Professional Documents
Culture Documents
OMAE2004-51201
OMAE2004-51201
HIGH HOLDING POWER TORPEDO PILE – RESULTS FOR THE FIRST LONG TERM
APPLICATION
Jairo Bastos de Araujo Rogério Diniz Machado Cipriano Jose de Medeiros Junior
Petróleo Brasileiro S. A. Petróleo Brasileiro S.A. Petróleo Brasileiro S. A.
jairoba@petrobras.com.br rogeriodm@petrobras.com.br cipri.AUTONOMO@petrobras.com.br
The heading of the unit is 208 degrees related to the true north.
The main particulars of the platform to be converted are given
in table 1.
The program DIGIN [5] was used to obtain the maximum load
on the pile top. The result computed was 5100 KN with 43.6o
on the horizontal plane.
Using the load values and its inclination on the torpedo top,
considered jointly with the soil data at Albacora Field site, T-98
behavior in the soil was obtained from the program
AEEPEC3D developed by Costa [6] based on a modeling three- Figure 3: Soil behavior for a Load of 9930 KN
dimensional applying finite elements method. Figure 2 shows applied 43.6o on the Torpedo.
the soil and the torpedo model divided in finite elements, Fig. 3
Because the two work lines are connected to the torpedo, the
pulling out load was determined by combining the AHV1 and
AHV2 pulling out forces as showed on Fig. 11. However, the
Figure 8: Monitoring equipment been recovered. AHV1 pulled vertically and the load value was obtained
directly on the winch, and the AHV2 pulled angularly, with
previously determined work line configuration and bollard pull.
Sometimes the wire cable was damaged after the torpedo shoot
operation and when used like work line.
ACKNOWLEDGMENTS
The authors would like to thank Petrobras for sponsoring
this work and for giving permission to publish this paper.
Figure 11: The work lines layout of the AHVs for REFERENCES
pull out operation. [1] API RP 2SK – “Recommended Practice for Design and
Analysis of Station keeping Systems for Floating Structures”,
second edition, December 1996.
FIELD TEST RESULTS [2] Palazzo, F. G., 2003, “FPSO Unit P-50 Mooring Analysis”,
The main results are shown in table 3. Technical Report I-RL-3010.62-1320-960-PPC-001, Rev. F,
PETROBRAS, Brazil.
Table 3: Summary of tests.
Tip angle 60o 30o 30o [3] Amaral, C. S., and Costa, A. M., 1996, “ Software
PROJETIL - Penetration Evaluation for Piles Deployed by Free
Water depth (m) 1195 1180 940 Fall Method in Clays”, PETROBRAS, Brazil.
Shock loads on AHV1, on account of the impact of the T-98 [8] Araujo, J. B., Almeida, J. C., and Rangel, M. O., 2002, “T-
shoots, were acceptable even for work line weight of 980 KN. 98 Handling, Deploying and Pull out Tests”, PETROBRAS
Executive Procedure No. MA-3504.00-6651-962-PSE-008.
The T-98 over boarding and recovery presented no problems.
There is a shoot height limit where the torpedo speed does not
increase anymore.