Professional Documents
Culture Documents
(ME 2501)
UNIT - 2
Inventory Models
Activity Description Duration (in Immediate
weeks) predecessor
A Obtain the budget 2 -
approval
B Obtain the machine 5 A
C Hire the operator 1 A
D Install the machine 1 B
E Train the operator 6 C
F Produce the goods 1 D,E
A fast food chain wants to build four stores. In the
past, the chain has used six different construction
companies and, having been satisfied with each,
has invited each to bid on each job. The final bids
(in thousands of rupees) are shown in the following
table. Since the fast food chain wants to have each
of the new stores ready as quickly as possible, it
will award at most one job to a construction
company. What assignment results in minimum
total cost to the fast food chain?
Construction Companies
1 2 3 4 5 6
Store 1 85.3 88 87.5 82.4 89.1 86.7
Store 2 78.9 77.4 77.4 76.5 79.3 78.3
Store 3 82 81.3 82.4 80.6 83.5 81.7
Store 4 84.3 84.6 86.2 83.3 84.4 85.5
An oil company has recently acquired rights in a certain area to
conduct surveys and test drillings to lead to lifting oil if it is found in
commercially exploitable quantities.
1. Internal factors
(i) Technology Used
(ii) Capacity
(iii) Financial Position
(iv) Work Force Required
2. External Factors
(i) Economic, Political and Social Condition
(ii) Fixed and Variable Cost
(iii) Efficiency & Effectiveness
(iv) Productivity & Profitability
Facility Location - Introduction
When does a facility Location decision arise:-
4. If the shipping quantities for all destination points are equal, the
location at which the transportation cost will be minimum can
be identified by taking the arithmetic averages of the X and Y
coordinates of the destination. But if the shipping quantities are
unequal, the location can be found using a weighted average
approach (the quantities to be shipped are taken as weights).
Where,
Xc= X coordinate of the center of gravity
Yc = Y coordinate of the center of gravity
Vi = Volume of items transported to and from location i
Xi = X coordinate of location i
Yi = Y coordinate of the location i
Illuastration
Figure shows the X and Y coordinates of seven retail locations of a retail chain.
Information regarding the quantity to be shipped to each of the seven
locations is given in Table 1. Using the center of gravity method, identify the
coordinates of the optimal location for the warehouse.
Volume-weighted X Volume-weighted Y
coordinate = Xc= coordinate = Yc =
Product layouts
Process layouts
Fixed-Position layout
Combination layouts
Basic Layout Types
Product layout
Layout that uses standardized processing operations to achieve
smooth, rapid, high-volume flow
Process layout
Layout that can handle varied processing requirements
Fixed Position layout
Layout in which the product or project remains stationary, and
workers, materials, and equipment are moved as needed
Product Layout
Raw Finished
Station Station Station Station
materials 1 2 3 4 item
or customer
Material Material Material Material
and/or and/or and/or and/or
labor labor labor labor
In 1 2 3 4
Workers
Out 10 9 8 7
Process Layout
Process Layout
(functional)
Cellular Production
Layout in which machines are grouped into a cell that can process
items that have similar processing requirements
Group Technology
The grouping into part families of items with similar design or
manufacturing characteristics
Functional vs. Cellular Layouts
67
STRING DIAGRAM
68
69
EXAMPLES
1. STORING TILES (ORIGINAL)
2. STORING TILES (IMPROVED)
70
FLOW DIAGRAM
71
TRAVEL CHART ( or, FROM-TO CHART)
72
EXAMPLE I
73
74
EXAMPLE II
Eight mixing machines are used to mix materials in different proportions, the final
mixtures being taken to an inspection bench (station 6). The mixes were transported
in 25 litres cans, which were placed on pallets and moved by a low lift truck
RECORD –
Movements are recorded on the shop floor on a study sheet of the type shown in the
next slide.
The entries show not only the journeys made but also the number of cans carried on
each trip.
75
76
77
78
79
80
Design Product Layouts: Line Balancing
OT
Output capacity =
CT
OT
CT = cycle tim e =
D
Determine the Minimum Number
of Workstations Required
(D)(å t)
N =
OT
c d e
0.7 min. 0.5 min. 0.2 min.
Example 1: Assembly Line Balancing
Revised
Time Assign Time Station
Workstation Remaining Eligible Task Remaining Idle Time
1 1.0 a, c a 0.9
0.9 c c 0.2
0.2 none - 0.2
2 1.0 b b 0.0 0.0
3 1.0 d d 0.5
0.5 e e 0.3 0.3
0.3 - - 0.5
Calculate Percent Idle Time
0.8 0.6
c d f g h
1.0 0.4 0.3
Solution to Example 2
a b e
f g h
c d
Parallel Workstations
Bottleneck
60/hr. 60/hr.
1 min. 1 min. 1 min.
30/hr.
1 min. 30/hr.
Parallel Workstations
Designing Process Layouts
Information Requirements:
1. List of departments
2. Projection of work flows
3. Distance between locations
4. Amount of money to be invested
5. List of special considerations
6. Location of key utilities
Example 3: Interdepartmental Work Flows
for Assigned Departments
30
170 10
1 3 2
0
A B C
Process Layout
Milling
Assembly
Grinding
& Test
Drilling Plating
Process Layout - work travels
to dedicated process centers
Assembly line balancing: Example
An activity consisting of three tasks: A, B and C.
ü Task A is first, and takes 0.5 minutes
ü Task B is next, and takes 0.3 minutes
ü Task C is the last, and takes 0.2 minutes.
96
Assembly line balancing: Example
Suppose that one worker performs all three tasks
(sequentially).
Then in an 8-hour shift, the worker could produce –
480 parts/day.
How?
97
Assembly line balancing: Example
Now suppose, three workers are assigned for the line, each
performing one of the tasks.
The first operator can produce 120 parts per hour, since the
task time is 0.5 min. Thus, a total of 960 parts/day.
The second worker takes only 0.3 min to finish the tasks
and hence can produce 1,600 parts/day.
Lastly, the third worker can produce 2,400 parts/day.
However, the second worker cannot produce 1,600 parts
because the first worker has a lower production rate. So the
second worker is idle some of the time waiting on
components to arrive from the first operator.
98
Assembly line balancing: Example
Same thing happens for the third worker.
So the maximum output of this three-operator assembly
line is 960 parts/day.
That is, the workstation 1 performing task A is a bottleneck
in the process.
99
Assembly line balancing: Example
Now suppose that two workers are assigned to the
assembly line.
The first operator performs task A; and the second operator
performs tasks B and C.
Now, since each operator needs exactly 0.5 min to complete
the assigned duties, the line is said to be balanced and the
production is 960 parts per day.
Thus, we have achieved the same output (of 960 parts)
using just two operators.
100
Assembly line balancing
Cycle time
The interval between successive outputs coming off the
assembly line.
In the previous example, if we use only one operator, the
cycle time is 1 minute. One completed assembly per
minute.
If two workstations are used, the cycle time is 0.5 minutes.
Finally, if three workstations are used, the cycle time is still
0.5 minutes. Task A is the bottleneck. Thus, the line can
produce only one assembly every 0.5 minutes.
101
Assembly line balancing: Cycle time
The cycle time cannot be smaller than the largest operation
time, nor can it be larger than the sum of all operation times.
Max. operation time £ CT £ Sum of operation times.
102
Assembly line balancing: Cycle time
However, if the required cycle time (based on the required
production rate) is smaller than the largest task time, then
the work content must be redefined by splitting some tasks
into smaller elements.
Alternatively, R = A/CT.
That is, for a given cycle time, we can determine the output
rate that can be achieved.
In the example, the shift has 480 minutes.
So for one-station configuration, R = 480/1.0 = 480
parts/shift
And for a two-station layout, R = 480/0.5 = 960 parts/shift.
103
Assembly line balancing: Equations
Sum of task times
Min. # of workstations required =
Cycle time
=
å t
CT
Total time available = (# workstations)(CT ) = N ´ CT
Total idle time = N ´ CT - å t
104
Product layout and work allocation problem
Standard services can be divided into sequence of steps that
all customer have to go through.
Resembles manufacturing assembly line.
The job requiring most time per customer is the bottleneck.
A well-balanced line would have all jobs of nearly equal
duration.
Grouping of activities (operations) should focus on line-
balancing and avoiding bottlenecks.
Additional stations at the bottleneck could also be
considered.
e.g. Himalaya mess layout.
105
Work allocation at an airport
3 2, 4
(40, 90) (40, 90)
1 5 6
(20, 180) (18, 200) (15, 240)
3 2, 4
(40, 90) (40, 90)
107
Facility design
Direct correlation between operations and facility design.
Design and layout represent the supporting facility
component of service package.
Factors influencing facility design: Nature and objective of
organization; land availability; flexibility; security;
aesthetics; community and environment.
108
Facility design factors
Nature of organization: The core service offered should
dictate the parameters of design. Appropriateness of design
also important.
e.g. Physician’s office should give patients privacy while
undergoing medical check-up.
Would you open an account in a bank which operates out of a
tin-shade?
109
Facility design factors
Flexibility: Design should be dynamic to allow for future
growth and changes in services.
e.g. Parking lot for a restaurant.
110
Cellular Manufacturing Layout
Heat Gear
-1111 Lathe Mill Drill -1111
treat cut
Heat
222222222 Mill Drill Grind - 2222
Assembly
treat
Heat
3333333333 Lathe Mill Grind - 3333
treat