Professional Documents
Culture Documents
0|Page
Table of Contents
1.0 THE PROJECT ............................................................................................................................ 2
1.1 Description and location ...........................................................................................................2
2.1 Land use ......................................................................................................................................2
2.1.1 Land Use Strategy ..................................................................................................................3
2.2 Development parking demand ................................................................................................3
2.2.1 General parking demand ......................................................................................................3
3.0 DESIGN REQUIREMENTS ....................................................................................................... 4
4.0 VOLUME TRAFFIC SURVEYS ............................................................................................... 4
4.1 Data collection.......................................................................................................................4
4.2 Survey Methodology and Analyses criteria .....................................................................5
4.3 Traffic Forecasting .....................................................................................................................6
4.3.1 Normal Traffic Volume and Composition ...........................................................................6
4.3.2 Floor Areas and Traffic generation rates .............................................................................9
4.4 Growth Rate.............................................................................................................................9
4.4.1 Future Traffic Generators ..................................................... Error! Bookmark not defined.
5.0 CONCLUSIONS AND RECOMMENDATIONS ....................................................................... 14
1|Page
1.0 THE PROJECT
Figure 1 below shows the location of the proposed area earmarked for the development.
Figure 1: Location map
Proposed Access
An access road to the development by the traffic traversing (B25) road has been proposed as
shown in figure 2 below
Figure 2: Proposed access point to the development
2|Page
A breakdown o f the proposed land use by intensity is presented i n able below while the
detailed development scheme Master Plan is provided in Appendix A
The parking requirements for individuals with disability for each parking location are
determined using the rates defined by the American with Disability Act (ADA) as presented in
the Table 3 below.
Table 3: General Parking Demand
Demand/Supply Requirements
1-26 1
26-50 2
51-75 3
76-100 4
101-150 5
151-200 6
201-300 7
3|Page
301-400 8
401-500 9
501-1000 2 percent of the total
1001 and over 20 plus 1 for each 100 over 1000
Source: ADA, Accessibility Guidelines for Buildings and Facilities (ADAAG, 2002).
Based on the above estimates, the development will require a total of not less than 1 parking
spaces dedicated to people with disabilities for the convenient shop
The above requirements form a basis for the Access road design and is important when one takes
into consideration the comfort, convenience and safety when entering or leaving the premises
developed along the main road. Circumstances where the motor vehicles are required to slow
down prior to turning onto the locations of interests may result into traffic snail up and
eventually lead to traffic jam for about 4-5 minutes only.
The proposed development is expected to have some impact on the existing road network. The
extent of the impact is expected to be experienced at the access to the proposed service station.
The proposed access to the service station to be carried out by the Developer who will ease the
traffic access to the station. The Developer will do acceleration and deceleration lanes (85M and
3.5M wide lane each) to ease access into and out of the station. In addition, the drainage along
the deceleration and acceleration lanes will be done to cater for storm drainage from the station.
The site for the proposed fuel service station is adjoined by Karatina-Kutus Road (B27) which
runs in a north-west-wards towards Kagumo from Kerugoya. Currently, Karatina-Kutus Road
(B27) is a 2 lane, 2 way single carriageway road, which are under Performance Based
Maintenance by the Kenya National Highways Authority (KeNHA).
Manual traffic data collection survey was undertaken from 6th of September through to 12th
September 2022 for sixteen (16) hours, i.e. from 6:30am – 6:30am at 2 Locations shown in
4|Page
Figure 4 below. The counts for less than 24 hours are the grossed up to 24 hours since the night
hours after 22.00 hrs showed negligible traffic. The traffic was converted to 24 hrs using the
24hour/16-hour traffic ratio.
Figure 4: Traffic survey locations
5|Page
Pick-ups, Jeeps, 4WDs, Vans All pick-ups, 4 WD cars and private vans
Matatus and Minibuses All public service mini-buses with seating capacity less than 45
Buses All public service buses with seating capacity more than 45
Light Goods Vehicles (LGV) All trucks with maximum laden weight of 5 tonnes
Medium Goods Vehicles All trucks with 2 axles and laden weight more than 5 tonnes
(MGV)
Heavy Goods Vehicles (HGV) All trucks with 3 – 7 axles
Other Vehicles Tractors, construction equipment, etc
6|Page
Table 5: 1.Near KPLC Substation Kagumo along (B27) Karatina-Kutus Road;
Time (Day/Night) 06/09/2022 07/09/2022 08/09/2022 09/09/2022 10/09/2022 11/09/2022 12/09/2022 TOTAL ADT
Motor cycles & Tuk-Tuk 386 471 404 378 393 409 473 2914 416
Medium Cars/ Saloon car 825 818 844 850 865 849 820 5871 839
(private cars)
Large Cars (4 x 4, Jeeps) 605 546 706 516 531 711 548 4163 595
Matatu (Max. 14 pass.) 500 488 515 429 444 520 490 3386 484
Light Truck Rigid (2-axles) 198 205 209 196 211 214 207 1440 206
Medium Truck Rigid (2- 312 324 329 320 335 334 326 2280 326
Axles)
TOTAL 3,038 3,045 3,216 2,907 3,055 3,266 3,061 21,588 3,084
7|Page
Table 6: 1. Near the proposed site along (B27) Karatina-Kutus Road
Time (Day/Night) 06/09/2022 07/09/2022 08/09/2022 09/09/2022 10/09/2022 11/09/2022 12/09/2022 TOTAL ADT
Motor cycles & Tuk- 402 351 277 211 364 304 205 2114 302
Tuk
Pedal Cycles 16 14 16 11 15 10 8 90 13
Medium Cars/ Saloon 725 786 773 689 625 706 571 4875 696
car (private cars)
Large Cars (4 x 4, 605 534 630 530 529 605 526 3958.5 566
Jeeps)
Matatu (Max. 14 pass.) 457 426 454 268 538 463 266 2872 410
Light Truck Rigid (2- 222 218 256 148 68 270 175 1357 194
axles)
Medium Truck Rigid 367 376 369 156 62 300 238 1868 267
(2-Axles)
Heavy Truck Rigid (3 or 111 101 103 58 39 86 102 600 86
4 Axles)
Articulated Truck, (3, 4, 40 43 44 26 20 40 35 248 35
5 or 6 Axles)
Others (Tractors, 2 3 1 2 0 2 0 10 1
Construction
Equipment)
TOTAL 2,990 2,871 2,943 2,111 2,280 2,805 2,138 18,138 2,591
8|Page
4.3.2 Floor Areas and Traffic generation rates
The proposed Fuel Service Station will be a mixed-use development. Table 7 below shows the
gross floor areas and usage.
Table 7: Proposed floor uses and areas
Floor use Area (M2)
1 Convenience Store 95 Sq m
2 Service Centre 120 Sq m
3 Resturant 250 Sq m
Generated/attracted traffic due to the developments was computed using the proposed Gross
Floor Areas (GFA) in accordance with the recommended traffic generation rates by the Institute
of Transportation Engineers (ITE) of the United States of America. The traffic generation rates in
Table 4 are considered conservative as car ownership and usage rates in the United States of
America are much higher than in Kenya. It is therefore reasonable to expect better actual levels
of service (LOS) if acceptable theoretical LOS is computed using the Highway Capacity Manual
(HCM) approach.
4.4.1.1 Introduction
In order to determine the traffic growth rates to be used in forecasting future traffic, data from
Kenya National Bureau of Statistics (KNBS) on national licensed vehicles trend over the years
and economic growth were also used to project traffic.
9|Page
2006 372530 195153 69716 50242 40010
2007 410812 202671 75347 55997 41803
2008 450137 209628 81285 61886 43485
2009 499679 219901 91431 84844 27039
2010 553397 226876 96355 89708 29418
2011 591958 234427 100180 91627 32002
2012 644805 242372 108001 93343 35763
2013 709812 252188 117570 95644 39736
2014 779256 277324 128251 98067 42661
2015 847745 290702 142036 100990 46566
2016 906358 303924 151668 103268 53802
Source: Economic Survey, 2020, Kenya National Bureau of Statistics, Ministry of Planning and
National Development
*Data for the year individual vehicles classes for 2017-2020 not released in report.
The exponential growth rate model was adopted for the analysis of the above data.
i Growth rate
It is difficult to model the equation in its current form. The equation can be converted to linear
form by taking its natural logarithm as follows:-
By plotting LNYt against t , the gradient of the line of best fit is equal to LN 1 i . The rate of
growth can therefore be calculated as:-
10 | P a g e
Table 3.4.2.2: Licensed vehicles growth factors
Vehicle Type Growth Rate (%)
Cars 8.95
Utilities, Panels, Vans, Pick-ups 4.40
Lorries, Trucks, and Heavy vans 7.64
Buses and Mini Buses 6.93
Trailers 2.56
Average 6.10
11 | P a g e
Table 3.4.4.1 Growth in GDP
GDP Growth 4.6 5.9 5.4 5.7 5.9 4.8 6.3 5.4
(%)
Induced traffic was considered as that traffic that would be entirely new and never existed before
due to increased accessibility of the area. It was noted that there is a possibility of developments
attracted by the improved condition of the road. These would comprise of market centres,
residential houses, institutions and increased commercial farming activities. From the socio-
economic analysis of the region, I considered generated traffic to constitute 6.0% (Average GDP
growth rate) of the year 2019.
Using average traffic collected in the seven days, a projected traffic (projected ADT) was
calculated as shown below. Projected traffic was considered for the next 10 years.
12 | P a g e
An exponential growth of traffic shall be anticipated and estimated using the formula below:
Tn=T0 (1+r)n
13 | P a g e
Total traffic in April 2023 when the development is expected to be complete and operational
was computed as the sum of generated and forecasted normal traffic at a 6% growth rate
indicated on the table above between years 2021-2036.
Table 14: Estimated traffic growth rates for normal traffic
Base Traffic
(2022) – (80% of Projected Traffic Projected Traffic
sum traffic for after 10yrs after 15yrs
Vehicle Type both directions (2032) (2037)
on heavier
Motor cycles & Tuk-Tuk station) 416 746 998
Pedal Cycles 25 45 60
Medium Cars/ Saloon car
839 1502 2010
(private cars)
Large Cars (4 x 4, Jeeps) 595 1065 1425
Matatu (Max. 14 pass.) 484 866 1159
Bus (Max. 50-60 pass.) 35 63 85
Light Truck Rigid (2-
206 368 493
axles)
Medium Truck Rigid (2-
326 583 781
Axles)
Heavy Truck Rigid (3 or 4
99 177 236
Axles)
Articulated Truck, (3, 4,
57 102 137
5 or 6 Axles)
Others (Tractors,
3 6 8
Construction
Equipment)
TOTAL 3,084 5,523 7,391
Based on the study, the average daily traffic for the base year (2022) is 3,084, while the year
10 (2032) and year 15 (2037) are 5,523 and 7,391 respectively.
After the construction, the attracted/generated traffic proposed fuelling station will be marginal
and this will not affect the operating levels of service of the Karatina-Kutus (B27) road. However,
for safe and effective manoeuvrability of the attracted/generated trips to the proposed petrol
station development proper road marking of the acceleration and deceleration lanes and with
channelization islands to separate lanes for easy manoeuvrability at the intersections between
Karatina-Kutus (B27) road and the acceleration and deceleration lanes.
14 | P a g e
It is concluded that the exiting and merging traffic can be well accommodated and served by the
provided acceleration and deceleration lanes.
15 | P a g e