3.1 PANEL MOUNTING – XLS CABINETS.

OVERVIEW : CAB
∂ The Model CAB1/ CAB2 / CAB3 are used to house system
modules like Powersupply, loop cards and battery.

∂ The CAB1/CAB2 /CAB3 consists of an outer door, an inner


door.

∂ It has three stages.

∂ Fixing of Backbox, Inner door and outer door.

∂ Fixing of CC5.

∂ Cabling and Termination.

∂ Card Guide fixing and Cards insertion.

WHERE TO FIX:
∂ Cab1- Back Box:

∂ Prior to installation consider the following:

∂ Mounting height for visual and manual access to the Per-


son MachineInterface (PMI) display. We can fix CAB1 at an
height of 1.9M from floor. Fig 1 & 2
1
∂ Consider the weight and size of the enclosure.

∂ Size: We can come to know area of wall required to fix the


panel.

∂ Weight: Helps to decide whether the strength of wall will


be sufficient to hold the panel.

Proprietary Information of Siemens Building Technologies IN BT SSP OPS TCG, July’17


All right reserved
Prior to installation consider the following..

∂ Do not locate the panel where it is exposed to high levels


of moisture.

∂ Do not locate the panel where there are high levels of vi-
bration or shock. Fig1.
Fig 1
∂ Position the backbox clear of obstructions so that the
front door opens freely and the controls and indicators
are easily accessible. –Fig2

Fig 2

Proprietary Information of Siemens Building Technologies IN BT SSP OPS TCG, July’17


All right reserved
HOW TO FIX BACK BOX:
Product Inspection

∂ Check material for any damage before attempting to fix


on the wall.

∂ Note: In the unlikely event that the panel has been dam-
aged in transit, you MUST NOT install it but contact
supplier factory for their returns procedure.

REQUIRED ACCESSORIES

for back box fixing

∂ Anchor fastners with washers and bolt.

REQUIRED TOOLS:
∂ Spanners and box spanners.

∂ Drilling machine and drill bit

∂ Hammer

∂ Heavy screw driver to remove the cable knockout

FIXING OF BACK BOX:


∂ Mark the locations of the two upper mounting bolts of
the backbox on the wall.

∂ Drill the two holes located in the previous step and screw
Proprietary Information of Siemens Building Technologies IN BT SSP OPS TCG, July’17
All right reserved
in the top bolts, leaving a small gap between the wall
and each top bolt.

∂ Remove the cable knockouts in the backbox for the entry


of field wiring. (Refer to location of knockouts.).

∂ Place the backbox over the two top bolts and allow it to
slide down over the bolts.

∂ Mark, drill, and install the two bottom bolts in the


backbox.

∂ Tighten all four bolts securely against the back wall of


the backbox.

HOW TO FIX INNER DOOR AND OUTER DOOR .

∂ Insert the inner door by placing it on hinges.

∂ Insert blank plates, as needed, in unused spaces on door


and secure with 10-32 nuts.

Proprietary Information of Siemens Building Technologies IN BT SSP OPS TCG, July’17


All right reserved
∂ Install the outer door by placing it on its hinges.

∂ Install the ground straps on both the inner and outer


doors

∂ Close the inner door and secure with the ¼ turn fastener.

∂ Close the outer door and secure with the key latch.