Professional Documents
Culture Documents
Theory-Based
22 Evaluation of
Public Private
Partnership Projects
and Programmes$
Mehmet Uzunkaya
ABSTRACT
The purpose of this chapter is to discuss theory-based evalua-
tion of public private partnership (PPP) projects/programmes
and to develop an intervention logical framework. It aims to
draw attention to the need to go beyond the measurement of
project/programme results to address not only the question of
whether or not the project/programme worked but also the
how and why questions. The study follows an interpretative
methodology. It analytically discloses the mechanics of theory-
based evaluation in relation to a ‘PPP theory’ and describes a
theory-based analytical framework that portrays an explicit
path towards ultimate impacts so as to assess, in a more system-
atic and integrated way, the success or failure of a PPP. Theory-
based evaluation is a promising evaluation approach that
would fit into the complexities of PPP projects/programmes
and would expand the available toolbox of evaluators. Proper
$
The usual disclaimer applies: The views, opinions, findings,
conclusions and errors in this chapter are strictly those of the author.
579
580 MEHMET UZUNKAYA
Introduction
This chapter discusses theory-based evaluation of public private
partnership (PPP) projects/programmes and proposes an interven-
tion logical framework. It aims to draw attention to the need to
go beyond the measurement of project/programme results to
address not only the question of whether or not the project/pro-
gramme worked but also the how and why questions.
Specifically, it describes a theory-based analytical framework that
portrays an explicit path towards ultimate impacts so as to
assess, in a more systematic and integrated way, the success or
failure of a PPP. In this way, evaluation would contribute to bet-
ter policy formulation and project implementation by exploring
and drawing lessons through tracking cause effect relations in
the design and execution of PPP project/programmes.
Evaluation of PPPs in the current practice generally follows
the traditional approach that utilizes the DAC criteria.1 The
1
OECD Development Assistance Committee (DAC)’s five evaluation cri-
teria are relevance, effectiveness, efficiency, impact and sustainability.
According to OECD (2000), relevance reflects ‘The extent to which the
objectives of a development intervention are still consistent with the tar-
get group’s needs and priorities and the partner’s and donor’s policies’;
effectiveness is ‘A measure of the extent to which a development inter-
vention has attained its objectives at the goal or purpose level’; efficiency
is ‘A measure of how economically inputs (funds, expertise, time, etc.)
are converted to outputs’; impact is ‘The positive and negative changes
produced by a development intervention, directly or indirectly, intended
or unintended’, and sustainability is ‘The continuation of benefits from
a development intervention (such as assets, skills, facilities or improved
services) after major development assistance has been completed’.
Theory-Based Evaluation of PPP Projects and Programmes 581
Assumptions:
1-Political support is objective, not interventive External Factors:
2-Creating capacity in the public sector leads to sound project management 1-Global financial situation
3-Flexible contracts facilitate better project management 2-Global economic growth
4-Project financing reduces agency costs and asymmetric information and solves the underinvestment problem. 3-Global interest rates
5-The counterfactual is direct public administration subcontracting
585
Figure 1. Intervention Logic for a PPP Programme in Transport Sector. Source: The Author.
586
THE DAC CRITERIA THE DAC CRITERIA (CONT’D)
1-RELEVANCE (To assess the relevance criterion the evaluator first constructs a “normative intervention logical 4-IMPACT
framework’’ for the program or project in question) - What are the real changes, (positive, negative, intended, unintended, direct, indirect) as a result of the PPP
- Whether the intervention logic of the program evaluated is consistent with the “normative intervention logic” project/program?
- Are there lacking elements in the evaluated program’s logic with reference to the “normative intervention logic” -Whether the PPP project/program has decreasing effects on logistic costs
MEHMET UZUNKAYA
- Whether the evaluated logic’s objectives consistent with sectoral policies? -Whether the PPP project/program contributes to increased mobility
2-EFFECTIVENESS -Whether the PPP project/program contributes to growth and international competitiveness
- Were objectives of the evaluated logic achieved? (e.g. Reduced VOCs, accidents, happier users, increased firm -Whether the PPP project/program contributes to increased service delivery and spatial development
value, more efficient system, reduced GHGs) -Whether the PPP project/program contributes to cleaner air and better environment; what are the
3-EFFICIENCY environmental effect?
- Were the achieved objectives cost efficient? In other words, whether the PPP program achieved value-for- -Whether the PPP project/program contributes to increased quality of life and welfare
money as compared to the counterfactual 5-SUSTAINABILITY
-Value of faster construction and earlier start of operations as compared to counterfactual -Whether the system is financially sustainable
-Value of additional time savings as compared to counterfactual -Whether the system is economically sustainable
-Value of additional accident reduction as compared to counterfactual -Whether the system is socially sustainable
-Value of vehicle operating cost (VOC) savings as compared to counterfactual -Whether user charges are affordable
-Whether the special purpose vehicle’s (SPV) financial situation is sustainable
BENCHMARK DEFINITIONS
ACTIVITIES
Pipeline of Sound Projects: A list of projects that have been tested for pre-feasibility and prioritized based on their respective net benefits and contributions to the collective transport system.
High-Quality Feasibility: A report that includes objective and scientific analysis of a PPP project from technical, legal, financial, economic, environmental and political perspectives; an assessment of incremental benefits, costs
and their distribution among key stakeholders; analysis of uncertainties, risks and their allocations among parties involved.
Sound Procurement: Procurement that is consistent with the needs of the procuring authority and with the approved feasibility of a PPP project.
Sound Risk Allocation and Management: Allocation of risks among stakeholders of a PPP projects such that each party is responsible for the risk that it is best able to manage.
Conductive and Robust Regulatory Framework: A legal framework that clearly defines mandates, responsibilities and accountables in PPP project and program implementation; includes necessary procedures to ensure economy,
effectiveness and efficiency; embraces clear guidelines for contract administration, conflict resolution, tariffs, subsidies, affordability and termination.
Flexible Contract: A PPP contract that is able to accommodate changes in variables that critically affect the feasibility of a PPP project during its economic life without compromising the overall feasibility, interests of key
stake holders and fair competitive conditions at the procurement stage.
OUTPUTS
Economic, Effective and Efficient Project: Projects constructed on time (also entering into the operational stage faster as compared to the counterfactual-direct public administration subconstructing-as a result of the incentives
that engage private sector to do so) and on budget and are able to function according to the intended purpose with an optimal cost-benefit balance.
Better Service Quality: Better provision of services as a result of private sector efficiency and competence.
Affordable Construction and Services: Cost of construction and services that are reasonably priced and commensurate with the level of provision they offer.
Financially Sound and Sustainable Projects: Projects having current and future cash inflow generation capacity and ability that are reasonably greater than cash outflows at a margin commensurate with international standards.
Reduced Agency Costs: Reduced conflicts of interest between shareholders of a sponsor and the management, as a result of the establishment of a separate special purpose vehicle (SPV) in PPPs (and thus increased value of the
firm).
Reduced Underinvestment Problem: Sponsors not forgoing (+)NPV projects; so as to maximize the wealth of shareholders, as a result of the establishment of a separate special purpose vehicle (SPV)
in PPPs (and thus increased value of the firm.)
Reduced Asymmetric Information: Reduced differences in information between sponsors and creditors as a result of the establishment of a separate special purpose vehicle (SPV) in PPPs.
Socioeconomically Sound Project: Projects having present value of social and economic benefits outweight the present value of social and economic costs.
Environmentally Sound Project: Projects having negative environmental externalities eliminated, minimized or reasonably compensated for.
On-budget Construction: Ex-post construction costs being in line with expected costs.
Public Side Interests: Interests spanning through general public welfare.
Private Side Interests: Interests of the sponsors and creditors.
OUTCOMES
Incremental Economic Benefits: Economic benefits net of economic costs (such as time savings, vehicle operating cost savings, accident avoidance) generated by the project throughout its useful life.
Efficient Transport System: A transport system in which alternative modes operate in harmony with each other at their financial and economic optimal.
Increased Firm Value of Sponsors: Increased share price of a sponsor as a result of reduced agency costs, elimination of underinvestment problem and asymmetric information.
Increased Public Sector Creadibility: Sense of success among citizens about public administrations due to increased satisfaction of users as a result of faster construction of project; and affordable and high-quality services.
IMPACTS
Increased Mobility: More efficient and comfortable movement of people and goods as a results of the PPP project’s (or PPP programme’s) incremental contributions to the system
Reduced Logistics Costs: Reduced cost of logistic services as a result of a more efficient transport system due to the PPP project’s (or PPP programme’s) incremental contributions to the system.
Growth-supporting Transport System: A transport system facilitating economic operations and contributing to value added in the economy.
Competitiveness-supporting Transport System: A more efficient transport system as compared to competitors, facilitating economic operations and thus contributing to increased competitiveness.
Figure 1. (Continued )
Theory-Based Evaluation of PPP Projects and Programmes 587
Theory-Based Evaluations
Even though its origins go as far back as 1930s, theory-based
evaluation has become a well-known approach after Chen’s influ-
ential book in 1990, Theory-Driven Evaluations (Coryn,
Noakes, Westine, & Schröter, 2011). Weiss (1995) also contrib-
uted substantially to the prominence of this approach in the eval-
uation community. After Chen (1990) and Weiss (1995), a rich
body of literature has developed on theory-based evaluations
(e.g., Astbury & Leeuw, 2010; Birckmayer & Weiss, 2000;
Chen, 2006, 2012; Coryn et al., 2011; Donaldson, 2005; Lipsey,
1993; Mercier, Piat, Peladeau, & Dagenais, 2000; Rogers, 2007,
2008; Rogers, Petrosino, Huebner, & Hacsi, 2000; Scriven,1998;
Sidani & Sechrest, 1999; Stame, 2004; Van Der Knaap, 2004;
Weiss, 2000; White, 2009). The following is a summary of the
main arguments supported by the two pioneering works of Chen
(1990) and Weiss (1995). These two works will be discussed rela-
tively longer as they lay the foundation for the subject matter.
Chen (1990)’s main argument was that theory, which plays
an important role in research to analyse and understand the sig-
nificance of research findings, had been thus far neglected in pro-
gramme evaluation. Most of the evaluation studies were lacking
a sound theory development and characterized by the prevalence
of input/output type of approaches. This type of evaluation, he
argues, focuses mainly on the overall relationships between the
inputs and outputs of a programme, neglecting the ‘transforma-
tional processes in the middle’. In this way, a gross assessment
of whether or not the programme worked can be made; however,
the underlying causal mechanisms cannot be understood.
Therefore, classical evaluation approaches are not able to answer
the how and why questions that enlighten the cause effect rela-
tions in the micro stages of a programme. Such black-box types
of evaluations do not provide insights about the relationships
between delivered/planned treatment, between official/operative
goals or between intended/unintended effects.
Chen asserts that, notwithstanding the contributions in many
aspects, the emphasis on scientific research methods and method-
ological issues in the early efforts of programme evaluations
resulted in an ignorance of the implications of programme the-
ory. In addition, the debates about whether qualitative or quanti-
tative methods should be used in evaluations also reinforced
the reputation of method-oriented approaches. This debate in
588 MEHMET UZUNKAYA
✓ Implementing organization
✓ Programme implementers
Theory-Based Evaluation of PPP Projects and Programmes 589
INPUTS
Inputs are the resources that the project or programme will need
to achieve its intended results. In a PPP project/programme, pub-
lic sector technical, financial, economic and regulatory capability
and expertise are critical inputs. Public sector uses these resources
to prepare, appraise, implement and evaluate PPP projects/
programmes. Similarly, private sector technical and finance
expertise contribute to sound PPP arrangements. One of the main
rational justifications of PPPs is the utilization of private sector
expertise in public investment projects.
The same is true for the construction and technical consul-
tancy as well as financial sector capacities. Construction sector’s
capacity feeds into on-time and on-budget completion of the PPP
facility. It is also critical that the PPP facility is constructed in line
with the standards specified by sponsors and lenders. During the
construction stage, technical consultancy sector plays a critical
role in supporting sponsors and public sector in technical aspects
of the construction. Financial sector capacity is important not
only in terms of providing debt and equity financing but also
in terms of the financial appraisal and due diligence of the project
in question.
Political will and support is another critical input for successful
PPPs. PPP programmes include a variety of organizations,
596 MEHMET UZUNKAYA
ACTIVITIES
Activities are the actions that are taken to bring about a desired
end (Coryn et al., 2011). Utilizing the inputs available, the
proposed intervention logical framework includes the following
activities.
Developing a pipeline of sound projects facilitates the
achievement of intended results of a PPP programme. The list of
possible projects should be developed on the basis of objective
criteria that would eliminate at the outset those projects that
are economically, financially and/or environmentally infeasible.
A sound project pipeline would also help timely preparation
and assessment of project documents (such as feasibility reports,
preliminary designs, environmental assessments), for which
sometimes adequate time and resources are not devoted to meet
strict time constraints.
PPPs require a multidisciplinary approach and complex
procedures as compared to conventional public procurement.
However, public-sector capacity to manage such demanding pro-
cesses is not always in place, especially in developing countries.
Therefore, it is vital to create PPP awareness and capacity in the
public sector. In spite of its promising potential, PPP method is
Theory-Based Evaluation of PPP Projects and Programmes 597
OUTPUTS
As a result of the activities described in the previous section, the
following outputs are expected: Projects implemented would
comply to time, cost and quality requirements. In other words,
effective and efficient projects that generate economic and finan-
cial benefits will be implemented. The projects will provide better
and affordable services with minimal or no construction cost
overruns. Economic and financial robustness along with on-
budget construction will bring financial sustainability.
As discussed earlier, at the heart of PPP arrangements is the
notion of project financing, which is a product of financial
Theory-Based Evaluation of PPP Projects and Programmes 599
OUTCOMES
Outcomes are direct or indirect changes that are expected from a
project/programme as a result of inputs, activities and outputs
(Coryn et al., 2011). While outcomes can be initial, intermediate
and long term (Coryn et al., 2011); this study is more interested
in long-term outcomes that are related to the needs of a PPP proj-
ect/programme’s target population.
Before going into the details of the expected outcomes, it
is necessary to note that they are assessed as compared to a coun-
terfactual. A counterfactual is the state that would prevail in the
absence of the project/programme in question. In a sense, it is the
‘without project/programme’ situation.
One of the most important outcomes of a successful PPP
arrangement is the generation of incremental economic benefits
as compared to the counterfactual. Here, an obvious counterfac-
tual would be the classical public procurement. In a transport
PPP project/programme (as is the case in our implementation
framework), for instance, vehicle operating costs would be
reduced as compared to counterfactual as a result of faster
construction and earlier accrual of benefits to the economy.
In a similar vein, traffic accidents would be reduced as compared
to counterfactual as the project would get into the operation
stage earlier. Another incremental benefit would be that users
would be more satisfied with the service they use as a result
of the physical quality of the investment and private sector
operating efficiency.
The efficiency on the project and more importantly on the
programme level would contribute to a more efficient transport
600 MEHMET UZUNKAYA
IMPACTS
On the impact level, the PPP project/programme with the
described outcomes contributes to increased mobility and
reduced logistic costs as a result of increased system efficiency
and effectiveness. Such a transport system supports higher
economic growth and improved international competitiveness.
A more efficient transport system with improved service delivery
and spatial development will lead to better environment and
cleaner air. Ultimately, the transport system would contribute
to increased user utility, quality of life and welfare.
Conclusion
This chapter investigates theory-based approaches in evaluating
PPP projects/programmes and proposes an intervention logical
framework. The aim is to draw attention to the need to go
beyond the measurement of project/programme results to address
not only the question of whether or not the project/programme
worked but also the how and why questions.
The study argues that theory-based evaluation is a promising
evaluation approach that would fit into the complexities of PPP
projects/programmes and would expand the available toolbox
of evaluators. The complexities inherent in both PPPs and
theory-based evaluations can be dealt with by designing norma-
tive intervention logical frameworks that include critical cause
effect channels, backed by theoretical and empirical foundations,
in a PPP intervention.
This chapter formulates a PPP theory, based on which a nor-
mative intervention logical framework is constructed. The frame-
work includes inputs, related activities, outputs, outcomes and
impacts, collectively forming a change model which describes the
causal processes in a PPP intervention. The causal processes
mainly draw on a combination of project finance theory and the
notion of public investments in relation to PPPs, which altogether
make it possible to define the micro stages of cause effect
relations in detail.
The proposed framework is designed for a representative
sector, transport, but can easily be adapted to other sectors that
PPPs are used. The aim here is to make an exercise on whether
theory-based approaches can be practically applied to the evalua-
tion of PPP interventions.
This study has considerable policy implications: First, devel-
oping countries should give upmost importance to the evaluation
of PPP projects and programmes. Given the exploding popularity
of PPP projects/programmes in developing countries, their timely
602 MEHMET UZUNKAYA
Acknowledgements
I would like to thank Robert Picciotto and Fredrik Korfker
for their editing contributions for a much shorter article ver-
sion of this chapter, which was published in Evaluation
Connections (Uzunkaya, 2016) of the European Evaluation
Society. The intervention logical framework presented in this
chapter took its final form, following the author’s initial pro-
posal, as a result of some amendments after a series of dis-
cussions in the Thematic Working Sub-Group on Evaluation
of PPPs within the European Evaluation Society. In this
respect, I would especially like to thank Dr. Nicolas Mathieu,
Dr. Danielle Nel and Fredrik Korfker for their helpful com-
ments and contributions.
References
Astbury, B., & Leeuw, F. L. (2010). Unpacking black boxes: Mechanisms and
theory building in evaluation. American Journal of Evaluation, 31(3), 363 381.
Birckmayer, J. D., & Weiss, C. H. (2000). Theory-based evaluation in practice
what do we learn? Evaluation Review, 24(4), 407 431.
Chen, H. T. (1990). Theory-driven evaluations. Newbury Park: Sage.
Chen, H. T. (2006). A theory-driven evaluation perspective on mixed methods
research. Research in the Schools, 13(1), 75 83.
Chen, H. T. (2012). Theory-driven evaluation: Conceptual framework,
application and advancement. In Evaluation von Programmen und Projekten
für eine demokratische Kultur (pp. 17 40). Germany: Springer Fachmedien
Wiesbaden.
Theory-Based Evaluation of PPP Projects and Programmes 603