PROJECT:-

CLIENT
CONTRACTOR

INDIVIDUAL SIEVE ANALYSIS TEST FOR JOB MIX FORMULA OF GRANULAR SUB BASE
MORTH & SPECIFICATION (FROM TABLE 400-1) GRADE: 1
Source of Material :
Samle Location: Stock Piles Date of Sampling:
Description of Material: 63mm Aggeregate Date of Testing:
Samle No-01 Samle No-02
Weight of Sample: 18365 gms Weight of Sample: 19352 gms

IS SIEVE Wt. Cum.Wt. of Cum.% of IS SIEVE Wt. Cum.Wt. of Cum.% of


% Passing % Passing
(mm) Retained Retained Retained (mm) Retained Retained Retained

75 0 0 0 100 75 0 0 0 100
53 5307 28.90 28.90 71.10 53 6614 34.18 34.18 65.82
26.5 13004 70.81 99.71 0.29 26.5 12676 65.50 99.68 0.32
9.5 54 0.29 100.00 0.00 9.5 62 0.32 100.00 0
4.75 0 0 100 0 4.75 0 0 100 0
2.36 0 0 100 0 2.36 0 0 100 0
0.425 0 0 100 0 0.425 0 0 100 0
0.75 0 0 100 0 0.75 0 0 100 0
pan 0 0 100 0 pan 0 0 100 0
Total wt. Total wt.
Samle No-03
Weight of Sample: 16324 gms

IS SIEVE Wt. Cum.Wt. of Cum.% of


(mm) Retained Retained Retained % Passing

75 0 0 0 100
53 4022 24.64 24.64 75.36
26.5 12264 75.13 99.77 0.23
9.5 38 0.23 100.00 0
4.75 0 0 100 0
2.36 0 0 100 0
0.425 0 0 100 0
0.75 0 0 100 0
pan 0 0 100 0
Total wt.
Remarks:
Contractor Representive JE AE EE
CLIENT
CONTRACTOR

INDIVIDUAL SIEVE ANALYSIS TEST FOR JOB MIX FORMULA OF GRANULAR SUB BASE
MORTH & SPECIFICATION (FROM TABLE 400-1) GRADE: 1
Source of Material :
Samle Location : Stock Piles Date of Sampling:
Description of Material: 20mm Aggeregate Date of Testing:
Samle No-01 Samle No-02
Weight of Sample: 10992 gm Weight of Sample: 12368 gm
IS SIEVE Wt. Retained Cum.Wt. of Cum.% of % Passing IS SIEVE Wt. Cum.Wt. of Cum.% of % Passing
(mm) Retained Retained (mm) Retained Retained Retained
75 0 0 0 100 75 0 0 0 100
53 0 0 0 100 53 0 0 0 100
26.5 41 0.37 0.37 99.63 26.5 240 1.94 1.94 98.06
9.5 10368 94.32 94.70 5.30 9.5 11351 91.78 93.72 6.28
4.75 104 0.95 95.64 4.36 4.75 42 0.34 94.06 5.94
2.36 479 4.36 100.00 0.00 2.36 735 5.94 100.00 0.00
0.425 0 0 100.00 0.00 0.425 0 0 100.00 0.00
0.75 0 0 100.00 0.00 0.75 0 0 100.00 0.00
pan 0 0 100 0 pan 0 0 100 0
Total wt. Total wt.
Samle No-03
Weight of Sample: 11358 gm
IS SIEVE Cum.Wt. of Cum.% of
Wt. Retained % Passing
(mm) Retained Retained
75 0 0 0 100
53 0 0 0 100
26.5 65 0.57 0.57 99.43
9.5 10894 95.91 96.49 3.51
4.75 93 0.82 97.31 2.69
2.36 306 2.69 100.00 0.00
0.425 0 0 100.00 0.00
0.75 0 0 100.00 0.00
pan 0 0 100 0
Total wt.
Remarks:

Contractor Representive JE AE EE
CLIENT
CONTRACTOR

INDIVIDUAL SIEVE ANALYSIS TEST FOR JOB MIX FORMULA OF GRANULAR SUB BASE
MORTH & SPECIFICATION (FROM TABLE 400-1) GRADE: 1
Source of Material;
Samle Location: Stock Piles; Date of Sampling:
Description of Material: 10mm Date of Testing:
Samle No-01 Samle No-02
Weight of Sample: 6598 gm Weight of Sample: 8312 gm
IS SIEVE Cum.Wt. of Cum.% of IS SIEVE Cum.Wt. of Cum.% of
(mm) Wt. Retained Retained Retained % Passing (mm) Wt. Retained Retained Retained % Passing
75 0 0 0 100 75 0 0 0 100
53 0 0 0 100 53 0 0 0 100
26.5 0 0.00 0.00 100.00 26.5 0 0.00 0.00 100.00
9.5 3277 49.67 49.67 50.33 9.5 3800 45.72 45.72 54.28
4.75 2315 35.09 84.75 15.25 4.75 3154 37.95 83.66 16.34
2.36 585 8.87 93.62 6.38 2.36 994 11.96 95.62 4.38
0.425 304 4.61 98.23 1.77 0.425 283 3.40 99.03 0.97
0.75 37 0.56 98.79 1.21 0.75 33 0.40 99.42 0.58
pan 80 1.21 100 0 pan 48 0.58 100 0
Total wt. Total wt.
Samle No-03
Weight of Sample: 5938 gm
IS SIEVE Cum.Wt. of Cum.% of
Wt. Retained % Passing
(mm) Retained Retained
75 0 0 0 100
53 0 0 0 100
26.5 0 0.00 0.00 100.00
9.5 2549 42.93 42.93 57.07
4.75 2299 38.72 81.64 18.36
2.36 794 13.37 95.02 4.98
0.425 68 1.15 96.16 3.84
0.75 47 0.79 96.95 3.05
pan 182 3.07 100 0
Total wt.
Remarks:

Contractor Representive JE AE EE
CLIENT
CONTRACTOR

INDIVIDUAL SIEVE ANALYSIS TEST FOR JOB MIX FORMULA OF GRANULAR SUB BASE
MORTH & SPECIFICATION (FROM TABLE 400-1) GRADE: 1
Samle Location: Stock Piles Date of Sampling:
Description of Material: sand Date Tasted:
Samle No-01 Samle No-02
Weight of Sample: 1500 gm Weight of Sample: 1500 gm
IS SIEVE Cum. Wt. Cum.% IS SIEVE Cum. Wt. Cum.%
Wt.Retained % Passing Wt.Retained % Passing
(mm) Retained Retained (mm) Retained Retained
75 0 0 0 100 75 0 0 0 100
53 0 0 0 100 53 0 0 0 100
26.5 0 0 0 100 26.5 0 0 0 100
9.5 40 2.67 2.67 97.33 9.5 86 5.73 5.73 94.27
4.75 61 4.07 6.73 93.27 4.75 69 4.60 10.33 89.67
2.36 314 20.93 27.67 72.33 2.36 124 8.27 18.60 81.40
0.425 739 49.27 76.93 23.07 0.425 681 45.40 64.00 36.00
0.75 330 22.00 98.93 1.07 0.75 522 34.80 98.80 1.20
pan 16 1.07 100.00 0.00 pan 18 1.20 100.00 0.00
Total wt. Total wt.
Samle No-03
Weight of Sample: 1500 gm
IS SIEVE Cum. Wt. Cum.%
Wt.Retained % Passing
(mm) Retained Retained
75 0 0 0 100
53 0 0 0 100
26.5 0 0 0 100
9.5 80 5.33 5.33 94.67
4.75 86 5.73 11.07 88.93
2.36 98 6.53 17.60 82.40
0.425 658 43.87 61.47 38.53
0.75 563 37.53 99.00 1.00
pan 15 1.00 100.00 0.00
Total wt.
Remarks:

Contractor Representive JE AE EE
PROJECT :- Widening & Strengtheing / Reconstruction work of Road From Mohanpur (on NH - 133) -
karkdih - Dalawar - Bhandaridih - Anjana More road (Length - 11.700 km) and Bhandaridih to Beldiha
(MDR - 206) Link Road ( Length - 5.425 km) (Total Length - 17.1225 km )
CLIENT RCD, GODDA, JHARKHAND
CONTRACTOR Rajbir Construction Pvt. Ltd.

INDIVIDUAL SIEVE ANALYSIS TEST FOR JOB MIX FORMULA OF GRANULA-SUB-BASE

MORTH & SPECIFICATION (GRADING-1 FROM TABLE 400-1)grade1


Samle Location: Stock Piles
Description of Material:
63mm Aggeregate
SIEVE ANALYSIS % OF PASSING
IS SIEVE(mm)
Sample No:1 Sample No:2 Sample No:3 Avg. % of Passing
75 100.00 100.00 100.00 100.00
53 71.10 65.82 75.36 70.76
26.5 0.29 0.32 0.23 0.28
9.5 0.00 0.00 0.00 0.00
4.75 0.00 0.00 0.00 0.00
2.36 0.00 0.00 0.00 0.00
0.425 0.00 0.00 0.00 0.00
0.75 0.00 0.00 0.00 0.00
pan 0.00 0.00 0.00 0.00
20mm Aggeregate
SIEVE ANALYSIS % OF PASSING
IS SIEVE(mm)
Sample No:1 Sample No:2 Sample No:3 Avg. % of Passing
75 100.00 100.00 100.00 100.00
53 100.00 100.00 100.00 100.00
26.5 99.63 98.06 99.43 99.04
9.5 5.30 6.28 3.51 5.03
4.75 4.36 5.94 2.69 4.33
2.36 0.00 0.00 0.00 0.00
0.425 0.00 0.00 0.00 0.00
0.75 0.00 0.00 0.00 0.00
pan 0.00 0.00 0.00 0.00
Remarks:

Contractor Representive JE AE EE
CLIENT
CONTRACTOR
INDIVIDUAL SIEVE ANALYSIS TEST FOR JOB MIX FORMULA OF GRANULA-SUB-BASE
MORTH & SPECIFICATION (GRADING-1 FROM TABLE 400-1)grade1
Sample Location: Stock Piles
Description of Material: Date of Testing:
10mm Aggeregate
SIEVE ANALYSIS % OF PASSING
IS SIEVE(mm)
Sample No:1 Sample No:2 Sample No:3 Avg. % of Passing
75 100.00 100.00 100.00 100
53 100.00 100.00 100.00 100
26.5 100.00 100.00 100.00 100
9.5 50.33 54.28 57.07 53.90
4.75 15.25 16.34 18.36 16.65
2.36 6.38 4.38 4.98 5.25
0.425 1.77 0.97 3.84 2.20
0.75 1.21 0.58 3.05 1.61
pan 0.00 0.00 0.00 0
Dust
SIEVE ANALYSIS % OF PASSING
IS SIEVE(mm)
Sample No:1 Sample No:2 Sample No:3 Avg. % of Passing
75 100.00 100.00 100.00 100
53 100.00 100.00 100.00 100
26.5 100.00 100.00 100.00 100
9.5 97.33 94.27 94.67 95.42
4.75 93.27 89.67 88.93 90.62
2.36 72.33 81.40 82.40 78.71
0.425 23.07 36.00 38.53 32.53
0.75 1.07 1.20 1.00 1.09
Pan 0.00 0.00 0.00 0.00
Remarks:

Contractor Representive JE AE EE
PROJECT:- Widening & Strengtheing / Reconstruction work of Road From Mohanpur (on NH - 133) - karkdih - Dalawar -
Bhandaridih - Anjana More road (Length - 11.700 km) and Bhandaridih to Beldiha (MDR - 206) Link Road ( Length - 5.425 km)
(Total Length - 17.1225 km )
CLIENT RCD, GODDA, JHARKHAND
CONTRACTOR Rajbir Construction Pvt. Ltd.
Blending for Job Mix Formula of GSB Grade 1
Tested by - Jointly Date:
Individual grading (% of finer) For different size of aggregate
Required Percentage
Permissible limit(As per M.O.R.T&H
63 MM 20mm 10mm Dust Combined (Fifth Revision)Sec 400-1 grading 1
Sieve Size 63mm 20mm 10mm Dust grading %
of finer
25% 10% 25% 40% Midium
Lower limit Upper limit
Limit
75mm 100.00 100.00 100.00 100.00 25.00 10.00 25.00 40.00 100.00 100 100 100
53 mm 70.76 100.00 100.00 100.00 17.69 10.00 25.00 40.00 92.69 90 80 100
26.5mm 0.28 99.04 100.00 100.00 0.07 9.90 25.00 40.00 74.97 72.5 55 90
9.5mm 0.00 5.03 53.90 95.42 0.00 0.50 13.47 38.17 52.15 50 35 65
4.75 mm 0.00 4.33 16.65 90.62 0.00 0.43 4.16 36.25 40.84 40 25 55
2.36mm 0.00 0.00 5.25 78.71 0.00 0.00 1.31 31.48 32.80 30 20 40
0.425mm 0.00 0.00 2.20 32.53 0.00 0.00 0.55 13.01 13.56 12.5 10 15
0.075mm 0.00 0.00 1.61 1.09 0.00 0.00 0.40 0.44 0.84 2.5 0 5
Aggregate size 63 mm, 20 mm, 10 mm, Sand mix in ratio 25:10:25:40 to achieve the combined grading.

Contractor Representive JE AE EE
PROJECT:- Widening & Strengtheing / Reconstruction work of Road From Mohanpur (on NH - 133) - karkdih - Dalawar -
Bhandaridih - Anjana More road (Length - 11.700 km) and Bhandaridih to Beldiha (MDR - 206) Link Road ( Length - 5.425 km)
(Total Length - 17.1225 km )
CLIENT RCD, GODDA, JHARKHAND
CONTRACTOR Rajbir Construction Pvt. Ltd.
Blending for Job Mix Formula of GSB Grade 1
Tested by - Jointly Date:
Individual grading (% of finer) For different size of aggregate
Required Percentage
Permissible limit(As per M.O.R.T&H
63 MM 20mm 10mm Dust Combined (Fifth Revision)Sec 400-1 grading 1
Sieve Size 63mm 20mm 10mm Dust grading %
of finer
30% 15% 20% 35% Midium
Lower limit Upper limit
Limit
75mm 100.00 100.00 100.00 100.00 30.00 15.00 20.00 35.00 100.00 100 100 100
53 mm 70.76 100.00 100.00 100.00 21.23 15.00 20.00 35.00 91.23 90 80 100
26.5mm 0.28 99.04 100.00 100.00 0.08 14.86 20.00 35.00 69.94 72.5 55 90
9.5mm 0.00 5.03 53.90 95.42 0.00 0.75 10.78 33.40 44.93 50 35 65
4.75 mm 0.00 4.33 16.65 90.62 0.00 0.65 3.33 31.72 35.70 40 25 55
2.36mm 0.00 0.00 5.25 78.71 0.00 0.00 1.05 27.55 28.60 30 20 40
0.425mm 0.00 0.00 2.20 32.53 0.00 0.00 0.44 11.39 11.83 12.5 10 15
0.075mm 0.00 0.00 1.61 1.09 0.00 0.00 0.32 0.38 0.70 2.5 0 5
Aggregate size 63 mm, 20 mm, 10 mm, Sand mix in ratio 30:15:20:35 to achieve the combined grading.

Contractor Representive JE AE EE
PROJECT:- Widening & Strengtheing / Reconstruction work of Road From Mohanpur (on NH - 133) - karkdih - Dalawar -
Bhandaridih - Anjana More road (Length - 11.700 km) and Bhandaridih to Beldiha (MDR - 206) Link Road ( Length - 5.425 km)
(Total Length - 17.1225 km )
CLIENT RCD, GODDA, JHARKHAND
CONTRACTOR Rajbir Construction Pvt. Ltd.
Blending for Job Mix Formula of GSB Grade 1
Tested by - Jointly Date:
Individual grading (% of finer) For different size of aggregate
Required Percentage
Permissible limit(As per M.O.R.T&H
63 MM 20mm 10mm Dust Combined (Fifth Revision)Sec 400-1 grading 1
Sieve Size 63mm 20mm 10mm Dust grading %
of finer
35% 10% 25% 30% Midium
Lower limit Upper limit
Limit
75mm 100.00 100.00 100.00 100.00 35.00 10.00 25.00 30.00 100.00 100 100 100
53 mm 70.76 100.00 100.00 100.00 24.77 10.00 25.00 30.00 89.77 90 80 100
26.5mm 0.28 99.04 100.00 100.00 0.10 9.90 25.00 30.00 65.00 72.5 55 90
9.5mm 0.00 5.03 53.90 95.42 0.00 0.50 13.47 28.63 42.60 50 35 65
4.75 mm 0.00 4.33 16.65 90.62 0.00 0.43 4.16 27.19 31.78 40 25 55
2.36mm 0.00 0.00 5.25 78.71 0.00 0.00 1.31 23.61 24.93 30 20 40
0.425mm 0.00 0.00 2.20 32.53 0.00 0.00 0.55 9.76 10.31 12.5 10 15
0.075mm 0.00 0.00 1.61 1.09 0.00 0.00 0.40 0.33 0.73 2.5 0 5
Aggregate size 63 mm, 20 mm, 10 mm, Sand mix in ratio 35:10:25:30 to achieve the combined grading.

Contractor Representive JE AE EE
PROJECT:- Infosys Campus SBD-I, Kolkata
CLIENT Infosys Campus SBD-I, Kolkata
CONTRACTOR M/S Ahluwalia Contracts (I) Ltd.
Blending Trials for GSB (Grade 1)
Tested by - Jointly Date:
Combined Grading
Individual grading (% Passing)
Trial 1 Trial 2 Trial 3
63mm 30% 25% 35% Permissible limit (As per M.O.R.T&H
Sieve Size
20mm 15% 10% 10% (Fifth Revision)Sec 400-1 grading 1

10mm 20% 25% 25%


Sand 35% 40% 30%
Passing Limit Passing Limit Midium
Passing Limit 1 2 3 Limit Lower limit Upper limit

75mm 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100 100 100
53 mm 70.76 100.00 100.00 100.00 91.23 92.69 89.77 90 80 100
26.5mm 0.28 99.04 100.00 100.00 69.94 74.97 65.00 72.5 55 90
9.5mm 0.00 5.03 53.90 95.42 44.93 52.15 42.60 50 35 65
4.75 mm 0.00 4.33 16.65 90.62 35.70 40.84 31.78 40 25 55
2.36mm 0.00 0.00 5.25 78.71 28.60 32.80 24.93 30 20 40
0.425mm 0.00 0.00 2.20 32.53 11.83 13.56 10.31 12.5 10 15
0.075mm 0.00 0.00 1.61 1.09 0.70 0.84 0.73 2.5 0 5
Aggregate size 63 mm, 20 mm, 10 mm, Sand mix in ratio 25:10:25:40 to achieve the combined grading.

Chart Title
120.00

100.00

80.00

60.00

40.00
100.00

80.00

60.00

40.00

20.00

0.00
1 2 3 4 5 6 7 8

Passing Limit 2 Column I Midium Limit Lower limit Upper limit


Contractor Representive JE AE EE
Project: - Widening & Strengtheing / Reconstruction work of Road From Mohanpur (on NH - 133) - karkdih -
Dalawar - Bhandaridih - Anjana More road (Length - 11.700 km) and Bhandaridih to Beldiha (MDR -
206) Link Road ( Length - 5.425 km) (Total Length - 17.1225 km )

Client :- RCD, GODDA, JHARKHAND


Contractor:- Rajbir Construction Pvt. Ltd.
Summary of G.S.B grading -1
MORT&H Specification limits
(Fifth Revision)
SL NO Description of test Result

1 Water absorption % of 63 mm Avg 1.12% Max 2%


2 Water absorption % of 20 mm Avg 1.22% Max 2%
3 Water absorption % of 10 mm Avg 1.28% Max 2%
4 Water absorption % of Dust Avg 1.35% Max 2%
5 Liquid limit Avg From 2 20.57% Max 25%
6 Plastic limit Avg From 2 N.P -
7 Plasticity Index Avg From 2 N.P Max 6%
8 M.D.D Avg From 3 2.230 gm/cc -
9 O.M.C Avg From 3 5.64% -
10 C.B.R Avg From 2 43.30% Min 30%

Contractor Representive JE AE EE
PROJECT :- Widening & Strengtheing / Reconstruction work of Road From Mohanpur (on NH - 133) -
karkdih - Dalawar - Bhandaridih - Anjana More road (Length - 11.700 km) and Bhandaridih to Beldiha
(MDR - 206) Link Road ( Length - 5.425 km) (Total Length - 17.1225 km )
CLIENT RCD, GODDA, JHARKHAND
CONTRACTOR Rajbir Construction Pvt. Ltd.
INDIVIDUAL SIEVE ANALYSIS TEST FOR JOB MIX FORMULA OF GRANULAR SUB BASE
MORTH & SPECIFICATION (FROM TABLE 400-1) GRADE: 1
Samle Location: Stock Piles; Source of Material : Mohanpur; Date of Sampling:
Description of Material: Dust Date of Testing:
Samle No-01 Samle No-02
Weight of Sample:1820 gm Weight of Sample:1602 gm
IS SIEVE Cum. Wt. Cum.% IS SIEVE Wt. Cum. Wt. Cum.%
Wt.Retained % Passing % Passing
(mm) Retained Retained (mm) Retained Retained Retained
75 0 0 0 100 75 0 0 0 100
53 0 0 0 100 53 0 0 0 100
26.5 0 0 0 100 26.5 0 0 0 100
9.5 94 5.16 5.16 94.84 9.5 67 4.18 4.18 95.82
4.75 52 2.86 8.02 91.98 4.75 61 3.81 7.99 92.01
2.36 169 9.29 17.31 92.69 2.36 394 24.59 32.58 67.42
0.425 950 52.2 69.51 30.49 0.425 532 34.21 65.79 34.21
0.75 534 29.34 98.85 1.16 0.75 530 34.08 98.87 1.13
pan 21 1.15 100 0 pan 18 1.13 100 0
Total wt. Total wt.
Samle No-03
Weight of Sample:1564 gm
IS SIEVE Wt. Cum. Wt. Cum.%
% Passing
(mm) Retained Retained Retained
75 0 0 0 100
53 0 0 0 100
26.5 0 0 0 100
9.5 116 7.42 7.42 92.58
4.75 37 2.37 9.79 90.21
2.36 126 8.06 17.85 82.15
0.425 844 53.96 71.81 28.19
0.75 432 27.62 99.43 0.57
pan 9 0.57 100 0
Total wt.
Remarks:

Contractor Representive JE AE EE
PROJECT :- Widening & Strengtheing / Reconstruction work of Road From Mohanpur (on NH - 133) - karkdih -
Dalawar - Bhandaridih - Anjana More road (Length - 11.700 km) and Bhandaridih to Beldiha (MDR - 206) Link
Road ( Length - 5.425 km) (Total Length - 17.1225 km )
CLIENT RCD, GODDA, JHARKHAND
CONTRACTOR Rajbir Construction Pvt. Ltd.
INDIVIDUAL SIEVE ANALYSIS TEST FOR JOB MIX FORMULA OF GRANULA-SUB-BASE
MORTH & SPECIFICATION (GRADING-1 FROM TABLE 400-1)grade1
Samle Location: Stock Piles
Description of Material: Date Tasted:
10mm Aggeregate
SIEVE ANALYSIS % OF PASSING
IS SIEVE(mm)
Sample No:1 Sample No:2 Sample No:3 Avg. % of Passing
75 100 100 100 100
53 100 100 100 100
26.5 100 100 100 100
9.5 50.34 54.28 57.08 53.9
4.75 15.25 16.34 18.36 16.65
2.36 6.38 4.38 4.99 5.25
0.425 1.78 0.97 3.85 2.2
0.75 1.22 0.58 3.06 1.62
pan 0
Dust
SIEVE ANALYSIS % OF PASSING
IS SIEVE(mm)
Sample No:1 Sample No:2 Sample No:3 Avg. % of Passing
75 100 100 100 100
53 100 100 100 100
26.5 100 100 100 100
9.5 97.35 94.25 94.66 95.42
4.75 93.28 89.63 88.92 90.61
2.36 72.33 81.37 82.37 78.69
0.425 23.09 35.95 38.49 32.51
0.75 1.12 1.17 0.95 1.08
Pan
Remarks: