PROJECT: CHA SOTTO

LOCATION: 350 SAN BARTOLOME ST., AYALA ALABANG

DELIVERY SCHEDULE
DATE AREA REMARKS
NINO CLOSET & VANITY (CARCASS) DELIVERED & INSTALLED
SOFIA CLOSET & VANITY (CARCASS) DELIVERED & INSTALLED
NOV. 24, 2022 DEN VANITY (CARCASS) DELIVERED & INSTALLED
GUEST VANITY (CARCASS) DELIVERED & INSTALLED
DEC 9, 2022 GUEST CLOSET (CARCASS)
DEN CLOSET
DEC. 13, 2022 MASTERS CLOSET & VANITY (CARCASS)
DEC 16, 2022 PANTRY
AUXILIARY KITCHEN (CARCASS)
DEC. 19, 2022 NINO/SOFIA CLOSET & VANITY DOORS/EXPOSED PARTS
MASTERS SHOE CABINET (CARCASS)
DEC 23, 2022 - CHRISTMAS BREAK/VACATION
JAN. 02, 2023
JAN. 06, 2023 MAIN KITCHEN (CARCASS)
JAN. 19, 2023 GUEST CLOSET DOORS/EXPOSED PARTS
DEN CLOSET DOORS/EXPOSED PARTS
JAN. 23, 2023 MAIN KITCHEN & AUXILARY KITCHEN DOORS/EXPOSED PARTS
JAN. 26, 2023 MASTERS CLOSET & MASTER SHOE CAB DOORS/EXPOSED PARTS

NOTE: Our installation is until December 22, 2022 only and we will resume by next year, January 2023.