PEKERJAAN PATOK KOTA BARU

NOVEMBER DESEMBER
No Nama Pekerjaan Volume Satuan CEK
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7

1 Penggalian Tanah 800 Titik 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 800


2 Perakitan besi patok 800 Titik 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 800
3 Pencetakan Patok precast 800 Titik 35 35 35 35 40 40 40 40 40 40 40 40 40 40 40 40 40 40 35 35 30 800
4 Angkut patok ke Lokasi 800 Titik 140 200 230 230 800
5 Penanaman Patok 800 Titik 42 42 42 42 42 42 42 42 44 42 42 42 42 42 42 42 42 42 42 800
6 Pasangan Batu 800 Titik 42 42 42 42 42 42 42 42 44 42 42 42 42 42 42 42 42 42 42 800
7 Pengecatan logo patok 800 Titik 42 42 42 42 42 42 42 42 44 42 42 42 42 42 42 42 42 42 42 800

Tukang Gali = 10 Orang


Tukang Cetak Patok = 10 Orang
Tukang Pasang Patok = 10 Orang
Cetakan / Bekisting = 50 Cetakan