Professional Documents
Culture Documents
The purpose of this Standard Maintenance Procedure is to provide maintenance practices for
electrical equipment at Praxair facilities. These activities should be followed to minimize the expected
outages of electrical equipment. By setting in place these procedures, employed in a structured
maintenance program, unexpected equipment problems and outages will be reduced.
1
7.1.2 Synchronous (See SMP-131).............................................................................. 19
7.2 Random Wound Motors (Operating at or below 600V)................................................... 19
7.2.1 NEMA Frame.................................................................................................... 19
7.2.2 Above NEMA Frame Size................................................................................... 20
7.3 Generators .............................................................................................................. 20
7.3.1 Cogeneration Type ............................................................................................ 20
7.3.2 Standby Generators ........................................................................................... 20
8. References .................................................................................................................... 22
Appendix A: Earth Resistance Testing ...................................................................................... 23
2. Introduction
The Electrical Specialist shall determine the applicability and interval of preventative
maintenance activities based on operating conditions, historical records, personal experience, and
equipment criticality. Operating and environmental conditions to consider may include but are not
limited to, equipment age, duty-cycle, load factor, temperature, cleanliness, humidity, and
corrosiveness. .
The Electrical Specialist may elect to add or omit steps of a preventative maintenance activity
based on its applicability, favorable (or unfavorable) conditions found in other similar inspections , and
operating factors of the equipment. Such modifications must be made with input from the Expert
Network and Operations Management unless parameters have been previously defined to delegate
authority to the Electrical Specialist. If a procedure step is omitted or added, notation in the Work Order
record shall indicate these details.
All electrical work described within, will be performed by qualified personnel, as determined by
plant management under the guidance of the Praxair Technology Center and region Reliability Centers.
A number of factors will be used in determining qualification: affiliation with recognized testing/service
organizations; experience; safety record; quality control programs; and training to list a few.
Prior to performing any of the activities described herein, a thorough review of all relevant
safety aspects must take place. All Praxair safety policies must be strictly adhered to. For this SMP,
Policy 2.05, “Electrical Safety” W
( orldwide S&ES Manual), or regional safety manuals should be
particularly observed. The completion of some of the activities listed in this SMP requires the use of a
Hazardous Work Permit (HWP). The pre-job discussion is essential and must be held with all involved
parties prior to starting work.
The plants and regional Reliability Centers share the responsibility for program
implementation. Record keeping is an integral part of this process. Each Reliability Center will use the
computerized maintenance management system (CMMS) program to record data and manage
maintenance work orders. Corrective work orders, originated from equipment inspections will also
employ the CMMS program. This will ensure communication between regions and Tonawanda.
If there are any questions about this document, or general electrical questions, please call the
Global Expert Network at the Praxair Technology Center.
This SMP is to be used in conjunction with the manufacturer's documentation. Due to the
varied manufacturers, types, vintages, and options, this SMP serves to point out significant areas of
maintenance. For specific procedures and additional requirements, manufacturer's literature should be
consulted.
2
3. High Voltage Distribution Systems
Oil and SF6 (sulfur hexaflouride) circuit breakers are used in primary
substations and transmission lines where high-speed opening and closing operations are required.
The breakers use the oil or the SF 6 gas as the arc suppression medium.
MAINTENANCE PROCEDURE
1. For oil circuit breakers (O. C. B.s) only, conduct a comprehensive oil
analysis, including dissolved gases (reference SMP-132 Appendix B
for recommended oil quality levels).
4. Visually inspect the external surfaces for rust and corrosion. Look
for oil leaks, and pressures on the SF6 gas and the air operator on
the O.C.B. Verify the area is clean and clear of operating
obstructions. Also, visually check the control box for corroded wiring
terminations and jumpers.
5. For oil circuit breakers, observe and document tank and bushing oil
levels. Generate a PM-R work order if any deficiency is found
6. For SF6 circuit breakers, verify and document the amount of SF6 gas
remaining in the cylinder. Replace cylinder with full one if required.
3
A. Inspect air compressor, change oil and replace belts.
10. Power factor tests are to be performed across each pole with the
breaker open and each phase-to-ground with the breaker closed. If
the breaker is a single tank (i.e., all three poles in one tank), then
with the contacts closed, the breaker shall be power factor tested
phase-to-phase in addition to the above tests. Power factor tests are
also to be performed on circuit breaker bushings. All measurements
are to recorded for future reference.
MAINTENANCE PROCEDURE
1. While under load, check the contacts for heat with a thermographic
monitor camera. (SMP-073)
4
1. Operate the switch and inspect the blade make and break
synchronization. Adjust if necessary
2. Operate the switch and inspect the contact position and contact
pattern. Adjust if necessary
3. Visually inspect all contact areas for signs of arcing. Repair / replace
as necessary
7. Coat the contact and holder very lightly with Mobil 28 (red grease) or
Carnuba wax product
MAINTENANCE PROCEDURE
1. While under load, check the contacts for heat with a thermographic
monitor camera. (SMP-073)
2. Operate the switch and inspect the blade make and break
synchronization. Adjust if necessary
3. Operate the switch and inspect the contact position and contact
pattern. Adjust if necessary
4. Visually inspect all contact areas for signs of arcing. Repair / replace
as necessary
5
5. Lubricate and verify operation of all key interlocks and sequencing of
schemes
8. Coat the contact and holder very lightly with Mobil 28 (red grease) or
Carnuba wax product
MAINTENANCE PROCEDURE
1. none
1. Operate the switch and inspect the blade make and break
synchronization. Adjust if necessary
2. Operate the switch and inspect the contact position and contact
pattern. Adjust if necessary
3. Visually inspect all contact areas for signs of arcing. Repair / replace
as necessary
7. Coat the contact and holder very lightly with Mobil 28 (red grease) or
Carnuba wax product
6
3.2 Aerial / Yard Bus
The aerial/yard bus consists of the structure and buswork in the main substation.
These systems usually consist of an incoming tower, structural steel, and a network of uninsulated bus.
Voltages may vary from 23,000V to 345,000V.
MAINTENANCE PROCEDURE
3. Verify the condition of all structural grounding straps. This is to include circuit
breakers, towers, supports, fencing, and static poles.
4. Visually inspect lightning arrestor insulator for any cracking or other damage.
Assure that any vent ports are clear and free of discharge. If surge counter
exists, record value. Verify that arrestor grounding is intact.
MAINTENANCE PROCEDURE
The ground grid is an integral part of the electrical distribution system that is often
neglected. Over 90% of the system lies buried under the operating equipment. Failure to maintain the
system can lead to unnecessary equipment damage and personal injury.
7
1. Check ground grid resistance with ground resistance fall-of-potential method
outlined in Appendix A.
Medium voltage oil circuit breakers and switches are devices which interrupt
a current flow utilizing oil to extinguish the resulting arc. Each time an arc is extinguished there is some
burning that occurs in the oil. It is imperative that the quality of the oil is regularly monitored to insure
that it maintains close to its original insulating characteristics. Typically, oil circuit breakers and
switches are used in systems that require fast interrupting times. This is necessary when the device
must interrupt full load or fault conditions.
MAINTENANCE PROCEDURE
3. Power factor tests are to be performed across each pole with the
breaker open and each phase-to-ground with the breaker closed. If
the breaker is a single tank (i.e., all three poles in one tank), then
with the contacts closed, the breaker shall be power factor tested
phase-to-phase in addition to the above tests.
8
4.1.3 Air Magnetic Circuit Breakers and Switches (See SMP-133)
MAINTENANCE PROCEDURE
Power feeders can be tested by insulation resistance tester. This will insure the cable
can be energized safely. On new installations cable should be high potential tested in accordance with
the Praxair Electrical Aboveground Electrical Specification AGE-6 [new installation levels]. Only high
potential test if preparations have been made to replace failed cable. If the cable fails, a pinhole
will be punched through the cable jacket.
1. None.
Medium voltage cable pits and wireways are relatively maintenance free. A common
misconception is that cable pits will remain free of water and contamination. Actually most pits and
wireways will eventually fill with water. Some are open to the atmosphere, while others may fill over
time due to humidity and condensation. The cable insulation is designed to handle water and most
contaminates. Do not attempt to remove water from a cable pit. Pits may contain low level methane
9
concentrations that could be ignited by a very low level arc. Also cycling the cables to dry then back to
wet conditions, will tend to age the insulation more quickly than keeping the cable jackets either wet or
dry. A second common wireway is a cable tray system. The cable tray should be continuous,
connected mechanically and by ground bonding jumpers. In fault conditions the cable tray acts as a
return path for fault currents. Keeping the cable tray system in good mechanical condition insures that
the protective devices will interrupt fault conditions as designed.
MAINTENANCE PROCEDURE
Most of the necessary work required to maintain cable pits and wireways is
mechanical and housekeeping. Remember when inspecting wireways such as cable trays that they are
an integral part of the facilities grounding system. Any mechanical damage should be corrected as
soon as possible.
1. Visual inspection.
1. None.
MAINTENANCE PROCEDURE
The capacitive plates of most capacitors are usually immersed in an insulating oil.
They vary in size, but for most Praxair locations will be about the size of a standard car battery or a Ni-
cad substation battery. Since the units are sealed, physical inspection is limited. Most capacitors have
insulating posts on which the electrical connections are made. These posts are generally porcelain and
can crack if mechanically abused.
2. The majority of these items are installed with fuses. The integrity of these
fuses should be verified during maintenance activities.
10
2. Clean the porcelain insulator and inspect for pitting.
A motor control center (MCC) is a collection of 480 volt molded case circuit breakers
and contactors, connected to a single main horizontal bus and smaller vertical bus sections. The units
typically feed motors up to about 300 horsepower, along with various area lighting and control power
loads.
MAINTENANCE PROCEDURE
Once a unit is checked out and in service, it tends to need minimal maintenance. The
major concern is keeping all electrical connections properly torqued to insure no hot spots develop
within the unit. The best indicator of a bad connection is the generation of heat when there is a current
flow.
1. Thermally scan each unit for excess heat generation at the cable
terminations and control terminations. (The unit must be in service and under
load.) (SMP-073)
Various plants have switches that can utilize either of two incoming power sources to
serve a single load. The switch is typically 480 volt, and is break before make in its operation. More
specifically, at no time can both sources feed simultaneously into a single load.
These devices are common in critical power units such as liquid backup system and
control power feeds. The most common is an automatic transfer switch with manually initiated return to
normal power. In the case where normal power is lost, the switch transfers to an alternate power supply
such as a standby generator. When normal power is restored, a manual return push button must be
pressed or computer signal initiated to transfer the load back. This is done to insure that the operator of
the site is in control of the unit when the transfer is made. Also when power is transferred back to
normal power, a brief outage will occur. All starters will drop out during this outage.
MAINTENANCE PROCEDURE
11
Maintenance for these units is much the same as for motor control centers. (See
section 5.1.) With the exception of functionally testing any motorized transfer circuits. The best
assurance that the system will function, is a periodic routine of full functional tests of the mechanical
operating system. This should be done both by the manual initiation of the transfer and by the
simulation of a loss of power condition.
Thermoscan the electrical connections to locate hot spots. (This test must be done with the
unit in service and under load. Remember that the test will only indicate heat if current is flowing,
therefore only one of the incoming power sources can be scanned at a time. (SMP-073)
2. Visual inspection to check for unusual heating. (This can be none with the
unit energized or de-energized. Special precautions should be exercised
while inspecting any unit with automatic operation.)
600 volt power cable is generally very simple in construction. The jacket is a single
extruded material designed to withstand the voltage and any external environmental conditions. When
replacing existing cables, the routing must be taken into consideration. Exposure to mechanical
damage, water, high temperatures and sunlight can prematurely age insulation systems, causing
failures.
MAINTENANCE PROCEDURE
Low voltage power feeders have a design life in excess of 20 years. The major
concern in maintaining low voltage distribution systems is the avoidance of mechanical damage.
12
5.5 Uninterruptible Power Supplies
Uninterruptible power supplies or UPSs, are common in control power supply design.
They operate by storing energy in dc form, usually in a rack of batteries. This stored energy is
continually monitored and float charged. When the primary power source is lost, the dc is inverted back
to ac to feed the load. Most UPSs operate with a static switch that is fast enough that the load will not
sense a loss of power.
A UPS also will act as an electrical filter. Due to the rectification and inversion process,
the power delivered to the load is generally very clean and free of spikes.
5.6.1 Lighting
Typical plant lighting systems should be maintained to insure that all areas
are illuminated consistent with the original plant design. When a light circuit is not functional, it should
be reported immediately, and corrected as soon as possible.
Each operating plant is equipped with a series of devices that enable the operators to
shut down the process in the event of an emergency. The last and most important shutdown device is
the plant emergency trip station. The station itself is a mechanical switch that is in an energized circuit
maintaining a relay in the main electrical interrupting device. When the switch is opened the relay is de-
energized and the interrupting device opens.
MAINTENANCE PROCEDURE
There are several ways to test the plant emergency trip stations. Each station can be
individually opened to insure the mechanical switch will operate. The relay in the switchgear can also
be operated functionally check the interrupter. The only way to fully test the system is to pull the
handle and operate the switchgear.
1. Check the plant emergency trip stations for physical damage and corrosion. If
the plant is down operate the field boxes to insure the handle will move freely.
13
MAJOR MAINTENANCE ITEMS
The best way to insure the plant emergency trip stations will function properly is to use
them whenever possible. The best way to accomplish this is to keep a log of the system operations and
when the plant is to be shutdown for maintenance, unload the compressors and functionally trip the
gear with one of the stations. As opportunities arise, alternate through each trip station and log any
problems that might occur. An alternate method is to exercise one trip station to confirm that the
breaker opens, then exercise the remainder of the stations, verifying that the PET relay drops out for
each station operation.
5.8.1 Batteries
Praxair facilities may have batteries in many applications. In this section the focus will
be on substation type wet cell batteries. These will typically by Nickel Cadmium (Ni-Cad) or lead acid.
The cell voltages may range from 1.35 volts to 12 volts per cell. Typical uses will be for uninterruptible
power systems, substation dc control power and backup generator starting. The Ni-Cad batteries offer
longer life and easier maintenance, while the lead acid batteries can deliver more power to a load in a
short time. In general terms, lead acid batteries have a life span of about 5-7 years, and Ni-Cad have
a life span of about 20 years with proper maintenance.
MAINTENANCE PROCEDURE
All batteries require periodic maintenance. Electrolyte levels must be maintained and
charge rates must be monitored constantly. Over charging can literally cook the electrolyte out of the
cells and could if left uncorrected, lead to an energy release. Undercharging could render the system
inoperative.
4. Measure and document the high-rate (equalize) voltage. Compare this to the
manufacturer’s specified level and adjust if necessary
5. Allow the batteries to equalize for a period of 24-hours following the high-rate
(equalize) charging
6. Measure and document the float / equalize voltage. Compare this to the
manufacturer’s specified level and adjust if necessary
14
7. Measure and record each cell voltage, when the battery charger is in float
charge mode
9. Visually inspect electrolyte level of each cell. Top off with distilled or
deionized water as needed to reach the proper level as specified by the
manufacturer
10. For lead-acid battery cells only, take and document specific gravity levels
11. Visually inspect all cell jars and covers for cracking or other physical damage.
This is to include damage due to ultraviolet radiation on plastic battery cases
12. Rinse flame arrestor vent caps with distilled or deionized water and let air dry
13. Inspect battery charger internals for any signs of unusual heating
1. Battery systems should be discharged with each cell being monitored. Any
weak cells should be drained and equalized. If they remain weak they should
be replaced.
5.8.2 Metering
MAINTENANCE PROCEDURE
5.8.3 Relays
MAINTENANCE PROCEDURE
15
Electro-mechanical protective relays must be maintained to insure the
reliability and coordination of the electrical system. A reliable major electrical service company should
be contracted to perform this specialized calibration.
5.8.4 Wiring
Variable Speed Drives (VSD) (or Variable Frequency Drives (VFD) or Adjustable
Speed Drives (ASD)) are electronic devices, generally installed at 480V in MCCs, that are used to vary
the speed of an induction motor. The VSDs can also vary the speed to above nameplate speed by
changing the frequency to the motor to above line frequency. Most drives work by taking a line
frequency supply and rectifying it into dc power. Through electronic switching the dc is converted to a
variable frequency ac output. Because the ac output is composed of a series of pulses, a filter (or
motor designed for inverted duty service) is recommended. Special care is taken during the design of
these systems as the feeder cable to the motor and the motor can be adversely affected by the
electronic switching of the drive.
MAINTENANCE PROCEDURE
VSDs require only minimal maintenance activities. Much like the modern digital
protective relays, they have self-test features internal to their programming.
2. Assure that the ventilation openings are clear and free of debris. Vacuum out
ventilation openings as needed.
16
1. Remove VSD cover and perform visual inspection. Items to be aware of
include:
• Internal screws and connections
• Observe dc link capacitor or any leaking / swelling
• Relay contacts for any pitting or roughness
• Wiring and conductors for physical abnormalities
• Observe resistor insulation for any cracks
Electrical process heaters require periodic maintenance to assure the condition of the
heater elements. As listed below this maintenance can be completed in one of two fashions,
depending on the operating state of the heater at the time of the maintenance.
3. Perform insulation resistance test at 500Vdc between the three phase legs
and ground. Record value
2. Measure and record the current on each phase leg. Verify reading with
heater rated output to assure that heater is functioning properly
6. Transformers
MAINTENANCE PROCEDURE
17
2. Thermally scan the connections for unusual heat.
Instrument transformers can be separated into two basic categories. Potential and
current transformers. Potential transformers operate in the same manner as dry type power
transformers and serve two basic functions. They provide power to instruments and monitoring devices
within the distribution equipment and provide a reference voltages for metering and protective
equipment. Current transformers provide instrumentation equipment with a ratio of the current in the
system. This can be used for monitoring, billing or protective purposes.
MAINTENANCE PROCEDURE
Instrument transformers, in general, have a dry construction and are not prone to drift
or failure. The wiring systems must be maintained, especially in circuits fed by current transformers. In
no circumstance open a current transformer circuit under load. A current transformer must
constantly feed a load or shorted jumper or it will fail, sometimes violently. The current transformer, if
opened while in service, will start to build up an increasing potential (voltage) that will eventually arc
through the insulation to ground.
18
7. Drives
Small motors, typically 10 to 250hp and 3600 or 1800 rpm, are manufactured
on a frame outlined in the National Electrical Manufacturers Association (NEMA) guidelines. This allows
the motors to be interchangeable between manufacturers. This fact, and the ability to rewind most of
the motors in less than a week, make these motors almost disposable.
MAINTENANCE PROCEDURE
The chief maintenance item in NEMA frame motors are the bearings. On the
larger machines, the bearings are typically frictionless. In NEMA machines the bearings are either ball
or roller bearing type. These bearings have a finite life and must be replaced. The life can be monitored
by vibration detectors.
The electrical windings of the motor are extremely difficult to inspect. The
best method of electrical inspection is a 1000 volt dc insulation resistance tester.
3. Verify that the motor is adequately grounded and that all connections
are secure and free of corrosion.
19
MAJOR MAINTENANCE ITEMS
MAINTENANCE PROCEDURE
The only real maintenance item in NEMA frame motors are the bearings. On
the larger machines, the bearings are typically frictionless. In NEMA machines the bearings are either
ball or roller bearing type. These bearings have a finite life and must be replaced. The life can be
monitored by vibration detectors, but the most practical maintenance practice is to replace the bearings
at a predetermined interval.
The electrical windings of the motor are extremely difficult to inspect. The
best method of electrical inspection is a 1000 volt insulation resistance tester.
7.3 Generators
MAINTENANCE PROCEDURE
In Praxair facilities there is often a need for an backup power supply. Whether
it is to support a liquid backup system or to keep a computer system on line the design is about the
same. Most Praxair generator systems are induction generators driven by a diesel or natural gas fired
motor.
20
MAINTENANCE PROCEDURE
The major concern in this type of a generator system is making sure that the
generator functions properly under the fully loaded condition. The most practical way to accomplish
this task is to load the generator (by operating load, fixed load bank, or installed load bank) on a regular
basis. This is the most straightforward method of assuring reliable generator operation.
3. Check all belts and hoses for cracking and wear. Replace as
necessary
8. If built-in load bank system is not installed, perform load test with
portable load bank or actual system load
21
3. Load generator to at least 80% of nameplate rating
8. References
The following documents may be consulted for additional information regarding equipment
maintenance:
22
Appendix A: Earth Resistance Testing
1. Direct
2. Slope
3. Fall-of-potential
4. Intersection
For Praxair plants we will use the fall-of-potential and intersection methods. The fall-of-potential
method is the most common and will be used on all small grounding systems (less than 100 feet at the
longest diagonal). The Biddle Ground Resistance Tester will be used for both tests.
FALL-OF-POTENTIAL METHOD
The fall-of-potential method is the most widely used of all the accepted ground tests. It is practical on
small and medium sized systems.
The test is accomplished by providing a measured amount of current between a current electrode and
the ground system being tested. A voltmeter will measure the voltage difference between the ground
system and a potential electrode which should be located on a straight line between the ground system
and the current electrode. By moving the potential electrode to various positions between the current
electrode and the ground system a plot of resistance relative to distance can be generated. The
resistance will increase as the potential electrode moves away from the ground system. As the
electrode approaches 62% of the way from the grounding system to the current electrode, the slope of
the graph should approach 0. This is the point where the resistance is out of the spheres of influence
of the ground system and the current electrode. This is the equivalent impedance to earth of the
system is being tested.
The Biddle tester will have specific instructions on probe spacing and lead connection. Although the
62% rule applies in most cases, the graph should be generated to ensure that the probe spacing is
sufficient to generate accurate results.
A qualified contractor should be contacted to perform the ground measurement test. For further
information contact the regional Reliability Center.
23