You are on page 1of 24

Item Nr.

Description Unit Actual Quantity


Water Supply Resrvoirs and Appurtnant Structures
1 Concrete Works m3 1580.07
2 Formwork m2 2873.94
3 Re-Bar kg 146993.16
4 HCB walls 200mm thick m2 2335.18
5 HCB walls 150mm thick m2 139.08
6 Plastering m2 2601.05
7 Screeding m2 1074.43
Water Supply Distribution System
Site Clearance depth not exceeding 200mm including
1 cutting of trees and bushes along the route of pipe m2
line to the width of 4m. 41576.88
Trench Excavation in ordinary soil formation to the
2 m3
depth not exceeding 1500mm and width 700mm 16858.92
Trench Excavation in rock formation to the depth not
3 m3
exceeding 1500mm and width 700mm 4095.83
Provide 150mm selected bedding material before and
4 m3
after laying of the pipe. 4659.03
5 Backfill with (Native material) m 3
17462.29
6 Back fill with aluviam material from Borehole area m 3
2080.2
Instalation of PE100 HDPE pipes with Straight
Couplings of standard coil lengths as per ISO 4427
8
and specification , PN 10,Cost Include Compression
Fittings Installation at Joints
HDPE, DN 63 m 7535.65
HDPE, DN 50 m 2286.002
HDPE, DN 40 m 620.81
HDPE, DN 32 m 25
Female Threaded Bronze or Brass Compreession
9
Gate Valve for Connection at Joint Point
DN 32mm PN 10 Pcs 1
DN 50mm PN 16 Pcs 91
OD 63mm PN 10 Pcs 73
DN 100mm PN 10 Pcs 0
DN 80mm PN 10 Pcs 0
DN 40mm PN 10 Pcs 76
Compression GS Male Nipples for Connection at
10
Joint Point
DN 32mm PN 10 Pcs 20
GS DN 40mm PN 10 Pcs 152
GS DN 50mm PN 10 Pcs 174
GS OD 63mm PN 10 Pcs 146
Compreession HDPE 100 Couppling for Connection
11
at Joint Point
DN 32mm PN 10 Pcs 1
DN 40mm PN 10 Pcs 32
DN 50mm PN 10 Pcs 69
OD 63mm PN 10 Pcs 96
HDPE 100 Compreession Tee for Connection at
12
Joint Point
DN 32mm PN 10 Pcs 1
DN 40mm PN 10 Pcs 15
OD 63mm PN 10 Pcs 80
DN 50mm PN 10 Pcs 64
GS Internal Theraded Compression Reducer for
13
Connection at Joint Point
DN 50x40mm PN 10 Pcs 96
OD 63x25mm PN 10 Pcs 24
OD 63x32mm PN 10 Pcs 15
OD 63x40mm PN 10 Pcs 73
DN 63x50mm PN 10 Pcs 45
HDPE 100 Compression Male Adaptor for
14
Connection at Joint Point
DN 32mm PN 10 Pcs 0
OD 63mm PN 10 Pcs 66
DN 40mm PN 10 Pcs 25
DN 50mm PN 10 Pcs 71
HDPE 100 Compression Female Adaptor for
15
Connection at Joint Point
DN 32mm PN 10 Pcs 1
New FemaleTreaded Adaptor, HDPE 63mm, PN 10 Pcs 315
New FemaleTreaded Adaptor, HDPE 50mm, PN 10 Pcs 120
New FemaleTreaded Adaptor, HDPE 40mm, PN 10 Pcs 39
HDPE 100,Compression Reducing Tee for
16
Connection at Joint point
DN 50x32x50mm PN 10 Pcs 20
OD 63x25x63mm PN 10 Pcs 9
OD 63x32x63mm PN 10 Pcs 13
OD 63x40x63mm PN 10 Pcs 16
OD 63x50x63mm PN 10 Pcs 20
New DN 50 x 40 x 50mm PN 10 Pcs 2
HDPE 100 ,Compression Cross Tee for Connection
17
at Joint point
DN 50mm PN 10 Pcs 20
OD 63mm PN 10 Pcs 33
HDPE 100,Y-Tee for Compression Connection at
18 Joint Point
DN 63 x 50 mm PN 10 Pcs 14
OD 63 X 63 mm PN 10 Pcs 12
HDPE 100, 90 Degree Bend for Compression
19
Connection at Joint point
DN 40mm PN 10 Pcs 14
DN 50mm PN 10 Pcs 19
OD 63mm PN 10 Pcs 32
1.4mx1.4m masonry Valve chamber construction as
shown in the drawing including 80cmX80cm metal
20 Nr
sheet for manhole cover with thickness 2mm with all
accessory. 271
Sewerage System Civil Works
Trench common excavation as per the drawing and
1 m3 34748.70
specification
2 Trench rock excavation m3 4264.50
Backfill of trench with excavated (native material)
3 m3 20598.98
material
Beddding and Backfill of trench with sellected
4 m3 7102.31
material
6 OD 200mm m 9502.59
7 OD 250mm m 474.00
8 OD 315mm m 548.00
9 OD 400mm m 361.00
10 OD 450mm m 162.00
11 Main lline (With Cast Iron Cover)
Type A Pcs 109.00
Type B Pcs 19.00
Type C Pcs 10.00
12 Around the building (With RC Cover)
Type A Pcs 319.00
Type B Pcs 27.00
Type C Pcs 2.00
Site Electric Works

C MANHOLE with cast iron top cover inscribed


1 Nr
with ''EL MH '' 100*100*10cm
101.00
2 Concrete Base for Light Poles Nr 436.00
3 Duct for Cabels Lm 11200.00
Internal Compound Road
1 Trench Excavation m3 32214.00
2 Trench Backfill Using Imported m3 4268.73
3 Trench Backfill Using Excavated m 3
6703.51
4 Masonry Ditch m3 15199.88
5 Concrete Pitching m 3
618.30
6 Ditch Cover pcs 10305.00
7 Pointing m2 22794.20
8 Concrete Pipe Installation lm 2593.00
9 Manholes at 20m Interval pcs 136.00
10 Concrete Curbing Type 1 m 13097.20
11 Sub-Grade m3 16062.72
12 Sub-Base m 3
10708.48
13 Base Course m 3
10708.48
14 Prime Coating m3 53542.40
15 Asphalt Surfacing m 3
2677.12
16 Concrete Curbing Type 2 m 12984.20
Executed Quantity Remaining Quantity Remark

1137.07 443.00
1714.16 1159.78
111475.87 35517.29
0 2335.18
0.00 139.08
349.66 2251.39
0.00 1074.43

22430.84 19146.04

13481.39 3377.53

116.31 3979.52

551.24 4107.79
1469.42 15992.87
54.20 2026.00

2158.76 5376.89
417.67 1868.332
- 620.81
- 25.00

0 1
0 91
0 73
0 0
0 0
0 76

0 20
0 152
0 174
0 146

0 1
0 32
0 69
0 96

0 1
0 15
0 80
0 64

0 96
0 24
0 15
0 73
0 45

0
0 0
0 66
0 25
0 71

0 1
0 315
0 120
0 39

0 20
0 9
0 13
0 16
0 20
0 2

0 20
0 33

0 14
0 12

0 14
0 19
0 32

0 271

9812.62
24936.08
448.50 3816.00
4415.65
16183.33
1149.40
5952.91
5189.32 4313.27
65.00 409.00
19.00 529.00
200.00 161.00
0.00 162.00

68.00 41.00
19.00 0.00
8.00 2.00

182.00 137.00
27.00 0.00
2.00 0.00

58 for
Fiber
101.00 Cables
0.00 436.00
0.00 11200.00

31746.42 467.58
3747.15 521.58
5580.30 1123.21
13024.99 2174.89
0.00 618.30
64.00 10241.00
352.00 22442.20
2013.00 580.00
80.00 56.00
7531.00 5566.20
15741.47 321.25
10280.14 428.34
433.78 10274.70
167.00 53375.40
167.00 2510.12
0.00 12984.20
Item Nr. Description Unit Remaining Quantity
Water Supply Resrvoirs and Appurtnant Structures
1 Concrete Works m3 443.00
2 Formwork m2 1159.78
3 Re-Bar kg 35517.29
4 HCB walls 200mm thick m2 2335.18
5 HCB walls 150mm thick m2 139.08
6 Plastering m2 2251.39
7 Screeding m2 1074.43
Water Supply Distribution System
Site Clearance depth not exceeding 200mm including
1 cutting of trees and bushes along the route of pipe m2
line to the width of 4m. 19146.04
Trench Excavation in ordinary soil formation to the
2 m3
depth not exceeding 1500mm and width 700mm 3377.53
Trench Excavation in rock formation to the depth not
3 m3
exceeding 1500mm and width 700mm 3979.52
Provide 150mm selected bedding material before and
4 m3
after laying of the pipe. 4107.79
5 Backfill with (Native material) m3
15992.87
6 Back fill with aluviam material from Borehole area m3
2026.00
Instalation of PE100 HDPE pipes with Straight
Couplings of standard coil lengths as per ISO 4427
8
and specification , PN 10,Cost Include Compression
Fittings Installation at Joints
HDPE, DN 63 m 5376.89
HDPE, DN 50 m 1868.332
HDPE, DN 40 m 620.81
HDPE, DN 32 m 25.00
1.4mx1.4m HCB Valve chamber construction as
shown in the drawing including 80cmX80cm metal
9 Nr
sheet for manhole cover with thickness 2mm with all
accessory. 271
Sewerage System Civil Works
Trench common excavation as per the drawing and
1 m3
specification 24936.08
2 Trench rock excavation m3 3816.00
Backfill of trench with excavated (native material)
3 m3
material 16183.33
Beddding and Backfill of trench with sellected
4 m3
material 5952.91
6 OD 200mm m 4313.27
7 OD 250mm m 409.00
8 OD 315mm m 529.00
9 OD 400mm m 161.00
10 OD 450mm m 162.00
11 Main lline (With Cast Iron Cover)
Type A Pcs 41.00
Type B Pcs 0.00
Type C Pcs 2.00
12 Around the building (With RC Cover)
Type A Pcs 137.00
Type B Pcs 0.00
Type C Pcs 0.00
Site Electric Works

C MANHOLE with cast iron top cover inscribed


1 Nr
with ''EL MH '' 100*100*10cm
101.00
2 Concrete Base for Light Poles Nr 436.00
3 Duct for Cabels Lm 11200.00
Internal Compound Road
1 Trench Excavation m3 467.58
2 Trench Backfill Using Imported m 3
521.58
3 Trench Backfill Using Excavated m 3
1123.21
4 Masonry Ditch m3 2174.89
5 Concrete Pitching m 3
618.30
6 Ditch Cover pcs 10241.00
7 Pointing m2 22442.20
8 Concrete Pipe Installation lm 580.00
9 Manholes at 20m Interval pcs 56.00
10 Concrete Curbing Type 1 m 5566.20
11 Sub-Grade m3 321.25
12 Sub-Base m 3
428.34
13 Base Course m 3
10274.70
14 Prime Coating m3 53375.40
15 Asphalt Surfacing m 3
2510.12
16 Concrete Curbing Type 2 m 12984.20
60 Days Remaining
Expected Daily
Remark
Performance

7.38
19.33
591.95
38.92
2.32
37.52
17.91

319.10

56.29

66.33

68.46
266.55
33.77

89.61
31.14
10.35
0.42

4.52

415.60
63.60

269.72

99.22
71.89
6.82
8.82
2.68
2.70

0.68
0.00
0.03

2.28
0.00
0.00

58 for
Fiber
1.68 Cables
7.27
186.67

7.79
8.69
18.72
36.25
10.31
170.68
374.04
9.67
0.93
92.77
5.35
7.14
171.25
889.59
41.84
216.40
Item Nr. Description Unit Remaining Quantity

Water Supply Resrvoirs and Appurtnant Structures


1 Concrete Works m3 443.00
2 Formwork m2 1159.78
3 Re-Bar kg 35517.29
4 HCB walls 200mm thick m2 2335.18
5 HCB walls 150mm thick m2 139.08
6 Plastering m2 2251.39
7 Screeding m2 1074.43
Water Supply Distribution System
Site Clearance depth not exceeding 200mm including
1 cutting of trees and bushes along the route of pipe m2
line to the width of 4m. 19146.04
Trench Excavation in ordinary soil formation to the
2 m3
depth not exceeding 1500mm and width 700mm 3377.53
Trench Excavation in rock formation to the depth not
3 m3
exceeding 1500mm and width 700mm 3979.52
Provide 150mm selected bedding material before and
4 m3
after laying of the pipe. 4107.79
5 Backfill with (Native material) m3
15992.87
6 Back fill with aluviam material from Borehole area m3
2026.00
Instalation of PE100 HDPE pipes with Straight
Couplings of standard coil lengths as per ISO 4427
8
and specification , PN 10,Cost Include Compression
Fittings Installation at Joints
HDPE, DN 63 m 5376.89
HDPE, DN 50 m 1868.332
HDPE, DN 40 m 620.81
HDPE, DN 32 m 25.00
1.4mx1.4m HCB Valve chamber construction as
shown in the drawing including 80cmX80cm metal
9 Nr
sheet for manhole cover with thickness 2mm with all
accessory. 271
Sewerage System Civil Works
Trench common excavation as per the drawing and
1 m3
specification 24936.08
2 Trench rock excavation m3
3816.00
Backfill of trench with excavated (native material)
3 m3
material 16183.33
Beddding and Backfill of trench with sellected
4 m3
material 5952.91
6 OD 200mm m 4313.27
7 OD 250mm m 409.00
8 OD 315mm m 529.00
9 OD 400mm m 161.00
10 OD 450mm m 162.00
11 Main lline (With Cast Iron Cover)
Type A Pcs 41.00
Type C Pcs 2.00
12 Around the building (With RC Cover)
Type A Pcs 137.00
Site Electric Works
C MANHOLE with cast iron top cover inscribed
1 Nr
with ''EL MH '' 100*100*10cm 101.00
2 Concrete Base for Light Poles Nr 436.00
3 Duct for Cabels Lm 11200.00
Internal Compound Road
1 Trench Excavation m3 467.58
2 Trench Backfill Using Imported m 3
521.58
3 Trench Backfill Using Excavated m 3
1123.21
4 Masonry Ditch m3 2174.89
5 Concrete Pitching m 3
618.30
6 Ditch Cover pcs 10241.00
7 Pointing m2 22442.20
8 Concrete Pipe Installation lm 580.00
9 Manholes at 20m Interval pcs 56.00
10 Concrete Curbing Type 1 m 5566.20
11 Sub-Grade m3 321.25
12 Sub-Base m 3
428.34
13 Base Course m 3
10274.70
14 Prime Coating m3 53375.40
15 Asphalt Surfacing m 3
2510.12
16 Concrete Curbing Type 2 m 12984.20
60 Days Remaining

Expected Daily
Required Machineries
Performance

Excavator/
Dozer Grader Loader Compactor
JH

7.38
19.33
591.95
38.92
2.32
37.52
17.91

319.10 0.03 1.06

56.29 0.19

66.33 0.22

68.46 0.34
266.55 0.89
33.77 0.11

89.61
31.14
10.35
0.42

4.52

415.60 1.39
63.60 0.21
269.72 0.90

99.22 0.33
71.89 0.24
6.82
8.82
2.68
2.70

0.68
0.03

2.28

1.68
7.27
186.67

7.79 0.03
8.69 0.04 0.09
18.72 0.04 0.19
36.25 0.45
10.31
170.68
374.04
9.67 0.64
0.93
92.77
5.35 0.06 0.02 0.01 0.01
7.14 0.08 0.03 0.01 0.01
171.25 0.68 0.34 0.34
889.59
41.84
216.40
0.158099371 0.734952907 3.905608384 3.54880989 0.64160872
1 1 4 4 1
d Machineries
Total Required Machineries
Compactor/ Concrete
Crane Water Truck
Tamper Mixer Type Nr
Dozer 1
0.21 0.21 Grader 1
Loader 4
Excavator/JH 4
Compactor 1
Compactor/Tamper 2
Crane 1
Concrete Mixer 4
Water Truck 5

0.23 0.23
0.09 0.09
0.00 0.00

0.29 0.29

0.21 0.21
0.73 0.73

0.87 0.04
0.94 0.04

0.26 0.26
1.42 1.42

0.16 0.24

0.02
0.03
0.68

1.805313 0.161111111 3.670521825 4.244713619


2 1 4 5
Item Nr. Description Unit Remaining Quantity

Water Supply Resrvoirs and Appurtnant Structures


1 Concrete Works m3 443.00
2 Formwork m2 1159.78
3 Re-Bar kg 35517.29
4 HCB walls 200mm thick m2 2335.18
5 HCB walls 150mm thick m2 139.08
6 Plastering m2 2251.39
7 Screeding m2 1074.43
Water Supply Distribution System
Site Clearance depth not exceeding 200mm including
1 cutting of trees and bushes along the route of pipe m2
line to the width of 4m. 19146.04
Trench Excavation in ordinary soil formation to the
2 m3
depth not exceeding 1500mm and width 700mm 3377.53
Trench Excavation in rock formation to the depth not
3 m3
exceeding 1500mm and width 700mm 3979.52
Provide 150mm selected bedding material before and
4 m3
after laying of the pipe. 4107.79
5 Backfill with (Native material) m3
15992.87
6 Back fill with aluviam material from Borehole area m3
2026.00
Instalation of PE100 HDPE pipes with Straight
Couplings of standard coil lengths as per ISO 4427
8
and specification , PN 10,Cost Include Compression
Fittings Installation at Joints
HDPE, DN 63 m 5376.89
HDPE, DN 50 m 1868.332
HDPE, DN 40 m 620.81
HDPE, DN 32 m 25.00
1.4mx1.4m HCB Valve chamber construction as
shown in the drawing including 80cmX80cm metal
9 Nr
sheet for manhole cover with thickness 2mm with all
accessory. 271
Sewerage System Civil Works
Trench common excavation as per the drawing and
1 m3
specification 24936.08
2 Trench rock excavation m3
3816.00
Backfill of trench with excavated (native material)
3 m3
material 16183.33
Beddding and Backfill of trench with sellected
4 m3
material 5952.91
6 OD 200mm m 4313.27
7 OD 250mm m 409.00
8 OD 315mm m 529.00
9 OD 400mm m 161.00
10 OD 450mm m 162.00
11 Main lline (With Cast Iron Cover)
Type A Pcs 41.00
Type B Pcs 0.00
Type C Pcs 2.00
12 Around the building (With RC Cover)
Type A Pcs 137.00
Type B Pcs 0.00
Type C Pcs 0.00
Site Electric Works
C MANHOLE with cast iron top cover inscribed
1 Nr
with ''EL MH '' 100*100*10cm 101.00
2 Concrete Base for Light Poles Nr 436.00
3 Duct for Cabels Lm 11200.00
Internal Compound Road
1 Trench Excavation m3 467.58
2 Trench Backfill Using Imported m 3
521.58
3 Trench Backfill Using Excavated m 3
1123.21
4 Masonry Ditch m3 2174.89
5 Concrete Pitching m 3
618.30
6 Ditch Cover pcs 10241.00
7 Pointing m2 22442.20
8 Concrete Pipe Installation lm 580.00
9 Manholes at 20m Interval pcs 56.00
10 Concrete Curbing Type 1 m 5566.20
11 Concrete Curbing Type 2 m 12984.20
12 Sub-Grade m3 321.25
13 Sub-Base m 3
428.34
14 Base Course m3 10274.70
15 Prime Coating m 3
53375.40
16 Asphalt Surfacing m 3
2510.12
60 Days Remaining

Expected Daily
Required Manpower
Performance

Labor
Forman Mason Carpenter Bar Bender
Forman

7.38 0.42 0.21 2.11 0.42 0.42


19.33 0.68 4.35
591.95 1.24 1.24 4.97
38.92 1.01 7.78
2.32 0.06 0.46
37.52 2.81
17.91 1.79

319.10

56.29 0.19

66.33 0.83

68.46
266.55
33.77

89.61 0.45
31.14 0.16
10.35 0.05
0.42 0.00

4.52 6.07

415.60 1.39
63.60 0.80
269.72

99.22
71.89 0.48
6.82 0.05
8.82 0.06
2.68 0.02
2.70 0.02

0.68 0.68 2.05 2.73 2.73


0.00
0.03 0.03 0.10 0.13 0.13

2.28 2.28 6.85 9.13 9.13


0.00
0.00

1.68 0.17 1.01 0.67 0.67


7.27 0.73 2.18 2.91 2.91
186.67

7.79 0.03
8.69
18.72
36.25 6.71 1.34
10.31 0.42 0.21 2.11 0.42
170.68 8.53 2.84 4.27
374.04 15.58 3.12
9.67 0.64 2.58 0.64
0.93 0.93 2.80 3.73 3.73
92.77 3.71 1.24
216.40 8.66 2.89
5.35 0.01 0.01
7.14 0.01 0.01
171.25 0.34 0.34
889.59
41.84
13.55699293 2.032983822 84.52715948 36.57719537 28.97673186
14 3 85 37 29
npower Total Required Man
Power
Electrician Plumber Labror
Type Nr
Forman 14
0.21 10.55 Labor Forman 3
4.35 Mason 85
7.46 Carpenter 37
9.73 Bar Bender 29
0.58 Electrician 2
11.26 Plumber 3
5.37 Labror 259

0.19

0.83

0.67 0.90
0.23 0.31
0.08 0.10
0.00 0.00

7.59

1.39
0.80
0.72 0.72
0.07 0.07
0.09 0.09
0.03 0.03
0.03 0.03

8.88

0.43

29.68

2.19
9.45
0.93 0.93 1.87

0.08

13.42
0.21 10.55
17.07
31.17
6.44
12.13
14.84
34.62
0.11
0.14
3.42

1.355238095 2.848757333 258.8359849


2 3 259

You might also like