TT-101 - Instrument-Commissioning-Checklist

1. An inspection checklist was completed for temperature transmitter TT-101 located at the TRZEBNICA project. 2. The inspection found that the equipment type, tag, installation, wiring, and HMI graphic were correct but the as-built drawings had not yet been sent to the client. 3. A state checklist showed the ambient temperature input from the PLC and local HMI matched but the high temperature state would need to be identified after heating and the sensor could be calibrated through a program adaptation.

Uploaded by

touili majdi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views2 pages

TT-101 - Instrument-Commissioning-Checklist

1. An inspection checklist was completed for temperature transmitter TT-101 located at the TRZEBNICA project. 2. The inspection found that the equipment type, tag, installation, wiring, and HMI graphic were correct but the as-built drawings had not yet been sent to the client. 3. A state checklist showed the ambient temperature input from the PLC and local HMI matched but the high temperature state would need to be identified after heating and the sensor could be calibrated through a program adaptation.

Uploaded by

touili majdi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

INSTRUMENTS CHECKLIST Page 1 of 1

Project:

Inspector: Project Name: JG4+ TRZEBNICA

Area: TRZEBNICA Client: NATURALNA ENERGIA

Equipment

Tag: TT-101 Description: Temperature transmitter percolate digester

Manufacturer: WIKA Model: TR11-H PT100 Serial Number:

Power supply: 19-28.5VDC Analog outputs: 4-20mA Digital outputs: 0

Inspection Checklist
Pass
No. Item to be Inspected Comments
(P/F)
1. Equipment type and class per P&ID and specification P

2. Equipment tag(s) installed and correct P

3. Installation of electrical circuit complete and correct P

4. Block and drain valves NA

5. Pneumatic / hydraulic tubing leak tested NA

6. Heat tracing / insulation / equipment housing P

7. Wiring correct P

8. Drawings marked up as-built Not yet sent to client F

9. HMI Graphic symbol and tag correct P

State Checklist

Pass
State Description PLC Local SCADA Comment
(P/F)
Input HMI
Ambient temperature 8.60 mA 3.5 °C NA To be calibrated P

50°C NA To be confirmed

100°C NA To be confirmed

Calibration
Setpoint Trip Point Actual Trip Point Calibration method Pass
State
(incl. units) (incl. units) (P/F)
ambient 9.00 mA / 3.7°C 8.60 mA From PLC program P

Max 20.00 mA / 100°C To be identified From PLC program

Comments:
- Medium and high levels of sensor feedback will be identified after heating
- The sensor can be calibrated by program adaptation
- Tag has to be installed

Company Name Signature Date


Methania Majdi Touili 06/12/2022
Tested By