after the whole installation has been connected up,
resistance tests shall be carried out at each sub-station and for each earth source
independently and the readings obtained officially and recorded. Three readings shall
be obtained for each sub-station relating to the two earth paths connected individually
and in parallel.
An Evershed and Vignoles or similar earth tester shall be used and all results
tabulated and handed to the Engineer.
ELECTRICAL IDENTIFICATION
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16050, apply to work of this
Section.
C. In case of conflict among the referenced standards and codes, the more
stringent provision will govern.
1.4 SUBMITTALS
PART 2 - PRODUCTS
A. Identify the wires and cables of feeders by means of fiber or non-ferrous metal
tags fastened with non-ferrous metal wires or bands throughout; fastenings for
metal tags of the same metal as the tag.
A. Engrave device plates for local toggle switches, toggle switch-type motor
starters, pilot lights, and the like, whose function is not readily apparent with
3mm high letter suitably describing the equipment controlled or indicated.
A. Stamp phase identification letters into the metal of the bus bars of each phase
of the main busses of each power center switchboard and panelboard; make
letters visible without having to disassemble any current carrying or
supporting elements.
A. Identify each outlet box, junction box and cabinet used in conjunction with
empty raceway for wires of a future system by means of identifiable markings
on the inside denoting the system.
A. Equip all electric switchboard rooms, electric closets, metal screened spaces
assigned to electric equipment and the like, with enameled sheet metal "red on
white" signs reading "Electric Equipment Room-No Storage Permitted";
mount signs at clearly visible locations within the rooms.
2.7 ENGRAVE
A. Device plate for receptacles other than 220 volt 10 and 16 amperes receptacles
with 3 mm high black letters and designating the following:
1. Voltage
2. Number of phases
3. Current rating.
2.8 MARK
2.9 NOMENCLATURE
2. Designate the feeder number and the name of the load supplied where
they control feeders.
C. The nomenclature used to identify feeder wires and cables to designate the
feeder number.
PART 3 - EXECUTION
3.1 INSPECTION
Do not proceed with work until unsatisfactory conditions have been corrected.
3.2 INSTALLATION
H. Label all conductors in wire-ways and pull and junction boxes with panel-
board designations and circuit number.
I. Identify Individually:
1. MV switchgear
2. RMU ring main units
3. Transformer
4. Switchboards
5. Main and feeder devices in switchboard
6. Distribution and circuit breaker panel-board
7. Safety switches
8. Audio-visual equipment cabinets
9. Boxes for fire alarm system
10. Cabinets, junction and pull boxes of all systems installed, i.e., fire
alarm (life safety) system, telephone, television, security, etc.
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16050, applies to work of this
Section.
D. The requirements of this section apply to wire and cable work specified elsewhere
in these specifications.
A. Work includes providing all wires, cables and connections, complete with all
accessories in accordance with Drawings and Specifications and as required for a
complete system. Wiring size referenced in this Section is metric, except as noted.
For special wiring for individual systems, refer to respective Section of these
Specifications.
C. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
B. Samples: Submit 25cm length cables of each type and size of wires and Cables,
Manufacturer Name, insulation class and reference No. Should be indicated on
the Submitted Sample.
PART 2 - PRODUCTS
A. GENERAL
Provide all of the mains cables shown on the drawings or detailed in the cable
schedules or the schedules of work.
All single and multi-core cables shall comply with IEC 502 and all conductors
shall be Aluminum or copper P.V.C. and XLPE insulated and P.V.C. sheathed
(0.6/1 K.v), armoured type as indicated on the drawings.
Copper conductors shall be stranded for sections 3mm2 and above. Signal and
control cables shall have solid conductors. Flexible cords shall have finely
stranded conductors.
For each lot of cable supply a certificate of origin issued by the manufacturer
stating its origin, manufacturer, constitution and standards to which it complies
with. In the absence of such documents, the Engineer reserves the right to require
that tests, at the Contractor's expense, be performed by an official laboratory on
samples taken from lots of cables delivered to the Site.
Cable installations whether so indicated or not shall include all joints and their
accessories at terminating ends or at tap-off points, earthing and bonding etc.
Carried to completion.
Joints in cable shall not be accepted unless so required in the Drawings. Cables
shall be supplied in lengths sufficient for a straight-through pull from termination
to termination.
The definition of "Low Voltage" given in the IEE wiring regulations shall apply
and "High Voltage" shall mean any voltage higher than low voltage.
All cables shall be delivered to site with the manufacturer's seals, labels, or other
proof of origin intact. Such labels and seals shall not be removed until the cable is
required for use, and shall be retained for inspection.
Cables shall be handled, terminated and installed in accordance with the cable
manufacturer's recommendations. The technical advice of the manufacturer's
recommendations. The technical advice of the manufacturer's specialists shall be
followed if any special conditions or unusual circumstances apply.
Where cable sizes are not indicated on the drawings or in the cable schedules, the
contractor shall be responsible for determining the correct size of each cable.
Cable sizes shall be determined on the basis of current rating and/or voltage drop
and/or earth loop impedance, together within allowance for grouping with other
cables and the method of installation, whichever is relevant, after taking into
account the type of cable, the ambient conditions, the method of installation and
the disposition of each cable relative to other cables.
Full details, with illustrations, of all cable supports and fixing devices shall be
submitted before any orders are placed or work put in hand. All cable supports
and fixing devices shall be designed to have a factor of safety of not less than 4
Wherever cables pass through walls, ceilings, partitions and the like, a heavy-
gauge PVC sleeve shall be provided, of internal diameter greater by at least 12
mm, but not more than 25 mm, than the diameter of the cable.
Where cables pass through walls and/or floors which form part of the building's
fire compartmentation, the hole(s) through which the cables pass shall be sealed
after the cables have been installed, so as to give the same standard of fire
resistance as the original wall or floor. Details of the proposed sealing method
shall be submitted prior to implementation.
All cables shall be separated from water, gas, and other piped services by a
distance of not less than 150 mm unless the circumstances of the installation make
this impossible.
Fire resistant cables will be used as indicated on the drawings and it shall be
copper conductors, XLPE/Steel wire armoured type fire rated for 3hours (950 °C),
category C,W and Z with normal operating temperature (90°C) to meet BS 6387.
Cabling and wiring installation shall be performed strictly in compliance with the
IEE wiring regulation.
Where two or more cables are run in parallel, they shall be fixed on galvanized
steel trays or in approved special cable supporting and protecting raceways.
Cables shall be fixed to the supporting structures with approved galvanized cast
steel clamps at distances not exceeding 20 diameters.
The cables installed inside the tunnels should be covered by fire resisting coating,
tenderers (the cable supplier) should submit the technical specification and test
procedures for the coating.
Note: all cables inside the tunnels should be covered with fire resisting coating
material which comply with the international standard specification IEC 60-332,
or IEEE383.
Tenderer should submit the type of this material including the technical
specifications and test procedures for the coating material.
The current carrying capacity of power cables should not be affected by the fire
retardant coating when applied at the thickness recommended by the manufacturer
and listed in the fire test reports.
Final sub-circuit work originating from light and power panel boards shall be
arranged as shown on the Drawings.
Final sub-circuit wiring shall have insulation class level not less than (450/750V).
Unless otherwise specifically indicated on the Drawings, all final sub-circuit for
corridor lighting and sockets shall be multi core cables installed on cable tray
above false ceiling.
At least 150 mm of free conductor shall be left at each outlet, switch point and
pull box for the making up of joints, or the connection of fixtures or devices,
except where conductors are intended to loop without joints through lamp holders,
receptacles and similar device boxes.
Generally, branch circuit conductor sizes are indicated on the drawings. Such
sizes are minimum requirements and must be increased, where required, to suit
the length of run and voltage drop, at no extra cost. Voltage drop from distribution
transformers to furthest outlets shall be maximum 5%.
All wires and cables shall be manufactured to comply with the relevant Standard
Specification I.E.C. or equal standard. The cables delivered to the Site shall bear
Rev.01 August, 2018 Wires And Cables
Section 16120
Page 5 of 19
the mark of identification of the manufacturer and the Standard to which it is
manufactured. Any cable not having identification marks shall be rejected.
Wires and cables of sizes over 16 mm² shall terminate with sweated or
compression type lugs. Insulating sleeve shall be used to protect any exposed part
of the conductor or sleeve projecting beyond any insulated shrouding or mounting
of a live terminal.
Glands for the various types of multi core cables shall be purpose made and
suitable for the equipment enclosure.
Joints and taps in multi core or single core feeders and sub- feeders shall be
effected in purpose made kits consisting of outer containing mould, thermosetting
insulating compound (or resin) and by use of appropriate tinned copper ferrules
crimped onto the conductors and taped before pouring in the compound.
Joints or taps on L.V. wires and cables shall be permanently accessible, and
unless permitted otherwise shall be made only in tap boxes or cabinet gutters.
Joints in branch circuits of conductor sizes up to 16 mm² shall be made by barrel
type connectors with pinching screws, the whole shielded in porcelain or
self-setting compound shroud. Shrouds of polythene or similar non-heat resistant
materials will not be permitted.
Joints in branch circuit conductor sizes larger than 10 mm² shall be made by
means of pre-insulated spring-type spring shall be corrosion resistant tempered
metal. Enclosure shall be a steel shell with an overall vinyl cap and skirt.
Connector shall be equal to "Scotchlock" as manufactured by the 3M Company.
Joints in branch circuit conductor sizes 16 mm², and larger shall be made by
two-bolt clamps protected with an insulating phenolic cover.
A. GENERAL REQUIREMENTS
The insulation class shall not be less than 18/30 (36) KV. Cables shall comply
with IEC 60502-2, BS 6622 and E.E.A specifications.
CONSTRUCTION
Each conductor shall have a zone resistant layer of cross- linked polyethylene
(XLPE) extruded on the screened conductor.
The thickness shall be 5.5 mm to correspond with the relevant IEC publication
60502-2 for 24 k.V. insulation level.
Identification of cables shall be carried out by embossing on the outer PVC sheath
the voltage rating (class), size and number of conductors, manufacturer's name
throughout the whole length of cables.
B. MEDIUM-VOLTAGE TERMINATIONS
Shielded power cable termination kits shall be factory engineered for the
application.
Termination kits shall meet or exceed all rating requirements of IEEE-48 for class
I terminations and the test sequence prescribed by IEEE-404, including 130 C
load cycling and 130 C impulse withstand.
Each kit shall include lengths of heat-shrinkable tubing to help prevent corrosion
and shifting of the shielding layers between the boot and the phase termination
installation point.
When grounding conductors are included, the kit includes lengths of heat-
shrinkable tubing and sealant material to seal each conductor from the boot to its
connection point.
Except in the case where it is terminated in full view onto a clearly labelled switch,
starter, distribution board or similar piece of apparatus, or onto a motor or other
item of equipment the function of which is evident, each and every cable end shall
be provided with an approved means of identification. In particular, this
requirement shall apply to all cables terminating on the back, or in the base, of
cubicle type or similar switchboard or control panel and in any other case where the
function of the cable is not immediately obvious.
(i) An engraved brass or aluminum label securely fixed to the cable sealing box.
The means of identification shall give the cable size, number of cores, and
function together with the cable reference number if one has been allocated.
All cables run above and under ground shall be identified by means of engraved
brass or aluminum label at intervals not exceeding 30 meters. The labels shall
bear details of the cable size, number of cores, function, and reference number (if
any) and shall be securely attached to the cables with galvanized iron or tinned
copper binding wires.
The tests to be carried out shall include but not necessarily be limited to:-
2. Inspect bolted electrical connections for high resistance using one of the
following methods:
3. Test Values
2. Bolt-torque levels.
3. Microhm or millivolt drop values shall not exceed the high levels of the
normal range as indicated in the manufacturer's published data. If
manufacturer's data is not available, investigate any values which deviate
from similar connections by more than 50 percent of the lowest value.
3. Inspect bolted electrical connections for high resistance using one of the
following methods:
2. Electrical Tests
4. Perform a dc high-potential test on all cables. Adhere to all precautions and limits
as specified in the applicable NEMA/ICEA standard for the specific cable.
Perform tests in accordance with ANSI/IEEE Standard 400. Test procedure shall
be as follows, and the results for each cable test shall be recorded as specified
herein. Test voltages shall not exceed 60 percent of cable manufacturer's factory
test value.
7. Insure that the maximum test voltage does not exceed the limits for
terminators specified in ANSI/IEEE Standard 48, IEEE 386, or
manufacturer's specifications.
9. Raise the conductor to the specified maximum test voltage and hold for
five minutes. Record readings of leakage current at 30 seconds and one
minute and at one minute intervals thereafter.
10. Reduce the conductor test potential to zero and measure residual voltage at
discrete intervals.
11. Apply grounds for a time period adequate to drain all insulation stored
charge.
3. Test Values
3. Microhm or millivolt drop values shall not exceed the high levels of the
normal range as indicated in the manufacturer's published data. If
manufacturer's data is not available, investigate any values which deviate
from similar connections by more than 50 percent of the lowest value.
6. Graphic plots may be made of leakage current versus step voltage at each
increment and leakage current versus time at final test voltages.
For the purpose of this specification, the description "small wiring" shall apply to
all low voltage cables and wiring connected directly or indirectly to the public
electricity supply system, or to any independent private supply system for the
purpose of supplying electricity to general power and lighting circuits, except the
following:
(ii) fire detection, alarm, and other security circuits operating at a voltage
level of 24 volts or less between conductors.
(iii) cables and wiring forming part of a system for the control and/or
supervision of the building engineering services.
All of the above cables and wiring included are fully described elsewhere in this
Specification under appropriate headings.
All cables to be used for small wiring shall comply with the relevant British
Standards.
The contractor shall submit with his Tender details of any internationally
recognized Standards and Codes of practice he proposes to use in lieu of, or in
addition to, those stated.
All wiring shall be carried out using one or more of the following wring systems,
as indicated on the drawings.
All cables to be used for small wiring shall comply with the relevant DIN/VDE
and IEC Standards.
PVC cables to and rubber cables to IEC/DIN/VDE shall not under any
circumstances be run underground.
No cables shall be installed unless the ambient temperature and the temperature of
the cable are above 0 oC, and have been so for the preceding 24 hours.
Where cables have subjected to temperatures below 0 oC, care shall be taken to
ensure that they are above that temperature for 24 hours before installation.
PART 3 - EXECUTION
3.1 INSPECTION
A. Examine conditions under which wires, cables and connections are to be installed.
Notify Engineer in writing of conditions detrimental to proper completion of the
work. Do not proceed with work until unsatisfactory conditions have been
corrected.
1. Connect all branch lighting and power circuits to panel boards so as to balance the
actual loads (wattage) within 5%. If required, transpose branch circuits when the
work is complete to meet this requirement.
2. At the request of the Project Manager or Consultant, perform all necessary tests to
show the above requirement has been fulfilled. Make such tests after the building is
Rev.01 August, 2018 Wires And Cables
Section 16120
Page 14 of 19
occupied.
3.3 INSTALLATION
C. Pull conductors simultaneously where more than one is being installed in same
raceway.
E. Use pulling compound or lubricant, where necessary; compound used must not
deteriorate conductor or insulation.
F. Use pulling means, including fish tape, cable, rope and basket weave wire/cable
grips which will not damage cables or raceway.
H. Complete conduit or raceway installation (joints made up tightly and the entire
run secured in place) before pulling wire and cable.
J. Support wires and cables at the upper end of all risers and at intermediate points
as required by the approved manufacturer and applicable electrical codes.
K. Seal, between the wire and conduit with a non-hardening compound approved for
the purpose, cable and wire entering a building from underground where cable
exits the conduit.
L. Install cable spacers where required. Provide conduit fittings for spacing of
cables at terminations, consisting of galvanized or cadmium plates, steel or
malleable iron threaded conduit and fittings and inserts of non-metallic insulating
material with openings adequate to accommodate cables being spaced.
M. In certain systems, equipment furnished by an approved manufacturer may
require a different number and arrangement of conductors from that indicated on
N. In wire ways and large pull boxes, lace and tie off conductors in groups of 3
phases and neutral (if used) as installed in conduits to limit conductor unbalanced
loading.
O. Leave all wires with sufficient slack at terminal ends and lighting fixtures for
convenient connections and servicing. Stow loose ends neatly in outlet box.
P. Provide splices and taps in accessible boxes, panel boards fittings, gutters,
terminal panels, etc., only. Provide materials compatible with the conductors,
insulation’s and protective jackets on the cables and wires.
R. Install splices and taps which possess equivalent-or- better mechanical strength
and insulation ratings than conductors being spliced. Use connectors which are
compatible with conductor material.
S. Tie all circuit and control wiring in cabinets, panels, pull boxes, and junction
boxes.
W. Prepare cables and wires, by cutting and stripping covering armor, jacket, and
insulation properly to ensure uniform and neat appearance where cables and wires
are terminated. Exercise care to avoid cutting through tapes which will remain on
conductors. Also avoid "ringing" copper conductors while skinning wire. Cut
armored jackets with tools made specifically for that purpose.
Y. All wires and cables installed in the return air ceiling spaces or similar areas to be
installed in metallic raceways.
Z. The underground cables shall be laid below the ground level. After the cables are
laid, the trenches shall be back-Filled to a depth of 15 cm with fine selected soil
free from lumps metallic or other foreign inclusions or where required by
engineer by fine sand. A continuous row of bricks shall be laid, then the
remainder of the trench shall be back filled in an approved manner with soil,
which shall be thoroughly consolidated.
Where the cables cross the asphalt roads and enter into building, they shall pass
through pipes type UPVC of size as indicated on the drawings.
Minimum overall sizes and details as indicated on the drawings & as approved on
the shop drawings.
B. All manholes shall be watertight and furnished with sump pits. Floor shall be
graded in order to accommodate draining to pit. Outside surfaces of manhole and
pull boxes shall be coated with an approved polyurethane water-proofing coating
of 1.8 mm minimum thickness (all sides and roof). Care shall be taken to assure
bonding of side coating with base membrane.
C. Bolted and Gasketed Manhole Frames and Covers: Cast iron of indicated size.
Set frame and cover to final grade as indicated or required. Fully coordinate with
the civil and landscape details.
D. Duct envelopes and conduit shall enter manholes and pull boxes at right angles to
box wall.
F. Bolt or studs imbedded in concrete for cable rack mounting are not acceptable.
G. Install pulling eye irons imbedded in walls opposite each duct entrance plus the
floor, and securely fastened to the manhole reinforcing rods before concrete is
poured.
J. Manhole frames and covers shall be cast iron, watertight, heavy duty type,
suitable for roads, pavement and garden loading, and have machined bearing
surfaces. Each unit (frame and cover) shall withstand not less than 400 KN , and
be set to final grade as required. Covers to be indented solid top design, with two
drop handles each. The word "Light Current manhole" or "Power manhole" , as
appropriate, shall be cast on the upper side of each cover.
A. Check for physical damage and proper connection in accordance with drawings.
E. Prior to energization, test wires and cables for electrical continuity and for short
circuits.
PART 1 - GENERAL
C. In case of conflict among the referenced standards and codes, the more
stringent provision will govern.
1.4 SUBMITTALS
PART 2 - PRODUCTS
2.1 RACEWAYS
A. Rigid Steel Conduit (RSC): Full weight steel pipe hot dipped galvanized
inside and outside, threaded, minimum 20mm, unless otherwise noted;
minimum 15mm for switch legs.
A. GENERAL
3. Earthing (grounding) Bushings: With lug suitable for the size and type
of earthing (grounding) conductor to be terminated.
3. Locknuts of the bonding type with sharp edges for digging into the
metal wall of the enclosure.
6. Sealing fittings of the threaded cast iron type. Where sealing fittings
are used to prevent passage of water vapor, utilize the continuous
drain type.
H. SUPPORTS
3. Multiple conduit (trapeze) hangers not less than 38cm x 38cm, 2,7mm
thickness steel, cold formed, dipped clamps. Hanger rods not less than
0.95 cm diameter steel.
A. OUTLET BOXES
1. PVC heavy gauge for concealed work, and galvanized cast iron or
aluminum with threaded hubs for exposed work; boxes of shapes,
cubic inch capacity, and sizes as required, suitable for installation at
respective location.
2. With mounting holes and with cable and conduit size knockout
openings.
5. For exposed work utilize 10cm round x 5cm deep for mounting on
ceilings and 10cm square x 5cm deep for mounting on walls, except
as otherwise required by construction, devices, or wiring.
A. Heavy gauge PVC, galvanized sheet steel with screw-on covers for interior
work, and galvanized cast iron and/or 2.7mm thickness stainless steel with
threaded hubs, gaskets for outdoors and damp locations; boxes of shapes,
cubic cm capacity, and sizes as required, suitable for installation at
respectable location.
PART 3 - EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
A. GENERAL
11. Test conduits required to be installed, but left empty, with ball
mandrel. Clear any conduit which rejects ball mandrel.
12. Provide long radius bends for empty raceway systems where required
to satisfy the system cabling requirements.
13. Install complete raceway runs before pulling in wire or cable. Install
raceways so that required conductors may be drawn in without injury
or excessive strain to raceway or cable. Where raceway size is not
indicated, follow applicable code.
15. For empty raceways over 3m long, provide fish or pull wire. For
3.8cm and larger pull wire to consist of steel core nylon rope and
terminal ball.
17. Do not support branch circuit conduits by the suspended ceiling or its
supporting members, lighting fixtures, mechanical piping, or air
conditioning ducts.
18. Conduits are not to cross pipe shafts or ventilating duct openings.
Avoid present and future openings in floor, wall or ceiling
construction, when so indicated on drawings.
20. Support riser conduit at each floor level with clamp hangers.
24. Do not install boxes back-to-back in walls. Provide not less than 150
mm separation.
25. Do not install aluminum products in concrete. Plug and seal conduit
interconnections.
26. Position recessed outlet boxes accurately to allow for surface finish
thickness.
29. Set boxes square and true with the building finish. Secure boxes to
the building structure and adequately support all boxes during
construction to prevent movement.
32. Mount outlet boxes for similar equipment at uniform height within
same or similar areas. Where mounting height or location of outlets
34. Except where special outlets are required, provide 10cm square wall
outlets with single gang raised cover and bushed plate for signaling
systems.
36. For conduit or cable tray runs exposed inside the building, mark
(stencil 3 M on centers, including in hung ceiling, with the notation,
"Danger, Volts," indicating the actual voltage (i.e. "Danger 11,000
Volts," "Danger 380 Volts").
38. For conduits and direct burial cable entering the building and for the
manholes preceding the conduits entry to the building, when
applicable perform the following:
39. Work with extreme care near existing ducts, conduits, cables and
other utilities to avoid damaging them.
41. Set floor boxes level and flush with finish flooring material.
Coordinate trim with type of finish, i.e., tile, carpet, etc.
3. Where located under the building, encase conduit for all runs above
5mm with concrete envelope with walls not less than 8cm thick.
2. Where located under the building, encase conduit for all runs above
5cm with concrete envelope not less than 8cm thick.
2. Use liquid tight flexible metal conduit for final connections to motor
terminal boxes, transformers and other vibrating equipment.
2. Cut ends square, ream smooth, wipe clean, apply approved solvent
cement and quarter turn as drawing up tight in accordance with
recommendations of manufacturer.
8. Screwed PVC conduit shall not be used unless specifically called for
on the drawings or when the PVC conduit is to be connected to metal
equipment, conduit and fittings with screwed entries. Where such
entries are not available, non-screwed male bushes and couplers shall
be used.
10. All bends shall be made using the correct size spring. Conduit sizes
of 25 mm and below may be set cold but all larger sizes shall be set
hot. A pipe vice shall not be used during this or any other operation.
The radius of any conduit bend shall not be less than 4 time the
outside diameter of the conduit. Naked flames shall not be used
directly to heat conduit for bending purposes. The use of conduit
bends having factures and conduits with any wrinkles on formed
bends is not permitted.
12. A protective conductor of not less than 2.5 mm2 with green and
yellow insulation shall be installed throughout, sufficiently long to
allow looping in and of fittings and accessories. Where expansion
couplers are used allowance shall be made in the length of the
protective conductor to accommodate any expansion.
CABLE TRAY
PART 1 - GENERAL
C. The requirements specified in this section apply to all related sections in this
Division. The requirements of all related sections, elsewhere in this division
also apply to this section unless specified to the contrary.
C. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
1.4 SUBMITTALS
B. Samples:- Submit 30 cm length of each size of cable tray complete with its
accessories and fittings.
PART 2 - PRODUCTS
A. GENERAL
8. Cable trays shall be perforated type and manufactured from mild steel
and to be galvanized after fabrication the galvanization must be hot dip
galvanized.
12. All cables shall be fastened securely by purpose made straps or saddles
to the cable trays.
13. Cable trays shall be connected by means of flexible tinned straps to the
nearest bare earthing conductors and at maximum of 30 meters spacing.
17. Perforate-type cable tray shall be used above the suspended ceiling. It
shall be manufactured from mild steel 2 mm thick, finished hot-dip
galvanized with a 20 mm return flange on both edges. Edge height 80
mm.
18. All components and accessories shall be hot-dip galvanized steel after
manufacture to give resistance to corrosion.
19. Same typical details of trays, ladder and perforated type are shown in the
drawings.
20. Cable tray width shall be chosen according to the number and diameter
of cables laid on the tray. all feeders and sub feeders shall be laid such
that their outer radius are spaced a distance equal to the diameter of the
largest cable.
B. SAFETY FACTOR
3. Design to be such that all like parts are interchangeable and that trays
may be readily assembled and joined without the use of special tools.
C. Fittings: at least the same thickness and cross sectional area of side members
and (rungs, bottom) as straight sections.
3. Cable ladder shall be manufactured from hot dip mild steel and
galvanized after fabrication.
J. All cable trays shall be heavy duty type unless otherwise indicated on the
drawings.
PART 3 - EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
C. Install integral fire stops where cable trays penetrates fire-rated walls and
floors. Seal between cable trays and opening and around opening with
fire-rated sealant not less than wall, or floor, fire ratings.
G. Route cable trays as required and make final field measurements before
ordering cable tray.
I. Provide hangers, rods, straps, special brackets, and other means of supporting
cable tray as required.
CABLE TRUNKING
PART 1: GENERAL
A. Drawings and general provisions of Contract, including General and special Conditions
and Division-1 (General requirements), apply to work of this section.
B. General Provisions for Electrical Work, Section 16050, apply to work of this Section.
A. Work includes providing all materials, equipment, accessories, services and tests
necessary to complete and make ready for operation by the Owner, all cable trunking in
accordance with Drawings and Specifications.
C. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
1.4 SUBMITTALS
B. Samples:- Submit 50cm length of cable trunking complete with its accessories and
fittings.
PART 2: PRODUCTS
A. GENERAL
3. Lengths of trunking shall be efficiently bonded to each other using strip copper
links not less than 12 mm wide x 1.5 mm thick and fixed with brass nuts, bolts and
asked serrated washers.
4. Lids shall be lipped and fixed at intervals not exceeding 1 meter by means of quick
release can fasteners. Steel screws and fasteners shall be protected against
corrosion by a finish at least equivalent to zinc coating to DIN/VDE or NEC.
5. Metal partitions in trunking shall be a minimum thickness of 1.2 mm and the finish
shall be of the same standard as the trunking. The method of fixing partitions to the
trunking shall not cause long term corrosion or electrolytic action and shall be such
that the partitions cannot be inadvertently displaced.
6. Connectors shall span the complete internal surface of the trunking and shall be
designed so that the trunking sections mate with butting joints.
7. Vertical trunking shall be supplied with a cable support unit with insulated pins at
intervals not exceeding 3 meters.
9. Trunking shall consist of base, snap-on covers, coupling end plates, wall flanges,
panel to trunking rubber grommet, elbows, tees, adaptor plates and all necessary
hangers supports and accessories.
10. Trunking shall be constructed of steel. All steel units shall be protected inside and
outside with a corrosion resistant finish such as zinc or cadmium, with a top coat of
enamel.
11. All trunkings parts shall be mechanically and electrically coupled while protecting
wires from abrasion.
B. Where any cutting or damage is caused during erection, the finish shall be made good.
All burrs and rough edges shall be removed. Where any corrosion has occurred it shall
be removed and the area treated with a rust- proofing agent. After this it shall be treated
by the application of either a zinc rich epoxy primer or equal alternative followed by a
coat of color matching paint.
C. Any fixing used for securing or fitting shall not cause any long term corrosion or
electrolytic action-black japanned fixing screws shall not be used. Where brackets are
used they shall be constructed of mild steel angle or channel iron finished to the same
standard as the trunking.
D. Connections to conduit, multiple box, switchgear and distribution boards shall be made
E. Where trunking crosses settlement and expansion joints a trunking joints shall be made.
The connector at this point shall be made with slotted fixing holes to permit a
movement of 10 mm in both the horizontal and vertical planes. The earth continuity
links across such joints shall be of braided copper tape not less than 15 mm wide x 2
mm thick having a resistance from fixing to fixing equal to or less than the links used
for the standard trunking joints.
The braid shall be long enough to allow for the maximum movement of the trunking.
The braid ends shall be folded, and sweated soiled.
PART 3: EXECUTION
3.1 INSPECTION
A. Examine conditions under which cable trunkings are to be installed. Notify Engineer in
writing of conditions detrimental to proper completion of the work. Do not proceed
with the work until unsatisfactory conditions have been corrected.
3.2 INSTALLATION
C. Install integral fire stops where cable trunking penetrates fire-rated walls and floors.
Seal between cable trunking and opening and around opening with fire-rated sealant not
less than wall, or floor, fire ratings.
D. At floor openings provide concrete curb, 10 cm wide and 10 cm high, around cable
trunking and seal with non-combustible material.
E. Provide electrical bonding and equipment earthing connections for cable trunking
Tighten connections to comply with tightening torques specified by manufacturers to
assure permanent and effective connections and grounds.
F. Anchor mounting hardware firmly to walls, floors, or ceilings, to ensure enclosures are
permanently and mechanically secured. Provide all hardware and accessories for proper
mounting.
I. Provide hangers, rods, straps, special brackets, and other means of supporting cable
trunking as required.
A. Prior to installing cables in cable trunking, test for electrical continuity of bonding, and
earthing connections, and to demonstrate compliance with grounding requirements.
WIRING DEVICES
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16050, applies to work of this
Section.
C. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
1.4 SUBMITTALS
2.1 GENERAL
A. Samples of all wiring devices detailed in this section and a choice of cover
plates shall be submitted to the Owner Authorized Representative for
approval/selection.
B. Wiring devices shall comply fully with the relevant European or International
Standards.
C. Each type of wiring devices where applicable shall be of the same manufacture
and where necessary of the same maker's catalogue number or description to
provide consistent appearance and finish.
D. Flush mounting wiring devices shall be fitted into purpose made metal boxes
only. All wiring devices shall be flush mounted except in plant rooms.
E. All boxes or sections of boxes for use with wiring devices must incorporate a
suitably marked earth terminal. Accessory plates shall be secured to boxes by
not less than two fixing screws. Where these screws do not provide adequate
earth continuity to metal plates or plates including parts to be earthen then a
bonding connection shall be provided from the earth terminal to the plate or
part. The bonding shall be protected with a green/yellow insulated sleeve. The
above requirement shall not apply to the earth socket on a socket outlet when
directly connected to a protective conductor.
F. All sockets and disconnect switches marked weather-proof shall not be less than
IP-55 for (indoor installation) and IP-67 for (outdoor installation)
G. Where more than one phase of a supply exists in a multi gang box the following
requirements shall apply :
A clearly visible label showing the maximum voltage present shall be arranged
as a warning notice before access can be gained to live parts.
Wiring and accessories connected to each phase shall be separated from each
other by fixed screens or barriers.
H. All faceplates for switches and sockets flush mounted type should be plastic
type.
A. All switches for lighting and associated circuits shall comply with BS or DIN
and shall be quick make and break for use on a.c. supplies. Switches shall be
single pole and rated not less than 10 A, 220 V for use only on a.c. systems,
including fluorescent or inductive loads to DIN/VDE or NEC standards.
E. Push buttons single units or forming part of a multi gang unit shall be rated at
10 A, 220 V. The switch shall be single/double-pole and arranged for push to
make/ to break the contacts as applicable for the application.
F. All push buttons and switches located in corridors or stairs shall be illuminated
type.
2.4 DISCONNECTING SWITCHES FOR A/C & ANY OTHER (1-Φ) DEVICE /
EQUIPMENT
All disconnect switches for A/C shall be double pole with pilot lamp.
All disconnect switches for any other (1-Φ) device / equipment shall be double pole
with pilot lamp and flex outlet.
Outlet plates for cables or flexible cords shall be similar to switch plates and complete
with not less than two fixing screws. Terminals shall be provided to accommodate
incoming wiring and outgoing cables or flexible cord. The unit shall be unfused and
shall incorporate an outgoing cable clamp or cord grip. The cover plate of white
moulded plastic shall have a smooth aperture for the cable/flexible exit.
The tests to be carried out shall include but not necessarily be limited to:-
5. Inspect bolted electrical connections for high resistance using one of the
following methods:
9. Verify that each fuse holder has adequate mechanical support and
contact integrity.
3. Perform an over potential test on each pole, phase to ground with cutout
closed. Ground adjacent cutouts, if applicable. Test voltage shall be in
accordance with manufacturer’s published data. In the absence of
manufacturer’s published data.
3. Test Values
2. Bolt-torque levels.
3. Microhm or millivolt drop values should not exceed the high levels of
the normal range as indicated in the manufacturer’s published data. If
manufacturer’s data is not available, investigate any values, which
deviate from adjacent poles or similar switches by more than 50 percent
of the lowest value.
PART 3 - EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
C. Install wiring devices only in electrical boxes which are clean, free from excess
building materials, dirt, and debris.
I. Verify exact locations of switches and receptacles with architectural and interior
design drawings.
J. Install switches indicated on plans for the various rooms directly adjacent to the
entrance door and as shown on the approved shop drawings.
K. Check the architectural drawings for the door swings and locate all switches on
the lock side of the openings. Verify in field prior to switch outlet installation.
L. Coordinate all final mounting heights with Architect's elevations and details
prior to installation. Where heights are different than those indicated or
specified, the architectural heights take precedence.
N. Where more than one wiring device is mounted in the same location, gang
mount such devices una common face plate.
PART 1: GENERAL
B. General Provisions for Electrical Work, Section 16050, apply to work of this
Section.
A. Work includes providing all materials, equipment, accessories, services and tests
necessary to complete and make ready for operation by the Owner, all
miscellaneous control equipment shall be in accordance with Drawings and
Specifications.
C. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
1.4 SUBMITTALS
PART 2: PRODUCTS
5. With arc shields and magnetic blow coils if interrupting duty exceeds 300
ampere.
6. Interrupting capability not less than six times rated full load current.
1. Spring assisted gravity open on normally open contacts and spring loaded
magnetically open in normally closed contacts.
B. With primary and secondary over current protection with fused switches in
accordance with the codes governing.
PART 3: EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
D. Tighten connectors and terminals, including screws and bolts, in accordance with
equipment manufacturer's published torque tightening values for equipment
connectors.
E. Mount all equipment in cabinets suitable for installation with all necessary bus
bars and terminal strips. Separate low and high voltage sections with barriers.
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16050, applies to work of this
Section.
C. In case of conflict among the referenced standards and codes, the more
stringent provision will govern.
1.4 SUBMITTALS
A. SWITCH INTERIOR
1. Switchblades fully visible in the OFF position when the door is open.
3. Industry listed lugs for aluminum and/or copper cable and front
removable.
B. SWITCH MECHANISM
C. ENCLOSURE
The tests to be carried out shall include but not necessarily limited to:-
1. Visual and Mechanical Inspection
6. Verify that fuse sizes and types are in accordance with drawings, short-
circuit studies, and coordination study.
8. Inspect bolted electrical connections for high resistance using one of the
following methods:
3. Electrical Tests
3. Test Values
2. Bolt-torque levels.
3. Microhm or millivolt drop values shall not exceed the high levels of the normal
range as indicated in the manufacturer's published data. If manufacturer's data is
not available, investigate any values which deviate from adjacent poles or
similar switches by more than 50 percent of the lowest value.
5. Investigate fuse-resistance values that deviate from each other by more than 15
percent.
PART 3 - EXECUTION
3.1 INSPECTION
E. Install disconnect switches used with motor-driven appliances and motors and
controllers within sight of controller position unless otherwise indicated.
F. Provide box with spare set of each size fuse used on project. Provide
nameplate on switch, indicating equipment served.
PART 1 - GENERAL
PART 2 - PRODUCTS
2.01 GENERAL
Unless otherwise specified all terse used shall comply with IEC 60076 and
DIN/VDE standards
A. CORE CONSTRUCTION
The lamination shall be clamped at top and bottom by steel channels, which
are interconnected by vertical steel bolts. The bottom steel channels shall
be used to support the transformer and the top steel channel shall
incorporate lifting lugs.
The core-clamping and supporting steel work after all forming, drilling and
shaping operations shall be thoroughly digressed and rinsed prior to
application of a zinc phosphate primer, rinsed again and finally coated with
an oven baked epoxy paint.
B. COIL CONSTRUCTION
Each transformer shall be a double wound type with both the H.V. and L.V.
windings individually encapsulated in rigid steel mould. The coils shall be
impregnated with quartz filled epoxy resin and cast under vacuum, to
produce a smooth finish without voids and undulations.
The size and spacing of the conductors used in the windings shall be such
that the coils are self-supporting prior to impregnation and where
applicable, shall allow the epoxy resin to fill all of the space in and between
adjacent layers and turns.
The coefficients of expansion of the windings and epoxy resin shall not
differ by more than 15%.
Ducts shall have discharge outlets, protected with metal mesh screens to
exclude debris, to correspond with core positions on each side. Ends shall
be capped.
Fans shall have spigot inlets, with 6 mm protective wire guard, and flanges
outlets to connect to mating flanges on the air ducts, and joint to
incorporate a flexible gasket.
Fans shall be direct driven by an internally fitted external rotor type motor
with extended lubricators.
The duty of each fan shall be identical and selected so that the total quantity
of air delivered is sufficient to maintain the transformer temperature within
the specified limits.
For shaft powers below 1kW stamped formed strip impellers may be used
provided required efficiency and balance grade can be achieved.
Where fan static pressure is less than 1kpa lock-formed joints and spot
welds may be used.
Fans and ductwork shall have a fully protective paint system to the same
standard as the core construction.
High and low voltage coils shall be provided with very high integrity
interturn insulation to Class F, to withstand the thermal and mechanical
stresses under the specified operating conditions.
E. MOUNTING OF COILS
F. INSULATION CLASS
The insulation system for transformer shall comply with climate and fire
classes E2, C2 and F1 respectively and as per IEC 60076-11 / BS EN
50541-1.
G DEGREE OF PROTECTION
I. The transformer control panel shall transfer the data (Winding temperature,
statues for fans working/alarm/trip) to RMU-RTU (as specified in section
16330) & to local BMS.
J. PERFORMANCE
a. GENERAL
The transformers shall comply with the requirements of IEC 726 in respect
of partial discharge, impulse withstand short circuit strength.
Unless otherwise specified the rated voltage class of the primary windings
shall be 22KV and secondary windings 0.4KV or 6.6 KV, at a frequency of
50Hz. The windings shall be connected for vector group DYn 11.
c. THERMAL RATING
Losses at no-load and loaded conditions shall be the lowest achievable for
the transformer type specified. These losses shall be stated in the
schedule(s) which accompany this Specification.
e. NOISE LEVELS
f. ELECTROMAGNETIC COMPATIBILITY
A. LIFTING
B. FRAME WHEELS
A. CONNECTION METHODS
Connection methods shall comply with IEC 76-4. Provision shall be made
by the manufacturer for the mounting and connection of cable boxes and/or
busbars as specified for the HV and LV conductor connections.
Where HV and LV cable boxes and/or busbars are specified these shall
generally be arranged on opposite sides of the transformer. However exact
positions shall suit the specified requirements of each individual situation.
B. TERMINAL MARKINGS
A visible warning notice shall be fixed adjacent to the tapping links and
worded as follows:
The thermostats shall be used to indicate winding temperature, and provide alarm
and trip indications, and to operate forced cooling fans and trip HV circuit
breakers where specified. Volt-free contacts shall be provided for relaying
signals to remote equipment.
Wiring from the thermostats to the temperature controller shall be carried out
with single core copper cables to DIN/VDE standards with LEF insulation.
Cables shall be contained in galvanized steel conduit supported from the
transformer steel work.
The temperatures at which the cooling fans shall be switched on and off shall be
adjustable within preset limits.
The power supply for the cooling fans shall be provided from the particular
transformer via a suitably fused switch. This switch shall bear the inscription in
yellow letters on a black background:
The starter assembly for the cooling the cooling fans shall comply with this
Specification. A warning label shall be fixed adjacent to the main isolating
switch bearing the inscription:
The tests to be carried out shall include but not necessarily be limited to :
10. Verify correct secondary voltage phase and phase neutral after
energization and prior to loading.
3. Microhm or millivolt drop values shall not exceed the high levels
of the normal range as indicated in the manufacturer's published
data. If manufacturer's data is not available, investigate any values
which deviate from similar connections by more than 50 percent
of the lowest value.
10. Typical excitation current test data pattern for three-legged core
transformer is two similar current readings and one lower current
reading.
11. Core insulation-resistance values should be comparable to
previously obtained results but not less than one megohm at 500
volts dc.
12. AC over potential test shall not exceed 65 percent of factory test
voltage for one minute duration.
DC over potential test shall not exceed 100 percent of the ac rms
test voltage specified in ANSI C57.12.91, Section 10.2 for one
minute duration. The insulation should withstand the over
potential test voltage applied.
E. SITE TESTS
All site tests shall be carried out in accordance with this Specification.
LV Supply system
. No-load voltage 400 V
. Number of phases 3 Phase
. System neutral 4 Wire
. Rating As indicated on the drawings.
LV Supply system
. No-load voltage 6600 V
. Number of phases 3 Phase
. System neutral 4 Wire
B. General Provisions for Electrical Work, Section 16050, apply to work of this
section.
A. Work includes providing all materials, equipment, accessories, services and tests
necessary to complete and make ready for operation. Instrument and metering shall
be in accordance with Drawings and Specifications.
C. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
1.4 SUBMITTALS
PART 2 - PRODUCTS
All electrical indicating instruments shall comply with IEC 51, DIN/VDE standards
and shall be digital type.
A. GENERAL REQUIREMENTS
B. COMMON SPECIFICATIONS
1. STANDARD IEC 51
b. Current : - 2 In continuously.
- 10 In for 10 seconds.
- 40 In for 2 seconds.
On 3-phase, 4-wire system, ammeter switches shall have four operating positions,
marked 'R', 'Y', 'B' and 'N', and an 'OFF' position, and shall enable the single
ammeter to read, in sequence, the currents in each of the three phases and the
neutral wire, On 3-wire systems ammeter switches shall have three operating
positions marked 'R', 'Y' and 'B' and an 'OFF' position. Ammeter switches shall be
connected so that the associated current transformers are short-circuited when they
are not connected to the ammeter.
On 3-phase, 4-wire systems, voltmeter switches shall have six operating positions,
marked 'R-Y', 'Y-B', 'B-R', 'R-N', 'Y-N' 'B-N', and an 'OFF' position, and shall
enable the single voltmeter to read, in sequence, each of the three line voltages and
each of the three phase-to-neutral voltages. On 3-wire systems, voltmeter switches
shall have three operating positions marked 'R-Y', 'Y-B' and 'B-R' and an 'OFF'
position.
Contractor may also propose any selector switch means to latest NORM industrial
standard/manufacturer standard should digital equipment is used and submit
proposal and seek consent form Engineer.
Rev.01 August, 2018 Instruments And Metering
Section 16290
Page 2 of 8
2.3 CURRENT TRANSFORMERS (CTS)
A. GENERAL REQUIREMENTS
All CTs shall comply with all relevant requirements of IEC, DIN/VDE standards
and shall have an Accuracy Class Designation according to the following table:
Unless otherwise specified in the schedules or drawings, the CTs are required for
use under service conditions not more onerous than those set out in IEC, DIN/VDE
standards.
CTS shall be designed either for measurement or for protection and shall not be
used in a dual-purpose role serving both instruments and protective gear.
So far as it is practicable, all CTs shall be of the ring type. Wound primary CTs will
only be accepted when the rated primary current is so low as to make the ring type
impracticable.
One side of the secondary of each CT shall be connected to earth at one point via a
bolted removable link.
For mattering circuits, either, a proprietary front of panel CT test block or special
"shorting" terminals within the panel shall be provided for test purposes.
All CTs whether of the ring type or the wound primary type, for use at voltages
exceeding 1000 V shall be epoxy resin encapsulated.
Where dual-ratio CTs are specified, they shall be provided with two separate
secondary windings capable of being connected in series or in parallel to give the
required ratio.
All CTs shall be provided with a rating plate bearing the information as stated in
IEC, DIN/VDE standards. All CTs shall be installed in accessible location. The
secondary connections shall be brought out by means of insulated leads, and made
off on a suitable terminal block-mounted in a readily accessible position.
Magnetization curves and/or type Test Certificates shall be provided for all CTs
associated with protection devices.
A. GENERAL REQUIREMENTS
Voltage transformers shall be of the type, rating, and voltage ratio specified in the
schedules or drawings.
All voltage transformers shall comply with all relevant requirements of BS 3941
and shall have an Accuracy Class Designation according to the following table:
Unless other specified in the schedules or drawings, the voltage transformers are
required for use under service conditions not more than those set out in IEC,
DIN/VDE standards.
Voltage transformers designed for a primary voltage not exceeding 4000 V shall be
the air insulated type, with the windings encapsulated in epoxy resin or other
suitable synthetic material.
Each voltage transformer shall have a rated burden at least 50% greater than the
total burden of the apparatus or instruments which it is to serve.
4. Inspect bolted electrical connections for high resistance using one of the
following methods:
5. Verify that all required grounding and shorting connections provide contact.
7. Verify correct primary and secondary fuse sizes for voltage transformers.
8. Lubrication requirements
3. Perform a polarity test on each transformer to verify the polarity marks or H1-
X1 relationship as applicable.
Test Values
2. Bolt-torque levels
3. Microhm or millivolt drop values shall not exceed the high levels of the
normal range as indicated in the manufacturer's published data. If
manufacturer's data is not available, investigate any values which deviate
from similar connections by more than 50 percent of the lowest value.
3. Inspect cover gasket, cover glass, condition of spiral spring, disk clearance,
contacts, and case-shorting contacts, as applicable.
2. Electrical Tests
PART 3 - EXECUTION
3.1 INSPECTION
A. Examine conditions under which instrument and metering are to be installed and
notify in writing of conditions detrimental to proper completion of the work. Do not
proceed with the work until unsatisfactory conditions have been corrected.
A. Prior to energization of instrument and metering devices test devices for intended
function Replace malfunctioning units with new units, and then demonstrate
compliance with requirements.
PART 1- GENERAL
B. General Provisions for Electrical Work, Section 16050, apply to work of this
Section.
C. Primary medium voltage switchgear and ring main units section 16330.
I. The requirements specified in this section apply to all related sections in this
Division. The requirements of all related sections, elsewhere in this division also
apply to this section unless specified to the contrary.
A. Work includes providing all materials, equipment, accessories, services and tests
necessary to complete and make ready for operation, all wiring devices in
accordance with drawings and specifications.
1.4 SUBMITTALS
PART 2 - PRODUCTS
Unless otherwise specified all terse used shall comply with IEC and DIN/VDE
standards
F. The kiosks should be designed and tested according to IEC 62271-202 and to be
complying with EEA requirements /specifications.
H. Sheet steel sections with weather-proof electrostatic coating, stone paint, alu-
zinc sheet steel.
I. Double roof system with natural air to facilitate the air circulation and support
the substation cooling system.
L. The MV and LV compartments are provided with double doors. All doors are
equipped with stainless steel rigid hinges and rigid locking devices. Also all
doors are equipped with rubber gaskets to keep a high degree of protection.
S. The kiosk shall be provided with suitable way to connect security pad lock on
outside doors.
T. Marking labels shall be fitted to indicate the on-off position of the switches.
U. The low voltage compartment shall have sliding button openings for exit of
outgoing feeder’s cables.
V. The panel’s doors shall be earthed with mean of copper conductor with cross
section area at least (6mm²).
W. The CSS shall be of glass reinforced polyester (GRP) construction, this applies
also to the roof, doors and ventilation louvers.
X. The design of the CSS shall be based on the safety to personal and equipment
during operation and maintenance, it shall be internal arc proof tested type(IAC-
AB) to the arc current levels(IAC AB,20 KA at 1 sec) to provide a high level of
personal safety to the general puplic and operators.
C- Low voltage compartment & bus bars: as specified in sections: 16430, 16490,
16492, 16290, 16491, and 16496.
2. 3 ACCEPTABLE MANUFACTURER
PART 1 - GENERAL
A. Work includes providing all materials, equipment, accessories, services and tests
necessary to complete and make the switchgear ready for operation by the Owner
in accordance with Drawings and Specifications.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 1 of 35
1.4 SUBMITTALS
PART 2 - PRODUCTS
The switchgear cubicles and interrupters shall be factory assembled and type-
tested. All switchgear components should be provided according to the latest
Egyptian Electricity Authority requirements. Refer to one line diagram.
Provide no. (4) Cassette Trolley with each switchgear for ingress and egress of
circuit breakers.
B. The stationary part of the cubicles are built as a self-supporting structure, bolted
together from rolled steel sheets of at least 2.5 mm gauge, rated for 24 kV. Each
cubicle is to be divided into three sealed and isolated compartments by metallic
partitions, i.e., the bus bar, cable connection and circuit-breaker compartment. The
vertical partitions shall carry automatic, phase-segregated safety-shutters made of
metallic material. These shutters are to be sealed in both directions, effectively
preventing ionized gases from fault-arcs to spread to the neighboring
compartment. Each compartment shall have its own pressure-relief device.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 2 of 35
C. The interrupter truck shall carry vacuum circuit-breaker, with associated operating
mechanism and auxiliary devices. By manually moving the truck it may be
brought into a distinct operating and isolating test position. The front-shield of the
truck shall engage firmly with the frame of the cubicle when locked in the
operating position, and become an arc and pressure-proof part of the enclosure.
E. The busbars shall be rectangular, drawn from pure copper with cross section area
1250 A and shall be mounted on ribbed, cast-resin post insulators sized to take up
the Electro dynamic forces resulting from short-circuits.
All main busbars and droppers shall be isolated by heat shrinkable tubes and the
connection points with suitable isolated covers.
- Rated voltage: 24 KV
- Frequency: 50 Hz
- Nominal operating voltage: 22 KV
- Power frequency withstand voltage at 50 Hz ~ 1 Min.: 50 KV
- Impulse withstand voltage 1.2/50 µs: 125 KV
- Short time withstand current KA, RMS, 3Sec: 25 KA
- Copper Purity not less than: 99.9 %
- Auxiliary voltage: 110 V.D.C
20%
F. The entire switchgear and circuit breakers shall be rated to operate continuously
under full capacity in 45oC ambient temp. conditions & relative humidity 90%
non-condensing.
H. Line and load side primary disconnects shall have flat, spring-loaded and silver-
plated pressure contacts for low contact resistance and good ventilation.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 3 of 35
A series of sturdy mechanical interlocks shall force the operator into the only safe
operating sequence of the switchgear, preventing positively the following:
3. Moving the truck into the operating position with the low voltage plug
disengaged.
4. Engaging the grounding switch with the truck in the "Operating" position, and
moving the truck into this position with the grounding switch engaged.
K. The winding of the instrument transformers shall be made of copper. And the
current transformers for each cubicle shall be dry type and shall be short circuit
proof. The short circuit current capacity shall be at minimum of 25 K.A for 3 sec.
at rated voltage. They will have separate secondaries for metering. And protection
each with suitable burden, the current transformers should be interchangeable
from lower core to higher core from the secondary side of the current transformer
not from the primary side and they shall be single phase.
L. The switchgear parts shall comply with the relevant I.E.C. standards specification
regarding design, workmanship and testing :
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 4 of 35
Watt-hour meters I.E.C. 62052.
M. Precaution shall be taken at contacts between aluminum and other material to
avoid electrolytic action.
N. Structure shall be designed to enable the addition of future panels from both sides.
Each incoming, outgoing feeder and bus-tie cubicle shall comprise circuit breaker.
The circuit breakers shall be vacuum type, mounted on withdrawable trucks, and
shall fulfill the following technical specifications:
Type vacuum
Rated voltage 24 KV
Nominal operating voltage 22 KV
Rated current:
- Incoming feeders: 1250 Amps
- Bus-tie: 1250 Amps
- Outgoing feeders: 1250 Amps
- Rated Breaking capacity KA: 25 KA, RMS
- Rated Making current capacity: 63 KA, Peak
- Rated operating sequence: O-0.3s-CO-3min.-CO
- Power frequency withstand voltage at 50 HZ ~ 1Min.: 50 KV
- Impulse withstand voltage 1.2/50µS: 125 KV
- Short time withstand current KA, RMS, 3Sec: 25KA
The circuit breaker is equipped with closing spring charged by an electric motor
operated by 110 V DC.
It shall have two electric coils one for tripping and the other for closing. Circuit
breaker opening and closing can be done electrically by push button at low voltage
compartment and mechanically at the circuit breaker.
Operating spring can be manually charged too. It shall be equipped with a counter
to count the number of operations and an indication of this spring status.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 5 of 35
Q. Each cubicle must be equipped with space heaters to prevent moisture & humidity
ingress (220 V x 2 x 100 W) one in cable compartment and the other in circuit
breaker compartment controlled by miniature breaker and by hygrostat.
R. All equipment (push buttons - indicating lamps - sockets and plugs – terminal
blocks for C.Ts & P.Ts and control …etc) must be made of hygroscopic and non-
flammable material.
S. The instruments shall be of flush type and mounted on hinged door at the front of
each cubicle.
V. Every incoming and outgoing feeder, cubicle shall be equipped with an earthing
switch.
W. When Vacuum circuit breakers are used, each incoming and outgoing circuit
breaker must be equipped with 3 No. distribution class surge arrestor.
X. The leakage path for fixing insulators and of P.Ts, C.Ts and surge arrestors should
be 2 cm/K.V or as per dimensions indicated in test certificate approved by
electricity holding company.
Z. The smart meters shall be supplied with their software and cables needed for
communicate it with any computers.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 6 of 35
The switchgear shall be of the totally enclosed indoor type, of size, rating and
arrangement as shown on drawings and indicated in the specification. The
complete assembly shall be floor mounted, free standing, with matching cases, to
form a continuous integral structure. The housing shall consist of folded sheet
steel sections welded together and shall be of robust construction. Switchgear
shall have front and rear access.
BB. Direct panel to panel busbar connection shall be made without the use of
interconnecting links.
The arrangement shall permit cables to enter from the bottom of the enclosure and
connect at their respective terminals without interference.
CC. Cable termination boxes shall be provided for incoming and outgoing feeders
having single core, XLPE insulated, Aluminum cables of 400 and 240 sq. mm.
cross sectional area.
AA. Facilities shall be provided for earthing the feeder side of the circuit breaker
without the use of loose attachments.
Finish shall be battle-ship gray, "or any other color approved by Engineer",
vermin-proof and suitable for the climatic conditions of the site.
AC. Each switchgear unit shall be provided with a metal rating and name plate giving
the required particulars in accordance with the IEC recommendations.
AD. Instruments and smart meters shall be of the flush pattern with phenolic-black
finish digital type.
1. One withdrawal, motor operated, vacuum type circuit breaker rated 1250A,
with 25 KA for 3 sec. short circuit breaking capacity.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 7 of 35
3. Three current transformers with separate secondaries 10 VA class 0.5 for
metering (0.5M5) and 15 VA for protection class (5P10). Ratio as indicated on
the drawings.
4. Three potential transformers each protected by H.R.C fuse for metering and
protection.
22000 110 110
Ratio 3 / 3 / 3
7. Smart Digital power meters V, A, PF, kW, KVAR, kWh, kVARh, max demand
with Modbus communication & the readings to be transmitted to SWG-RTU.
11. One flag relay with a reset push button and alarm for each of the following
(aux power loss – A.C loss – any M.C.B trip – protective relay trip).
12. One master horn for switchgear to give alarm during the following cases:
13. One microprocessor type digital protection and control relay equipped with
ethernet TCP/IP communication port with the following functions:
a. Three phase non-directional over current and short circuit (ANSI
50/51) (Three stages) relay with definite time delay characteristic.
b. Non-directional earth fault relay (ANSI 50N/51N) definite time
characteristics.
c. Three phase directional over current relay (ANSI 67).
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 8 of 35
d. Directional relay for directional earth fault protection (ANSI 67N).
e. Three phase under/over voltage relays adjustable between (ANSI
27/59).
f. Relay characteristic must be coordinated with and approved by the
Electric Power Authority.
g. The protection relay shall also function as a communicating remote
terminal unit for its associated MV cubicle. the relay shall be
equipped with a digital I/O module for providing control and
obtaining status as per the following:
close/open/trip of circuit breaker
status of circuit breaker position (open/closed)
status of circuit breaker truck (connected/disconnected)
status of earthing switch (connected/disconnected)
status of general alarm (aux power loss or trip signal)
The protection relays shall also transmit all its measurement
readings (A, V, PF, kW, kVAR, kWh, kVARh, maximum
demand, waveform capture) through communication bus to the
CCC & COC buildings.
1. One withdrawable, motor operated, vacuum type circuit breaker rated 1250 A,
with 25 KA for 3 sec. short circuit breaking capacity.
2. One set of insulated busbars rated 1250 Amps and designed to withstand
electrodynamics forces under worst short circuit conditions of 25 KA.
4. One microprocessor type digital protection and control relay equipped with
ethernet TCP/IP communication port with the following functions:
a. Three phase non-directional over current and short circuit (ANSI 50/51)
(Three stages) relay with definite time delay characteristic.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 9 of 35
b. Non-directional earth fault relay (ANSI 50N/51N) definite time
characteristic.
c. Relay characteristic must be coordinated with and approved by the
Electric Power Authority.
d. The protection relay shall also function as a communicating remote
terminal unit for its associated cubicle. the relay shall be equipped with
a digital I/O module for providing control and obtaining status as per
the following:
close/open/trip of circuit breaker
status of circuit breaker position (open/closed)
status of circuit breaker truck (connected/disconnected)
status of earthing switch (connected/disconnected)
status of general alarm (aux power loss or trip signal)
The protection relays shall also transmit all its measurement
readings (A, V, PF, kW, kVAR, kWh, kVARh, maximum
demand, waveform capture) through communication bus
to the CCC & COC buildings.
8. Smart Digital power meters V, A, PF, kW, KVAR, kWh, kVARh, max demand
with Modbus communication & the readings to be transmitted to SWG-RTU.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 10 of 35
16. One master flag relay with a reset push button and alarm for each of the
following (aux supply loss – A.C loss – any M.C.B trip – protective relay
trip).
1. One with drawable, motor operated, vacuum type circuit breaker rated 1250 A,
with 20 KA for 3 sec. short circuit breaking capacity.
3. Three ammeters (smart digital type) & transmit the signals to SWG-RTU.
5. One microprocessor type digital protection and control relay equipped with
Ethernet TCP/IP communication port with the following functions:
a. Three phase non-directional over current and short circuit (ANSI 50/51)
(Three stages) relay with definite time delay characteristic.
b. Non – directional earth fault relay (ANSI 50N/51N) definite time
characteristic.
c. Relay characteristic must be coordinated with and approved by the
Electric Power Authority.
d. The protection relay shall also function as a communicating remote
terminal unit for its associated cubicle. the relay shall be equipped with
a digital I/O module for providing control and obtaining status as per
the following:
close/open/trip of circuit breaker
status of circuit breaker position (open/closed)
status of circuit breaker truck (connected/disconnected)
status of earthing switch (connected/disconnected)
status of general alarm (aux power loss or trip signal)
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 11 of 35
The protection relays shall also transmit all its measurement
readings (A, maximum demand, waveform capture) through
communication bus to the CCC & COC buildings.
7. Automatic electrical interlock between the incoming & bus coupler circuit
breakers shall be provided as follows:
a. Bus tie circuit breaker is normally switched off while the incoming
feeders circuit breakers are switched on.
b. If the incoming feeder circuit breaker in any section is switched off, then
the bus tie circuit breaker can be switched on.
15. One master flag relay with a reset push button and alarm for each of the
following (aux. power loss – A.C loss – any M.C.B trip – protective relay
trip).
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 12 of 35
2.3 General Specifications for Smart Grid Switchgear Remote Terminal Unit (SWG-
RTU)
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 13 of 35
- All waveform capture performed by the protection relay
b. Protocol
The SWG-RTU shall comply with IEC 870-5-104 IEC 870-5-101 DNP3.0 standard
protocol. The RTU shall support Secure Authentication according to IEC 62351-5.
c. Transmission
The communication system is based on optical fiber. The SWG-RTU power supply
shall be sized to supply the communication modem.
e. Cyber Security
e.1. In order to secure all controls and data acquisition, the SWG-RTU shall be
designed to be compliant with NERC and IEC62351 requirements. The SWG-RTU
shall support secure access based on RBAC, with the possibility to configure the roles.
e.2. Local and remote access connection shall be secured for maintenance (locally and
remotely) with HTTPS, SFTP, IPSEC and SSH protocols.
Authentication shall be based on a Radius server.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 14 of 35
- SWG-RTU shall support remote firmware updates.
- Compatible with a full centralised RBAC management in compliance with
IEC 62351-9.
- Device hardening.
- Disabled or unused functionality shall not compromise security.
- Unnecessary services and programs shall be removed. If removal is not
possible, the unnecessary services and programs shall be disabled.
e.5. Communication
The SWG-RTU shall comply to security standards
The RTU shall follow the IEC 62351 standards and at least:
- IEC 62351-5 : 2013
- IEC 62351-8
e.6. Communication security
The RTU shall support network and transport layer encryption using IPSec.
e.7. Management of Security passwords
- The SWG-RTU service application shall support individual user passwords.
- Passwords shall be stored together with a salt using an allowed cryptographic
hash function.
- The RTU service application shall enforce a high complexity of passwords.
- The RTU shall lock the access after several password error.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 15 of 35
e.8 User Authentication
- The RTU shall authenticate the communication parties on the WAN interface using
a challenge-response protocol based on message authentication codes The RTU
shall terminate the connection if the user authentication fails.
- The RTU shall authenticate the communication parties on the Local Maintenance
interface.
- It shall be possible to configure the SWG-RTU so that it blocks authentication
requests, either temporarily or permanently, from an account after a number of
failed login attempts. The number of failed login attempts and the time the account
is blocked shall be configurable.
Equipment data for materials covered under this section shall include but not be
limited to the following:
Construction and installation details for the 24KV primary medium voltage
switchgear equipment.
Floor plan and top views showing outline dimensions and arrangement of cubicles.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 16 of 35
2.4 TESTS
A. Supply test results to confirm that the switchgear have been tested to substantiate
designs according to applicable Standards verifying not only the performance of the
switch but also the suitability of the enclosure venting, rigidity and bus bracing. In
addition, factory test each switch in accordance with approved Standards.
B. All tests shall be carried out by the manufacturer at works and at his expense and
under control and supervision of EEHC.
C. The contractor is responsible for testing all medium voltage switchgear and all
protection equipments, …etc. as per EEHC requirements on his expenses.
2.5 BATTERY
A. Battery characteristics:
3. Battery shall be delivered empty and can be stored for a long period under
specified conditions without affecting final application requirements.
5. All the accessories, such as bolts, washers and links necessary for
connecting cells series should be delivered.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 17 of 35
6. The battery shall be delivered complete with the mounting racks.
7. Each battery shall be provided with a voltmeter to measure the cell voltage,
a hydrometer to measure the specific gravity of the electrolyte, the
necessary copper connections and the necessary quantity of the hydroxides
(potassium hydroxide lithium hydroxide).
A. The battery charger shall have nominal voltage 110 V DC. It will be three-
phase bridge-connected. The bridge consists of three silicon controlled rectifier
(SCR) and three diode. It will have float charging and high rate charging
regimes operating on the principle of constant voltage output. The charger must
have the possibility of both manual and automatic switching – over from one
regime to the other one depending on the state of battery bank. The charger
shall soft start features.
B. The output voltage, at any regime, must be adjustable and stable within the
specified range when output current is varied form 0 % to 100 % of its rated
value, AC supply voltage and/or frequency fluctuate within the specified
ranges.
C. A control unit must be added so that the load supply voltage is regulated 110
5% V DC independent on the charger output without any instantaneous
interruption of load supply.
D. The charger must be equipped with a DC voltage regulating unit for feeding the
control, signal and protection circuits of medium voltage switch-board within
the specified voltage range at either battery float or high rate charging regime.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 18 of 35
E. The charger is to be equipped on all sides (input and outputs) with miniature
circuit-breakers having thermal and magnetic releases on all poles and with the
following specification:
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 19 of 35
G. The output DC voltage of the charger shall not be affected by reversing of the
phase sequence.
a. AC side
1. Phase(s) failure
2. over voltage & under voltage
3. Input CB (provided with over load and short circuit protection)
4. Varistors (AC surge suppression)
b. DC side
3. Reverse polarity
4. Two output circuit-breakers one for load, other for battery charging
(provided with over current and short circuit protection)
c. Charger side
d. Trip actions
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 20 of 35
e. Alarm actions
f. Control
1. On/off switch
2. Mode selector
A. It shall be of metal enclosed type and comprise all the necessary control switches
and measuring instuments. It shall be furnished with necessary protective and
signaling devices.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 21 of 35
2.8 SMART GRID RING MAIN UNITS (Type-A and Type-B)
A. Regarding Smart Grid distribution network, There shall be two types of RMUs
a. Type-A RMU: Monitoring Only
C. Ring main unit GIS Type with service continuity LSC2-PM according to IEC62271
feeding each transformer comprises two (2) or three (3) numbers of three-pole load
break switches rated 630 Amps, 24 KV for the incoming / link / outgoing feeders
cables and one (1) three-pole fusible load breaker switch and tripping if one fuse
blows to protect the transformer, at 24KV for the outgoing cable connected to the
transformer as indicated on the drawings.
D. Ring main unit feeding the auxiliary transformer of MV switchgear comprises three
(3) numbers of three-pole load break switches rated 630 Amps, 24KV two for the
incoming ring main feeders cables and one (1) load break switch with fuse for the
outgoing cable connected to the auxiliary transformer.
E. The RMU and busbar shall all be contained in a stainless steel enclosure filled with
SF6 at maximum 0.3 bar relative pressure to ensure the insulation and breaking
functions. This compartment is a sealed pressure system, in accordance with the
IEC 62271-1 standard, with a service life time of 30 years. In addition. No refilling
of the gas shall be required during the whole service life time.
G. The tank shall be made of ≥2 mm AISI 304 unpainted stainless steel and be able to
withstand an accidental internal overpressure of ≥ 2.1 bars (relative).
H. The switchboards shall be designed so as to prevent access to all live parts during
operation without the use of tools.
I. MV Cable connection bushings shall be accessible from the front of the RMU. The
bushings should be conveniently located for working with cables specified and
allow the termination of these cables in accordance with the instructions supplied.
The profiles of the cable connection bushings shall be in compliance with EN
50181 standard.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 22 of 35
J. Transformer protection feeder shall be used by a LBS switch-fuse combination
L. The switches shall have 3 positions, open-disconnected, closed and earthed, and
will be constructed in such a way that natural interlocking prevents unauthorized
operations.
M. An operating mechanism can be used to manually close the switch and charge the
mechanism in a single movement.
N. It shall be fitted with a local system for manual tripping by an integrated push
button.
P. Cable termination boxes shall be provided for the incoming and outgoing.
Q. They shall be GIS ring main unit of 3 pole gang operated type capable of
interrupting safely, their nominal full load current.
S. The load break switches shall be operated by hand-operated handles through levers.
Protective barriers must be provided to safeguard the personnel from unintential
contact with the live parts during switching operations.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 23 of 35
Marking labels shall be fitted to indicate the ON/OFF positions of the switches and
the hand-operated handles shall be provided with locks, where required.
Insulating barriers shall be inserted between the open contacts when working on
cables.
T. Earthing switches are to be provided on the feeders’ side to enable earthing the
cable feeders when working on the cables.
U. Mechanical interlocking between the load break switches and their relevant earth
switches such that no load break switch can be switched on as long as his mate
earth switch is in the ON position and vice versa.
V. Ring main unit must be equipped with earth fault indicators as indicated on the
drawings of the type and according to the Egyptian Electricity Authority
requirements.
Z. All load break switches installed in (Type – B) RMU’S shall be motorized type.
a. Each RMU function shall be equipped with a Voltage Presence Indicator (VPI) on
the front cover to indicate whether there is voltage in the cables.
b. The voltage indicator shall be in compliance with IEC 62271-206 standard.
c. Cable connection bushings shall be equipped with capacitive dividers that will
supply low voltage power to the voltage presence lamps.
d. The lamps shall be of high performance LED technology to insure high visibility
and long life duration. Three voltage sensing inlets shall be provided on each
function to allow checking the phase concordance.
e. It shall be possible to replace the voltage presence indicator while unit remains
energized, guaranteeing the safety of people.
2.10 Communicating Fault Passage indicator with integral voltage detector FPIVD
a. Each of the two Incoming Load break switches shall be equipped with a fault
passage indicator with integral voltage detection device (FPIVD).
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 24 of 35
b. The voltage signal shall be taken from the Voltage Presence Indicator (VPI)
connected to capacitive divider in each load break switch cable bushing.
c. The voltage detection device shall display the MV network voltage in percentage
of the network service voltage. It is not allowed to use a voltage measuring tool to
calibrate the device
d. The fault passage indicator function is used to detect and localise the faulty part of
the network.
e. It shall indicate short circuit and earth faults with a high performance red LED on
the front panel.
f. It shall indicate permanently the load currents of each phase and memorise the
maximeters of each phase.
g. It shall indicate both phase-to -phase and phase-to earth faults.
h. In order to guarantee a fault validation on cable with low load value, a validation
by voltage presence shall be provided.
i. It shall be equipped with both automatic and manual setting modes.
j. It shall be dual powered device such that the FPI function is self-powered however
the communication function shall be with external power supply used for the
communication RTU.
k. It shall provide an output for external lamp gathering short circuit and earth fault
remote indication as well as a relay or transistor output for ADMS interface.
l. The current sensors shall be mounted onto the RMU bushing
m. it shall be communicating using Modbus protocol to the RTU
n. It shall indicate permanently that it is in operation, it could be by means of the
permanent load indication.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 25 of 35
e. The RMU-RTU shall be expandable by adding modules, the number of modules
shall not be limited and not based on a rack design.
f. The RMU-RTU consumption shall be limited to 10W per substation.
g. The RMU-RTU shall be configurable locally or/and remotely.
h. A configuration tool, based on PC, shall be provided for configuration of the
RMU-RTU. This tool shall be connected locally or remotely to download and
upload the configuration.
i. A web server shall be integrated into the RMU-RTU communication unit and shall
provide facilities for maintenance, settings including cyber security settings, and
historical logs display. This Web server shall be accessible locally and remotely,
by mean of a standard laptop PC. Locally the maintenance tool shall be connected
to the RMU-RTU by Ethernet communication port.
j. The firmware shall be updated either locally or from the central system.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 26 of 35
- In addition to these direct interfaces with the RMU, the number of operations
shall be transmitted to the ADMS
- The interface shall control the switch motorisation through a dual output which
provides the 48Vdc voltage to the interface relay located into the switchgear.
- The control operation shall be secured by a select before execute procedure, the
48Vdc power supply to the motor shall be activated only during the execute
phase.
- All monitoring data shall be transmitted to CCC & COC buildings via the
communication cables.
2.13 Archives
Events and measurement shall be archived in logs.
Events shall be stored in the archive logs with a time resolution of 1ms, and a
discrimination of 10ms.
All the logs shall be available from a maintenance tool connected to the RTU or sent
on request to the Remote Control Centre.
2.14. Communication
2.14.2. Protocol
The RTU shall comply with IEC 870-5-104 IEC 870-5-101 DNP3.0 standard
protocol. The RTU shall support Secure Authentication according to IEC 62351-5.
2.14.3. Transmission
The communication system is based on optical fiber. The RMU-RTU power
supply shall be sized to supply the communication modem.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 27 of 35
The measurement shall be spontaneously sent to ADMS according to configuration
of:
- Threshold
- Dead band
Battery
The battery capacity shall maintain a backup time of 2 hours for all
the voltage outputs and shall permit 10 Open/Close cycles of the
switchgear.
The battery shall be able to withstand ambient temperature 50 C.
The single 12Vdc battery shall be periodically checked, and a battery
fault shall be transmitted to the ADMS.
The maximum battery charging time shall be 24hours.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 28 of 35
Monitoring
The power supply shall deliver the following statuses to the ADMS
End of life detection
Battery disconnected
Absence of power input
Voltage output faults
Battery fault
Any other data should be available through a serial link
communication.
In order to secure all controls and data acquisition, the RTU shall be designed
to be compliant with NERC and IEC62351 requirements. The RTU shall
support secure access based on RBAC, with the possibility to configure the
roles.
Local and remote access connection shall be secured for maintenance (locally
and remotely) with HTTPS, SFTP, IPSEC and SSH protocols.
Hardening
Device hardening
- Disabled or unused functionality shall not compromise security.
- Unnecessary services and programs shall be removed. If removal is not
possible, the unnecessary services and programs shall be disabled.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 29 of 35
Interface minimization
- Each interface shall support only the data types and protocols needed to meet
the functional requirements.
- Unused interfaces and ports shall be removed. If removal is not possible, the
unused interfaces and ports shall be disabled.
- A complete list of supported data types and supported communication
protocols per interface shall be provided.
- All hardware interfaces that are used for programming or debugging shall be
completely removed after production.
Account hardening
- The RMU-RTU shall not contain active default, guest and anonymous
accounts.
- All remote access to root accounts on the RMU-RTU shall be disabled.
- All Vendor-owned accounts where feasible shall be removed.
- The list of all accounts on the RMU-RTU shall be provided.
Communication
Compliance to Security standards
The RTU shall follow the IEC 62351 standards and at least:
- IEC 62351-5 : 2013
- IEC 62351-8
Communication Security
The RTU shall support network and transport layer encryption using IPsec.
Configuration
- Access to the RMU-RTU by configuration tool shall be possible only through
secured connection: HTTPS for Webserver and SSH for console and
configuration tool.
Access control
RBAC
- The RTU shall support the implementation of Role-based Access Control in
compliance with IEC 62351-8.
- It must be possible to configure the privileges of individual roles. It must be
possible to carry out changes by configuration files through a secure way.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 30 of 35
- It must be possible to define more roles for future applications.
- It shall be possible to assign each role individual security credentials.
- It shall be possible to bind roles to individual user accounts on the RMU-RTU.
The minimum following function and data shall be controlled through RBAC:
- Configuration files
- Software update
- User management
- Executing program or shell command
- I/O on local maintenance access
A specific tool shall permit to configure the security policy, role and password.
Management of Security passwords
- The RMU-RTU service application shall support individual user passwords.
- Passwords shall be stored together with a salt using an allowed cryptographic
hash function.
- The RMU-RTU service application shall enforce a high complexity of
passwords.
- The RMU-RTU shall lock the access after several password error.
User Authentication
- The RMU-RTU shall authenticate the communication parties on the WAN
interface using a challenge-response protocol based on message authentication
codes The RMU-RTU shall terminate the connection if the user authentication
fails.
- The RMU-RTU shall authenticate the communication parties on the Local
Maintenance interface.
- It shall be possible to configure the RMU-RTU so that it blocks authentication
requests, either temporarily or permanently, from an account after a number of
failed login attempts. The number of failed login attempts and the time the
account is blocked shall be configurable.
Central management of user account
- The RMU-RTU should allow managing user authentication through a Radius
server.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 31 of 35
Security Log
- The RMU-RTU shall provide a local audit trail for all security events that
occur.
- Log files shall be produced in Syslog format.
- Security events shall be logged locally in a dedicated security log or/and on a
SYSLOG server.
Security testing
- The RMU-RTU shall comply with ACHILLE Level1.
2.15 TESTS
A. Supply test results to confirm that the switchgear and ring main units have been
tested to substantiate designs according to applicable Standards verifying not only
the performance of the switch but also the suitability of the enclosure venting,
rigidity and bus bracing. In addition, factory test each switch in accordance with
approved Standards.
B. All tests shall be carried out by the manufacturer at works and at his expense and
under control and supervision of Egyptian Electricity Authority.
C. The contractor is responsible for testing all medium voltage switchgear and ring main
unites and all protection equipments...etc. as per EEA requirements on his expenses.
Equipment data for materials covered under this section shall include but not be limited
to the following:
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 32 of 35
The equipment data to be provided prior to ordering any material covered by this section
shall include but not be limited to the following:
PART 3 - EXECUTION
3.1 INSPECTION
B. Routine work tests shall be carried out at the manufacturer's works in the presence
of the Owner's consultant.
3.2 INSTALLATION
C. Mount the switchgear assembly on floor steel aligning channels elevated above
floor level by a concrete pad and as noted on the drawings. Provide shims to
achieve level installation.
D. Insure that switchgear are shipped in sections, which can be fitted through the
available structures.
E. Bond together the switchgear structure, sections and all terminating with a bare
copper earth cable and connect to the switchgear earth bus and to the earthing loop
as required.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 33 of 35
equipment connectors. Where manufacturer's torqueing requirements are not
indicated, tighten connectors and terminals to comply with tightening torques
specified in UL Standard 486A and B.
H. Provide 6.35mm minimum thick x 60cm wide insulation mat in front of ring main
units and rear of freestanding equipment.
I. Provide protective covering during construction for medium voltage switchgear.
J. Touch-up marred or scratched surfaces to match original finish for the switchgear.
3. Set all circuit breaker relays trip rating for maximum coordination with
upstream and downstream devices, including ground fault trips where supplied.
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 34 of 35
3.4 PERSONNEL TRAINING
Rev.01 August, 2018 Primary Medium Voltage Switchgear & Ring Main Units
Section 16330
Page 35 of 35
SECTION 16430
PART 1 - GENERAL
A. Drawings and general provisions of Contract, including General and special Conditions and
Division-1 (General requirements), apply to work of this section.
B. General Provisions for Electrical Work, Section 16050, apply to work of this Section.
E. Primary Medium Voltage Switchgears And Ring Main Units section 16330.
J. Specification Section 15241: Mounting and Isolation of Mechanical and Electrical Systems and
related contract drawings, apply to this section of the work.
A. Work includes providing all materials, equipment, accessories, services and tests necessary to
complete and make all switchgears ready for operation in accordance with drawings and
specifications.
A. Manufacturers: Firms regularly engaged in the manufacture of switchgears of the types, and
capacities required, whose products have been in satisfactory use in similar service for not less
than 5 years.
B. Standards Compliance: Comply with requirements of applicable local codes, IEC – 61439-1&2
and IEC – 60947&IEC-61643 Standards pertaining to switchgear.
C. In case of conflict among the referenced standards and codes, the more stringent provision will
govern.
A. Product Data: Submit manufacturer's data for switchgears, including size, enclosures, and
electrical ratings and characteristics.
B. Shop Drawings: submit dimensional layout on architectural background drawings.
D. If selectivity coordination study is failed for any reason, contractor is responsible to change or
add any number of breakers, relays, such that the selectivity coordination shall be fully achieved
with no extra cost to the employer.
Submit a comprehensive short circuit study as well as voltage drop calculations based on the
actual impedance values of the electrical components such as utility short circuit level at the
medium voltage 22KV (shall not be less than 750MVA), transformer, bus bars and cables ... etc.
PART 2 - PRODUCTS
2.1 GENERAL
B. The switchgears shall be 660 V class 3PH, 50HZ completely wired and type tested at the factory,
ready for installation on the site. Sectionalizing shall be accomplished and bracing provided for
access of the equipment into the building.
C. Switchgears shall be designed and manufactured to comply with IEC -61439, VDE 660 Part 500,
UTE 63 - 410.
D. The Electrical installation has been designed to give load balance across the phases as far as
possible but it is the contractor's responsibility to maintain or improve the balance when making
connections to bars etc.
When the final commissioning is to be completed, the contractor shall allow in his tender for
checking loads and altering connections in order to achieve as even a balance over the phases as
possible.
2.2 CONSTRUCTION
A. The switchgears shall be of the totally enclosed, front and rear. accessible, indoor type, of size,
rating and form 2b arrangement as indicated on the Drawings. The complete assembly shall be
floor mounted, free standing, with matching cases, to form a continuous integral structure.
C. Switchgears shall be completely enclosed with hinged front covers and removable steel plates of
not less than 2 mm gauge on sides, top and rear.
D. All fastenings between structural members shall be bolted, not welded, to provide flexibility
during installation.
E. The arrangement shall permit the busbars and/or cables to enter from the top or bottom of the
enclosures as shown on the Drawings and connect at their respective terminals without
interference.
F. A modular arrangement shall be used to permit interchanging differently sized device cover
plates without additional drilling of structure.
G. Structures and busses shall be arranged to permit future sections to be added. A suitable cover
plate shall be provided for temporary protection.
H. Switchgears shall be dust, vermin and rodent proof IP42 according to IEC-60529.
J. The switchgear busses shall be braced for a short-circuit duty as indicated on the drawings.
K. All bolted and plug-in connections shall be Electro-silver plated to a minimum thickness of
0.0125 mm.
L. Suitable arrangement and equipment shall be provided for extracting and unloading the
circuit-breakers from their cells.
M. A special trolley shall be supplied together with the switchgear for removal or installation of the
air-circuit breakers from their compartment for maintenance or repair.
N. An earth bus extending the entire length of the assembly shall be provided. The bus shall be sized
in accordance with the Regulations.
O. The switchgear shall be sanded and rust inhibited after fabrication, Electro - static painted on
both inside and outside surfaces colour shall be Grey.
Q. The Switchgear shall be provided with Ethernet switch with suitable no. of data ports to collect
the data from the circuit breakers, smart digital power meters and transfer it to local BMS &
RMU-RTU (a specified in section 16330).
A. All copper bus bars, switching devices and connections shall be of sufficient sizes and silver
plated at contact to limit the temperature rise to 25 C over an average ambient temperature of 45
C outside the enclosure.
All bus bars and connections shall be accessible for inspection and maintenance purposes.
C. Bus bars are to be of high conductivity copper and rigidly supported to withstand the mechanical
stress of a rated short- time withstand current of 80KA (rms) for 1 sec. in accordance with IEC
recommendation No. 439-1
D. Main bus shall be of continuous construction. Main bus joints and all top connections shall be
silver plated and tightly bolted to insure maximum conductivity.
E. Bus bars shall be clearly marked with their respective phase colors and shall be furnished for
future extensions.
F. Clearance to earth and to other live metal are to be in accordance with the standards.
G. The main set of bus bars shall be housed in segregated chamber at the top. Bus bar top covers
shall be capable of supporting a man weight without deflection.
H. Incoming and outgoing supplies to switchgears shall be either busways or cables as indicated on
drawings.
I. A full length ground copper bus shall be provided. The ground bus shall be bounded to the metal
enclosure of each compartment and to metering and relaying. Lugs shall be provided one at each
end of the ground bus and one in each cubicle for the user's copper ground cables.
J. The cross sectional area of neutral bus bars shall not be less than that of the associated phase bars.
K. Access to bus bars and bus bar connections shall be possible only after the removal of covers
secured by bolts or studs. Such covers shall be identified externally by engraved laminated labels
bearing the inscription "BUSBARS DANGER 380 VOLTS" in 30mm high black lettering on a
yellow background.
L. Connections from main and dropper busbars to the supply side of functional units shall be by
means of dedicated conductors. Conductors installed on a loop in principle shall not be
acceptable.
M. All neutral supply/load connections shall be made via the enclosure containing the associated
functional unit. Common neutral terminals shall not be acceptable.
N. Where specified in the schedules, or shown on the drawings, switched neutrals shall be provided.
Otherwise bolted neutrals shall be provided. The bolted section shall be mounted in the
compartment containing the associated functional unit or as a separate functional unit and be safe
and easy to access.
Q. The cross section area of the earth bus bars shall be at least 50% of that of the phase’s bus – bars.
R. All the bus bars shall be insulated with heat shrinkable colored in red, yellow, blue and black for
the 3-phases and natural bus bars, respectively.
S. The bus bars shall be mounted on insulators made from porcelain or cast resin according to the
IEC standard.
A. Main circuit wiring shall be LSF insulated to IEC, DIN/VDE standards and, where appropriate,
sized for Type 2 protection coordination to IEC 947, but with a minimum size of 2.5mm2.
Connections to and from functional units shall be segregated from control and adequately
supported to withstand the forces due to short-circuit faults. The sizes of wires shall be calculated
in accordance with the IEE Wiring Regulations.
B. All cable connections shall be made at fixed terminals with no intermediate joints.
C. Insulated conductors shall not rest against bare live parts or exposed sharp edges.
A. All non-screened auxiliary wiring, except that which is required to be screened, shall be carried
out on 600/1000V grade insulated, multi-stranded flexible conductors complying with IEC,
DIN/VDE standards.
C. All auxiliary wiring shall be identified at both ends with numbered and resistor color coded
ferrules. These numbers shall be shown on the control schematic wiring diagram.
D. All auxiliary wiring shall be contained within cabling trunking and totally segregated from power
wiring as far as practicable. Wiring of circuits at different voltage categories, e.g. L.V. and ELV,
shall be segregated. Joints will not be permitted on wiring between devices.
E. Cable trunking shall be of the ventilated type with clip-on covers and purpose made junctions and
accessories. Cables shall not occupy more than 25% of the trunking cross-sectional area.
F. Wiring not contained within trunking shall be strapped in looms with removable straps and held
in place by suitable cleats. Looms shall not exceed more than 25 wires. Self-adhesive straps shall
not be acceptable.
G. All wiring connections from trunking and looms to devices shall be run in straight lines,
horizontally and vertically, and be neatly dressed.
H. Wiring to door mounted devices shall be flexible and provided with a large enough loop to clear
the edge of the opening. Protection against abrasion shall be provided by means of flexible
conduit or spiral wrapping securely fixed at each end.
Rev.01 August, 2018 Low Voltage Switchgear Assemblies
Main Distribution Board
Section 16430
Page 5 of 13
I. Where wiring passes through partitions it shall be protected against abrasion by thermoplastic
grommets and spiral wrapping.
J. Interconnections between functional units shall be contained within a separate cabling chamber
or trunking. All cables shall terminate on the functional unit terminals within the cubicle.
2.6 LABELS
A. All enclosures containing functional units shall be clearly labeled with a circuit, unit reference
and current rating.
B. All labels shall be of the engraved type made from suitable multi-layer laminate and shall be
fixed with zinc plated cheese head instrument screws. No other type of label will be acceptable.
C. Every functional unit shall be labeled separately from all others. External labels shall have letters
not less than 5mm in height and internal labels not less than 3mm. The letters shall be black in
color on a white background.
D. All covers/doors not fitted with interlocked switched disconnectors enclosing unshrouded live
equipment shall be fitted with warning labels inscribed "DANGER 400V ISOLATE BEFORE
OPENING".
E. Warning labels shall have black letters on a bright yellow background. Wherever possible, letters
shall be not less than 30mm in height. On small covers and doors letters of 20mm or 10mm in
height shall be used.
F. Cable boxed shall be clearly labeled both externally and internally with the circuit and functional
device number.
G. All terminal blocks shall be labeled relative to the respective functional unit.
H. Every control and metering device, selector switch, pushbutton and indicator light shall be clearly
labeled to indicate its purpose.
I. Main identification labels shall be provided on the assembly together with a rating plate.
J. Fixed and with drawable portions of equipment including fixed and plug-in devices shall be
labeled with drawable portions cross-referenced to their fixed part.
2.7 EARTHING
A. Each assembly shall be provided with a continuous copper earth bar running the whole length
sized in accordance with IEC 60865 standards for the prospective short-circuit current.
B. Discrete terminals shall be provided for connection to all the protective conductors. Each
individual section of the assembly shall be separately bonded to the main earth bar.
A. All components shall be installed in accordance with the instructions of their manufacturers. This
requirement does not negate the requirement for type and routine testing as specified elsewhere in
this Specification.
C. All actuators for emergency switching devices shall be mounted between 0.8m and 1.6m above
the base of the assembly.
D. All components shall be installed and wired such that their function is not impaired by interaction
such as heat, arcs, vibration, and fields of energy present in normal operation.
E. Barriers for manual switching devices shall be designed such that arcs caused by switching under
normal operation or the interruption or making of a fault current shall not present a danger to the
operator.
F. All removable and with drawable components shall be installed and designed such that they can
be safely disconnected or connected to supply circuits while the associated conductors are live.
G. All spare contacts on relays, contactors, and the like shall be wired to easily accessible terminal
blocks, suitably positioned for future external wiring.
H. Assemblies shall be provided with a spare set of fuses mounted on polyethylene coated spring
clips adjacent to the fuse chart on the doors of a separate cubicle. A total of 20% of each size of
fuse shall be provided with a minimum 4 number of each size.
When commissioning is complete the panel shall be handed over with this complete set of spare
fused. A fully detailed fuse chart shall be provided in the same cubicle as the fuses.
I. Where moulded case circuit-breakers are installed they shall be fitted with rotary action handles.
The handles shall be lockable in the "OFF" position.
A. The manufacturer's range shall include fully interchangeable contact blocks and lamp holder
blocks which can be fitted to all actuators including switches and push-buttons.
B. Selector switches shall be of the rotary type, with lever or key operated actuators as specified in
the schedules or shown on the drawings.
C. Pushbuttons shall be of the flush type. Colors shall be as specified in the schedules and to IEC,
DIN/VDE standards.
D. Pushbuttons used for emergency stop purposes shall be of the mushroom head type, with a twist
to release action or key reset as specified in the schedule.
E. Contact blocks shall have double break silver plated contacts, in 'NO' or "NC' configuration rated
at not less than 5A resistive at 220V 50HZ.
G. Indicating lamps on control circuits shall be equipped with completely sealed dual wound safety
isolating transformers and in-built test relay.
H. Fuse failure lamps shall be of the neon type with current limiting device
A. Cable terminations and space for terminations shall be suitable for the sizes of cable called for in
the design, refer to Cable Schedules.
B. Terminal blocks shall be made of thermosetting melamine or polyamide material with a low
tracking index and good flame resistance, tested to withstand a temperature rise of 90 C above
ambient temperature.
Provision shall be made for permanent labels to be applied to each terminal for identification
purposes.
D. All terminals for control wiring shall have provision for plug-in test spills and in addition be
fitted with isolating links. Current carrying parts shall be made of tinned brass or copper.
E. Completely shrouded terminals of the tunnel type shall be used for cup to 10mm². The screw
clamp connection shall be vibration proof, self-locking and suitable for clamping two condo.
F. Stranded cables up to 10mm² shall be terminated in copper or copper alloy ferrule shall retain all
strands of the cable.
G. Terminals for cables in excess of 10mm² shall be of the double connection type with bolted studs
for the connection of cable lugs. The terminal and stud size shall be adequate for the current
carried and the size of cable. Suitable insulating partitions and protective covers shall be
provided.
H. All auxiliary wiring except screened cables shall be connected to incoming/outgoing cables Via
insulated terminal blocks, screw/screw type, clipped onto DIN rails. There shall be sufficient
space on the DIN rail for future terminal blocks of not less than 10% or 5 No. whichever is the
greater.
J. Plugs and fixed sockets for the application shall be provided for the termination of screened
cables.
K. All terminations shall be mounted at least 0.2m above the base of floor mounted assemblies.
K. All load terminals shall be suitable for the types and sizes of cables as specified in the schedules
and drawings.
A. All assemblies shall be tested in accordance with the requirements of IEC 61439..
Where TTAs are specified, certification shall be provided for all type and routine tests to
DIN/VDE standards.
Where PTTAs are specified, compliance with the test requirements of BS 5486, shall be either by
type testing or by extrapolation from type tested assemblies or individual parts of similar,
representative construction. Verification of the Type Testing Certification or the appropriate
extrapolation calculations shall be provided. Certificates shall also be provided for routine tests in
compliance with DIN/VDE standards.
D. Calculation from first principles for temperature rise and short-circuit strength will not be
acceptable.
E. Verification of the short-circuit withstand strength is not required for assemblies having a rated
PSSC not exceeding 10KA or those protected by current limiting devices with a cut-off current
not exceeding 15KA.
F. Verification of the short-circuit withstand strength is not required for auxiliary circuits connected
to transformers whose:
(i) Rated power dose not exceed 10KVA for a rated secondary voltage of not less than
110V.
or
(ii) Rated power does not exceed 1.6KVA with a rated secondary voltage of less than 110V,
and whose relative short-circuit voltage is not less than 4%.
G. Works tests shall include inspection of all wiring and a complete electrical functioning test.
H. Protection relays shall be tested by primary current injection with currents equal to overload,
short-circuit and earth fault conditions.
The tests to be carried out shall include but not necessarily be limited to:-
5. Verify that fuse and/or circuit breaker sizes and types correspond to drawings and
coordination study as well as to the circuit breaker's address for microprocessor-
communication packages.
7. Inspect bolted electrical connections for high resistance using one of the following
methods:
8. Confirm correct operation and sequencing of electrical and mechanical interlock systems.
9. Lubrication requirements
15. Verify that filters are in place and/or vents are clear.
2. Electrical Tests
5. Perform an overpotential test on each bus section, each phase to ground with phases not
under test grounded, in accordance with manufacturer's published data. If manufacturer
has no recommendation for this test. The test voltage shall be applied for one minute.
9. Voltage Transformers
3. Test Values
3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as
indicated in the manufacturer's published data. If manufacturer's data is not available,
investigate any values which deviate from similar bus by more than 50 percent of the
lowest value.
PART 3 - EXECUTION
A. Examine conditions under which switchgears are to be installed, and notify in writing of conditions
detrimental to proper completion of work. Do not proceed with work until unsatisfactory conditions
have been corrected.
B. The tests to be carried out in accordance to IEE 17th. Edition, BS 7671, all other relevant international
standards.
C. Upon installation at site all L.V panels should be subjected to testing as performed in the factory to
ensure that no damages has occurred in transit and the panels are safe to be energized (SAT).
3.2 INSTALLATION
C. Tighten connectors and terminals, including screws and bolts and equipment grounding
connections, in accordance with equipment manufacturer's published torque tightening values for
equipment connectors.
F. Fill out switchgears circuit directory card upon completion of installation work.
G. Provide equipment earthing connections sufficiently tight to assure a permanent and effective
ground for switchgears.
A. Upon completion of installation of switchgear and after circuiting has been energized,
demonstrate capability and compliance of switchgear with requirements. Where possible, correct
malfunctioning units at site, then retest to demonstrate compliance; otherwise, remove and
replace with new units and retest.
B. Prior to energization of switchgears circuitry, check all accessible connections to manufacturer's
tightening torque specifications.
C. Prior to energization of switchgears, check with earthing resistance tester phase-to-phase and
phase-to-ground insulation resistance levels to ensure requirements are fulfilled.
D. Prior to energization, check switchgears for electrical continuity of circuits, and for short circuits.
The system supplier is responsible to provide all required switches, auxiliary contacts, relays, wiring,
terminal blocks transducers to provide signaling and metering information for the central control system
and to accept START/STOP, open/close, set point from it.
Relevant signals are listed under controls, BMS and motor control panels drawings and data schedules.
All signals to the BMS system should be potential free to actuate devices of less than 20 VA. @ 220 volt.
In any device will need more than 20 VA. at any operating condition the supplier should add interposing
relays.
All analog measures coming or going to the BMS should be coordinated with the BMS supplier (either 4-
20 MA or 1-5 volt or -10 volt).
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16010, applies to work of this
section.
A. Work includes providing all materials, equipment, accessories, services and tests
necessary to complete and make ready for operation, all distribution Boxes in
accordance with Drawings and Specifications.
1.4 SUBMITTALS
A. Product Data: Submit manufacturer's data for distribution Boxes including size,
enclosures, and electrical ratings and characteristics.
PART 2 - PRODUCTS
A. Distribution Boxes shall be provided with number of fuses rated as shown on the
drawings and to be as specified by EEA.
Distribution Boxes shall be designed for three different sizes as follows:
B. Distribution Boxes shall comply fully with the requirements of IEC, DIN/VDE
standards.
D. Distribution Boxes shall be provided with a suitable earth bar and neutral bar,
with adequate provision for the connection of a circuit protective conductor for
each outgoing feeder.
E. Terminals for the neutral conductor shall allow the individual connection of
conductors having a current carrying capacity equal to the full current carrying
capacity of the phase conductor.
G. Distribution Boxes shall have a side-hung hinged front cover, attached by means
of lift-off hinges, and fitted with cylinder type locking handles and provided with
lock and key or other approved means. Covers shall be braced or folded in such
a manner as to prevent distortion or whip, and shall be fitted with dust-proofing
gaskets or edge seals.
L. Each distribution Box shall be provided with an engraved plastic label on the
outside of the front cover, bearing the designation of the Box and its reference
number, if any, as given on the drawings or in the schedules. The label shall be
fixed in position by chromium-plated set screws. Each such label shall be not
less in size than 100 mm x 30 mm, and shall bear the required inscription in
white on a black background, using letters and/or digits not less than 5 mm high.
B. Lighting panels shall comply fully with the requirements of IEC, DIN/VDE
standards.
D. Lighting panels shall be provided with a suitable earth bar and neutral bar, with
adequate provision for the connection of a circuit protective conductor for each
outgoing way.
E. Terminals for the neutral conductor shall allow the individual connection of
conductors having a current carrying capacity equal to the full current carrying
capacity of the phase conductor.
F. When the means of isolating the lighting panels from the incoming supply is not
to be mounted immediately adjacent to the board, means shall be provided in the
lighting panels to indicate whether or not the supply is "ON".
H. Lighting panels shall have a side-hung hinged front cover, attached by means of
lift-off hinges, and fitted with cylinder type locking handles. Covers shall be
braced or folded in such a manner as to prevent distortion or whip, and shall be
fitted with dust-proofing gaskets or edge seals.
K. Lighting panels shall be arranged for top or bottom or top and bottom entry
according to the requirements specified on the drawings or in the schedules.
L. Lighting panels shall be provided with detachable end plates as specified in the
schedules or drawings.
M. Each lighting panels shall be provided with a durable circuit chart fixed to the
inside of the cover or immediately adjacent and bearing typewritten details, in
plain language, of the circuits supplied by each of the ways. The chart shall be
on heavy weight paper or thin card, and shall be protected by means of a rigid
transparent plastic cover, it shall be mounted in such a way that it can easily be
removed for correction or alteration, then replaced. The size of the chart shall be
such that there is adequate space of recording all of the required information and,
in any case, shall not be less than A5 (210 mm x 148 mm).
N. Each way in the lighting panels shall be clearly numbered to correspond with the
numbering on the circuit chart.
O. Each lighting panels shall be provided with an engraved plastic label on the
outside of the front cover, bearing the designation of the board and its reference
number, if any, as given on the drawings or in the schedules. The label shall be
fixed in position by chromium-plated set screws. Each such label shall be not
less in size than 100 mm x 30 mm, and shall bear the required inscription in
white on a black background, using letters and/or digits not less than 5 mm high.
B. The lighting panels shall be provided to control the street lighting circuits by
photocell element, timer and selector switch automatic-off-manual through
lighting contractor as shown on the drawings.
A. ASSEMBLES
B. FUNCTIONAL UNITS
2.4 COMMISSIONING
(i) The energizing of functional device circuits and equipment which have
previously been inspected, tested, found to be satisfactory and capable of
being energized with complete safety.
(ii) The starting up of all electrically powered plant and equipment, including
that supplied and installed under other contracts, and as specified in the
schedules.
PART 3 - EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
C. Tighten connectors and terminals, including screws and bolts and equipment
earthing connections, in accordance with equipment manufacturer's published
torque tightening values for equipment connectors.
D. Fasten enclosures firmly to walls and structural surfaces, ensuring that they are
permanently and mechanically anchored. Provide all angle units and
accessories for proper mounting.
PART 1 - GENERAL
A. Drawings and general provisions of Contract, including General and special Conditions and
Division-1 (General requirements), apply to work of this section.
B. General Provisions for Electrical Work, Section 16050, apply to work of this section.
C. The requirements of this section apply to air circuit breakers with solid state trip units specified
elsewhere in these specifications.
A. Work includes providing all materials, equipment, accessories, services and tests necessary to
complete and make ready for operation, air circuit breakers with solid state trip units as shown in
accordance with Drawings and Specifications.
A. Manufacturers: Firms regularly engaged in the manufacture of air circuit breaker of the types and
capacities required, whose products have been in satisfactory use in similar service for not less
than 5 years. Provide air circuit breakers produced by a manufacturer listed as an Acceptable
Manufacturer in this section.
B. Standards Compliance: Comply with requirements of applicable local codes, IEC 947, EN 60947
and Standards pertaining to air circuit breakers which have been UL listed and labeled.
C. In case of conflict among the referenced standards and codes, the more stringent provision will
govern.
1.4 SUBMITTALS
A. Product Data: Submit manufacturer's data for air circuit breakers with solid state trip units.
PART 2 - PRODUCTS
2.1 GENERAL
A. Air circuit-breakers shall be provided with solid state trip units fixed type as indicated on the
drawings, shall be in accordance with NEMA or IEC standards requirements.
B. All circuit breakers connected in one electrical circuit should be fully selective & coordinated, if
selectivity coordination study is failed for any reason, contractor is responsible to add or change
Rev.01 August, 2018 Air Circuit Breakers
Section 16490
Page 1 of 8
any number of breakers, relays,… such that the selectivity coordination shall be fully achieved
with no extra cost to the employer.
2.2 CONSTRUCTION
A. GENERAL REQUIREMENTS
ACBs shall be metal-clad, horizontal cassette type with positively driven "ON/OFF" indication.
B. INTERCHANGE
Means shall be incorporated to prevent the wrong circuit-breaker being racked in at fixed
position.
C. SECURITY
Means shall be provided to padlock the breaker in the service, isolated and test positions; and to
close and independently padlock the shutters as specified in the schedules. It shall not be possible
to withdraw or rack-in shall be prevented.
Robust padlocks or cylinder locks shall be provided to lock each circuit-breaker in one or other
position during on-site testing and commissioning. This shall include locking the shutters closed
when a circuit-breaker is racked out. Two sets of keys shall be provided for each padlock,
together with a key cabinet and key schedule.
D. ACBs shall be fitted with the protection devices solid state type, instruments indicators and
auxiliary control functions as specified in the schedules/drawings.
E. OPERATING MECHANISMS
Where specified, operating mechanisms shall be the trip-free type and shall have a latching
current equal to the short-circuit prospective value. Alternatively, the ACB shall be fitted with an
instantaneous digital trip or making current release which operates when the ACB is closed onto
a short-circuit. Anti-pumping devices shall be fitted to all operating mechanisms.
The specific method of closing shall be as specified in the schedules or drawings, as one of the
following:
(i) Type MSO: Manual, spring operated closing arrangement with a handle for charging and
releasing the spring in one stroke.
(ii) TYPE MSM or MSE: Manual, spring operated arrangement where the spring is charged
to a latched position pending mechanical/electrical initiation of closure. The spring
system shall incorporate the facility of charging for a second closure when the breaker is
closed.
(iii) TYPE MWS: motor wound charged spring as types MSM or MSE. Motor wiring and
control circuitry shall be internal.
(iv) TYPE SOC : solenoid operated from d.c. when available or rectified a.c.
Facilities shall be provided to remove or blank off the integral mechanical "CLOSE" pushbutton
where it could be used to override protection devices, lockout relays or remote operating signals.
Mechanisms which store energy shall be fitted with stored energy status indicators.
F. OPERATING FACILITIES
The ACB shall have facilities for isolation, withdrawal and test position operations with the ACB
isolated. Carriage position switches shall be provided for connection into appropriate control
circuits to permit electrical interlocks to be defeated when the ACB is in the isolated and (where
applicable) test positions as specified in the schedules.
Where specified in the schedules/drawings, earthing facilities shall be provided, to earth the
circuit and busbars in the service, test and isolated positions.
G. OPERATION CLEARANCE
Circuit-breakers shall be installed with full clearances for arc-chute vents and adequate side
clearances for unimpeded operation and maintenance.
2.3 RATING
A. GENERAL REQUIREMENTS
The service performance characteristics shall be as specified in the schedules and drawings.
Ratings specified are the required on-site ratings. Written confirmation shall be provided to
confirm that specified ratings will be obtainable under the conditions in which each circuit-
breaker operates. Operating conditions shall include due allowance for ambient temperature,
enclosure, physical situation, position and attitude of the ACB and the proximity of other devices
on full load.
B. LABELLING
A label shall be provided, in a clearly visible position on the front of each circuit-breaker on
which the service performance characteristics shall be displayed.
A. RELAYS
Protective relay requirements shall be selected so as to ensure full discrimination between system
levels by the tenderer. Protective relays shall be of the solid state type with adjustable for long
time, short time and instantaneous protection features, in addition to ground fault proection for all
breakers of 1000 AMP. and above. Relays shall comply with IEC, NEC,NEMA, DIN/VDE
standards.
All relays shall be provided with test facilities for use in commissioning and testing from the
front of the switchgear.
B. TRIPPING CHARACTERISTICS
Details of tripping characteristics shall be provided for each type of ACB at time of tender. The
details shall include manufacturer's full current discrimination tables showing over current and
short-circuit discrimination and, additionally a full set of overlay transparency discrimination
curves to enable discrimination settings to be checked.
All over current and short-circuit protective devices (relays as item "A" above) shall have
separately adjustable time and current settings. Adjustments and settings shall be possible from
the front of the ACB. The setting adjustment devices shall be behind a lockable cover plate, or
similarly protected against unauthorized access.
Energy for protective devices shall be obtained from integral current transformers. Separate
current transformers shall be of the accuracy class specified in the schedules and comply with
IEC, DIN/VDE NEMA standards, and of suitable ratio and rating for the operating conditions. If
the circuit-breaker is de-rated because of high temperature then the current transformers shall be
replaced with ones suitable for the higher operating temperatures. Protection current transformers
shall not be de-rated.
Under voltage, trip and closing coils which shall incorporate adjustable time delay shall
incorporates adjustable time delay shall be wired out to secondary isolating contacts in the same
position on each breaker to ensure interchangeability of ACBs with the same service performance
characteristics.
ACB’s trip units shall be equipped with the Breaker Communications Status Module to perform
the following functions:
ON/OFF indication.
Trip indication.
D. COMMISSION LABEL
A label shall be provided, in a clearly visible position on the front of each circuit-breaker, on
which the final commissioned release setting for that circuit-breaker shall be displayed.
A. ACB auxiliary circuits shall be arranged to provide a wiping action on contacts during
withdrawal and re-instatement of the ACB, to and from its isolated position
B. On completion of the switchgear installation, each ACB shall be provided with auxiliary contacts
available for future use for both the ACB contact operation and the isolation operation as
specified in the schedules/drawings. Wiring to the switching contacts shall be ferruled and
brought to a terminal block.
C. All auxiliary contacts shall be mounted in accessible positions and away from possible electrical
and mechanical danger.
Rev.01 August, 2018 Air Circuit Breakers
Section 16490
Page 4 of 8
2.6 SHUTTERS
A. Where ACBs are isolated, safety shutters shall automatically cover exposed conductors.
B. The shutters shall be able to be padlocked in the closed position, but shall be capable of being
fixed open where tests require conductor contact.
C. Shutter shall operate automatically by the movement of the circuit-breaker, preferably without
using springs.
2.7 FINISHES
A. Special treatments and finishes such as tropicalisation, anticorrosion finish and cold-climate
treatment shall be applied where specified or where conditions make such treatment necessary.
2.8 TOOLS
A. Loose equipment shall include test leads and a lifting and transporting device plus any other tools
or equipment needed for routine maintenance.
THE TESTS TO BE CARRIED OUT SHALL INCLUDE BUT NOT NECSSARILY BE LIMITED TO :-
7. Inspect moving and stationary contacts for condition, wear, and alignment.
8. Verify that primary and secondary contact wipe and other dimensions vital to satisfactory operation
of the breaker are correct.
9. Perform all mechanical operator and contact alignment tests on both the breaker and its operating
mechanism in accordance with manufacturer’s published data.
10. Inspect bolted electrical connections for high resistance using one of the following methods:
2. Electrical Tests
2. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with the
circuit breaker closed and across each open pole for one minute. Test voltage shall be in accordance
with manufacturer’s published data.
4. Perform insulation-resistance tests on all control wiring with respect to ground. Applied potential
shall be 500 volts dc for 300 volt rated cable and 1000 volts dc for 600 volt rated cable. Test
duration shall be one minute. For units with solid-state components, follow manufacturer’s
recommendation.
12. Activate auxiliary protective devices, such as ground-fault or undervoltage trip devices, to insure
operation of shunt trip devices. Check the operation of electrically-operated breakers in their
cubicles.
13. Perform minimum pickup voltage test on shunt trip and close coils.
14. Verify correct operation of any auxiliary features such as trip and pickup indicators, zone
interlocking, electrical close and trip operation, trip-free, antipump function, trip unit battery
condition, and reset all trip logs and indicators.
3. Test Values
2. Bolt-torque levels.
3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as indicated
in the manufacturer's published data. If manufacturer's data is not available, investigate any values
which deviate from adjacent poles or similar breakers by more than 50 percent of the lowest value.
6. Trip characteristics of breakers should fall within manufacturer's published time-current tolerance
bands.
7. Minimum pickup voltage on shunt trip and close coils should be in accordance with manufacturer's
published data.
A. Examine conditions under which air circuit breakers are to be installed and notify in writing of
conditions detrimental to proper completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
B. The tests to be carried out in accordance to IEE 17th. Edition, BS 7671, all other relevant international
standards.
C. Upon installation at site all Air circuit breakers should be subjected to testing as performed in the
factory to ensure that no damages has occurred in transit and the panels are safe to be energized
(SAT).
3.2 INSTALLATION
A. Install air circuit breakers as indicated, in accordance with manufacturer's written instructions,
requirements of applicable Standards, and in accordance with recognized industry practices to
ensure that installation complies with requirements and serves intended function.
A. Prior to energization of air circuit breakers, test devices for continuity of circuitry and for short
circuits. Replace malfunctioning units with new unites and then demonstrate compliance with
requirements.
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16010, apply to work of this
section.
A. Work includes providing all materials, equipment, accessories, services and tests
necessary to complete and make miniature circuit breakers ready for operation in
accordance with Drawings and Specifications.
C. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
1.4 SUBMITTALS
D. All MCB’s should be rated at service short circuit entrance level for incoming and
outgoing for each panel .
E. The joule integral (I² t) energy withstand let-through shall be specified for each
MCB.
F. In multi-pole MCBs, including four-pole, all poles shall open, close and trip
simultaneously.
2.2 MECHANISMS
2.3 SECURITY
A. MCBs shall be proved with effective means of locking in the "OFF" position.
B. The manufacturer's standard range shall include all MCB ratings, characteristics
and auxiliaries specified in the schedule.
3.1 INSPECTION
A. Examine conditions under which miniature circuit breakers are to be installed and
notify in writing of conditions detrimental to proper completion of the work. Do
not proceed with the work until unsatisfactory conditions have been corrected.
3.2 INSTALLATION
PART 1 - GENERAL
A. Drawings and general provisions of Contract, including General and special Conditions and Division-1
(General requirements), apply to work of this section.
B. General Provisions for Electrical Work, Section 16050, apply to work of this section.
C. The requirements of this section apply to moulded case circuit breakers solid state type specified
elsewhere in these specifications.
A. Work includes providing all materials, equipment, accessories, services and tests necessary to complete
and make moulded case circuit breakers ready for operation in accordance with Drawings and
Specifications.
A. Manufacturers: Firms regularly engaged in the manufacture of moulded case circuit breakers solid state
type whose products have been in satisfactory use in similar service for not less than 5 years. produced
by a manufacturer listed as an Acceptable Manufacturer in this section.
B. Standards Compliance: Comply with requirements of applicable local codes, IEC 60947-2, IEC 60947-4,
IEC 60947-4-1 and Standards pertaining to moulded case circuit breakers solid state type (adjustable for
long time , short time and instantaneous protection features).
C. In case of conflict among the referenced standards and codes, the more stringent provision will govern.
1.4 SUBMITTALS
A. Product Data: Submit manufacturer's data for all types of moulded case circuit breakers, including solid
state type.
PART 2 - PRODUCTS
A. DEFINITIONS
The definitions of terms and symbols used in this Specification are those used in IEC 60947-2.
Moulded case circuit-breakers solid state type, all MCCB's shall comply with IEC 60947-2 plus any
additional requirements of this Specification.
All MCCB's shall be equipped with solid state release (adjustable for long time and short time and/or
instantaneous protection depends on the selectivity achievements features).
MCCB’s trip units shall be equipped with the Breaker Communications Status Module to perform the
following functions:
ON/OFF indication.
Trip indication.
Breakers of 1000A rating and above shall be provided with ground fault protection as per NEC
requirements.
C. GENERAL
2.2 CONSTRUCTION
A. MANUFACTURE
MCCB's shall be manufactured with double insulation of the front face, insulating auxiliary
components from the main power poles thereby allowing as far as reasonable the fitting of auxiliary
units on site without full isolation of the unit.
B. CURRENT RATINGS
Rated currents, rated service short-circuit breaking capacities and trip release settings shall be as
specified in cable installation schedules and on drawings.
Current ratings as specified in the schedules and drawings are for interrupted duty at 220/380V in the
final installed location on site under full load operating conditions of the complete installation, i.e.
taking account of heat produced by other devices and the ambient temperature, physical situation,
enclosure, position and attitude of the MCCB.
The appropriate de-rating factors shall be applied to manufacturer's standard ratings when selecting
MCCB's to meet the specified ratings.
C. TRIPPING CHARACTERISTICS
Details of tripping characteristics shall be provided for each type of MCCB. The details shall include
manufacturer's full current discrimination tables showing overload and short-circuit discrimination and,
additionally, a full set of overlay transparency discrimination curves or software program to enable
discrimination settings to be checked.
D. TEST CERTIFICATES
Complete certificates shall be provided for each type of MCCB, stating the service and ultimate short-
circuit capacities.
E. CONTACTS
The contact arrangement of current-limiting MCCB's where applicable shall be such that the current-
limiting contacts are in series with the main contacts and remain closed in normal operation, including
time delayed over current tripping.
Contacts shall be arranged so that normal current is carried by low-resistance silver alloy or other non-
welding material while arcing is handled by tungsten contacts.
Multi-set contact MCCB's shall be arranged using one set of contacts for thermal current and other for
arc interruption.
F. TERMINALS
Terminals shall be sized to accommodate the size and type of cable of incoming and outgoing circuits
as specified in the schedules or drawings. MCCB's shall be provided complete with terminal shields.
Terminals shall be arranged for direct connection to busbars, front or rear as required by the
switchboard design.
All poles of multi-pole circuit-breakers shall be constructed so that contacts open, close and trip
simultaneously. It shall not be possible for one or more poles to be closed while another remains open
and vice-versa.
G. OPERATING MECHANISMS
Operating mechanisms shall be over-center, quick-make, quick-break type having operation in which
speed of operation of the breaker is independent of the operator.
Where solenoid operated MCCBs are specified in the schedules or drawings, the operating voltage shall
be as scheduled. Separate solenoids shall be provided for opening and closing operations. Built-in push
buttons shall be provided for local operation.
Indication of the "ON", "OFF" and "TRIPPED" conditions shall be provided not only by the position of
the handle but also by means of a colored band, or line which shall be visible when the circuit-breaker
is on but not when it is off or tripped.
Indication shall be provided to confirm that all main contacts have separated.
H. ENCLOSURES
Moulded case covers and non-interchangeable trip elements shall be permanently sealed at works to
prevent tampering, but the trip elements may be changed/Adjusted and re-sealed on site by using
suitable tools.
MCCB's shall be certified as satisfying the leakage current testes called for in IEC 60947-2 with
regards to safety isolation.
MCCB's used for motor starting shall satisfy the Type 2 coordination requirements called for in IEC
60947-2.The MCCB and the starter shall preferably be of the same manufacture, and in all cases shall
be tested together and certified as satisfying the co-ordination requirements.
All MCCB's shall be of the same manufacture and those of like kind shall be of the same type. This
requirement applies to loose or individually mounted MCCB's as well as to those incorporated within
assemblies such as control panels, switchboards and distribution boards.
I. PROTECTION MECHANISMS
Each pole shall provide inverse time over current protection and adjustable high set instantaneous
tripping and in accordance to item 2.1 (B) above. All poles shall be tripped simultaneously if one
detects a fault.
Trip units of ratings up to and including 250A shall be built in. Trip units above 250A shall be
replaceable.
All adjustable trips shall be visible and adjustable from the front with the breaker in position.
Adjustments to trip settings shall be made to all poles simultaneously by means of a common
adjustment mechanism.
J. OPERATING FACILITIES
Facilities shall be provided for the use of a hand-held tester for on-site testing of all operational
features.
Where specified in the schedules/drawings, earth leakage trips, shunt trips, undervoltage trips and
remote operation shall be provided. These accessories shall all be factory assembled and tested.
Energy based limiting MCCB's which require replacement of the current limiters after operatic shall not
be re-settable until such replacement has been made.
A. Examine conditions under which residual current devices are to be installed and notify in writing of
conditions detrimental to proper completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
B. The tests to be carried out in accordance to IEE 17th. Edition, BS 7671, all other relevant international
standards.
C. Upon installation at site all C.B’s should be subjected to testing as performed in the factory to ensure
that no damages has occurred in transit and the panels are safe to be energized (SAT).
The tests to be carried out shall include but not necessarily be limited to:-
6. Inspect bolted electrical connections for high resistance using one of the following
methods:
2. Electrical Tests
2. Perform insulation-resistance tests on each pole, phase-to-phase and phase-to-ground with the
circuit breaker closed and across each open pole for one minute. Test voltage shall be in accordance
with manufacturer’s published data.
2.6 LABELLING
A. On the front of each MCCB a visible label shall be fitted and described as follows:
- Rated current and trip setting (for MCCB's with multiple current ratings the maximum value shall be
marked plus, without ambiguity, the value for which the MCCB has been adjusted)
- Rated voltage
- Manufacturer's name or trade mark
- Type designation, catalogue number or serial number
- Rated short-circuit capacity in amperes
- Reference ambient temperature if different from 30 oC
A label shall be provided, in a clearly visible position on the front of each circuit-breaker, on which the
final commissioned release setting for that circuit-breaker shall be displayed
PART 3 - EXECUTION
A. Examine conditions under which moulded case circuit breakers are to be installed and notify in writing
of conditions detrimental to proper completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
B. The tests to be carried out in accordance to IEE 17th. Edition, BS 7671, all other relevant international
standards.
C. Upon installation at site all L.V panels should be subjected to testing as performed in the factory to
ensure that no damages has occurred in transit and the panels are safe to be energized (SAT).
3.2 INSTALLATION
A. Install moulded case circuit breakers as indicated, in accordance with manufacturer's written
instructions, requirements of applicable Standards, and in accordance with recognized industry
practices to ensure that installation complies with requirements and serves intended function.
A. Prior to energization of moulded case circuit breakers test devices for continuity of circuitry and for
short circuits. Replace malfunctioning breakers with new breakers and then demonstrate compliance
with requirements.
C. In case of conflict among the referenced standards and codes, the more
stringent provision will govern.
1.4 SUBMITTALS
C. When incorporating overcurrent and short circuit trips and used as circuit-
breakers RCD's shall comply also with IEC, DIN/VDE. When used as
disconnectors or switched RCD's shall comply also with IEC, DIN/VDE.
G. RCD's shall have the appropriate short-circuit strength for the location in the
system at which they are installed and shall be capable of making, carrying
and breaking the full short-circuit current. This requirement shall apply
whether or not the RCD is the sole or main circuit breaker at that point in the
system.
I. RCDs shall not be used as the sole means of protection against direct contact.
J. Every RCD shall be provided with a test button and an engraved, clearly
legible label stating "TEST FREQUENTLY"
K. RCD's shall be suitable for loads with high crest factors and shall operate
correctly irrespective of the harmonic or direct current content of the wave
form.
PART 3 - EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
CONTACTORS
PART 1 - GENERAL
C. In case of conflict among the referenced standards and codes, the more
stringent provision will govern.
1.4 SUBMITTALS
2.1 GENERAL
PART 3 - EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
PART 1 - GENERAL
B. The requirements specified in this section apply to all related sections in this
Division. The requirements of all related sections, elsewhere in this division also
apply to this section unless specified to the contrary.
C. General Provisions for Electrical Work, Section 16010, apply to work of this section.
A. Work includes providing all materials, equipment, accessories, services and tests
necessary to complete, make ready and set to work for operation by the Owner,
power factor capacitors correction shall be in accordance with Drawings and
Specifications.
C. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
1.4 SUBMITTALS
A. Product data: Submit manufacturer's data for centralized automatic power factor
capacitor assemblies including sizes, enclosures, electrical ratings and characteristics
and wiring diagrams.
PART 2 - PRODUCTS
2.1 GENERAL
C. Each assembly (unit) shall provide 95% power factor correction with built in sa
feguards to prevent over capacitance.
2.2 RATINGS
A. The voltage rating of the power factor correction equipment shall be 380 volts
between phases.
B. The total KVAR capacity of the assembly units shall be as indicated on drawings.
B. Each three phase capacitor shall be furnished with an approved pressure sensitive
interrupter. The interrupter shall disconnect all three phases at the same time to
maintain a balanced circuit.
D. Dielectric material shall be low loss, less than 0.5 watts per KVAR.
E. Dry cells encapsulation medium shall be a thermoplastic material which allows out
gassing to engage the pressure interrupter.
I. All capacitor cells shall have threaded terminals for wire connection.
J. To reduce line transients on system no stage shall switch more than 120 KVAR and
no capacitor cell shall exceed 25.0 KVAR.
2.4 CONTROLS
A. All controls shall be mounted on enclosure door for easy inspection and service.
B. A door interlock shall be provided to disconnect control power when enclosure door
is opened.
C. A personnel ground fault breaker shall be provided to disconnect control power upon
accidental contact with control power and earth (ground).
1. Controller shall measure the reactive current on every passage of the voltage
through zero.
2. A LED display shall be provided to indicate the stages that are on.
6. Controller shall be able to select 1:1:1, 1:1:2, and 1:2:2 switching sequence of
capacitor steps.
7. Controller shall be able to display power factor with indication for an inductive
or capacitive power factor.
1. Three "Push-To-Test" blown fuse pilot lights, one per phase-door mounted, to
indicate a blown fuse condition.
2. Each fused phase, of each 50 KVAR step, shall have its own blown fuse
indicating light mounted in close proximity to the fuse for easy identification.
2.5 ENCLOSURE
A. The enclosure shall be fabricated from 2.65 mm minimum thick, cold rolled steel.
D. Capacitor cells shall be accessible for visual inspection and replacement from the
front of the cabinet.
F. The enclosure door shall have a three point latch with key locking handle.
A. All power wiring shall have a thermoplastic insulation rated for 105 degrees C at 500
volts.
B. System wiring connections shall be made to copper bus bars braced for 65,000 amps
or greater.
E. Air core transient suppression coils shall be provided in series between the contactors
and capacitor cells.
A. Capacitor "cells" shall be provided with discharge resistors to reduce residual voltage
to less than 50 volts within one minute of de-energization, unless local codes govern
otherwise.
2.8 FUSES
A. To provide for major fault protection, line fuses shall be provided on all three phases
of each switched stage and fixed bank.
B. Line fuses shall be current limiting, U.L., recognized Class T type. Minimum
interrupting ratings shall be 200,000 amps for fuses of 30 amps and above.
C. Fuses shall be designed for capacitor applications and shall be rated not less than
200% capacitor current rating.
A. The capacitor shall be rated for continuous duty at 40 degree C ambient at 1,000
meters and below.
B. Total Harmonic Distortion (THD) of 5% on either the voltage and current wave-
forms shall not effect the life of capacitors, contactors or controllers.
C. A + 10% variation in line voltage shall not effect the life of the capacitor.
D. All capacitors should be rated at 380 volt and can withstand 440 volt.
A. Provide in each assembly, space and connection such that if in the future, chokes and
filters will be required, the installation can be accomplished in the field with
minimum down time.
2.11 TESTING
B. The automatic capacitor bank shall be tested for proper operation prior to leaving the
factory. The following checks, measurements, and operations must be confirmed and
recorded for each stage.
- WIRE CONNECTIONS
- TORQUE CONNECTIONS
- PHASE TO PHASE, RESISTANCE CHECKS
- CONTROLLER OPERATION, MANUAL OPERATION
- CONTROLLER OPERATION, AUTOMATIC OPERATION
PART 3 - EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
C. Mount the switchboard assembly on flush steel aligning channels elevated above
floor level by a concrete pad and as noted on drawings. Provide aligning shims to
achieve level installation where channels cannot be provided.
D. Insure that centralized automatic power factor capacitor assemblies are shipped in
sections which can be fitted through the structures and openings available.
E. Bond together the centralized automatic power factor capacitor assemblies structure,
sections and all conduits terminating at same with a 120 mm² bare copper earth
(ground) cable and connect to the switchboard earth (ground) bus and to the earthing
(grounding) grid as required. Provide conduits terminating at centralized automatic
power factor capacitor assemblies with Earthing (Grounding) Wedges of the required
size.
J. Provide control fuses, with five spare fuses for each rating.
A. Upon completion of installation of equipment and after circuitry has been energized,
test equipment to demonstrate compliance with requirements. When possible,
field-correct malfunctioning units, then retest to demonstrate compliance; otherwise
remove and replace with new equipment and retest.
2. Check centralized automatic power factor capacitor assemblies for continuity and
for short circuits.
3.4 MAINTENANCE
A. All maintenance and inspection on the capacitor assembly shall be done with the
system disconnect device in the open position.
C. An annual inspection of the capacitor cell shall be done to identify failing capacitor
cells (a bulged cover is the symptom to watch for).
STREET LIGHTING
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16010, apply to work of this
section.
B. The supplier shall submit calculations performed by the latest version of the
DIAlux lighting design software and submitted for all typical lighting
installations of the project for the consultant review and approval.
C. The contractor shall install a mockup from each supplier in the project site for
each type of fittings for the owner and the consultant review and evaluation.
Unless specified otherwise the LED street lighting system shall conform in
design, material, construction and performance to the latest editions of the
IEC/CIE standards, their corresponding British/European (BS EN) or
American (IEEE, ANSI, UL) standards and in particular to the following
publications:
C. In case of conflict among the referenced standards and codes, the more
stringent provision will govern.
1.4 SUBMITTALS
E. Test reports from an independent test laboratory that shows total lumens of the
luminaire (absolute photometry) and test report for other electrical tests.
F. LM79 test report for the luminaire with all significant product data and all
performance data including Total Luminous Flux, Luminous Efficacy (lm/W),
Correlated Color Temperature (CCT), Color Rendering Index (CRI), Power
Factor, Wattage, Driver Current, Chromaticity Coordinates and so on.
G. LM80 report from LED vendor for LED used in luminaire with all pertinent
data concerning conditions of testing, ambient conditions, type of equipment,
type of LED source including numbers tested, operating cycle, drive current
for life test, initial luminous flux, lumen maintenance data, failures, etc.
H. LM82 test report for the whole luminaire detailing on the results of
measurement of electrical and photometric properties as a function of
temperature with all significant product data and all performance data
Rev.01 August, 2018 Street Lighting
Section 16500
Page 3 of 18
including Input Power/Voltage/Current, Luminous Flux, Luminous Efficacy
(lm/W) at 50oC, Chromaticity Coordinates, Driver Temperature and so on.
I. Factory Pre-release Reliability test reports for the LED (chip, diode or
package) from Joint Electron Devices Engineering Council (JEDEC), or
similar international approved equivalent organization.
N. Test report for Salt Spray (Fog) test performed as per ASTM B117-07a-2011
showing effect on the body of the luminaire and also effect on light output
after this test.
P. Documentation of the expected useful life time including the testing and
calculation of useful life. And verification of site lighting performance at that
life. If the site defined performance methods are used, the interpolation
between the three sets of LM-80 data.
T. Unless the above documents are submitted with the offer, the offer will not be
considered.
PART 2 - PRODUCTS
2.1 GENERAL
A. The LED street lighting luminaire shall be fully aesthetic in design and shape,
from a modern concept and a state-of-the-art technology luminaire. The
Rev.01 August, 2018 Street Lighting
Section 16500
Page 4 of 18
luminaire shall be manufactured and tested to comply fully with the
requirements of IEC/BS EN 60598-1 and shall be CE or UL certified, or
comply with equivalent international standards with all certification made
available. The luminaire shall have Class-1 insulation in accordance with
above IEC/BS EN with provision of earthing and shall be from American,
European, or Japanese origin.
B. The LED light source and the driver shall be compliant with the Restriction of
Hazardous Substances Directive (ROHS) No. 2002/95/EC as adopted by the
European Union and the luminaire shall be designed for ease of component
replacement and end-of-life disassembly.
C. The luminaire and associated equipment shall be of the proven best quality
and current models, for which replacement parts, like drivers, LED modules,
etc. are and will be available for the normal expected useful life of the fittings
and associated equipment.
E. The luminaire shall have a degree of protection of minimum IP-66 for the
optical compartment and driver or driver compartment in compliance to
IEC/BS EN 60529 against the ingress of dust and moisture under all operating
conditions and shall be suitable for wet location. It shall have a minimum
mechanical strength rating of IK-07. All synthetic materials shall be 100% UV
Stable. The luminaires not having the required degree of protection and
mechanical strength will be rejected.
G. The LED luminaire shall be tested for Photobiological safety and shall be of
Risk Group 1 in accordance with the requirements of IEC/BS EN 62471 and
all test reports submitted.
H. All LED’s and controllers should be supplied with the luminaires as per the
manufacturer recommendations.
L. A minimum life time of L85 (10K) 60,000 hrs can be accepted at designated
ambient temperature of 50 ºC in accordance to IES TM-21-11.
N. All luminaires shall be provided with LED chip compatible with the control
gear used.
Q. All LED luminaires shall work at 50ºC ambient temperature, 90% relative
humidity & storage temperature of 80 ºC.
R. The light source should have full cut off angle that emit no light upward.
S. The contractor should stick to the specified lighting fixture manufacturer for
each type of lighting fixture.
T. All tests submitted shall be from test bodies that are ISO 17025 (PT) certified
or accredited NVLAP.
A. The light source shall be high power white light emitting Diodes (LEDs) with
individual efficacy of minimum 140 Lumens/watt arranged modularly to
provide the required lighting output. All lumen figures shall be Deliver (Hot)
Lumens.
C. The LEDs colour temperature shall be 3000K with a colour rendering index of
more than 70.
D. TM-21 reported life time should be run for 10,000 hrs confirming soldering
point temperature (Tsp) used in (coming from Thermal Management Test
report at elevated ambient temperature 50ºC) and selected driver current
(Maximum 500mA).
E. All LED luminaires shall be supplied complete with LEDs controller as per the
manufacturer recommendations.
F. All cables shall be secured within the luminary body to prevent loose lengths
from touching hot surfaces or becoming trapped beneath cover plates. Cable
clips or cleats shall be captive and if secured by adhesive, shall not loosen with
age.
G. Wiring within the fixture shall be 125ºC, 500V and to be as per manufacturer
recommendation.
I. Extreme high power LED, Multi-die LED, COB & Medium power LED are
not accepted.
General:
C. The Driver and driver output current shall be fully tested and compatible with
the exact LED chips /engine of the luminaire.
I. All drivers shall have protection features (short circuit, overload & thermal
protection).
K. Drivers shall comply with BS EN 55015 and IEC/BS EN 61000-3-2, 3-3 with
regard to the RFI and EMC compliances.
L. Drivers shall have a total individual luminaire Harmonic Distortion (THD) of:≤
20% in accordance with IEC/BS EN 61000-3-2 or ANSI C82.77 (2002). The
Contractor shall measure the harmonic at the supply point (LV side of the
distribution substation) after the installation of all the LED fixtures and adopt
harmonic compensation methods to limit the total harmonics distortion in the
supply voltage to maximum 5% as per IEEE 519 Regulations.
The LED luminaire system efficacy shall be greater than 100 lumens/watt at 50oC
ambient temperature and 90% relative humidity, driving current 500 mA and CCT:
3000 K.
The luminaires shall be fitted with optical refractors & diffusers. Different optics shall
be proposed to exactly suit the specific applications. Independent laboratory photometric
test reports shall be submitted for the luminaire photometric files used in the lighting
calculations. The testing should conform to IESNA LM-79-08 standards.
The cover of the luminaire shall be from clear, high heat and shock resistant, tempered
glass and the optical assembly of the luminaire shall be totally sealed for the degree of
protection specified. The glass cover shall be of adequate thickness encased in stainless
steel or die cast aluminum alloy frame with substantial hinges and catches. Covers made
from acrylic or polycarbonate materials will not be accepted.
The LEDs shall be removable/replaceable by modular means without any possible risk
to maintaining luminaire photometry for future upgrading/maintenance requirements.
Substantial heavy duty heat sinks shall be provided for mounting the LED modules to
ensure excellent heat dissipation. The design of the heat sinks shall be such that there is
a direct thermal path from the led junctions to the atmosphere thus providing a thermal
Rev.01 August, 2018 Street Lighting
Section 16500
Page 8 of 18
transfer effect throughout the life of the luminaire. The heat sinks shall be adequately
designed to enable the luminaires to work efficiently in extreme climatic conditions. The
luminaire shall be provided with a demonstrated ventilation arrangement allowing heat
to be dissipated to the atmosphere. The luminaire shall be designed to prevent collection
of debris on the heat sinks by proven and stated means.
The thermal management test report (ISTMT) should be run at 50oC. The report shall
use thermal camera shots to determine high die temperature and should declare clearly
Tsp values as well as driver current used at designated ambient temperature of 50oC.
(Result must be used on useful life time calculations using TM-21 and LM-80 reports).
The Manufacturer shall provide test certification in accordance with IEC 60068 – 2 68
Part 2 Test L: Dust and Sand and should be submitted by the manufacturer from an
independent / independently certified test laboratory. The test certificate should provide
evidence that the heat increase inside the housing enclosure with dust and sand should
not be more than 10% of the heat inside without the accumulation.
The lighting calculations shall be performed by using the latest version of the DIALux
lighting design software and submitted for all typical lighting installations of the project
with the IESNA LM-79 for the luminaire photometric files used in the calculations.
Complete type tests shall be carried out and submitted on the LED luminaire as per the
latest IEC/BS EN 60598-1 & 2-3 at an internationally recognized independent test
laboratory (ASTA, DEKRA, CESI, or approved NCB) to be submitted with the CB
certificate.
The manufacturer shall provide all necessary equipment (including all electrical and
illumination test meters) and shall measure and record values of luminance and
illuminance at all predetermined positions. These measurements shall be witnessed by
Site Supervision Engineer, who may require demonstration of the accuracy and
reliability of any instruments used.
2.10 GUARANTEE:
A. Written Warranty from both supplier and agent for ten (10) years for the whole
luminaire starting from commissioning date (warranty includes but not limited to
LEDs Chips, Modules, wiring, driver, connectors, terminal blocks, hardware’s,
Glass, PCBs…etc.) and any luminaire or driver that will fail or mal-function
within this period shall be replaced free of charge.
The smart poles are distributed in the new Cairo capital roads as indicated on the
drawings.
Each smart pole shall be manufactured to fit all or some of the following components
that will be supplied by the client as mentioned below, except (lighting fixture, Dali
driver, Dali gateway, Dali controller, …etc) which will be supplied by the contractor,
and all these components to be installed by the smart poles contractor.
The contractor is fully responsible to make all needed coordination between all
manufacturers for the below components:
a. LED lighting fixture complete with Dali Driver. ( supplied by contractor)
b. Controller complete with safety relays (to ensure power cutoff to the billboards
and lighting luminaries). (supplied by contractor)
c. Dali Gateway. (supplied by contractor)
d. CCTV camera.(supplied by client)
e. Digital signage. (supplied by client)
f. Managed Switch & Fiber Optic Converter. (supplied by client)
g. Wi-Fi Access Point. (supplied by client)
h. Evacuation Loud Speakers. (supplied by client)
i. Power Supply. (supplied by client)
j. Public address loud speaker. (supplied by client)
k. Microcell with antenna. (supplied by client)
l. UPS (500W, 2hrs.backup time). (supplied by client)
m. The communication equipment shall be installed in main cabinet (60cm
diameter), IP-67 and shall be equipped with [ventilation fans, access control, door
sensor which shall be activated if the cabinet door is opened without using the
access card and to send alarm signal to CCC and COC buildings] the shape of the
cabinet shall be decorative type as approved by the Arch. Consultant. (supplied by
contractor).
All the components should be designed to withstand extreme weather conditions and
high temperature, and to be installed inside the pole itself or in a weatherproof steel
enclosure attached to the pole.
Install the power cables inside the smart poles in a separate raceway rather than the
raceways used for communication cables.
Smart poles should have the capability to incorporate backhaul for connectivity over
optical fiber.
The contractor shall approve the smart lighting poles from all the concerned
authorities and fulfill all their requirements prior submitting the offer to the consultant
for approval.
The contractor shall submit one sample from the smart pole complete with all
components at the site for final approval from client\consultants before starting the
manufacturing of the rest of the poles.
The lighting control system shall be a state-of-the art computer addressable lighting
management system providing total flexibility of control through addressable control
and monitoring of every street luminaire in New Cairo Capital.
The system forms a structural part of the lighting installation, and the system
architecture is based upon a simple hierarchical network. Although a system may
control many thousands of addressable points, each uniquely identified, monitored
and configurable, the modular network comprises essentially of the following basic
elements:
1. DALI Driver:
The DALI driver specifications shall be detailed with the lighting fixture
specifications.
2. DALI Controller:
The maximum DALI cable length shall be not exceed 280 meter and to provide
Dali extender (inside the lighting pole) if the length will exceed that limit.
The controller shall be provided with No. of channels equal to the no. of
controlled lighting circuit (as indicated in the drawings) plus two channels as
spears.
3. DALI Gateway:
It provide web interface delivering access to the inbuilt time check & schedule
editor functions.
The gateway shall have large storage capacity. This saves configuration time &
ensure accuracy for phone & tablet control.
Inbuilt web server — allows the user to check system settings via the network
hardware checker and system roll call tools.
Inbuilt time clock and schedule manager allow the user to manage operation and
task scheduling without advanced technical knowledge.
4. Main Controller:
The main controller shall be located at the COC (Command Operations Center)
building.
o Monitoring all incoming data from the DALI gateways installed in the
lighting poles.
o Providing dimming range from (0% – 100%).
o Providing clear indication of the ON/OFF status of each street lighting
fixture.
5. PC Central Controller:
PC central controller shall be equipped with the latest Intel Processor loaded
with the dimming control system software and project graphics; it shall be
supplied as minimum with:
The Software shall additionally support Smart Client as an app for iOS,
Android, Windows Phone and Windows RT. Client software for smart devices
The software shall have free editor for creating any large and complex projects,
including online simulation mode.
The user interface and menus are multilingual. Any language (culture) can be
used in the interface. The language is switched directly in and at the client at
runtime.
o Providing clear indication of the ON/OFF status for each street lighting
fixture.
o Providing dimming range from (0% – 100%) for each street lighting fixture.
o Fault log manager with recording of messages according to DIN 19235, any
number of messages, including linking of external documents or URLs, with
logbook function and non-changeable storage of the entries in SQL-based
database.
o Presence simulation as ring memory with recording and tag-synchronous
playback.
o Astro time switch for control after sunrise and sunset, with offset channels
and output of the sun position and solar hours.
o Operating hour meter for consumers with 50/50 or 3/3 division to average
wear.
o Self-managed cloud solution based on FTP data transfer, backup of any data
and data volumes.
o File logger for recording any values in csv files.
o Bidirectional IP coupling with third party products.
o JSON / XML Parser for querying data from external sources.
o Calendar as a universal time switch with Outlook-like operation, activation /
deactivation via communication object, date series with adjustable repeat
patterns.
o Plotter with data recording of measured values in SQL-based databases,
without limitation.
o QR code Encoder for the display of coded information.
o Sequencer module for the control of any loads and load groups.
o SIP video door station graphically freely configurable
o Soft PLC can be used as often as required in the project, without limitation
of inputs, outputs and gates, including mathematical functions and
controller, including integrated simulation mode.
7. Managed Switch:
The managed switch shall be supplied by the client. The contractor is fully
responsible to make all needed coordination with the manufacturer.
PART 3 - EXECUTION
3.1 INSPECTION
3.2 INSTALLATION
C. Install each fixture properly and safely. Furnish and erect hangers, rods,
mounting brackets, supports, bases, cables, canopies, channels, frames, and other
equipment required.
D. Furnish lighting fixtures complete with appurtenances required for the proper,
safe and distortion-free installation in the various surfaces in which they appear.
F. Do not install fixtures and/or parts such as finishing plates and trims for recessed
I. Make splices in internal wiring with approved insulated "wire nut" type
mechanical connectors, suitable for the temperature and voltage conditions to
which they are subjected.
J. Use wire suitable for temperature, current, and voltage conditions to which it is
subjected where utilized for connections to or between individual lamp sockets
and lamp auxiliaries (i.e., wires which do not constitute "through circuit"
wiring).
L. Install all lighting units set true and free of light leaks, warps, dents, and other
irregularities.
N. Rigidly align continuous rows of lighting fixtures for true in-line appearance.
C. Certify that the equipment has been properly installed, adjusted, and tested.
Design Criteria
All the suppliers shall submit Lighting calculations using the latest version of DIAlux
lighting design software for all typical lighting installations of the project and for each
road based on the following parameters.
1. All Main roads shall be classified as M2, local roads shall be classified as M3.
2. The lighting poles height shall be as indicated on the plans.
3. The set back of the lighting poles shall be as indicated on the road cross
section.
4. The Bracket projection shall be maximum 1 mt. length and the inclination
shall be 5oC maximum.
5. The spacing between lighting poles shall be as indicated on the plan.
6. The maintenance factor shall be 0.7.
A. Standards shall be of hot dip galvanized steel poles as indicated on the drawings.
Foundations shall be of reinforced concrete; either cast in place or pre- cast and shall be
complete with the required anchor bolts, conduits. Anchor bolts shall be set from
template provided by the manufacturer of the lighting pole standard. Standards shall be
equipped with anchor bases and shall be designed to support the associated luminaires
with a reasonable factor of safety under a wind load equivalent to 150 kilometers per
hour. Arms shall accommodate luminaires. Shafts and bracket arms shall be wrapped
with a heavy water resistant paper for protection during shipment and erection.
B. Shaft. The steel shaft of the pole shall be fabricated from not less than 4 millimeter best
grade. The shaft shall have only one (1) longitudinal, automatically, electrically welded
joint and shall have no intermediate horizontal joints nor welds. Only one (1) length of
steel sheet shall be used, which shall be formed into a continuously tapered shaft, having
a taper of approximately 20 millimeters per meter or as supplier recommendation. After
forming and welding the tapered shaft shall be longitudinally cold rolled under sufficient
pressure to flatten the weld and increase the physical characteristics of the shaft so that
the metal will have a minimum. An opening shall be furnished near the top of the shaft
to provide a cable entrance from the shaft into the bracket arm. A special steel adapter
shall be welded into this opening providing a smooth cable guide for wiring and a
support for the attaching plate which is welded to the bracket arm. The pole top of the
shaft shall be secured in place by means of setscrews.
Each pole shall be provided with cable connection box and miniature breaker for
installation in pole with access door. The connection box shall be polycarbonate plastic
enclosure form for through wiring up to (3 x 35 + 25)mm2
C. Slider over base made of die cast Aluminum consists of three parts should be provided
as indicated on the drawings.
D. Bracket arms. The bracket arm assembly shall be as indicated on the drawings and
according to manufacturer standard and coordinated with the luminaries.
PART 1 - GENERAL
B. General Provisions for Electrical Work, Section 16010, applies to work of this
Section.
Work includes providing all materials, equipment and accessories, required for testing
and commissioning of all systems, equipments and services relating to the electrical
works.
B. In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
1.4 SUBMITTALS
B. Testing Sheets: Submit a recommended test and commissioning sheets as per IEE
wiring regulations 16th. Edition.
PART 2 - TESTING
A. The consultant shall inspect and test at the makers' works, during manufacture
and after completion, all or any particular manufactured material, apparatus or
equipment ordered by the contractor for incorporation in the works, in order to
prove that the material, apparatus or equipment meets the requirements of this
The contractor must arrange on his expenses for works tests to be attended by the
Owner's consultant for all tests specified in different sections of specifications.
B. The Contractor shall submit to the Owner's authorized Representative, at the time
of issue, three copies of each and every order for bought in material, apparatus
and equipment intended for incorporation in the works.
Each such order shall clearly state whether the item(s) which it covers is or are
subject to inspection or test before despatch to site.
D. The results of each and every test carried out in accordance with the provisions of
this specification shall be accurately and comprehensively recorded on a form of
test certificate signed by the person in charge of the testing procedure and
countersigned by the contractor and four copies of every such test certificate shall
be submitted to the Owner's Authorized Representative.
E. Every test certificate shall include, in addition to all other requirements the date
and time of the test, the ambient conditions, a fully detailed description of the
test(s) carried out, the results obtained, and any relevant performance curves.
F. The Contractor shall be responsible for ensuring that the Owner's authorized
Representative is advised in writing whenever material, apparatus or equipment is
ready for inspection or test at his own or his suppliers' premises. At least seven
days notice shall be given, and due allowance shall be made for this period of
notice in drawing up the program of works.
J. When the contractor has ordered equipment from a manufacturer who, in turn,
has bought-in major components from a secondary supplier, the Owner's
Consultant shall have the right to elect to inspect such components at the works
of the secondary supplier, and the contractor shall ensure, when placing his
orders, that such rights are secured.
For the purposed of this clause, inter-departmental orders within the same
organization shall be treated in the same manner as orders involving separate
organizations.
K. The Owner's Consultant shall have the right to waive, at his sole discretion, the
requirements relating to his inspection of materials, apparatus, and equipment at
the makers' works. The exercise by the Owner's authorized Representative of this
right shall not in any way relieve the contractor of his obligation to carry out the
prescribed tests and to submit test certificates.
L. No work shall be painted or otherwise prepared for despatch until it has been
inspected by the Owner's Consultant, or inspection has been waived and despatch
has been authorized.
M. When one or more of the Contractor's purchase orders covers the supply of a
number of like components or items of equipment, the Owner's authorized
representative shall have the right to select that one item or component of each
type and rating be subjected to type tests as described in the relevant National
Standard. Other similar items may then be subjected only to routine tests.
A. The Contractor shall carry out all necessary checks and tests to prove that the
completed installations fully comply with specified requirements.
C. All of the required checks and tests shall be carried out in accordance with a
program to be agreed with the Owner's Authorized Representative, and facilities
shall be made available for the Owner's Authorized Representative to be present
at all such checks and tests if he so desires.
E. Every test certificate shall include, in addition to all other requirements, the date
and time of the test, the ambient conditions, a fully detailed description of the test
(s) carried out, the result obtained, and any relevant performance curves.
G. No work shall have a final paint finish until it has been inspected by the Owner's
Authorized Representative or painting has been authorized, unless the final paint
finish is necessary to provide the necessary climate protection.
I. The Owner's Authorized Representative shall have the right to waive, at his sole
discretion, the requirements relating to his inspection of materials, apparatus
equipment and installations and the witnessing of tests thereon. The exercise by
the Owner's Authorized Representative of this right shall not in any way relieve
the Contractor of his obligations to carry out the prescribed tests and to submit
test certificates.
B. An insulation resistance test, carried out with a 'Megger' insulation tester or other
similar type of testing instrument, to measure the insulation resistance between
each conductor and the remaining conductors and between each conductor and
the metallic sheath, if any, and armouring. The test voltage to be applied shall be
as follows:
C. The above tests shall be carried out both before and after any voltage tests and the
insulation resistance shall not be less than the figures in BS 6346, Table, 6, for all
E. The Contractor shall submit proposals on the appropriate test voltage in respect
of other types of cable.
F. An earth continuity test shall be carried out to verify that the cable armouring and
metal sheath, if any, have been properly bonded to earth.
With all control circuits disconnected but with all isolators closed and power
fuses fitted, the panels shall be subjected to a voltage test across the following
points:
The voltage levels and test direction shall be in accordance with the relevant
National Standard for the equipment provided.
A. The Contractor shall inspect and carry out tests on all the system and equipment
earthing provisions in accordance with the requirements of the IEE Wiring
Regulations.
B. The method of test and the selection of suitable test instruments shall conform to
the guidelines given in the IEE Wiring Regulations, 16 th. Edition.
C. These tests shall be carried out on all system and equipment earthing supplied,
installed and connected under this Contract.
E. The Contractor shall inspect and re-test the system and equipment earthing
provided under this Contract thirty days prior to the end of the Defects Liability
period. The Contractor shall give the Owner's Authorized Representative seven
days notice of his intent to carry out these tests.
PART 3 - COMMISSIONING
(i) The energizing of electrical distribution circuits and equipments which have
previously been inspected, tested, found to be satisfactory and capable of being
energize with complete safety.
(ii) The setting of electrical protective devices and systems, where relevant, in
accordance with the directions of the Owner's Authorized Representative or,
failing such directions, in accordance with sound electrical engineering practice.
(iv) The verification of the performance of all such plant and equipment by the
carrying out, where required, of further tests and the making of all necessary
adjustments so as to obtain optimum performance.
B. Compliance with the requirements of this Section of the Specification shall not, by itself,
in any way relieve the Contractor of any of his obligations under the Contract.
C. The Contractor shall ensure that all connections and adjustments are made correctly, and
that the installations and equipment are in a completely safe and satisfactory condition.
F. The Owner's Authorized Representative shall have power to appoint and independent
Commissioning Engineer to act on his behalf in the control of all activities relating to the
commissioning process, and in such matters the said Commissioning Engineer shall be
deemed to be and authorized representative of the Owner's Authorized Representative
G. The Contractor shall be wholly responsible for ensuring that all switching operations and
all work on electrical circuits and equipment which have once been energized are carried
out in a thoroughly safe manner and shall operate, and rigidly adhere to, an approved
'permit-to-work' system. For this purpose, the Contractor shall appoint an 'authorized
person' as defined in the Electricity (Factories Act) Special Regulations, and shall
communicate the name of such person in writing to the Owner's Authorized
Representative.
J. If required by the Owner's Authorized Representative, the Contractor shall present the
information from the commissioning schedule in the form of a flodiagram or a PERT
('Critical Path') chart.
O. Following completion of commissioning, each item of equipment or, where several items
of equipment are interdependent, the complete plant shall operate continuously and
satisfactorily under normal operating conditions for a period of 72 hours without defect
of any kind. In the event of any defect or mal-operation becoming apparent during this
period the Contractor shall forthwith determine the cause and rectify it by means of
repair, replacement, adjustment or modification and the reliability run shall be re-
commenced. All materials, equipment and labour required to locate and rectify any such
defect shall be provided by the Contractor at his own expense.
Q. The Owner's Authorized Representative shall have power to require that the hole of the
plant, equipment and installations, or selected parts thereof, be re-inspected and, if
necessary, re-tested immediately before the end of the contractual maintenance period,
and the Contractor shall be responsible for making all necessary arrangements with the
Owner.
Division 16000:
1. Allied (U.S.A)
2. Wheatland (U.S.A)
3. Flexicon (U.K)
4. Burn (Thailand)
5. RYMCO (Mexico)
6. Halex (U.S.A)
3. Decoduct (Dubai)
5. Al-Rehab (Egypt)
1. Novo (Egypt)
2. Technological (Egypt)
Rev.01 August, 2018 List Of Recommended Manufacturers
Section 16999
Page 1 of 6
3. Emeco (Egypt)
4. Elswedy (Egypt)
1. Novo (Egypt)
2. Technological (Egypt)
3. Elswedy (Egypt)
1. Energya (Egypt)
3. Elswedy (Egypt)
4. GC3 (Egypt)
6. BICC (Egypt)
1. Raychem (U.S.A)
2. Elastimold (U.S.A)
1. CMP (Nickel steel type for multi-core cables and brass nickel type for single core
cable) (U.K)
2. PFLITSCH (Nickel steel type for multi-core cables and brass nickel type for single
core cable) (Germany)
3. Hawke (U.K)
1. Bticino (Italy)
2. Legrand (France)
3. M.K. (U.K)
4. Jung (Germany)
2. Legrand (U.K)
3. Eaton (U.K)
1. Siemens (Germany)
3. ABB (Germany)
4. Telemecanique (France)
2. Eaton (U.S.A)
3. Siemens (U.S.A)
4. Katko (Finland)
5. Socomec (France)
6. Square D (U.S.A)
1. ABB (Egypt)
2. Tesar (Italy)
3. El-Sewedy (Egypt)
4. Siemens (Germany)
1. ABB (Egypt)
2. El-sewedy (Egypt)
3. Emas (Egypt)
(Provided that all circuit breakers to be imported)
1. Furse (U.K)
3. Wallis (U.K)
2. ABB (Egypt)
(Provided that all circuit breakers to be imported)
3. Legrand (France)
4. GE (Poland)
5. Emas (Egypt)
(Provided that all circuit breakers to be imported)
16495 CONTACTORS
1. Lighting Fixtures :
General Electric (ERS) (U.S.A)
2. Lighting Poles:
INCO STEEL (Egypt)
EL-Sewedy (Egypt)
El-Babtin (Egypt)
3. Control system:
Phoenix contact
Schreder
Philips
Osram