Change Management Plan

Date Prepared: 25-12-2018 Project Title: PMP Translator

Change Management Approach

Any change to any component of the project management plan like subsidiary
plans or project baselines should be processed through integrated change
control.
Definition of Change

Schedule Change can be requested by any stakeholder for any variance


discovered related to start, end dates or durations of critical activities, project
milestones, schedule reserves or project start and end dates.
Scope Change can be requested by any stakeholder for any variance
discovered related to project deliverables, product scope, project exclusions,
project activities/work packages, activities descriptions mentioned in the WBS
dictionary.
Budget Change can be requested by any stakeholder for any variance
discovered related to activities cost or cost reserves.
Subsidiary Plan Change can be requested by any stakeholder for any
needed change in any subsidiary plan or any component of the project
management plan.
Project Document Change any update to any project document can be
performed after project manager approval and doesn't need to go through
integrated change control procedures.

Change Control Board

Name Role Responsibility Authority


George Shahat Managing Director Head of CCB 2 Votes
Adel Ramzy Project manager Member 1 Vote
Magdy Rady IT manager Member 1 Vote
Karim Adel Marketing manager Member 1 Vote

Change Control Process

Change Request Submittal All change requests are submitted through organization's
change control system
Change Request Tracking All change requests are tracked through organization's
change control system
Change Request Review All change requests are reviewed by project manager to
evaluate impacts on the project constraints
Change Request Approval All changes are approved or rejected by CCB
Change request Disposition Project manager is responsible for change request
disposition