RENCANA ANGGARAN BIAYA

Propinsi : Jawa Barat Lokasi : Rumah ..................


Kabupaten : Cirebon : RT. 00 RW. 00
Kecamatan : Depok
Desa : Kejuden

Volume Harga Dana Dari Dana


URAIAN Dari Dana Satuan Satuan Swadaya DD
Total
Swadaya DD Rp. Rp. Rp.
Bahan
1 Paku 11.00 11.00 kg 22,000 - 242,000
2 Semen 40 kg 10.00 10.00 zak 58,000 - 580,000
3 Pasir pasang 4.00 4.00 m3 125,000 - 500,000
4 Batako 880.00 880.00 bh 4,000 - 3,520,000
5 Kaca 0.50 0.50 m2 110,000 - 55,000
6 Kayu 6/12 Kusen 7.00 7.00 ljr 120,000 - 840,000
7 Kayu 8/10 3.00 3.00 ljr 125,000 - 375,000
8 Kayu 5/7 12.00 12.00 ljr 45,000 - 540,000
9 Kayu 3/4 6.00 6.00 ljr 25,000 - 150,000
10 Daun Pintu 2.00 2.00 lbr 500,000 - 1,000,000
11 Engsel Pintu 4.00 4.00 bh 24,000 - 96,000
12 Kunci 2.00 2.00 bh 60,000 - 120,000
13 Asbes gelombang (1,5 x 0,8) 7.00 7.00 lbr 25,000 - 175,000
14 Kaca Nako 0.50 0.50 m2 400,000 - 200,000

Sub Total 1) Ia - 8,393,000.00


Upah
1 Pekerja 65.0 65.0 Oh 70,000 - 4,550,000
2 Tukang 25.0 25.0 Oh 80,000 - 2,000,000

Sub Total 2) IIa - 6,550,000.00


Alat
1 Benang 1.00 1.00 bh 7,000 - 7,000
2 Ember Cor 2.00 2.00 bh 11,000 - 22,000
3 Meteran 1.00 1.00 bh 28,000 - 28,000
Sub Total 3) IIa - 57,000.00
Total Biaya DD (a+b ) 15,000,000.00
Sumber Dana
Total Biaya Swadaya (a+ b) -
JUMLAH TOTAL ( DD + Swadaya ) 15,000,000.00
Terbilang : Lima Belas Juta Rupiah