CAVINKARE PRIVATE LIMITED

PURCHASE ORDER

Invoice To Order Number : 4500092646


CavinKare Pvt. Ltd, Dated : 14.12.2022
PlotNo16-17,Sector4 Qtn No / Contract No :
IIE SIDCUL,Ranipur,Haridwar, Terms of Payment : As Per Mutually Accepted Terms
Haridwar,249403 UK-Uttarakhand Mode of Payment : Bank Transfer(NEFT&RTGS)
GST NO: 05AAACB3754B1ZA
PAN.No: AAACB3754B

Delivery At : Supplier : Code : 3709042


CavinKare Pvt. Ltd, MENTOR WATER EXPERTS PVT LTD
PlotNo16-17,Sector4 Cubic Tower 65 Ballupur
IIE SIDCUL,Ranipur,Haridwar, Dehradun
Haridwar,249403 UK-Uttarakhand 248001
GST NO: 05AAHCM1789Q1ZQ
Dear Sir,
Please supply the following item/s in accordance with the terms & conditions stated herein.
1. Please ensure that your supply confirms to our specification. Non-compliance with terms/specs may lead to rejection.
2. Purchase order no. and date must be mentioned in your delivery challan/s and Invoice/s.
3. In case of any legal disputes arising out of this transaction,it is mutually accepted that the competent courts at Chennai alone will have exclusive
jurisdiction.
4. You are responsible for compliance to applicable legislation related to Environment,Health and Safety during transit to till the time material unloaded at
any CKPL Premises.
5. Appropriate packing of materials to avoid any spillage or damage during transit.(Use of good quality packing materials).
6. Please provide appropriate method of loading & unloading & MSDS to the transporters.
7. Please verify the vehicle/transportation unit before loading of any consignment.Below points of to checked.
I.Use only appropriate vehicle with necessary protection of the material.Vehicle use for transportation should comply with Motor Vehicle act 2020.
II.Use appropriate protective material inside/outside the carrier of the vehicle to avoid any damage/spillage of material.
III.Maintenance,sanitation details of the transporting unit/Containers to be verified.
IV.Use appropriate tracking facilities (GPS) for tracking during transit.
Note : Appropriate > As per our signed agreement/packaging & quality requirement....

S.No Item code & Description HSN UOM Qty Del.Date Rate Value
001 NO 1 28.02.2023 2780320.00 2,780,320.00
- EFFLUENT TREATMENT PLANT 75 KLD -
IN: Central GST 9.00 % on 2780320.00 250,228.80
IN: State GST 9.00 % on 2780320.00 250,228.80
Actual Unit Price 2,780,320.00 3,280,777.60
==============
Price as per scope mentioned in this Technical Offer-,
Rota Meter (Flow Meter) 1 NOS, Make # Astral
Bar Screen # 1 NOS , MOC- SS 304 , Standard # IEIL
oil Skimmer # 1 NOS # Standard # IEIL
Clarifier Feed Pumps # 2 NOS , Make # Kirloskar/LEO
SMFT # ION EXCHANGE
Lamella Clarifier 11 Plates Prefabricated # 1 NOS, Make # ION EXCHANGE
Dosing CDS # 3 NOS with High Speed Stirrer # Make- ION EXCHANGE
Air Blowers With pump # 2 NOS # Make # ION EXCHANGE/ Everest
Clarifier Feed Pumps # 2 NOS , Make # Kirloskar / LEO
Lamella Clarifier 11 Plates Prefabricated # 1 NOS, Make- ION EXCHANGE

For CavinKare Pvt. Ltd

Authorised Signatory

Page : 1 of 2
CAVINKARE PRIVATE LIMITED

PURCHASE ORDER

Invoice To Order Number : 4500092646


CavinKare Pvt. Ltd, Dated : 14.12.2022
PlotNo16-17,Sector4 Qtn No / Contract No :
IIE SIDCUL,Ranipur,Haridwar, Terms of Payment : As Per Mutually Accepted Terms
Haridwar,249403 UK-Uttarakhand Mode of Payment : Bank Transfer(NEFT&RTGS)
GST NO: 05AAACB3754B1ZA
PAN.No: AAACB3754B

Delivery At : Supplier : Code : 3709042


CavinKare Pvt. Ltd, MENTOR WATER EXPERTS PVT LTD
PlotNo16-17,Sector4 Cubic Tower 65 Ballupur
IIE SIDCUL,Ranipur,Haridwar, Dehradun
Haridwar,249403 UK-Uttarakhand 248001
GST NO: 05AAHCM1789Q1ZQ

S.No Item code & Description HSN UOM Qty Del.Date Rate Value
Chlorine Dosing tank PVC 5000 Litters # 1 NOS , Make # Sintex / himgiri
Dosing System # 1 NOS , Make # ION EXCHANGE
MGF & ACF # Media as per 1200mm-Dia , Standard IEIL
Sludge Recirculation Pump- 2 NOS, Make # Kirloskar / LEO
Filter Press Manual # 24 Plates With Screw Pump #Approved by ION EXCHANGE
ICPW , Standard # Approved BY ION EXCHANGE
Existing ,Electrical Panel Modification # Standard & Approved By ION EXCHANGE,
002 AU 1 28.02.2023 36000.00 36,000.00
- Installation and Commissioning -
IN: Central GST 9.00 % on 36000.00 3,240.00
IN: State GST 9.00 % on 36000.00 3,240.00
Actual Unit Price 36,000.00 42,480.00
==============
Plant Installation and Commissioning, and ETP Plant observation for one month
- Charges -
________________________________________________________________________________________
PAYMENT TERMS & CONDITIONS : 20% Advance against PO, 60% advance
against readiness of material for dispatch, 10% after Installation and
10% payment after Erection

1.Kindly ensure that in factory premises use proper PPEs while


performing any maintenance/service activity.
2.Kindly ensure that any activity which you are performing in factory
premises should not affect to Environment, person safety, and
work/product quality.
3.CavinKare is Not Responsible for any material damage during transit.
4.CavinKare is Not Responsible for any property (Like: material delivery
vehicle, Equipment Etc.)Damage in company premises.

Total : INR 3323257.60


Amount in Words : THIRTY THREE LAKH TWENTY THREE THOUSAND TWO HUNDRED AND FIFTY SEVEN
PAISE SIXTY ONLY

For CavinKare Pvt. Ltd

Authorised Signatory

Page : 2 of 2
Pure & Cure Healthcare Pvt.Ltd.(Pure & Cure)
Plot No.26A,27,28,29 & 30 Sec 8A, I.I.E.,SIDCUL,Ranipur Haridwar Uttarakhand India 249403
Ph N.o: 01334-234327-234328 01334-234330 E-Mail : works@akums.in

GSTIN No. : 05AAECP0713G1ZX Mfg Lic No : 51/UA/SC/P-2013


CIN No. : U24232DL2005PTC266385 31/UA/2013
PURCHASE ORDER
110312 Vendor GSTIN No. 05AAHCM1789Q1ZQ PURCHASE ORDER 4500718789
MENTOR WATER EXPERTS PRIVATE LIMITED P.O.DATE 07.06.2021
16 A PRAKASH NAGAR, CHAKRATA ROAD
DEHRADUN 248001 Uttarakhand
0135275224 7351011031 Our PAN No. : AAECP0713G
industry@mentorwater.in State Code : 05

SNo. Item Description UOM Quantity Accep Rate INR Del.Date Amount INR
tance
Limit
+ %
1 EFFLUENT TREATMENT PLANT(250KLD) NOS 1.000 0.0 3600000.000 31.08.2021 3600000.00
MAKE: ION EXCHANGE PLANT INLET
CAPACITY : 250 m3/DAY INLET
EFFLUENT FLOW :CONTINUOUS
OPERATING HOURS :24 FLOW ;250 KLD
PH:5.0 # 8.TOTAL SUSPENDED SOLID
(TSS):250-350 mg/l TOTAL
DISSOLVED SOLID (TDS) : 750 mg/l
REST DETAILS AS PER ATTACHED
ANNEXURE LOCATION NEARF-BLOCK
Mat.No: 50007234 HSN No: 8421
JICG @ 9% JISG @ 9%
2 EFFLUENT RECYCLE SYSTEM(250KLD) NOS 1.000 0.0 2900000.000 31.08.2021 2900000.00
MAKE: ION EXCHANGE RO FEED FLOW
:13 M3/hr RO FEED TDS :750 mg/l
RO PERMEATE FLOW :6.5 M3/hr RO
PERMEATE TDS :<(><<)>50 mg/l RO
REJET FLOW : 6.5 M3/hr RO REJECT
TDS : <(><<)> 2100 RECOVERY : 50%
ERS SYSTEM FOR 50% RECOVERY OF
250KLD ETP EFFLUENT. THESE WILL
BE INSALL IN PLANT PREMISES NORTH
SIDE (NEAR F-BLOCK)
Mat.No: 50007235 HSN No: 8421
JICG @ 9% JISG @ 9%

1 of 3
PURCHASE ORDER
110312 Vendor GSTIN No. 05AAHCM1789Q1ZQ PURCHASE ORDER 4500718789
MENTOR WATER EXPERTS PRIVATE LIMITED P.O.DATE 07.06.2021
16 A PRAKASH NAGAR, CHAKRATA ROAD
DEHRADUN 248001 Uttarakhand
0135275224 7351011031 Our PAN No. : AAECP0713G
industry@mentorwater.in State Code : 05

Incoterms : EXW - GOA Total Item Value 6,500,000.00


PAYMENT TERMS : 25% ADVANCE PAYMENT IN: Central GST 585,000.00
AGAINST ABG VALID FOR 4 MONTHS FROM PO IN: State GST 585,000.00
DATE , 65% AGAINST PI BEFORE DISPATCH
THE MATERIAL AND BALANCE 10 % AFTER
SUCCESSFUL INSTALLATION AND
COMMISSSIONING AND HANDOVER SYSTEM WITH
3 MONTHS TRIAL HANDOVER AFTER DESIRED
TDS.

DRAWING SUBMISSION WITHIN 7-10 DAYS FROM


THE DATE OF PO.
INSTALLATION COMMISSIONING AND
SUPERVISION IN VENDOR SCOPE
INSTALLATION PERIOD : 4 WEEKS AFTER
CIVIL WORK COMPLETION.
COMMISSIONING : 2 # 3 WEEKS AFTER
INSTALLATION.

SUPERVISION FOR 03 MONTHS POST


COMMISSIONING WILL BE FREE OF COST

ALL WORK SHOULD BE DONE WITHOUT SHUT


DOWN OF EXISTINTG PLANT.

FREIGHT WILL BE PAID BY PURE AND CURE


ONLY RS.100000/- IF FREIGHT VALUE GOES
HIGHER THAN 1 LAC IT WILL BE PAID BY
MENTOR WATER/ION EXCHANGE.
(INR.SEVENTY-SIX LAKH SEVENTY THOUSAND RUPEES AND ZERO PAISE) Grand Total 7,670,000.00
For 250 KLD ETP+ UF+ RO
· Bar Screen
· Oil <(>&<)> Grease
· Equalization tank.
· INDION®HRSCC (High rated Solid Contact Clarifier)
· Aeration tank
· Secondary Clarifier
· Clarified water Tank
· Chlorine Contact tank
· INDION® MGF
· INDION® ACF
· UF Feed tank
· INDION®Ultra Filtration
· RO Feed Tank
· INDION® Reverse Osmosis
· RO Permeate Storage Tank
· Sludge Holding Tank

2 of 3
PURCHASE ORDER
110312 Vendor GSTIN No. 05AAHCM1789Q1ZQ PURCHASE ORDER 4500718789
MENTOR WATER EXPERTS PRIVATE LIMITED P.O.DATE 07.06.2021
16 A PRAKASH NAGAR, CHAKRATA ROAD
DEHRADUN 248001 Uttarakhand
0135275224 7351011031 Our PAN No. : AAECP0713G
industry@mentorwater.in State Code : 05

· Sludge Handling system


Rest details as per attached annexure.
GENERAL TERMS AND CONDITIONS
01.PACKING AND FORWARDING INCLUSIVE IN VENDOR SCOPE
02.TRANSIT INSURANCE-INCLUSIVE IN VENDOR SCOPE
03.LIQUIDATED DAMAGE: IN CASE, YOU WILL NOT BE ABLE TO DELIVER THE
MACHINES WITHIN SCHEDULED TIME, YOU WILL BE LIABLE TO PAY US LIQUIDATED
DAMAGES @1% OF COST OF MACHINERY PER WEEK OR PART THEREOF WITH THE
MAXIMUM OF 10% OF TOTAL COST.
04.INSTALLATION,COMMISSIONING AND SUPERVISION : INCLUSIVE IN VENDOR
SCOPE.
05.WARRANTY: ALL ABOVE MATERIAL WILL BE GUARANTEED FOR A MINIMUM PERIOD
OF 12 MONTHS FROM THE DATE OF SUCCESSFUL INSTALLATION OR 18 MONTHS FROM
THE DATE OF INVOICE. HOWEVER, DURING WARRANTY PERIOD, IF THE MACHINE
GOES UNDER BREAKDOWN, THE DAYS UNDER BREAKDOWN SHALL NOT BE CONSIDERED
IN THE ABOVE WARRANTY PERIOD AND WARRANTY PERIOD WILL BE EXTENDED
06.DQ,IQ,OQ,PQ DOCUMENTS AND TEST CERTIFICATES TO BE PROVDIED BY YOU ON
FOC BASIS.
07. STAMPPING IN THE VENDOR SCOPE FROM WEIGHT AND MEASUREMENT DEPTT.
Terms & Conditions of Purchase Order
The following points needs to be adhered while making an invoice. In absence of any of these mandatory
requirements, the invoice/ material WILL NOT be accepted:
01.All invoices must bear our Purchase Order No. and the same delivery address needs to be mentioned as in
the Purchase Order header.
02.The criteria of Quality as defined in the Purchase Order must be followed, failing which, the bill/
material will not be accepted.
03.The materials/ machines must be dispatched with proper E-Way bill wherever applicable.
04.The original invoice and other related documents must be addressed to our Commercial Dept as per the
address mentioned in the Purchase Order header.
05.No payment shall be paid, if the Vendor does not deposit the GST amount timely and furnish the appropriate
return within due date.
06.In case advance payment has been made, Vendor will timely deposit GST and will file appropriate return
within time. In case of failure recovery will be made along with applicable tax, interest and penalty.

PREPARED BY APPROVED BY APPROVED BY APPROVED BY APPROVED BY


ANOOPDUKLAN Purchase Head Plant Head Finance MD
Corp.Off: Saraswati Vihar, Mohan Place, LSC, Block-C, 305 Delhi Ph:011-47511000 Fax:011-27023256

3 of 3
Disc. %
Disc. %
Disc. %
Disc. %
Disc. %
*

?/ ur Education Foundation
September 10,2022

M/S. MENTOR $TATER EXPERTS pVT. LTD.


Cubic Tower, 65 Ballupur,
Chakrata Road,
Dehradun - 248001(UD.

Attn: Mr. Raiender Chamoli

Sub : WORK ORDER FOR SUPPLY, INSTALLATION, TESTING &


COMMISSIONING OF 6OKLD SEWAGE TREATMENT PLANT STITH
EQUIPMENTS FOR PROPOSED INTERNATIONAL SCHOOL PUNE
AT OPPOSITE CLUB HOUSE, YOO VILLAS AT VILLAGE WAGHOLI -
412207, DISTRICT PUNE, MAHARASHTRA.

Dear Sir,

\i7ith reference to your final offer dated 07.09.2022andvarious


discussions had with you for the
above mentioned work, we are pleased to accept your offer and issue this Work Ordei to
lres fe,
SITC of STP Works for the above mentioned project.

It is expressly understood and agreed that your last tender submission is unconditional and in full
compliance with the technical and commercial terms of the tender docurnents and its acldenda,
subject to the qualifications / deviations attached to your Tender Form.

COMMERCIAL

SCOPE OF WORK

Supply, Installation, Testing & Commissioning of Sewage Treatment Plant based


on MBBR Technology of 60 KLD capacity (Moving Becl Bio Reactor Technology
* Ultra Filtration) with Equipmenrs as per attached price Scl-reclr-rle.

) CONTRACT AMOUNT

Wc are pleased to arvard the above mentioned work for a total amount of
Rs' 70,94,592/- (Rupees Sevenry Lacs Ninery Four Thousand Five Hundred
Ninety Two Only) inclusive of all taxes & duues but excluding GST which shall be
payable extra as apphcable on the basis of Schedule of Rates enclosed herewith.

otr eo(SBE"undation

Director
[)age - I

r:t
I I .gr 13s 271 leoo F7 .o.p.omm@unisonindiq com
H I *:::ff::.%11?1ltt,.oror,na
Registered under The Componies Act, AO13 I CIN NO.: U8O9O4UReOl7NpLoOglgl
3. TIME SCHEDULE

Since timeof compleuon is the essence of this contract all efforts should be made by you
to complete all the works within 16 (Sixteen) Weeks or as per the below schedule:

o Delivey Time: delivery shall be 8 - 10 weeks ftom the date of issue of Work Order
& advance.
o Installation time: Installation shall be 8 weeks from the date of receiving of mateial
at site.

'Ihe date of start of this cofltract shall be considered from the date of issue of this work
otdet and date of handing over of the completed installation shall be as per the above
agteed milestones which shall form part of the contract.

4. BASIS OF DESIGN

As per tender document and drawings and shop drawing duly approved by the
consultant.

5. PRICE

(r) This is an item rate contract and the price quoted shall be final within the scope of the
drawings, Specifications and B.O.Q. as mentioned in tender documents. These unir rates
shall remain Ftm and shall not be subject to any revision whatsoever during the currency
of this cofltract. The above agreed prices are FOR Site Pune.

(r) The overall item rates are inclusive of all taxes & duties, other levies, PF, ESI, license for
wotking at State of Mahatashffa, cartage, lead, lift, cost of material and labour, Insurance,
Packing, Forwarding, Transpottation, Loading, Unloading etc. and nothing extra shall be
payable on these accounts. Howevet GST shall be paid extra as per actual.
The Scope of work also includes obtaining 1. Consent to Establish, and 2. Consent to
Operate from Pollution Conffol Board for entire project. Fee for which will be paid as
per mutual agreement between both the parties

6. QUANTTTY VARTATTON

The UNIT item rates will remain frm for Qty. variation up to any extent.

7, PAYMENT TERMS

It is agreed that payment shall be made as under:

(, 5o/o of the contract value shall be paid as advance along with the work order.
(ii) 25o/oof the contract value shall be paid against approval of shop drawings and
technical submittals.
(r") 45o/oof the contract value shall be paid against readiness for dispatch of material
against submission of Performa Invoice.

DIT Edu
Page - 2

Director
(t) 1,0o/o of the contract value shall be paid against Installation / Erection of all
equipments duly certified by the Project Nlanager.
(") 1,5o/o & commissioning duly
r>f the contract value shall be paid against testrng
certified by the Project Manager /consultant and after submission of Handing
over documents / OEM Certificates f manufactuter cettificates etc. All requiled
as per tender document.

8. LABOUR CESS

Labour cess shall be deducted @ 1o/o of the value of worh done.

9. DEFECT LIABILITY PERIOD / WARRANTY PERIOD

Your Defect Iiability Period/comprehensive Warranty on all equipment / complete


installation of the plant shall be 3 (Three) Years from OEM from the date of
completion of commissioning or handing over whichevet is later. Mentot $Vater Experts
Pvt I-td.'s shall submrt full system 3 Years' waffaflt:! (performance and extended
warranty) on non-judicial stamp paper duly notarized by the competent authority. All
OEM Certificates shall also be submitted along with the waff^nq certificate. All inclusive
comprehensive mainteflance is also part of scope of DLP.

Any defects in material or workmanship obserwed during the execution of wotk or


within defects liability period shall be rectified by you at your own costs within time
frame specified by us. In case you fail to rectify any defects, the same will be rectified by
us at your risks and costs.

10. EXISTING FACILITIES


You will ensure, while worldng, that no damages are done to other facilities and will
make all necessaly provisions to protect them while executing the wotk at site and
proper screening of work will be done so that other neighborhood buildings / facilities
are not disturbed. It shall be noted that all liabilities shall be yours incase of any damage
to any of the surrounding buildings, our property or other agencies properry worki.ng at
site due to any negligence during execution.

t't. THE FOLLOWING RECORDS ARE TO BE MAINTAINED AT SITE


. Measurement books for different subheads.
. Site order book.
. Ptogramme of work displayed at site.
. Material teceipt and tesung register.
. Statutory liabilities like PF, GST etc.

12. ESCAU.TION

It is hereby agreed that there shall not be paid any Escalation either on material ot labour
during total contract period.

DIT Undation

Dlrector Page - 3
13. SPACE FOR LABOUR HUTMENT / SITE INFRASTRUCTURE

You shall be allowed to set up youf site inftastructure and stores at the place earmarked
by the PMC. Temporary construction of stote shall be under your scope. You shall
make your own arrangement for housing for your labourers at your own cost outside the
site ptemises. You shall also be responsible for making al1 necessary arrangements for
labour's sanitation and security fot such hutment/ infrastructure at youf cost. Also, you
shall remove all such temporary coflstruction, etc at your own risks and costs before
handing over and as and when directed by the Owner/ PMC.

14. INSURANCES

The quoted rates are inclusive of all habilities towards Provident Fund / ESI for all
workers employed by you in the construction work. A statement along with copy of
challans showing the details of PF / ESI compliance shall be submitted by you monthly.
You shall also indemnify the Owner against any claims on the same during and after the
project.

The quoted rates are inclusive of all the insurances like CAR policy Workmen
Compensation, Third Party Insurance etc. will be submitted with the Owner within 15
Days of start of the work. All the insurances submitted shall be kept live till the final
handing over the site after the commissioning.

Necessary insurance of labour against any injuries to labour or damage to tools & plants
on account shall be got done by you and the copy of the same sent to us. The Client
^ny
shall not be responsible for any injudes or damage to labour or equipment etc. in any
mannef.

15. PERMISSIONS

You shall attange, provide all relevant documents, test reports ofl successful
commissioning of STP required in connection with the work at your own cost for
seeking,Permission from Maharashtra State Pollution Control Board. You will provide
all assistanc e in arranging the same. Consent to establish and consent to op"rrte from
pollution conttol board are also in your scope.

16. LIQUIDATED DAMAGES

LiquidatedDamages /Penalty shallbelevied @0.5%o of thecontractvalueperweekof


delay after agreed completion time, limited to a maximum of 5o/o of the contract value
(inclusive of amounts, increases or decreases, in respect of change orders).

17. PRICED BILL OF QUANTITIES

It is confrmed that the work executed shall be measured and paid for as per the actual
quantities executed as per the shop drawings duly approved by the Consultants f
Atchitects only.

DIT Ed n Foundation

Page - 4
Director
18. TESTING

All the tests on materials, equipment, and workmanship that shall be necessary in
connection with the execution of the \7ork shall be done by you from NABL acctedited
Lab from outside at your cost as detailed in the contract document.

19. WATER & ELECTRICITY

\Water & Electricity shall be drawn from the main civil Contractor's designated metered
point installed at site on chargeable basis. Any furthet distribution / storage shall be
arranged by you at your own cost upto any height / level. Al1 consumption charges
recorded in the meter against the same shall be paid to the Civil contractor direcdy by
you.

20. LOCKABLE STORAGE OF MATERIAL

Only space shall be provided to you for making lockable store. You shall make your own
store and lock & key arrangement to store the material. You shall be responsible for
watch and ward of the material whether procured by you or free issued to you (if any).
You shali be responsible for any pilferage, theft and damage of the equipment f material
till it is installed, commissioned and handed over to us.

21. SAFETY PROVISIONS

The Conmactor shall take full responsibility for the adequate stability and safety of all
their site operations and methods of execution of work, subject to provision of excepted
risks and special risks. The Contractor shall at his own expense affartge for the safety in
his operations as required. Safety provisions shall be as per the latest safety manuals
published by Indian Standard Institution, Statuary Rules, Regulations and Provisions of
contfact conditions and as per the attached Safety Manual issued by the Project Manager.
In case the Conmactor fails to make such arrangements the Owner / Prcject Manager or
his Authorized Representative shall be entided to cause them to be provided and to
recover the cost thereof from the Contractor. "Site Safety Measures" and all "Safety
Habits are required to be taken and ensured by the 'Conttactor'. This includes wearing
safety helmets, gumboots while working, gloves and safety belt etc. electtical safety and
proper housekeeping at project site.

22. REVENTION OF POLLUTION

The Contractor shall ensure that at all times during the execution of the works that all
reasonable precautions are taken to the satisfaction of the Owner / Project Manager f
his Authorized Representative to prevent pollution of site and of the environment.
Furthet, the Contractor shall take all the steps necessary to protect the Environment and
comply with all the NGT rules, regulations, notifications etc as applicable and indemnify
the Owner / Project Manager against the same.

You shall comply with the following at the project site in addition to the strict
compliance of the NGT gurdelines as applicable today:

NIT E Foundation

Page - 5
Director
All debris/garbage and wastes resulting from the execution of the work wrll be
removed immediately from the site to avoid any nuisance/hazards to other
agencies /working staff.
a Tyres of each vehicle to be washed before going out of the site.
a Compliance of all Covid-L9 guidelines shall be stricdy followed as mentioned in
attached Annexure.

Non-compliance of the above will atttact a recovely of Cost ph;s 20oh of that particular
items.

23. COYID-l9 COMPLIANCE

The Contractor shall adhere to follow government rules, regulations and advisory to
compliance of Covid-19 precautions at site during execution period. !7o* must be
undertaken in compliance with guidance published by the Ministry of Health / Nodal
Agency for compliance relevant to the work and intended to limit the risk of spreading
Covid-19. Any of the pertnit, approval related to Covid-19 required to be taken from
government or any other authority will be taken care by Contractor. Covid-19 special
gutdelines is attached as an Annexure.

24. SCAFFOLDING

It is conftmed that all scaffolding as required for the project shall be arranged and
provided by you at your owfl cost. You shall be responsible for its assembling, fixing &
dissembling as per your requirement at site.

25. CONSENT TO ESTABLISH AND CONSENT TO OPERATE (CTO)

You shall be contractually obligated to liaison with Pollution Control Board, Pune,
Maharashtra for obtaining approvalf consent to establish and approval/consent to
operate from Pollution Control Board (PCB) fot all packages for the entire project will
be in your scope. Actual cost of the same shall be reimbursed to you post issuance of
consent. Handing over of the plant will be consideted after receiving CTO permission.

26. TECHNICAL COORDINATION POST ISSUE OF WORKORDER BY PMC


A1l technical coordination post issue of Work order and day to day supervision at site
shall be handled by our PMC M/s. Jones Lang LaSalle Propety Consultants (India)
Pvt. Ltd. (ILL).

27. OTHERS

1. Panel shall be from same manufactuters as in othet packages as approved by


Client/PMC.
2. Contractor shall submit to the Client quartedy test reports for raw f teated / flushing
water.
3. Conttactot's Supervisor shall be well quali{ied with 4-5 yrs experience.
4. Dudng Maintenance period the Vendor's resources should be well dressed up with
safety equipments like safety shoes, gloves, nose mask, oxygen cylinder, all personal
protective equipments. Also shall maintain the following documents like
. log book,

Drr Educslildation Page - 6

Director
. daily chemical consumption
. plant parameters like- MLSS, pH, Clearity, Smell, TDS on site
. trouble shooting within 24 hrs
5. Cost of consumables like sodium hypo, HCL, NaOH, Bacterial Culture etc. are to be
used during installation is included in above prices.

28. EXCLUSIONS
The followings are the exclusion from the conttact amount:
l. Civil works like tanks, foundations, MS hand tail etc.
2. Disposal of dried sludge.
3, Sewer inlet into Bar scteen chambet, oudet for treated water.
29. CONTROL
You shall be responsible for Quality control monitoring through periodical audit at your
own cost. '

30. You will be required to furnish detailed works programme for all Blocks /micro level
pert chart in relation to the overall compleuon time. Vfeekly project co-ordination
meeting will be held at site to monitor above programme / progr.rr and wherever
required. Suitable modrfication shall have to made by you to achieve overall targets. A
full-time technically qualified Project Manager of requisite experience will need to be
stationed at site during execution period to ensure co-ordination, quality, safety, progress
etc. and to update the Owner, Architects & Project Manager about the progress besides
replying ther queries.

31. As per statutory provisions, deductions shall be made on account of Income tax / other
statutory deductions etc. from your bills as applicable and nothing extra shall be payable
on this account.

32. You shall abide by all labour laws in respect of all the labour/manpower engaged for this
work. In the event of any liability on DIT EDUCATION FOUNDATION by virtue
of its being the Principal Employer, due to your failure to comply with all required
statutory compliances, you will indemnify and reimbutse the amount payable by
DIT EDUCATION FOUNDATION on this account.

33. Samples of matedals to be used in wotk must be got approved ftom the Consultants /
Architects / Prcject Managers well in advance before taking up the execution.

34. Materials tequired fot satisfactory completion of work shall be of best quality, make,
grade, as mentioned in the Pdce Schedule and f or conf<>rming to Indian standatd
specification (atest edition), wherever appl-icable, and apptoved by Engineer-in-
Charge / P rcj ect Manager.

35. All disputes & differences of any kind in the contract, it shall be amicably settled or
otherwise the arbitrator shall solely be deputed by the Chairman of DIT EDUCATION
FOUNDATION, the disputes and differences that still arise shall be subject to the
iurisdiction of appropriate courts.

36. CANCELLATION OF THE CONTRACT:


Any time without any prejudice DIT EDUCATION FOUNDATION shall have the
right to cancelfTerminate th.e contract fully/pardy giving prior written notice of 3 days
oti eoucataon Foundation
Page - 7

Director
to you. No compensation other than the completed acuvities will be paid to you with in
one month.

37. DIT EDUCATION FOUNDATION shall be at liberty and is empowered to curtail


the scope of work of any item in part/full from this contract and can get it executed by
own depattmentally or from some other agency aly time, for which no compensation
shall be allowed to you. ^t

You will submit & execute a Tripattite lTarranty Agreement on a non-judicial stamp paper of Rs.
100/- (R.upees Hundred only) after completion of work & handrng of the plant along with your
final bill.

We are sending this work order in duplicate. I{ndly sign the duplicate copy in token of your
acceptance of all terms and conditions of this letter and return the same to us. The tender
document issued to you shall also form patt of this contract which shall be also be signed.

!7e look forward to your support and co-operation in timely completion of this work.

Thanking you,
Fot DIT EDUCATI ON FOUNDATI ON
ucetion Foundatior

We heteby acknowledge teceipt of the Work Ordet and confirm our acceptance of the
same.

Fot and on behalf of M/S. MENTOR WATER EXPERTS PVT. LTD.

(Raiendta Chamoli) Date:


Executive Directot

Enclosure: 1. Price Schedule


2. Covid-19 Guidelines
3. Tender Document

Page - 8
ANNEXURE

GUIDE LINES FOR STUDY AND FOLLO\UT INTO PRACTICE

COVID-l9 (OMICRON & other variants) SPECIAL GUIDE LINES

WORK PLACE Common Facilities 1,. No labour / worker shall be allowed to stay at
site.
2. One sepatate Isolation room has to be made
available at site in case of a worker having fevet
/ discomfort of unusual symptoms found.
3. No food to be prepared at site.
4. All workers and labours are having proper
documents like I-Card, i\dhar Card, Arogya
Seru App, IVledical checkup certiFtcate, a letter
from builder and the company regarding their
sion to be presence at that site on

(r) For each and every labouts and all other staff
or person at site enters, aII arc to be checked
with temperature apparatus, it is mandatory for
all and record is to be maintained at site.
(ii) Authenticated sanitlzer point is must and
prefembly at the entrance to the site is to be
installed prior to commence the work /
(iir) One person among the staff is nominated to
ensure that every one must go through this
spray tunnel at least befote work starts, after
lunch and at the end of tl-re days work.
(rg All staff members are provided with a small
bottle of sanitizer to apply on tireir hands at an
houdv interval of time.
(v) AII tools and tackles wl-rich are to be used by
hands must be sanitized with mobile tnanuai
spray gun with authentic sanitizet.
(vi) Along wrth First Aid I(t, VITI\MIN "C"
tablets must be in sufficient stock so tl-rat it can
be distributed once in a day to all staff
members, labours and workets.

Petsonal Care (t) It is absolutely mandatory to wear Face Mask,


without which no person should allowed at site
and at site office.
(ii) SufFrcient quantity of washable face mask and
hand gloves to be provided to all persofl at site,
office, labourers and workers.
(iii) Flelmets on the head and apron is must to wear
and helmets are kept sanitized at least twice a
day, also reusable hand gloves and masks to be
washed on daily basis.

(iv) Not to throw discatded mask and hand


gloves anywhete on the site, it is strictly
ibited, collect it at definite small
ucat
Page - 9

Director
container with lids and disposed it off
eithet by burning to ash or to Govt. gatbage
collection vehicle. This is extremely
important and all wotkers, labouters and
site persons needs to be vigilant on the

(v) Develop a habit to wash hands daily 3 times


before lunch and 3 times aftet lunch till end of

(vi) I(eep always for all labourers and workers 2


numbers of water bottle each of one litre, one
hlled with drinking water and one filled with
one spoon sugar, salt and vitamin "C" tablet in
to it or a lime water into it. Develop a habit to
drink after every 30 minutes some water to
keep throat wet from inside and person

Social Distancing This is exttemely impottant and all the time


should be observed and maintain even during
the wotk
(, Don't gather all the site wotkers for tea or
snacks or even lunch and dinner but in a small
group of 3 to 4 members at a time with keeping
distance o[ minimum 6' (six feet) from person

(ii) Plan the site level activities in such a way that


the minimum distance of 4 feet is to be
maintained between all the workers and
labouters.

TECHNICAL Itis exffemely important to keep study above


STAFF AND and made practice / culture to work as per
MANAGEMENT above mannef and later on as pef the new
At this point of time it is important to educate our
working hands, workers and labours and keep
observing and support them in maintaining their
sanitized condition and healthy environment in
which all are working to develop not only self
confidence but to improve confidence level into

INFORX,{ IMMEDIATELY OR IN ADVANCE


TO CLIENT, PMC incase of deficiency in the
stock of sanitizer, soap or medicine, mask, gloves or
other necessary requirements at site to cop up the
situation in advance.

Along with site fumigation and sanitization, vehicles


also needs to be sanitized on daily basis.

It is actually collective responsibility of


all workers
and site engineers and superwisors, but specially to
site supervisors and engineers, keep maximum
focus on to maintain site condition clean and

Page -

Director
l'r1,gicnic.

Iieep all table top sLrrface clean and all record books
propedy filles and a cleaned up with a cloth soaked
in dilute disinfectants / sanitizer daily.

Note: a. Any suggestion, change as per the


infotmation available and as per the site
condition and nature of ptoiect is invited
fot imptovement.

b. Poster at the entrance to the site is to be


fixed which ptovides methodology through
pictures how to keep oneself safe and
hygiene as per the Govt. guidelines.

.'ducation Foundation

Director

Page- ll
Schedule of Rates FINAL BOQ. SEWAGE TREATIVENI PLANT
lnternational School pune

SCHEDULE OF QUANTITIES
PREAMBLE:

The proposed Sewage treatment plant at WCI Campus, Pune shall consist of the following facilities :

'l The Sewage and Kitchen waste ( through the desired Grease traps) shall be collected in a common Collection-cum-Equalisation tank (designed for final capacity ).

2 This will be followed with secondary biological treatment system which will be designed in the modular form. The blowers and diffused aeration system shall also be

3 This will be followed with filtration and disinfection units, again designed in modular form i.e. one set dedimted to 1 module and common standby units. UV is proposed

4 lt is proposed to have separate collection tanks for lrigation, Flushing and Soft Water. The scheme is enclosed. The transfer pumps/ hydropneumatic systems for

5 Separate secondary sludge Aerobic sludge digestor-cum-thickner is proposed with provision for supemanant withdrawal and sludge dewatering system such as filter

6 All items ofwork under this Contract shall be executed skictly to fulfill the requirements laid down under "Basis of Design" in the specifications. Type of equipment,

7 The unit rate for all equipment or materials shall include cost in INDIAN RUPEES (lNR) for equipment and materials including all taxes and dutjes and also including

8 The rate for each item of work included in the Schedule of Quantities shall, unless expressly stated othemise, inctude cost of:

a. All nateials, fixing materials, accessodes, appliances tools, plants, equipnent, transport, labour and incidentals required in preparatbn for and in the futl and entire

b. Wastage on mateials and labour.

d. Liabilities, obligations and isks aising out of Conditions of Contract.

e. All requirements of Specifications, whether such requirements are mentioned in the item or not. The Specifrcations and Drawings where available, are to be read as

f. ln the event of conflict between Bill of Quantities and other documents including the Specifications, the most stingent shalt apply. The interpretation of the Architect /
9 The Contractor shall procure and bring MaterialsiEquipment to the site only on the basis of drawings approved for construction and shop drawings and not on the basis

1 0 The contractor shall include for making all the opening in walls etc. as required for his work. However, the contractor €n coordinate with civil work to provide necessary

1 1 The work shall be carried out in conformity with the plumbing drawings and within the requirements of architectural, HVAC, electrical structural and other specialized

1 2 The contractor shall cooperate with all trades and agencies working on the site. He shall make provision for hangers, sleeves, slructural openings and other

13 On award of the work, contractor shall submit a schedule of construction in the form of a PERT chart or BAR chart for approval of the Project Manager.

14 Onawardoftheworkthecontractorshallbeissuedtwo(2)setsofconsultant'sdrawings. Thedrawingsshallbethebasisofcontractor'sshopdrawings.

1 5 Shop drawings are detailed working drawings coordinated with other trading work, which incorporate the contractor's details for execution of the work and incorporate

16 All shop drawings should detail pipe routing and levels, showing location of other seruices at crossings elc., cable runs, route cable trays and all allled works and must

17 All shop drawings will be made on Autocad and coloured prints has to be produced for site work.

1 I All rates quoted are inclusive of cutting holes and chases in walls and making good the same with cement mortar / water proofing of appropriate mix and strength as

'19 The contractor shall, from time to time, clear away all debris and excess materials accumulated at the site failing which the same shall be done by Prc.iect Manager at

20 After the fixtures, equipment and appliances have been installed and commissioned, contractor shall cleanup the same and remove all plaster, paints, stains, stickers

21 On completion ofall works, contractor shall demolish all stores, remove all surplus materials and leave the site in a broom clean condition, failing which the same shall

DIT Educati

Director

sTP-SOQ- l
Schedule of Rates FINAL BOQ . SEWAGE TREATI\4ENT PLANT
lnternational School Pune

TREATMENT PLANT (MOVING BED BIO

Design, supplying, installing, testing & commissioning of


Treatment Plant (excluding excavation, back filling & disposal of

of effluent - Domestic Sewage from toilet, kitchen waste

Total Phosphorus' Less than 5


Total - Less than 10
Coliform - Less than 230 NiINP/100m1

to be added in the scheme of civil works


1- Contractor shail ersure submlss/bn of detailed GA drawings
Section), P&l diagram, schematic diagram for the above said component
additional component if so requhed for the complete working of the STP

,ly, installation, testing & commissioning of Stainless Steel


se and Fine Screen with 10 mm and 5 mm bar spaces and
arrangement. (Common for present and future phases)with
arrangement (size 450 mm wide x 450 mm high approx) -

per lon Exchange standard only 1 sceen of 7 mm

Grease Trap with Belt type oil skimmer of suitable size


of 1200 liquid depth in brick work of class 75 with cement
1 :6), inside plastering 16 mm thick with cement mortar1 :3 with floating

neat cement and rough plaster on outside. lncluding SS bucket as


to collect the grease. RCC top slab with 500 mm dia medium
covers with frame (weight of covers 58 Kg & weight of frame
), necessary 50 mm thick foundation concrete ( 1 :2:4)
'1

1 ,15,000.00
lon Exchange approved (lf we put a OGT at the outlet

Supply of MS hot dip galvanized puddle flanges in accordance to BS


D as required to be provided (in the structural slab and wall) of
)meters. Puddle flanges shall be provided for all the structural compon
the STP. The installation of the puddle flanges shall be carried out by
contractor in accordance to the Civil GA drawing (to be prepared
STP contractoo at the required levels & position, under the

Supply of plastic manhole step/foot rest (@ 300 mm c/c)


ne compound injection molded around 12 mm dia (Fe-415)
bar. Provision of the foot rest is envisaged in various t
of the STP for the purpose of accessability. The installation
the foot rest shall be done by the civil contractor as per civil GA drawing

Supply. installation, testing & commissioning of 10 mm


plate rectangular manhole cover with frame for the feasibility of access

the adendum - rate qiven tor 1


Supply of venl pipes of 1 00 mm dia with mosquito proof grating suitable

Supply, installation, testing & commissioning of displacer type level

5 as per per the adendum rate given for 1 (we

s1 P-SOQ- 2
Schedule of Rates FINAL BOQ. SEWAGE TREATI!'IENT PLANT
lnternational School pune

Item Description Unit


Rate Discount iate Net Amount After
Qtv Net Amount
Discount
I Supply, installation, testing & commissioning of Float & Board type leve
indicator with isolation valve at top / bottom, & making the installatior
Lot 5 6500 325 6,175.00 32,500 00 30,875.00
5 as per per the adendum - rate given for 1 (transparent tube type leve
ndicator could be used cost shall be Rs -6500 for each tank)
9 Supply, installation, testing & commissioning of non clogging type
;ubmersible pumps complete with all accessories, motor of required
lapacity. Delivery header with isolation valve, pressure gauge on delivery
ine with isolation cock, level controller (with wiring) to control the level 01
rump automalically Provison shall be kept to
run both pumps
;imultaneouslV in case of emeroencv. PumDS shall have followino duiv:

9.1 Submersible Sewage Pumps (Non-cutter type) for transfer of Raw Sewage
from EQT to Anoxic (Domestic Effluent) - (2 Nos.1 working & 'l standby) :

0
Flow rate (each) = 1.2 LPS each 0
Head = 15 Mtr Set 1 245000 12250 2,32,750.00 2,45,000.00 2.32.750.OO
MOC : Cl
:Solid handlino size for this oumD shall be 35-40 mm)
1ow rate is more than 60 KLD, cutter type sewage pump of Grundfos make
;hall be supplied-price shall be Rs,-245000 (kirloskar make pump,1.42
acs)
9.2 Surface Horizontal Non clog Sludge recirculations pumps for STP (2
\os.1 workino & 1 standbv) :
:low rate (each) = 1.0 LPS each
= ti-E m
ng size for this pump = 7-B mm Set 1 ti4500 3225 61,275.OO 64.500.0 51 ,2t5.UU
flow rate is less for sludqe re circulation, Make, Kirloskar
9.3 Supply, installation, testing and cornissioning of Submersible Mixer / Gea
lvlotorised Agitator for Anoxic Tanks of suitable capacity and rating fo
STP Set 1 1 45000 7250 1,37,750.00 1,45,000.00 1,37,750.00
Cap. And specillcation required , Agitator make Universal (gear box
Classic/Premilrm molor-ARR/Siemcnc/marethan\
94 Plant room sumD Dumo (2 Nos -'l workino + 1 Standbv)
Flow rate = 2.0 LPS
Head = 12 Mts Set 210000 1 0500 t,99,500 Z,'] U,UUU,UU 1 ,99,500.00

5olr0 nanolrng stze tor thls pump shall be l5 mm).


rainaoe pump of Grundfos make considered of DPK 1 0.50
rrovision of guide ropes lo guide submersible pump from upper level t(
rperational level in sump basin wilh channels / angle section oI NiISEP shal
le made by the STP contractor.

10 ir diffusion syslem shall include the followino:

10.1 Twin type rotary air blowers including standby capable of delivering 75
cum/hr of free air at 0.6 kg/cm2 driven lhrough "V' belt or directly coupled
through flexible coupling to a TEFC motor of suitable HP Suitable for 41 5 t
10% volts, 3phase, 50cyclesA/C supply. (1 Nos - 1 working + 1 Standby)
Set 1 398000 19900 3.78.1 00.00 3,98,000.00 3,78, 1 00.00
As per lon Exchange standard air blower of 1 25 m3/hr at-0.35 kg/cm2
Dressure of lon Exchanoe brandino (Everest )make-shall be suoolied
'10.2 Air piping shall comprise of pipes droppers / laterals with UPVC (Sch 40)
Header complete with all fittings such as tees, crosses, plugs, sockets
elbows, reducers, supports & clamps, puddle flanges etc cutting chases 8
making good. Contactor to submit detailed P & I indicating their proposal.
Lot 1 34500 1725 32.775.OO 34,500.00 32,775.OO

10.3 Non clog type air dispersion system comprising of coarse and fine bubble
diffusers capable of handling 3 5 cfm of air with oxygen transfer efficiency ol
3-4% per/meter water depth. Air dispersion grid shall be assembled in
modular form so lhat they can be replaced / repaired easily from platform al
the top.(lmported fine bubble membrane diffusers) Lot 1 87500 4375 83,1 25.00 87,500.00 83,1 25.00

Votei A/ disperslon system shall be provided for Sewage Sump, aeration


'ank and Sludoe Holdino Tank

11 Providing and fixing all piping (as described below) and isolation contro
valves for makino the svstem comolete.

UPVC Sch 40 Submerged air piping


N/S Epoxy : Air piping & pumped effluent riser (non-submer
PVC piping : Pumped effluent (submerged) & tank overflow pipe line
Gl (Heavy) r lnterconnectlng pipe line after delivery header of pump/ filter Job 74500 3725 70,775.00 74,500.00 70.775.00

12 Supplying, installing, testing & commissioning of Bronze Ball valve and ail
llsnFrsion 6rid rc.adriirad f6r STP rc da<..ihad,h^va Job 1 24700 23,465.00 24,700.00 23,465.00
valve size-32 mm & air arid stze,so mm
13 Supply, lnstallation, Testing & Commissioning of tube deck media in tube
settling Tank (Secondary settling tank) for effective settling of flocs formed
during chemical reaction process complete with all fittings, accessories &
support required to complete the svstem functional . Set 1 435000 217 50 4,13,250.00 4,35,000.00 4,13,250.00
on Exchange shall be providing Lamella settler for best output with no re-occurin(

'14 Supply of MBBR media consisting of Virgin PE carrier modules with Surfac(
rot less than 500 l\,12ll\,13 of suitable capacity and as per manufacturer'{
-ecommendation for Reactor tanks alongwith suitable sludge remova
lrranqement either bv oumDS or air liftino oumos. Set 1 165500 8275 't,57 ,225.00 1 ,65,500.00 1,57,225.00
tuantity of media = 4 m3, lvlake,lon Exchanqe
't5 iupplying, installing, testing & commissioning of hypochlorite solution dose
romprising of 100 Litres capacity FRP tank with inlet / outlet connection
liping & valves alongwith metering (0-'12 lph) pump for dosing.
Set 1 24500 23,275.OO 24,500.00 23,275.OO

Drr Ecrue"r,&;H:""
s1 P-SOQ- 3

Director
Schedule of Rates FINAL BOO. SEWAGE TREAT|llENT PLANT
lnternational School pune

Rate Discount Rate Net Amount After


Item Description Unit Qtv Net Amount
Discount
16 Supply, installing, testing & commissioning of ultravoilet dis-infection unit
The unit shall have over 99.9% bacterial reduction from inlet to outlet. Th€
dis-infeclion chamber shall be constructed of SS 3161 on all welted parts
The UV lamp shall be of low pressure mercLrry vapour type wiih hard glass
enclosure, the sockets shall be waler tight & vibration resistant. The lamF
life shall be rated for 6000 hours. The unit shall be complete witf
temperature safety control, lamp out alert circuit & UV radiometer with 4 -
20 mA output.

The UV unit shall have with reactor, cabinet housing, cabinet cooling
treatment chamber, electrical panel, temperature safety control, lampou
alert, UV radiometer along with UV monitoring system and UV monitorin(
readout panel. The UV Dosage should be > 60,000 uW - Sec / sq.cm. Th€
lamps should be selected based upon the flow requirement of respectiv€
I rnit

16.1 or Irriqation Water Transfer Pumps DeliverV (2.0 LPS) Nos 1 68250 3413 64,837.00 68,250.00 64,837.00

16.2 or Soft Water lransler PUmPS (Z.U L Nos 1 68250 34'13 64,837.00 68,250.00 64.837.00

16 3 Water SuDDlv Pumos (2.0 LPS) Nos 68250 341 3 64,837.00 ti8,250.00 64,837.00
Vlake- Alfa, Note: autowiper shall not required,only Hour meter shall b€
1n/an al^n^ with I I\/
1 Supply, installation, testing and commissioning of package type Ultra
Filtration system of suitable capacity for STP of following capacities
complete with pre-treatment system comprising of UF hollow libre
membranes, high pressure pumps, chemical dosings, backwash pumps,
piping, valves, y-strainers, treated water transfer pumps, pressure gauges,
turbidity meter, ORP meter etc complete. The unit shall have all interlocking
for safe operation of plant. The unit shall have skid mounted electrical panel
complete with required starters and shall also have all Annuanciation and
Controls. lndication instrumentation such as TDS meter at inlet / outlet, pH
indicator, flow meter & totalizer shall also be provided. PLC with input /
output modules shall be integrated with all auto equipments / valves in auto
mode. The piping shall be heavy duty SS 304 (Non-Iilagnetic). The pumps
shall be of SS construction. The basis of desagn shall be for feed water inlet
Tnq 1 2On PPII
^f

60 KLD capacity 985000 49250 9,35 750 00 9,85,000.00 9,35,750.00


l\ilake-lon Exchange,Cap. 3.5 m3/hr, ORP meter does not come along ou
UF System,UF feed pumps shall be in Cl body-2 No's but backwash pumt
shall be in SS316, 1 working model, air compresser shall also be provide(
along with UF, lvlicroprecessor based control system shall be provide(
alonq (PLC panel provided with hiqher capapcitv UF svstem)
18 Supplying, installing, lesting and commissioning of SS vertical centrifuga
pump. Each pump shall have TEFC 2900 RPI\il three phase electric motor
The pump shall have cast iron head, base plate SS Shaft / lmpeller i
lntermediate chamber along with motor, pressure gauge with isolation cock,
lsolation valve, NRV on delivery line. lsolation valve, strainer (with by-pass)
at suction. Pump shall be provided with mechanical seal, suitable vibration
elimination pads of approved design, drain pipe with valve (25 dia). The
pump shall be suitable for auto / manual operation. The installation shall be
complete with all necessary ancillaries, accessories including base plate

18. 1 Capacity : 1.5 LPS each

lFilter Feed PumDs & Softener Feed Pumol incl. s No 4 98500 4925 93.5/5.00 3,94,000.00 3,74,300.00
lvlake- Grundfos. Model-CR5-6
18.2 Caoacitv:2.0 LPS each
Head : 45 lvl
RPlil : 2900
lsoft Water Transfer Pumps) incl. standbv No 1 546000 27300 5, I 8.700.00 5,46,000 00 5, 18,700.00

Mrka- Gnrndfnq lHvdr6M"lriF- rrCPFS-7I A Rc 5 A6 L.s

18.3 CaDacitv: 2.0 LPS each

,|
Ilrrioation Pumos) incl. standbv No. 546000 27300 5,18,700.00 5,46,000.00 5.1 U. /UU,UU
qw<lam ,41 I 4OnO OO=9 ?O OOO/-
Mlake- Grundfos (HvdroMultiE- 2xCRE5-7) @ Rs.5.46 Lacs

18.4 3apacity : 2 LPS


lead: 45-50 lvl
RPM :2900
No 1 546000 7300 5,1 8, /00.00 5.41i.000.0u 5,1 8,700.00

Makc- Gnrn.lfos lHvdroMrrltiF- 2xCRF5-71 ta) Rs 5 46 I acs

19 f,roviding, fixing, testing


& commissioning of vertical MSEP filter witt
edequate dirt holding capacity. Fabricated from lvlS sheet as pe
nanufacturer's specifications complete with intitial charge fllter medi€
ncluding painting inside with lwo coats of non toxic epoxy and with one coa
rf zinc chromate two coats of synthelic enamel paint outside. lncludin(
:oncrete foudation with cement plaster complete as required. The filter shal
rlso be provided with set of internals for raw water inlet and bottotr
:ollecting system. Complete with frontal piping (heavy) and butterfly valves
lpcinnad 1 60 m / ca. valn.ih?
^n
[/]S filter wilh Eooxv as oer lon E
19.1 er for Domestic Water seruices
:ilteration Rate 14000L/Sqm/Hr
:low Rate : 1.5 LPS Set 1
'185000 9250 '1,75,750.00 1.85.000.0 1.75.750.4
t li/bkdtuEr(dtdr C} n f Ou Il c el t I u I
19.2 Aclivated Carbon Filter
Iteration Rate 1 40001/Som/Hr

,GP sTP-SOQ, 4
Schedule of Rates FINAL BOQ. SEWAGE IREATMENT PLANT
lnternational School pune

ding, fixing, testing & commissioning of MS water softening I


FRP lining (suitable for 3 Kg/Sqcm working pressure) complete
charge wilh T-40 NA Resin, multiport valve with built in ejector
all operations) regeneration system and HDPE tank,
at inlet, outlet and back wash (each with isolation cock),
and water hardness testing kit & associated works. Softener shall

and resin 400 Liters and vessel size shall be Dia-600 mm,
Resin -lNDlON 220 Na l\ilake lon Exchange, Comptete

, installing, testing and commissioning of dosing system


water treatment plant) consisting of one HDPE tank of 1 00
with a positive displacement diphragm dosing pump
flowrate of 0-6 lph. The motor shall be suitable for operation at
/ single phase/s0 Hz. Supply. The pump shall be supplied complete
polypropylene piping, valves, strainers, low level switch
fitlings. The pump shall be speed & stroke control Asia Llill

providing sall for the testing and operation

, installation, testing and commissioning of top discharge


bucket type Centrifuge of Suitable Capacity suitable for 60 KLD
with feed pump (Screw Type) - 2 No. (1 working + 1 slandby)
1 No. standby stator, associated valves, pressure guage, level switches,
polymer dosing tank, interconnecting piping and poly dosing system
associated piping, valves and items as per approved P&l

as lon Exchange recommend fllter press of '14"x14':14 plates


w pumps-1 no's (After discussions with Consultant lvlr. Amit (

Supply, installation, testing and commissioning


Magnetic Flow Meter for Total Plant Capacity with pulsed
having automatic'Zero' correction wilh Bi directional
compacl instrument version with measuring
and Amplifier integrated in one mechanical unit (Suitable
flow range, inleuoutlet connections, lP 67 protection,
ipe material SS 304, Electrode material,SS 316 with '16 character x 2 L
CD Alphanumeric Display for flow rate, totalizer, diagnoslic message,
with high & low flow programmable throught the range.) with
for inlet flow measurement before screen chamber.

per lon Exchange approved make

Providing & lixing digital type water meter with direct reading dial in KL
with all internal parts in gunmetal or brass, butterfly valve, strainer,
distance piece for easy removal in future, Bourden type pressure guage
isolation cock including necessary test cedificate Complete with all type
Plumbing & Electrical connections, accessories, wiring, conduits
supports complete with all respect. The signal from read out shall be 4-
1 ,01,'t75.00
are recomending electromagnelic flow meter of 50 mm for better
output with totaliser and longer life (For lrrigation -1,For

fixing level controllers, pressure swtich and transmitters


pumps to starUstop the pump at set level. lncluding wiring,
pump to panel & all other accessories as required to operate

be used to automate the -soft water transfer pumps


pumps , irrigation water transfer pumps (if decided by

,installing, testing & commissioning of PH Correction


comprising of '100 Ltrs Cap. HDPE (chemical grade) tank with inlet
connection and along with 01 no. metering pump of
for dosing of solution (0 6 LPH). MoC of Pump shall be in

place of item no-26 & 27 we recommend to use automatic pH


inbuilt dosing system costing Rs.2,75,000/ including dosing tank

& fixing on line pH meter diqital type for lvlonitoring the


after Terliary treatmnent & before disposal. lncluding electrical
panel to flow meter. Complete with all type of Plumbing &
accessories, wiring, conduits & supports complete with
32,775.OO

Providing and flxing system of Online Monitoring system


such as Dassolved Oxygen, PH, ORP, Conductivity
Temprature, Turbidity, TSS, Ammonium, Nitrate, COD, BOD, TOC, DOC,
SAC. The unit shall be CPCB approved and have LCD display of all
The controller shall be mounted in a control cabinet with an
1 enclosure of suitable rating, digital energy meter in the control
for BMS, 12 month memory log, consist of all required sensor

sTP-SOQ- s
Director
Schedule of Rates FINAL BOQ - SEWAGE TREATI!1ENT PLANT
lnternational School pune

Rate Discount late Net Amount Atter


Item Description Unit Qtv Net Amount
Discount
29 Motorised Valve of 40/50 mm with actuator, float switch,DC adapter, valve
shall be in SS304 MOC, l\i1ake- Sanucair/equivalent ;et 5 54500 2725 51,775.OO 2,72,500.00 2,58.875.00
4- flushing tanks(1 on each block),'l- soft water tank(cooling tower),for

TAL CARRIED TO SUMMARY 69,63,450.00 66,1 5,276.00


SEWAGE TREATMENT PLANT

lesign, fabrication, assembling. wiring, supply, installation, testing and


lommissioning of motor control centre shall be fabricated out of 14 gauge
IRCA sheet steel in form in 3b formation with reinforcement of suitable size
lngle iron, channel 'T' sections irons and /or flats wherever necessary
lable gland plates shall be provided on top as well as at the bottom of the
lanels. Panels shall be treated with all anticorrosive process before painting
ls per speciflcations with 2 coats of red oxide primer and final approved
;hade of powder coated paint. 2 No. earthing terminals shall be provided for
3 phase,4 vJire, 50 Hz supply system. Lifling hooks shall also be provided
n case of large panels. Approval shall be taken for each panel before
'abrication. Cadmium Plated hardware shall be used in fabrication of
)anels. Quoted rates shall inclusive of cables. cable trays, control cabling,
rarthing (in accordance to speciflcation) with earthing from panel to each
nolor / coriomenl

\rCC -1 lsewaoe Treatment Plantl

amos I PN M(l(ll-l with the lollowino accessories

r. 0-415 volts 96 x 96 mm square voltmeter with selector switch shall be


)rotected bv 2 amos TP MCB. 1 Set

). 0-200 amps 96 x 96 mm square ammeter with selector switch and 100/5


rmps 1oVACL:'I CTs. l Set
Phase indicatino lamDs shall be orotected bv 2 amD SP N/CB-3 Set

3us Bar
150 amps TPN (25 KA) aluminium bus bar with heat shrinkable insulation

futqoinqs
a 2 No. suatable raling IViPCB for 1.5 KW DOL starter and outgoing feeder
to EQT sewage transfer pumps motor (including 1No. standby). Each
compartment shall contain auto / manual selector swtich and indicaling r

oushbutton lamos with N/ICB for ON / OFF i TRIP of motor.

b. 2 No. suitable rating I/PCB for 1.5 KW DOL starter and outgoing feeder
to Sludge Transfer Pumps - STP (including 1No. standby). Each
compartment shall contain auto / manual selector sMich and indicating /

l.mnc \^rith [re R f^r nN / OFF / TPlp nf m^t^r


^,,<hhrni^n

c. 1 No. suitable rating MPCB Ior 2.5 KW DOL starter and outgoing feeder
to Anoxic Tank Mixers - STP (including 1No. standby). Each compartmenl
shall contain auto / manual selector sMich and indicatinq / pushbutton
l,mna u,ith nre R f^r nNl / / Telp m^t^.
^trF ^f

d. 2 No. suitable rating t\4PCB for 5.0 KW direct on line starter and outgoing
feeder to air blowers (including 1 no. standby) ' STP. Each compartmenl
shall contain auto/manual selector switch and indicating lamps with l\ilcB's
for'ON/OFF/TRIP' status of motor.

e.3 No. suitablerating [i1PCB for No. 1.5 KW direct on line starter and
cutgoing feeders to fllter feed pump (including 1 no. standby). Each
compartment shall contain auto/manual selector switch and indicating
amps with MCB for'ON/OFF/TRIP' status of motor.

f. 2 No. suitable rating N/IPCB for No. 2.5 KW direct on line starter and
cutgoing feeders to soft water transfer pump (including 1 no. standby). Each
/
compartment shall contajn auto manual selector switch and indicating
amos with IICB for 'ON/OFF/TRIP' status of motor.

g. No. suitable rating MPCB for No.s KW star delta starter and outgoing
1
feeders to Flushing Water Hydro-pneumatic. Each compartment shal
contain auto/manual selector switch and indicating lamps with MCB for'ON
/ OFF / TRIP' status of motor.

n 2 No. suitable rating MPCB for No.2.0 KW direct on line starter and
Jutgoing feeders to irrigation pump (including 1 no. standby). Each
compa(ment shall contain auto / manual selector switch and indicatinc
amDs with N/CB for 'ON/OFF/TRIP' status of motor. 0

. 2 No. suilable rating MPCB for 3.0 KW DOL starter and outgoing feeder tc
Plantroom Sump Pump (including 1No. standby). Each compartment shal
:ontain auto / manual selector swtich and indicating / pushbutton lamps with
[raR f^r nNl / ntrF / TPIP m^t^.
^f

. 2 No. suitable rating MPCB for 3.5 KW djrect on line starter and outgoing
Feeders to Centrifuge - STP. Comparlment shall contain auto/manua
selector switch and indicating lamps with IiICB's for 'ON/OFFffRIP'status
lf motor.

(. 'lNo. suitable rating MPCB for No.s KW star delta starter and outgoing
leeders to UF SKID . Each compartment shall contain auto/manual selector
switch and indicating lamps with NICB for'ON i OFF / TRIP' status of motor.
,IT Felrra^r:^- r- --
r\-rt

Dr*cterG# s] P.SoQ. 6
Schedule of Rates FINAL BOQ. SEWAGE TREATIV]ENI PLANT
lnternational School pune

Item Description Unit


Rate Discount Rate
Net Amount
Qtv
Discount
r. 2 No. suitable rating IVIPCB for No. l0 KW star delta staner and outgorn!
'eeders to axial flow fan. Each contpartment shall contain auto/manua
ielector switch and indicating lamps with MCB for'ON / OFF / TRIP'status
)f motor.

). Spare MCB's of followino caoacities:

i. 32 amps TPN MCB'S 2 Nos


ii 40 amps TPN NiICB's 2 Nos.

Note: All MCCB', to be suitable for motor duty and shall be of 25 KA


breakino caDacilv

Drovision shall be made for providing potential free contacts to all pumps
starters for connection to buildino automation svstem
fle have added BMS potential free contacts for each pump & motor
'cxceot dosinn cvstpm ,nd I lF <v<faml
\.4CC -1 for STP as described above No. 1 465000 23250 4,41 ,7 50.00 4,65,000.00 4,41 ,750.00

2 Supply and llxing in position 1 m wide lnsulation mat made of elastomeric


polymers Material (Class -A) of 415V grade as per lS 156422006
Thickness of insulation mat shall be not less than 2 mm to withstand 1.'1 KV
dielectric strength AS PER lS 15652 : 2006. lt should be complete as per
speciflcations & directions of Engineer-in-charge. lt should be complete as
per speciflcations & directions of Enqineer-in-charqe. RIM 10 3450 173 3,277.00 34,500.00 32,770.00

3 Supply and fixing in position the best quality Danger Boards of approvec
shape and size as specified by Local Electricity Authorities written in Englisl
& Local Lanouaoes No. 2 1450 73 1,377 .OO 2,900.00 2,754.OO

4 Supply and flxing in position the approved "Shock Treatment Charts' writter
n English and Local Language. These charts shall be framed in teak wooc
frame and covered with olass. No. 1 ,1qn 2.O42.OO 2,150.00 2,042.OO

IOTAL CARRIED TO SUMMARY 5.04.550.00 4.79,316.00

DIT -4\i';cn Foundation


\!94+-
Director

sl'P-SOQ- 7
GSTIN : 05AAFCR8606M1Z1

R.S. Infrasolutions Private Limited


Admin. Off : 201, Gangasagar-B, Amrapali Marg, Vaishali Nagar, Jaipur, Ph. : +91 141 4054200 Fax : 141 4026493

(Purchase Order)
Purchase Order No.- RSI/RISHIKESH/BRO/2022-23/PO/12 Date:. 03.08.2022
To,
M/s. Mentor Water Experts Pvt. Ltd.
16-A,Prakash Nagar, Chakrata Road
Dehradun (Uttarakhand)
Kind Att.- Mr. JP Rai (9068000789)

Project Name-LAYOUT, DESIGN, DRAWING AND CONSTRUCTION OF ADM BLOCK, OTM ACCN FOR OFFICERS/
SUPERVISOR’S/JCO’S/OR’S, MARRIED ACCN, MI ROOM, DENTAL CLINIC AND OTHER INSTITUTES INCLUDING DEVELOPMENT
OF AREA, EXTERNAL SERVICES SUCH AS ROAD/PATH, WATER SUPPLY, ELECTRICITY DISTRIBUTION LINES, SEWERAGE LINES,
WATER STORAGE TANK, ETC FOR HQ CE (P) SHIVALIK AT MAJRIGRANT DISTT DEHRADUN IN UTTARAKHAND STATE ON EPC
MODE

Subject: Purchase Order for Packaged Type Pre-Febricated Modular Sewage Treatment Plant 150KLD

As per your offer MWEPL/IEIL/2022-23/277/R5 & discussion with you, we are accepted your offer
consists of the following Annexure:

Annexure I Design Basis Sheet Attached


Annexure II Introduction Sheet Attached

Annexure III Process Details Sheet Attached

Annexure IV Technical Details of Electrometrical & Civil Work Sheet Attached

Annexure V Make and Material of Construction Sheet Attached

Annexure VI Price and commercial terms & Exclusions Sheet Attached


Price for supply, installation, testing & Commissioning of Pre- Fabricated Sewage Treatment Plant Capacity of
150 KLD shall be Rs. 41,95,000/- (Rs Forty One Lacs Ninety Five Thousand Rupees Only)

 Terms of Payment
30% advance , 60% of the order value along with taxes and duties against readiness of material for
dispatch, 10% against installation.

 Freight
FOR Destination at HQ CE (P) SHIVALIK AT MAJRIGRANT DISTT DEHRADUN

 GST
Inclusive

 Delivery
Within 8-12 weeks after receipt of advance along with technically and commercially clear purchase order
and E/C time 20-25 days

Regd. Off : 275, Gangasagar-A, Amrapali Marg, Vaishali Nagar, Jaipur-302021, E-Mail : rsinfrasolutions@gmail.com
GSTIN : 05AAFCR8606M1Z1

R.S. Infrasolutions Private Limited


Admin. Off : 201, Gangasagar-B, Amrapali Marg, Vaishali Nagar, Jaipur, Ph. : +91 141 4054200 Fax : 141 4026493

 Warranty
The plant supplied by you will remain under warranty for a period of 12 months from the date of
commissioning against any manufacturing defects.

 Contact Person name : Manoj Sharma(9413340773) Kewal Rawat (9887480962)

 Billing Address : 69, Naturoville, Lal Tappar, Haridawar-Dehradun road, Uttarakhan-248140

 GSTIN No. : 05AAFCR8606M1Z1

 PAN No. : AAFCR8606M

 E-Mail Id : rsinfrashivalik4@gmail.com

Thanking you,

Regd. Off : 275, Gangasagar-A, Amrapali Marg, Vaishali Nagar, Jaipur-302021, E-Mail : rsinfrasolutions@gmail.com
Ref: MWEPL/IEIL/2022-23/277/R5 Dated-02/08/2022

To,
The R S Infrasolutions Private Limited
Haridwar , Nutraoville , Lal Tappar , Dehradun

Project - BRO Doiwala Dehradun


Subject: Offer for Packaged Type Pre-Fabricated Modular Sewage Treatment Plant 150 KLD

Dear Sir,
Refer to our discussions & site visit regarding your requirement of Sewage Treatment Plants Cap.150 KLD,
Based on same we are pleased to submit our Techno-commercial proposal for 150 KLD for your kind consideration and
approval.

We are authorized channel partner of M/s- Ion Exchange (I) Ltd.- which is world leader in water & waste waterfor the
last 60 years.

Our offer consists of the following Annexures:

Annexure I Design Basis


Annexure II Introduction
Annexure III Process Details
Annexure IV Technical Details of Electrometrical & Civil work
Annexure V Make and Material of Construction
Annexure VI Price and Commercial terms& Exclusions

We hope the above is in line with your requirement. Please revert for any further information / clarifications.

Thanking you,

FOR MENTOR WATER EXPERTS PVT. LTD.

JP Rai
90680 00789

1
ANNEXURE – I

PACKAGE SEWAGE TREATMENT PLANT USING FLUIDISED MEDIA REACTOR (FMR) TECHNOLOGY.

DESIGN BASIS

Design Capacity 150 m3 /day

Operating Hours 20

Design flow rate 7.5 m3/hr

Sewage Characteristics Raw Sewage Treated Water


BOD (ppm) 250 -450 <=10 mg/l
COD (ppm) 500-700 <=25 mg/l
TSS (ppm) 250-450 <=5 mg/l
Oil and Grease < 50 <=2 mg/l
Temperature Ambient
NH4-N <=5 mg/l
N-Total <=10 mg/l
Fecal Coliform <=100
PO4-P <=2

Use of treated water:

For low end purposes such as Gardening, Car washing, Road washing etc.

2
ANNEXURE -II

INTRODUCTION FMR - FLUDISED MEDIA REACTOR

Conventional waste water treatment technologies like submerged aerated fixed film (SAFF) reactor, Trickling filters or
other activated sludge processes have inherent disadvantages of large area of operation, higher power inputs and
constant operator attention.

In line with our endeavor to introduce latest technologies related to Water & Waste water treatment, Ion Exchange (I)
Ltd. has developed FMR a Fluidized Media Reactor using attached growth process for Waste water treatment.
As compared to conventional Technologies FMR media reactors are compact, energy efficient and user friendly.

The FMR process refers to the operation of activated sludge tanks in various configurations in a combination of

1) Suspended biomass,
MLSS (mixed liquid suspended solids) and
Attached biomass, which is attached to the FMR media.

This technology is based on MBBR/FAB technology.

Basic principle
Flock forming organism’s form clusters or attach to available surfaces. The FMR carrier material allows high biomass
concentrations per cubic meter of material, which:
Increases the specific volumetric capacity of activated sludge tanks
Controls biomass activity
Reduces operating cost
FMR SCHEME:

Sewage water
NaOCl
Lamella

Bar Screen

Chlorine Contact

Air Blowers
FMR Tank

3
The FMR technology is a single tank design unit; incorporating
A Oil grease trapper ,
A specially designed tanks with synthetic media,A Lamella settler, and
A chlorine contact tank.

The bar screen removes larger floating matter and suspended particles. Screened sewage flows into the FMR tank,
which contains the FMR media. The FMR media significantly increases the surface area for bacterial growth. Air is
supplied through fine diffusers. Bacteria oxidise the organic matter present in the sewage. Oxidised sewage
overflows
in the lamella settler. Suspended particles in the treated wastewater settle, with a part of the settled sludge sliding
back
to the aeration tank. The lamella plates provide larger surface areas, thus reducing the settling tank size. Treated
water
overflows into a chlorine contact tank, wherein the treated water is disinfected by dosing hypochlorite solution
through an electronic dosing system.
Advantages using FMR
Significant reduction in space requirement due to high surface area & loading rate of FMR media.
Reduced power and operating costs
No Sludge recycle
No moving parts, less maintenance
FMR is best suitable when
Designing a new waste water treatment plants when operating cost & space are constraints
Upgrading of existing waste water treatment plants
Operate plants in low temperature areas
Reduce bulking problems in existing treatment plants

Applications of FMR
Decentralized compact sewage treatment plants for Residential complexes,
/ Hotels / Commercial Center’s / Office Premises / Industries and Rural
Communities.
II) Industrial wastewater treatment from:

4
ANNEXURE - III

PROCESS DETAILS

5
Bar Screen:
Raw sewage from the source is usually received into the bar screen chamber by gravity. Screen provided will remove
all floating and big size matter such as plastic bottles, polythene bags, glasses, stones, etc., which may otherwise
chokethe pipeline and pumps.

Equalization Tank
Usually, sewage generation is more during morning hours and evening hours. Visually no sewage is generated during
night hours. Any biological system needs constant feed for bacteria to work efficiently. Hence, it is important to put an
equalization tank to collect the excess flow during peak hours and feed sewage in lean hours. A typical equalization
tank has a capacity of 8 – 12 hours of average flow rate. The tank is generally of civil construction by client. Provision
of
air grid is to be made for thoroughly mixing the sewage to make it of homogenous quality and to keep the suspended
matter in suspension and to avoid septic conditions.
Anoxic Tank
Our scope starts from transfer of sewage from Equalization Tank to Anoxic tank. The distance of transfer should not
exceed beyond 20 meter. The transfer pump can be either submersible or non-submersible type for this application.
However, we have considered centrifugal non-submersible type, nitrification & de-nitrification shall be done with the
help of slow RPM motor mounted on MS painted stand & fixed with SS agitator having 2 agitating blades.

Fluidised Media Reactor (FMR)


Fluidised Media Reactor (FMR) as the name indicates consists of floating media of various shapes and sizes.
The main objective of adding this media is to make available more surface area for bacteria to grow on, thereby
maintaining and retaining maximum possible bacterial population in a limited volume. The FMR media material allows
biomass Concentration of 20 – 40 Kgs/m3 material. Thus, FMR consists of combination of biomass in attached as
well
as suspended form. High concentration of biomass enables reduction of aeration tank and in turn reduction in overall
cost. Volume of the media shall vary from 6 to 25 % based on the concentration of organic matter.

Another main feature of the FMR is its compactness. The FMR consists of biological system for removal of organic
matter (BOD, COD), lamella for clarification and chlorine contact tank for disinfection. As all units are placed inside a
single tank, it saves space and also increases operational ease.

In FMR, raw sewage enters at the top of the tank. Air is introduced at the bottom of the tank through fine bubble
diffusers. Media will be in suspension because of the turbulence created by the air. The bacteria required for the
oxidation of the organic matter is
attached to the media and some part is suspended in the tank. After oxidation, the bacteria grow in number and need
to
be separated from the aeration tank liquor. The lamella section inside the FMR helps in clarification and separation of
the bacteria (sludge) and clear overflow flows into chlorine contact tank. Lamella plates helps in increasing the
settling
area and removing the particles effectively in a smaller plan area. In chlorine contact tank, Sodium hypo Chlorite
(NaOCl) is added for disinfecting the clarified sewage. Baffle plates are provided to make better contact.

The chlorinatedtreated sewage then flows out of FMR either for further treatment or for disposal.

6
Chlorination tank
After settling tank chlorine shall be dosed to remove bacterial effects at Chlorination tank by chlorine dosing pump.

Break water tank


The clarified water shall be stored in break water tank to feed in Filtration plant and carbon filter for final treatment.

Multi Grade Filtration Plant


After Break water tank it will be pumped to filtration plant to treat further

Activated carbon Filter


After Filtration plant filtered water shall be pass through ACF to remove chlorine and smell and colour .

Final treated water tank


Final treated water shall be stored in final tank for further re- uses and other low end applications.

Sludge:
The sludge from the Clarifier to be transfer from the bottom of the Clarifier once in a week by gravity/pump to SHT
and it will be pumped to filter press/Drying bed to final dewatering.
Final solid shall be used as manure and water shall be re-circulated to EQ.

ANNEXURE - IV

TECHNICAL DETAILS OF MECHNICAL EQUIPMENTS FOR STP –IEIL/ MWEPL Scope

S. Details of Mechanical work Quant Make MOC


No. ity
1 S. S. Screen made up of SS sheet of 7 mm thickness 1 No. IEIL SS 304
having size- 500 mmx1000 mm & perforation of 7-10 mm
2 Sewage Feed Pumps from EQT to Anoxic/STP Type- Non- 2 Nos. IEIL approved CI with
Submersible self-priming Flow rate –7 . 5 M 3 / H r , (1w coating
Head –10-meter,HP/RPM-3/2900 +SB)
3 Air Blowers for Aeration in STP and EQTCapacity – 185 2 Nos. IEIL approved CI
m3/hr @0.37 Kg/cm2
HP/RPM- 5 /1200
4 Membrane Diffusers (Coarse Bubble) for EQT /SHT 20 IEIL approved
DIA - 6 Inches Nos. EPDM/SILI
Cap. 5 m3/hr (Max) CON
5 Membrane Diffusers (Fine Bubble) for EQT /SHT 10 NosIEIL approved
DIA - 6 Inches EPDM/SILI
Cap. 5 m3/hr (Max) CON

7
6 AIR GRID AirLine for Diffusers in EQT, SHT and FMR 70–80- IEIL approved
Reactor meter MS/UPVC/
Air line in MS, submersible piping shall be in CPVC/UPVC Approx CPVC
with proper MS support .

7 STP -MBBR REACTOR: this is the main reactor which has 1 set IEIL MS
the provision of aeration and removal of BOD & COD, coating of
reactor shall have the size of –8.7 x2.13x2.2 meter anti-
corrosive
paint
8 FMR/MBBR/ Media specially designed Media for additional 4 m3 IEIL PVC virgin
surface area, this media shall be made up of PVC virgin plastic
plastic for longer life
9 Lamella Settler this is settler being used for separation of 1 set IEIL FRP plates
sludge & treated water with the help of FRP plates inclined at
60 Degree and fitted in a MS- painted with anticorrosive paint,
no of plates shall be 22 having size of 1.4 meter & 1.7 meter
with thickness of 10 mm fully supported with MS strips.
10 Filter Feed Pumps 2 Nos. IEIL approved CI
Flow Rate – 10 m3/hr. @ 30 M. HeadHP/RPM - 2/2900 (1w
Type- Centrifugal Monoblock +SB)
11 Multi Grade Filter- for removal of suspended solids 1 No IEIL MS with
Capacity –10 m3/hr. Epoxy
DIA- 1000mm Painted
HOS-1875 mm
MOC- MS with Epoxy painted
12 Activated Carbon Filter- for removal of color & odor 1 No IEIL MS with
Capacity –10 m3/hr. Epoxy
DIA- 1000mm Painted
HOS-1875 mm
MOC- MS with Epoxy painted
13 Sludge Transfer Pump from SHT to Filter Press 1 No IEIL CI
Type- Screw Pump APPROVED
Flow rate - 2 m3/hr HP/RPM- 1/1500
14 Filter Press 1 No. IEIL CI/PP
Plates- 14 APPROVED
Size – 14”x14”
15 Electrical Control panel having sufficient drives, along with 1 No. IEIL-CPRI GI
all pump’s automation and control level switches. APPROVED
16 Agitator for Anoxic Tank 1 No. IEIL SS
Slow RPM-50-60 APPROVED
Agitating rod with 2 agitating blades
17 Re-circulation pumps 2 No. IEIL CI

8
Cap. 20 m3/hr at 10-meter head, APPROVED
Rating -1.5/ as per OEM
18 Electrical Wiring as per CPWD standard having cable tray & 1 lot. IEIL
required support as pe site need/requirement APPROVED

19 Break Water Tank –HDPE Cap.10,000 Ltrs 1 Himgiri/Eqvt


20 Sludge Holding Tank-HDPE Cap. 10,000 Ltrs 1 Himgiri/Eqvt
21 Interconnecting Pipe works 1lot Jindal/Prince/ MS-
Supreme EP/PVC
22 Electrical Wiring from panel to each pump/motor 1 Lot
Polycon/havel
s
23 Drawing- GA with sectional drawing for civil works and tin 1 job
shed

Details of Required Civil work - STP (Client’s Scope)

Sno Desc. Size in meters Volume of Tanks in Civil cons.

1 Bar Screen Chamber 1mX1mX1.1m 1 m3 –RCC


2 Oil & Grease Trap 3.5Mx1mX1m 3 m3 –RCC
3 Equalization Tank 8X5X3 m 76 m3 -RCC
4 Treated Water Tank As per client 50 M3- RCC
5 Sludge Drying Bed 1x1x1.5-3 No’s In Brick works
6 CC Foundation for As per drawing/design In CC
equipment’s

Exclusions –
a) Sewer lines into Bar Screen Chamber.
b) Safety & Security of material at site.
c) Approach Road to STP site.
d) Fresh Water Line up to STP Area.
e) Water & Electricity up to STP.

9
ANNEXURE - V
MAKE & MATERIAL OF CONSTRUCTION-
Description Make MOC
Feed pump JOHNSON/KIRLOSKAR/KSB CI
Bar Screen ION EXCHANGE SS
Aeration Tank/Reactor CIVIL TANKS RCC
FMR Media ION EXCHANGE PP
Diffuser (Tube Type) EDI, USA Rubber (EPDM)
Blower EVEREST CI
Secondary Clarifier Tank CIVIL RCC
Lamella Boxes Ion Exchange MS with anti-corrosive coating
Chlorination tank CIVIL RCC
Chlorine dosing pump Asia LMI/ Milton ray HDPE Tank / LDPE tank
MGF ION EXCHANGE MSEP
MGF Feed Pump KIRLOSKAR / JOHNSON CI
ACF ION EXCHANE MSEP
Screw Pump UT/Roto CI
Filter Press Water to people/ Pharmtech
Butterfly valve CRANE / Audco / Eqvt. CI
Pressure gauge H GURU / Gluke / Eqvt.
Pipe JINDAL/TATA – B class /SUPREME MS/PVC
Electrical panel MCB Siemens/ L&T/ Havels/ Eqv.

ANNEXURE - VI
PRICE & COMMERCIAL TERMS
Sewage Treatment Plant Complete in MSEP
Our price for supply, installation, testing & commissioning of Pre-Fabricated Sewage Treatment plant Capacity of 150
KLD shall be 41,95,000/-(Rs. Forty One Lacs Ninety Five Thousand Rupees Only)
------------------------------------------------------------------------------------------------------------------------------------------------

Exclusions –
* All civil works / RCC Tank’s, Equipment’s Foundation as per MWEPL/IEIL Design
* Supervision shall be provided by MWEPL/IEIL
*Civil Works i.e Tanks, Tin shed/ Canopy for equipment
* Operator Room
* Water & Electricity up to STP.
* Safety & Security of material at site.
* Electro-mechanical equipment & Drawing shall be in MWEPL/IEIL Scope

10
TERMS OF PAYMENT:
1. 30% advance against bank guarantee valid till completion of supplies.
2. 60% of the order value along with taxes and duties against readiness of material for dispatch and submission
Of perform invoice on prorata basis.
3. 10% against installation.

Fright: FOR at site

GST: inclusive

DELIVERY:
Within 8-12 weeks after receipt of advance along with technically and commercially clear purchase order andE/C
Time 20-25 days.
VALIDITY:
Our offer will remain valid for 30 days from the date of this offer and for schedule of supplies as mentioned above.
WARRANTY
The plant supplied by us will remain under warranty for a period of 12 months from the date of commissioning against any
Manufacturing defects.

PLACEMENT OF ORDER you are requested to place your order in favor of M/s- Mentor Water Experts Pvt. Ltd.
Add- 16-A,Prakash Nagar,Chakrata Road, Dehradun
Ph-0135-2752443/7217343777,Mo-9412950122,7351002100Email- mentorwaterexperts@yahoo.com

11
GraphicEra Deemed to be
Accredited by NAAC with Grade A
University Ph
Bell Road.Clement Town
Dehradurn-248002 Uttarakhand
0135-2644183., 2642799
Fax 0135-2644025
Approved by AICTE Ministoyof HRD Govt ot india www.geu ac. in

GEU/R-1383/GEIMS/21 November 16, 2021

Purchase Order
(Graphic Era Institute of Medical Sciences)

To
Mentor Water Experts Pvt. Ltd
Corp. Office, Cubic Tower, 65-Ballupur,
Chakrata Road, Dehradun,
mentorwaterexpets@gmail.com
pump@mentorwater.in,
Mr. Rahul Singh Rawat, 73510110o3

Subject: Purchase of Grundfos Make Pumps.

Dear Sir/Madam,

This has reference to your quotation, Reference No. MWEPLIGIN/2021-22/664-R2 dated November
13, 2021, the institution is pleased to place the purchase order of the following product (make and
model) along with other specifications as listed in your quotation

1. Price and Specifications:

SL NO UNIT RATE(in Total


DESCRIPTION UNIT rupees) Discount on Amount
Unit rate Total Ater S %
Amount additional
Discount)
CHAPTER 1: HIGH SIDE EQUIPMENT
PUMP
1.1 PRIMARY WATER
Supplying installation, testing and
commissioning of mentioned capacity
& head given below for primary water
Circulating. Thepumps shall be close
coupled, single stage, centrifugal ,end
Suction with backpull out design
Hence the rotating unit can be
removed and Serviced withou
the suction and
disconnecting
discharge piping The pump and base
frame shall be factory assembled at
the pump manufacturer's facility
Installation instructions shall bee
included with pump at time o
shipment. The pump manufacturer
shall have complete unit
responsibility. The pump shall be
balanced statically and dynamically
The pump are constant speed. The

XPer
Ptradun)
2m trom the source. The pump shall
be required to meet
specification
mentioned and per drawings and
schedules. The Pumps shall be BMS
compatible.
The scope of work shall include
Lifting, shiting & positioning of pump
at location shown on drawing.The
pump shall be having:
1 Fnd suction/ Radial Split
casing
type pump.
2 Suitable HP TEFC squirrel
cage induction motor with class 'F
insulations& elficiency class IE-3
1450 pm synchronous speed
operating on 415 +/-10% volts 3
phase, 50 HzA.C.supply.
3. Lot-Expanded polystrene
(T.F.Quality) insulations of not less
than 7Smm thick duly cladded
between aluminiIm sheets of 0.5 mm
thickness and pro perly clamped to
pump n wo semicrcular section as

per specilications.
4 Min. pump etticiency at duty
conditions shall be 70% (Minimum
ECBC 2017 standards or ASHRAE
90.1-2017 standards whichever Is
stringent)
The Pump shal be capable to
Connun1cate eliectively with BMS.
6. Pump shall have Mounting frame
with Anti vibration pads.
Note-Total HHead Loss given is
iLELEm requirementlor the system.
AcTual Head shall be calculated &
contirmed by the vender
at time of Bidding.
1.1.1 I440 USGPM,15 meter head (1 Nos. 2 2,80,830.00 59,680.00 4,42,300.00|
Working +1 standby)

Grundfos Make- NB 125-250/255

Pump with Bronze lmpeller, MS


Base Frame, IE-3 motor, 22 KWw

1.1.2 720 USGPM, 15 ineter head (1


Working+1 standby)
Nos. R/o 2,09,175.00 42,945.00 1,66,230.00

eXper
Pehfedun;
sP
Grundfos Make- NB 100-250/235
Pump with Bronze lmpeller, MS
Base Frame, IE-3 motor, 11 KW

1.2 SECONDARY WATERPUMP


Supplying. installation, 1esting and
commissioning of mmentioaed capacity
&head for
secondary water circuit
with VFD. The
pumps shall be close coupled, single
stage, centrifugal, end suction with
back-pull out design with Dedicated
microprocessor based
pump
controller with paralle pumping
software duly downtoaded, suitable to
un oD variable Irequency drives as
required and multiple ditferential
pressure sensor transimitters as
necessary and as described in the
specitications. Hence the rotating
unit can be renoved and serviced
without distonnecting the suction and
discharge piping. The pump and base
rame shall be factory assembled at
the pump manufacturers facility
lostallation instructions shall be
1claded with pump at time o
shipment. The pump manufacture
shall Ihave Complete unit
responsibility.The Unit shall be
complete in all respect and it should
teet the specification.Drawing &
Schectule. The scope ol work shall
include 1Littiog, shilüng &p0sitioning
of punp at location shown on

drawing
1 End suction/vertical split casing
ype pump/Horizontal dischare.
2 NO- Suitable HP, TEFC squirre
Cage hduction Inotor with class 'F
insulations & elliciency class IE-3
1450 rpim synchronous speed
0perating on 415 -10% volts,3 phase
. 50 HzA.C.supply.
3 The total sound intensity with all
pumps in operation should not exceed
75 dB at a distance of 2 meters. The
Pumps to be capable of providing 10%
higher flow rate. All rotating parts are
to be covered withh au encasing. The
dhuty point or the pump shall be
the curve.
defined i pump
4 Variable secondary Panelshould

xpers
Behradun

18 n
have One dedicated muld pump
proressor based purmp controller with
paraliel pumping software duly
Stalled.The pump selected for
Variable speed drive shall be capable
of perlormmng satislactorily over a
wide range of speed, allowing a speed
Variation from 20 to 100 %.The
pump logic controller assembly shall
be listed and appxoved by
Underwriter's Laboratory, Inc. (UL).
The controller shall be specifically
designed for variable speed pumping
applications.
5 Microprocessor based control
panel shall have suitable hardware &
software so that it can be integrated
directly to BMS with standard
Communicationopen protocol using
backuet / Modbus.
6.All pumps to br provided with
separate P 54 rated variable
trequency drives with integrated
input d-sconnect switch. Control
paiel should also c01sist of cooliig
tari
(ALI Lhe Secondary Pump set will have
Combined control panel and shall be
suitable for connecting all the Pump
with their rated
capacityof motor)
VED The variable frequency drive(s)
shal be pulse width modulatioon
PWM) type, microprocessor
centrolled design. VFD shall be
Capable of operating iu3 voltage rangeS
of 210V or 415 V +/ 10%% AC, three
phase at trequencies of 48 to 63 Hz
VFD shail be factory fitted and unit
thounted.
Min Ppump elliciency dt duty
cOnditions shall be 709% [Minimium
ECBC 2017 standards or AsHRAE
90.1-2017 staidards whichever is
stringent):
Lot-Expanded polystrene (T.F.Quality)
insulauois of not less than 75mm
iick duly cladded between
aluminium sheets of 0.5mm thickness
and properly clamped to pump in two
Semicircular setti
tion per
Specilications.
Lot- Mounting frame work with anEt
vibratio pads,

per
Dehradun
P
Note- Total lead Loss given is
manieun requirenment tor the
Actual Head shall be calculatedsystem.
&
conlimed by the vender
at time ot
Bidding
L.2.11440 USGPM, 33 meter head (1
Working-! standby)
No.
6,33,770.00 1,34,670.00 9,98,200.00 9,48,290.00
Grundfos Make- NB
125-315/338
Punp with Bronze linpeller, MS
Base Frane, IE-3 niotor, 45 KW

1.2.2 720 USGPM.33 meter head (1 No.


Working+! standby R/o 2,67,755.00 55,034.00|2,12,721.00|
Grudfos Make- NS
100.315/316
Pump with Bronze lnpeller, MS
Base Frante. 1E-3 notor, 22 KW
1.2.3 Controi Panel for Secondary System No 1 8,96,040.00 1,90,410.00 7,05,630.00 6,70,348.50
Not
Giundfos Make-
2P-2V1DPT 45KW_IP55 Ind Fdr
h ayplng nstel Yn Bus e
Panel W/O BPS ABB cluicalu apoued nedel u pknuaENAÉAAP
1.3 CONDENSOR WATER PUMP P aNfOPL H5 Kw TPA IND wo BPS A
Supplyitg, installation, testing and
comissioning of mentioned capacity as
&head for condensor water circuit mevrcti0nuol en belou ololia
Tlhe pmps shall
be dlose coupled, single stage
Cenulugal, end suction with backpull
Scheolul)
oat design. Hence, the rotating unit
Can be removed and serviced without
disconnecting he suction and
discharge piping. The pump and base
frame shall be factory assembled at
tihe puup anutacturers facility
nstallation instruetions shall be
ncluded with puiup at time ol
shyusetit The pump manufacturer
sthall ave Complete unit
responsibility. The pump shall be
balanced statically and dynamically.
The punmp are constant speed. The
nuise level shall not exceed 75 dbA at 2
% trura the source. The pump shall be
Tequared meet specification
eritioned and per drawings and
Schedues. The Pump Shall be BMS
CLompatible.The Pump shall have

Je1eXper
Deradun
following
End
1 suction Radisl split casing
type
putnp.
2 Suitable HP TEFC squirrel
cage
11ductio1 motor with class F
nsulativons & elliciency class 1E-3
1450 rpm synchronous speed
operating on 415 +/-10% volts 3
ph.ase, St HzA.C.supply.
3.Mit putrp efticiency at duty
conditions shall bE 70%
(Minimum
FCBC 2017 standards or ASHRAE
90.1-2017 standards whichever is
stringent)
4 The
Pump shiall be capablele to
commncate electively with BMS.
The pamp shall be
with M0unting
Itae with Anti Vabration pads.
Note- Total Head Loss given is
minum requremeit for the system.
Actual liead shall be calculated &
CUntired by the vender

at time of Bidding.
1.3.1 1800 USGPM. 30 meter head (1
Working
Nos.
5,58,495.00 1,18,683.004,39,812.00 4,17.821.40
Grundfos Make- NK 150-315/310
Pumpwiti Bronze lmpeller.MS
Base Frame, IE-3 motor, 55 KW
1.3.2 900 USGPM 30 meter head (1 Nos. 3,00,265.00 63,810.002.36,455.00 2,24,632.25
standby
Grundfos Make- NE 100-315/334
Pump with Bronze limpeller, MS
BaseFrane,IE-3 motor, 30KW
1.4HO WATER PUMP
Sippiynginstallation, testing and
CunaisstOniDg ot inentioned capacity
& head given below for hot water
ireulating. The pumps shall be close
Coupled, single stuge, centrifugal ,end
Suction with backpuil out design
Hence the rotating unit can be
remaved and serviced
without
discomiecting he Suction and
discharge piping. 1he pump and base
Irame shall be factory assembled at
Lhe puinp manufacturer's facility
installation instuctions shall be
included with pump at time
o
shipme1t. The pump manulacturer
shall have Cummplete unit
esponsibility, The pump shall be
Ivalanced statically and dynanically
ihe puinp are consiant speed. The
nose level shall not exceed 75 dbA at

KAaterxper
Dehradun

10//2
2m from the source. The pump shall
De required to meet specitieatio
tenitioned and per drawings and
schedales. The Puips shall tbe BMS
compatible.
The scope of work shall include
Lafting, shifting & pusitioning of pump
at location shown on drawing.The
Dump shall be having:
1. Ead suction/ Radlial Split casing
ype pup.
Suitable IP. TEFC squirrel
cage induction notor with class 'F
insulations & eficiency class IE-3
1450 Tpm synchronous speed
operating on 415 +/-10% volts
phase, 50 Hz A.C.supply.
3. Lot-Expanded polystrene
(TFQuality) insulations of not less
than 75Simm thick duly cladcded
between aluminiuim sheetS of 0.5 mm
thuckress and properly dlamped to
putnp i two seImicircular section as
per specitications
4 Min. pump efficiency at duty
conditions shall be 70% (Minimum
ECHC 2017 standards or ASIHRAE
90 1-2017 standards wihichever is

stringent
The Pamp shall be capable too
coinitnicate eflectively with BMS.

6.Punp shall have Mounting frame


with Ant vibration pads.
Note- Total Head Loss given is
Tininun requirement tor the system,
iead shall be calculated &
actual
conlirmed by tihe vender

at timeof Bididing.
1.4.1 140 USGPM, 30 meler/ as per Nos. 1,98,670.0o 42.170.003.13,000.00 2,97,350.00
calculati0n head (1 Working+1
Standby)
Grundfos Make- NB S0-315/303
Pump witla Bronze lmpeller, MS
Base Frame, 1E-3 totor, 5.5 KW

TOTAL AMOUNT (Ks.) R29,78,627.15/


Rupees Twenty Nine Lakh Seventy Eight Thousand Six
FHundred Twenty Seven only

Jejen
Dehradyn
perts
2.Terms &Conditions
GST: Extra - 12% on pumps and 18 % on Control Panel.
Delivery Charge: Included upto Dehradun Only.
Payment Terms: 10% advance with PO , 10 % advance within 15-20 days, 70 %
against Pl before dispatch from Factory and 10 % after Commissioning of pumps.
Delivery Time:4 to 12 weeks
BOQ Application Pump Motor Kw QTY Delivery Time
No Description
Primary Pump NB125-250/255 A- 22 Kw 4 Wecks
1.1.1 F-B-BAQ2E
Secondary NB125-315/338A- 1 nos on 4 woeks and 1
Pump F-B-BAQQE 45 KW 2
nos on 6-7 weeks
1.2.1

Variable 2P_2V_1DPT 45 11-12 weeks


1.2.3
Secondary KW_IP41_ind Fdr
Control Panel Panel_W/O BPS
ABB
Condensor NK150- 7-8 weeks
55 KW
pump 315/338Y1F1BE
1.3.1
-SBAQE455
1.3.2
Condensor NB100-315/334A- 30 KW 1 4 Weeks
pump F-B-BAQE
Hot NB50- 4 Weeks
1.4.1 water 315/303A-F- 5.5 KW
Pump A-BAQRE

Validity of offer: 15.11.2021.


Order Cancellation Charges: 30% of Order value.
Demurrage Charges : As Actual.
Material Storage at Chennai : Any order which is not cleared at the date of readiness of
goods whould be 1% of order value, per week.
Warranty: 12 Months from the date of commissioning or 15 month from the date of
dispatch, whichever is earlier.
Installation: Supply in our scope, Installation, all connection shall be in client scope.

Registrar
Copy to Finance Officer

aterperts
D e h r a d u n
Synergy Thrislington
Village Beer Plassi, P.O. - Manjholi,
Tehsil Nalagarh, Distt. Solan 174101
(Himachal Pradesh) India
Tel. No.: +91-1795-265375
E-mail: info@synergythrislington.com
Website: www.synergythrislington.com Thrislington

WORK ORDER

Ref. ST/ESTC/UK/WO/2021/04 DATE: Feb 09th2022

MENTOR WATER EXPERTS PVT LTD


Cubic Tower,65-Ballupur,
Chakrata Road,Dehradun(Uttarakhand)
248001
Ph-0135-2752443
Mo-7351002100/9412950122

Sub: Work Order for 500*04 Nos. 2000 LPD ETC Solar water heater system works as per attached Schedule
of rates at Polytechnic building Ramanagar Uttarakhand

Dear Sir,

This has reference to subsequent offers and your final offer vide mail MWEPL/SOLAR/2021-22/1013/R3 3rd we

are pleased to place the work order for the Solar power & Water Heating system at our ongoing project at

Ramnagar Uttarakhand of amount of Rs 2790000 (Rupees twenty seven lac ninty thousand only) including
GST accepted by us (Attached is the copy of scope of work and schedule of rates).

Terms and conditions:

1. All tools, equipment, consumables etc. will be arranged by you


2. You will take all safety precautions

3. You will abide all rule and regulations

4. You will abide by all statutory regulations as applicable


5. You wil be responsible for all your manpower and materials

6. Electricity and water shall be provided by Client at one point and further distribution shall be done by

AFS as per requirement

Cement and concrete is in client scope

.
8. Payment terms:

Payment Terms for LV System head:


10% advance on drawing approval
50% on material delivery

20% Pro- rata installation

10% on successful testing and


commissioning
10% shall be released after DLP of one year from the date of handing over

9. Special Conditions: Work to be done as per CPWD specifications


10. Shop drawing to be submitted in three prints A-2 size and soft
copy in auto CAD format within 5 days
after issue of Work order

11. Warranty shall be valid for a period of one year from the date of commissioning and handing over
12. Procurement to be done after written
approval from Engineer-In charge
13. Test certificates to be submitted
along with each bill

14. Any extra item shall not be executed without


written approval from Engineer In charge
15. Completion time within 45 days
16. Billing shall be done as per actual measurement

17. Billing should be in the of


name "M/s Synergy Thrislington", Village Beer Plassi, P.O.- Manjholi, Tehsil
-

Nalagarh, Distt.- Solan, HP-174101. GSTIN: 02ACHFS5278F1Z3

18. Site Address: ESTC Polytechnic, Kaniya village, Tehsil-Ramnagar, Distt.- Nainital, UK-244715
Kindly acknowledge the receipt of this "Work Order" and sign the duplicate copy as a token of your

acceptance.

Thanking you,

(Authorized Signatory)
For: Synergy Thrislington

Accepted by:
Title

Seal
Sub ESTC_Solar power & Water heating system
(SOLAR PV AND SOLAR HEATER)
Item No.
Description Qty Unit Rate Amount
1 |Supply, Installation, Testing and Commissioning of
ongrid Solar Photovoltaic Power Plant conforming to
MNRE specifications as amended, consisting of
Mono/Poly Crystalline silicon solar cells, net metering
facility/Zero Emmiting Device, necessary protections,
earthing, mounted on Aluminium/Gl structure of
suitable strength with following components complete
as required:
a) Solar Photovoltaic Module of capacity 330 Wp or
above, manufactured in India, conforming to IS
14286/IEC 61215, IS/IEC 61730-Part-1, IS/IEC 61730-
Part-2. Solar Photovoltaic Module conversion efficiency
shall not be less than 16.5%. PV modules used in solar
power plants/ systems must be warranted for their
output peak watt capacity, which should not be less
than 90% at the end of 10 years and 80% at the endof
25 years.
b Power Conditioning Unit (PCU) of 350-800 V DC
Input voltage range and 400 V AC, three phase, 4 wire,
50Hz +/-2.5 Hz, output voltage suitable to generate AC
Power with efficiency not less than 97%, total
|harmonic distortion less than 3% and suitable
for ambient temperature from 0 to 50 degree C. The
PCU shall adjust the voltage and frequency level to suit
the Grid Votage Frequency. c) Data Monitoring System
complete with accessories.

d) Fixing of Array junction box & Main junction box


with IP 65 protection and termination
arrangement for incoming and outgoing cable along
with glands, lugs and other accessories etc. as
required.
e) Lightning and surge voltage protection.

) Connections & Interconnections by supplying &


size XLPE insulated copper conductor
fixing required

|1.1 kV grade armoured power and controlc


between solar modules, main power cable to grid
supply PCU unit along with supplying & fixing of

and other accessories


necessary channel/conduit lugs
etc. as required
50 KWp 2,550,000.00 2,545,000.00
SITC of 125 A 25 KA FP MCCB in Powder coated MS
same make as MCCB) i/c spreader
enlosure(of
terminals complete asrequired
Job

capacity solar water heating


SITC of 2000 Itr per day
Tube Collector) suitable
with ETC (Evacuated
system suitable working
m o r e than
90% absorvity and
for celsius should be installed
at roof top of
approx 70 deg
complete with necessary
the existing building
with following configuration:
as required
hardware etc
Qty Unit Rate Amount
Item No. Description
Job 250,000.00 245,000.0o
Capacity 2000 Itr per day
of Hot water tank: SS304 L
MOC
y p e : Cylindrical Horizontal

Corrosion protection: Al + Mg Sacrificial Anode


Supporting Structure : Hot Dip galvanized Structure
In/Out water type: Non pressurized
PUF, 38 kg/m3
Type and Density of Insulation:
Thickness of Insulation: 50 mm
material: GI
Outer cladding
Cladding Thickness: 0.35 mm
Supplying, laying and fixing of 25 mm dia. B class GI
pipe on surface or recess complete i/c supplying and|
fixing rockwool insulation of density 20 kg/m3 and
cladded with minimum 0.63 mm thickness Aluminium
sheet, i/c necessary fixing with clamps, supports etc as
required.
100 mtr

Total Amount 2,790,000.00


ByREGISTERED/SPEED POST
Government of India
O/o The Executive Engineer
Central Public Works Department
atat ufetaru.
Ranchi Project,
CPWD
Airport Road, Hinoo, Ranchi-2
Email id:-eerpdcpwd@gmail.com & eerpd.cpwd@gov.in
i -54(CISF-STP)/touo/2022/)1-2y

e t utetotat, doatottofto,
t at-834002 ATERETS)

Mentor Water Experts Pvt. Ltd.


Cubic Tower, 65 Ballupur, Chakrata Road,
Dehradun, Uttarakhand - 248001.
Augmentation of capacity (150 KLD) of Sewerage Treatment Plant based on MBBR Technology
including design, supply, installation, testing and commissioning at 2nd Reserve Bn., CISE, Ranchi
Jharkhand).
(NIT No. 02/NIT(Modified)/EE/RP/CPWD/2021-22.)
HEtE,
78,92,713/
(3tOE ET a U o 7 AT rt dzg ATT) F [Schedule "A" for Specialized work 57,65,627/-(aA TIT

Schedule "B" for General Civil work 21,27,086/-(aota

Toattotofao, f adt saA TE AT }i E HBZIGT 3TCt (Performance Guarantee). " u at

i 31/10/2022 a Etott
ATut aE t Ageter Programme Chart (Time and Progress) and applicable labour licenses,
Registration
with EPFO, ESIC RAI BOCW Welfare Board at FT TU 3T 3 A T wT JudaaT Tafa d e

3ATYeDT 8TTHTT|

H T : (i) Form - III

For & On Behalf Of The President Of


India|
FORM-IIII
Under Rule 21(2) of the Contract Labour (Regulation and Abolition) Central Rules,
1971

Form of Certificate by Principal Employer

Certified that:
1. I have engaged the applicant (name of the Contractor Mentor Water Experts Pvt.
Ltd., Cubic Tower, 65 Ballupur, Chakrata Road, Dehradun, Uttarakhand - 248001

as a contractor in my establishment for the work "Augmentation of capacity (150


KLD) of Sewerage Treatment Plant based on MBBR Technology including design,
Ranchi
supply, installation, testing and commissioning at 2nd Reserve Bn., CISF,
Jharkhand)" to be carried till 31.10.2022.

2. I undertake to be bound by all the provisions of the Contract Labour (Regulation and
Abolition) Act, 1970 (37 of 1970) and the Contract Labour (Regulation and Abolition)
Central Rules, 1971 in so far as the provisions are applicable to me in respect of the

employment of contract labour by the applicant in my establishment.

3. The engagement of contract labour in the said work is not prohibited under sub
section (1) of section 10 of the Contract Labour (Regulation and Abolition) Act, 1970
(37 of 1970) or an award of a settlement.

Place: Ranchi.
Date: 18.01.2022
Signature of Príncipal Employer
Name and address of the establishment
To
i) The Labour Enforcement Officer (Central)
E-191, Sector-1I, HEC Colony, P. O. - Dhurwa, Ranchi.

ii) The Assistant Regional Labour Commissioner (Central)


E-191, Sector-II, HEC Colony, P. O. - Dhurwa, Ranchi.

iii) The Inspector,


The Regional Labour Commissioner (Central)
E-191, Sector-I1, HEC Colony, P. O. - Dhurwa, Ranchi.
Our ref:- AS/SB/CHD/HYATT/CDWP/2021-22/2207 Date:- 22-07-2021

MENTOR WATER EXPERTS PVT. LTD.


1Corp.Office: Cubic Tower, 65-Ballupr,Chakrata
Road,Dehradun-248001

Kind attn:- Mr. Chamoli

SUB:- PURCHASE ORDER FOR CHILLED WATER PUMPS FOR OUR HYATT PROJECTS

Sr No. Description Model Flow (USGPM) Head (Mtr) Pump Eff Qty Unit Price Total Price
Hyatt Haridwar
1 Primary Chilled Water Pump NB 65-125, 2 pole, 7.5 KW 425 16 79.50% 3 72765 218296
2 Secondary Chilled Water Pump NB 65-160, 2 pole, 11 KW 425 26 80.40% 3 110850 332551
3P_3V_1DPT_11KW_IP41_Ind Fdr
3 Control Panel 1 304577 304577
Panel_W/O BPS ABB WTH Modbus
4 Condensor Water Pump NB 80-160, 2 pole, 22 KW 680 30 78% 3 142716 428149
Hyatt Dehradun
1 Primary Chilled Water Pump NB 50-125, 2 pole, 4 KW 250 16 74.50% 3 57320 171961
2 Secondary Chilled Water Pump NB 50-125, 2 pole, 7.5 KW 250 26 74.50% 3 71279 213836
3P_3V_1DPT_7.5KW_IP41_Ind Fdr
3 Control Panel 1 249890 249890
Panel_W/O BPS ABB WTH MODBUS
4 Condensor Water Pump NB 65-160, 2 pole, 11 KW 400 29 79.50% 3 110850 332551
Hyatt Jaiselmar
1 Primary Chilled Water Pump NB 65-125, 2 pole, 5.5 KW 400 16 78.8 3 67159 201478
2 Secondary Chilled Water Pump NB65-125/144_2Pole_11KW 400 26 78.9 3 110850 332551
3P_3V_1DPT_11KW_IP41_Ind Fdr
3 Control Panel 1 304577 304577
Panel_W/O BPS ABB WTH Modbus
4 Condensor Water Pump NB80-160/165_2Pole_15KW 640 26 76.8 3 120621 361864
Grand Total ₹ 34,52,280 /-

Commercial Terms and Conditions :


1. Basic Price : Ex-Sites
2. Packing & forwarding charges : Inclusive
3. Taxes & duties : GST extra - 12% on pumps & 18 % on Controller Panel, or as applicable at the time of dispatch.
4.Freight : Included
5. Payment Terms : 25 % advance and 65% against Proforma Invoice before despatch , balance 10% after Commissioning .
6. Supply & supervision of commissioning of pumps will be in our scope.
7. Delivery : 6- 8 weeks for Pumps & 8-10 weeks for Control Panel , Clear Purchase Order with manufacturing clearance (Shall be provided by us

FOR AVONAIRE SOLUTIONS

SUNIL BHARDWAJ