Instruction manual

Installation recommendations
Sécheron DC switchgears

Document number: SG840230TEN


Language: EN  |  Revision: #01  |  Issue date: 01.03.2017

Established by: V. Rivero 01.03.2017

Checked by: xxxxxxxxxxxx 01.03.2017

Released by: S. Poncet 01.03.2017

—  Number of pages: 62 —


Sécheron SA Tel: +41 (0)22 739 41 11
Rue du Pré-Bouvier 25 Fax: +41 (0)22 739 48 11
1242 Satigny - Geneva substations@secheron.com
CH-Switzerland www.secheron.com

Copyright© 2017 Sécheron SA


Geneva, Switzerland.
Reproduction in whole or part or disclosure to a third party prohibited.

Design modifications
This document is not contractual and contains information corresponding to the
level of technology at the date of release.
Sécheron reserves the right to modify and/or improve the product, whose
characteristics are described in these documents, as required by new technology
at any time.
It is the purchaser’s responsibility to inform himself, no matter what the circumstances,
of the product’s maintenance conditions and requirements.
Sécheron reserves all rights, especially those arising from our general delivery
conditions.
Despite the most careful scrutiny, this document may contain errors or incomplete
statements or details. We accept no responsibility for damages resulting from
incorrect documentation.

Document information
It is important to keep this manual for the lifetime of the equipment and to pass it on
to any subsequent owner or user.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Revision changes

Revision changes
Revision Date Established by Description
#00 21.02.2017 V. Rivero • Preliminary version.
• Updated § H.2.5 Insulation resistance test.
• Added § G.3. Insulation sheet tips.
#01 01.03.2017 V. Rivero
• Updated § G.4.2 Levelling.
• Updated § G.5.1. “Standard” variant.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
3
Revision changes Installation recommendations

This page intentionally left blank.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
4 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Table of contents

Table of contents
A. Introduction 9
A.1. Goal of this manual . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
A.2. Document information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
A.3. Guarantee . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
A.4. After Sales Services (RMA) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

B. Safety precautions 11
B.1. Hazard information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
B.2. Danger . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
B.3. Personnel requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
B.4. The two-person rule of working . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
B.5. Voltage levels . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

C. Abbreviations 13

D. Delivery and storage 15


D.1. Delivery status . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
D.2. Packaging . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
D.3. Transport . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
D.4. Taking delivery of goods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
D.5. Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
D.5.1. Storage conditions (IEC 61992-1, Appendix B - 2001) . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
D.5.2. Short term storage (few days) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
D.5.3. Long term storage (more than few days) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

E. Conditions of use 19
E.1. Normal operating conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19
E.2. Particular operating conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
5
 Installation recommendations

F. Preliminary information 21
F.1. General requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
F.1.1. Generalities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
F.1.2. Floor flatness and level . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
F.1.3. Floor insulating principle . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22

F.2. Before starting any work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23


F.3. Important mechanical general rules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23
F.4. Consumable parts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
F.5. Tools needed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
F.6. Installation material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
F.7. Opening cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
F.8. Handling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

G. Installation 29
G.1. Cubicles preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
G.2. Example of installation layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
G.3. Insulation sheet tips . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
G.4. Positioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
G.4.1. First unit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
G.4.2. Levelling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
G.4.3. Following cubicles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

G.5. Attachment of the cubicles together . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32


G.5.1. “Standard” variant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
G.5.2. Variant with separation sheet between the cubicles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
G.5.3. Variant with insulation sheet between the cubicles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

G.6. Fixing on floor (principle) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35


G.7. Busbar and earth bar connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
G.8. Earth connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
G.9. High-voltage connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
G.10. Low-voltage connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

H. Service and maintenance 39

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
6 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Table of contents

H.1. Safety precautions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39


H.2. Maintenance plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
H.2.1. Periodicity and controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
H.2.2. Visual control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
H.2.3. Cleaning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
H.2.4. Greasing instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
H.2.4.1. MBS cubicles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
H.2.4.2. SECUB-2 cubicles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
H.2.5. Insulation resistance test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
H.2.6. Prevent condensation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
H.2.7. Treatment of screwed contact surfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
H.2.8. Checking tightening . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
H.2.9. Replacement of components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
H.2.10. Protection against corrosion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
H.2.11. Once maintenance works are completed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51

H.3. Racking in and out of the MBS HSCB trolley . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52


H.3.1. Procedure to rack-in the HSCB trolley . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
H.3.2. Procedure to rack-out the HSCB trolley . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

H.4. Insertion-extraction HSCB drawer SECUB-2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54


H.4.1. Extraction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
H.4.2. Insertion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
7
 Installation recommendations

This page intentionally left blank.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
8 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Introduction

A. Introduction
DANGER!
To ensure maximum safety, technicians and operators must read the section B. Safety
precautions, before starting installation, maintenance and adjustment of the equipment
or operation.

A.1. Goal of this manual


The purpose of this document is to describe the equipment delivered by Sécheron SA.
These operating instructions do not contain information about all product types and cannot cover
every conceivable installation, operation and maintenance condition.
The pictures and colors used to illustrate this description are not contractual.

For further information, or specific questions that are not dealt with in this document, please
contact your local Sécheron representative.

A.2. Document information


Throughout this document:
• The numbers between brackets (X) refer to the corresponding positions in the figure shown in
the same section.
• The blue texts are hyperlinks, used to navigate in the PDF.

A.3. Guarantee
With exception to certain cases, the guarantee period is as indicated under our “General Delivery
Conditions”.

A.4. After Sales Services (RMA)


For requests concerning After Sales Services or for any return of goods to Sécheron, please refer
to our website www.secheron.com and click “Services” then “Return Merchandise Authorization
(RMA)”.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
9
Introduction Installation recommendations

This page intentionally left blank.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
10 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Safety precautions

B. Safety precautions
B.1. Hazard information
Hazard information in this document have the following meaning:
DANGER!
Immediate danger to life!
Failure to observe this information will result in death or serious personal injury!
WARNING!
Risk of serious personal injury!
Failure to observe this information could result in death or serious personal injury!
CAUTION!
Risk of minor personal injury!
Failure to observe this information may result in minor personal injury!
IMPORTANT!
Risk of damage to equipment!
Failure to observe this information could result in damage to equipment!
IMPORTANT!
Observe antistatic precautions when handling memory cards!
Remarks, notes.

B.2. Danger
Safety recommendations complementary to the customer’s regulations.

DANGER!
High voltage electricity can kill or cause serious injury.
All work carried out on the equipment must be performed with power off and with the
equipment secured.
Never touch the high voltage parts before the high voltage circuit is disconnected and the
earthing protection is installed.
Modifying, removing, deactivating or otherwise changing components in any way may
affect the safety of the device.
Not using parts from the original manufacturer can affect the performance and safety of
the device and automatically waives the warranty provided by Sécheron.
Equipment that appears damaged or defective should be disconnected or made
inoperative and secured against unintended operation until it can be repaired by qualified
personal.
Comply with the applicable local regulations.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
11
Safety precautions Installation recommendations

B.3. Personnel requirements


WARNING!
If safety precautions are not followed, there is a risk of personal injury.

The personnel operating the equipment is responsible for the safety and the work carried out.
Technicians and operators are responsible for:
• The equipment and the working area around the device.
• The personnel in the equipment area and working area.
• Ensuring that the safety test is fully completed before the high voltage circuit is connected.
Installation, operation and maintenance must be performed by skilled and instructed technicians
only. Technicians and operators should be certified according to local regulations and
requirements.
A skilled person is:
• An individual with technical knowledge or sufficient experience to enable that individual to
avoid hazards associated with electricity and extended to the hazards presented by the
mechanical devices and chemicals used.
An instructed person is:
• An individual adequately advised or supervised by a skilled person to enable that individual
to avoid hazards associated with electricity and extended to the hazards presented by the
mechanical devices and chemicals used.

B.4. The two-person rule of working


The purpose of this rule is to limit the consequences of accidents or sudden illness.
DANGER!
As a general rule, staff must not work alone where a significant hazard exists. A second
person who can provide appropriate assistance in the event of an emergency must be
available.

B.5. Voltage levels


DANGER!
The voltage levels of the auxiliary and control circuits can also represent a potential
danger.
Apply safety measures!

Refer to the specific electric diagrams of the equipment to determine the applied voltage.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
12 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Abbreviations

C. Abbreviations
Abbreviations commonly used in Sécheron documents:

Abbreviation Meaning
AC Alternating Current
BMS Contactor 
CB Circuit Breaker
CR10 Return current detector 
DC Direct Current
DISPLAY Optional display module for the SEPCOS 
DS Disconnect Switch
ECO resistor HSCB coil resistor
EMC ElectroMagnetic Compatibility
ESS Energy Storage System
HMI Human-Machine Interface
HSCB DC High Speed Circuit Breaker 
HSCB type E DC High Speed Circuit Breaker with electric holding coil 
HSCB type M DC High Speed Circuit Breaker with magnetic holding coil 
HV High Voltage
IDS Direct tripping system
IGBT Insulated-Gate Bipolar Transistor
IPT InterPhase Transformer
LBS Load Break Switch
LED Light-Emitting Diode
LTD Line Test Device 
LTD-C Line Test Device with reduced voltage 
LTD-D Old Line Test Device with full voltage replaced by LTD-F 
LTD-F Line Test Device with full voltage 
LV Low Voltage
MBS DC panel, type MBS 
MBS 500 DC panel, type MBS, 500 mm width 
MBS 800 DC panel, type MBS, 800 mm width 
MCB Miniature Circuit Breaker
MIU10 Isolated amplifier for current measurement 
MPCB Motor Protection Circuit Breaker
MV Medium Voltage
NC Normally Closed contact
NO Normally Open contact

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
13
Abbreviations Installation recommendations

Abbreviation Meaning
OCC Operation Control Command
OVPD Over Voltage Protection Device
PLC Protection and control unit / Programmable logic controller
RC Resistor-Capacitor
SCADA Supervisory Control And Data Acquisition
SCMS Stray Current Monitoring System
SEC Contactor 
SECUB DC panel, type SECUB 
SECUB-2 DC panel, type SECUB-2 
SEPCOS Protection and control unit 
S-Web SEPCOS user interface program 
SW Series Switches 
SWG Earthing Switch 
SWI Change over Switch 
SWS Disconnector 
TVP Touch Voltage Protection
UR Series Circuit Breakers 
VLD Voltage Limiting Device
VLD-B Basic VLD (with contactor)
VLD-H Hybrid VLD (with contactor and Thyristor)
VM10 Isolated amplifier for voltage measurement 
VM12 Isolated amplifier for voltage measurement 
VP10 Isolated relay for voltage presence detection 
WDG Watchdog

  Products, devices or equipment developed by Sécheron.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
14 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Delivery and storage

D. Delivery and storage


D.1. Delivery status
In workshop, the equipment is subject to a control to ensure that their construction is compliant
and that it is ready for operation.
The equipment is delivered by unit or in small groups of panels.
The material that relates to the different busbar, the installation equipment and the operating
accessories are generally packed separately.

D.2. Packaging
The packaging is defined according to the delivery conditions.
• Equipment without packing.
• Equipment with simple packing.
• Equipment with packing for maritime transport or equivalent.
–– Desiccant bags supplied for transport.
–– Packed in a sealed polyethylene film or in aluminium.
IMPORTANT!
Do not open the cases if you do not intend to proceed immediately with installation on the
final site! The packaging protect the equipment!

D.3. Transport
DANGER!
Apply safety precautions during transport of equipment!
Cases must be moved with specific lifting machines.

D.4. Taking delivery of goods


On receipt of the delivery, check all items for damage and verify with the delivery note that the
delivery is complete.
In the event that damages are stated at the time of the delivery, the consignee shall immediately
notify them on the delivery note remitted by the forwarder and then inform the supplier, should the
consignee has a doubt about any not visible damages, the supplier highly recommend that such
statement is also indicated on the delivery note and the supplier informed. Passed a contractual
delay of seven (7) days after the date of receipt of the material, the forwarder nor the supplier can
not in any circumstances be hold as responsible for any eventual damages.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
15
Delivery and storage Installation recommendations

D.5. Storage
D.5.1. Storage conditions (IEC 61992-1, Appendix B - 2001)
• Ambient temperature during transport and storage: between -25 °C and +55 °C (-13 °F and
131 °F).
• Maximum daily average ambient temperature: +35 °C (95 °F).
• Absolute maximum ambient temperature: +40 °C (104 °F).
• Minimum ambient temperature during operation: -5 °C (23 °F).
• Indoors, air shall be clean and its relative humidity shall be not more than 50% RH at the
maximum temperature of +40 °C (104 °F). Relative humidity may be higher if the temperatures
are lower, for example, 90% RH at +20 °C (68 °F).
• The warehouse must be closed, securized and with a regulated ventilation (temperature /
humidity).

D.5.2. Short term storage (few days)


ff EQUIPMENT WITHOUT PACKING
• Do not dirty the room with corrosive or combustible gases, with dust, smoke, steam or salt.
• Prevent rodent damages on cables and inside the cubicles.
• Cover the equipment with a protection film.
• Ensure a sufficient ventilation.

ff EQUIPMENT WITH SIMPLE PACKING


• Do not dirty the room with corrosive or combustible gases, with dust, smoke, steam or salt.
• Prevent rodent damages on cables and inside the cubicles.
• Partially open the packing to ensure a minimum ventilation.

ff EQUIPMENT WITH PACKING FOR MARITIME TRANSPORT OR EQUIVALENT


• Store the equipment in a covered place that is dry and sheltered from the wind.
• Protect the cases against dirt, water and other possible damages.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
16 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Delivery and storage

D.5.3. Long term storage (more than few days)


Contact the manufacturer.

ff EQUIPMENT WITHOUT PACKING, WITH SIMPLE PACKING OR UNPACKED


• Do not dirty the room with corrosive or combustible gases, with dust, smoke, steam or salt.
• Prevent any dust accumulation in the warehouse.
• The cleaning interval should be defined depending on the pollution degree.
• Prevent rodent damages on cables and inside the cubicles.
• Check for any humidity or condensation mark inside and outside of the cubicles.
• Allow to Sécheron SA or to his representative to get to the storage place for regular inspections.
• Carry out frequent visual controls (at least every 15 days). If damages are detected, Sécheron
SA has to be informed immediately and pictures must be sent in order to estimate the damages.
• Any cubicle or equipment has to be connected to the auxiliary power supply in order to test
regularly the equipment, which includes:
–– Switching on of the control and protection relay SEPCOS.
–– Opening and closing of the circuit breaker.
–– Opening and closing of the disconnector switch.
IMPORTANT!
All the cubicles must be connected to 230 VAC in order to supply the material with
permanent heating. If the equipment does not include heating, use auxiliary heaters to
maintain a dry air!

ff EQUIPMENT WITH PACKING FOR MARITIME TRANSPORT OR EQUIVALENT


• The original maritime packing provides a 1-year guarantee.
• Raise the cases (e.g. using wooden blocks) in order to protect them against flooding and
water infiltrations.
Because of the maritime vacuum-packing, the opening of the packaging for inspection has to be
required to Sécheron SA. Opening could not be done without Sécheron’s authorization.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
17
 Installation recommendations

This page intentionally left blank.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
18 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Conditions of use

E. Conditions of use
E.1. Normal operating conditions
IMPORTANT!
The panels are always installed indoor and never exposed to outdoors conditions!
• Altitude........................................................... > - 120 m and < 1400 m (> -393 ft and < 4593 ft)
• Atmospheric pressure......................................................................................77,8 to 110,4 kPa
• Ambient temperature during Service........................................... - 5 to + 40°C (23 °F to 104 °F)
• Maximum daily average temperature................................................................... + 35°C (95 °F)
• Relative humidity.......................... 50% at + 40°C ; 90% at 20°C (50% at 104°F ; 90% at 68°F)
IMPORTANT!
Ventilation and / or heating in the spaces intended for installation of the equipment shall
be capable of maintaining the temperature and humidity of the ambient air within the
limits stated above!
• Pollution PD3 / PD4..................................................................................... Level 1 of EN60721
• Vibrations and shocks...................................................... According to Annex B of EN 50123-1
• Fire hazardous...............................................................................................................Class F0

E.2. Particular operating conditions


IMPORTANT!
Particular operating conditions are to be agreed between the customer and the
manufacturer!
• Site altitude above 1400 m (4593 ft).
–– Take into account the reduction in dielectric strength of the air.
• Increased ambient temperature.
–– The current carrying capacity is reduced.
–– Use of additional cooling facilities for heat dissipation.
• Atmospheric conditions.
–– High humidity or rapid / major temperature fluctuations.
–– Prevent condensation with appropriate countermeasures, e.g. additional electric heaters.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
19
 Installation recommendations

This page intentionally left blank.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
20 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Preliminary information

F. Preliminary information
F.1. General requirements
F.1.1. Generalities
DANGER!
Apply safety precautions!
Installation works must be carried out only by personal duty qualified and trained!
Refer to B. Safety precautions

The place where the installation will be carried out must be ready before the beginning of the
operations.
The necessary works for the routing of the power and control cables (drilling, channels, etc.)
must be completed.
Always refer to the layout drawings.

IMPORTANT!
Drill the floor holes for fixing only AFTER having positioned the cubicles!

F.1.2. Floor flatness and level


IMPORTANT!
To avoid improper functioning of doors, HSCB trolleys and associated shutters, the
cubicle assemblies must respect the following flatness and level tolerances!

ff Flatness
± 1 mm per section length of 1 meter.

ff Level
Maximum 1 mm per meter on the floor, without however never exceeding ± 3 mm over the total
length of the enclosures assembled side by side.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
21
Preliminary information Installation recommendations

F.1.3. Floor insulating principle


DANGER!
The DC cubicles must be mounted insulated from the floor. The connection of the
equipment to the main earth has to be made only in one point, foreseen for that purpose,
at the output of the low impedance relay.

The solution adopted by Sécheron SA for the earthing of the cubicles is the use of a low
impedance protection relay. This solution implies that the cubicles must be mounted insulated
from the floor to ensure a correct operation of the protection relay.
Recommended insulation value: > 100 kΩ.

This value ensures an optimum insulation, sending a maximum of the fault current through the
protection relay, guaranteeing the correct operation of the protection in case of a fault (voltage
presence in the frame). This insulation can be insured by an insulating sheet of 1-2 mm thick.
Another solution is the use of an automatic levelling insulating cement.

1 2

“64”
I>

6
4
7

1. DC circuit breaker cubicles 5. DC cubicles earth bar *1


2. DC panel 6. Insulation sheet
3. Low impedance relay 7. Floor
4. Main earth

IMPORTANT!
When fixing the cubicles on the floor, take care to avoid any contact between the frame
and any part considered as electrically earthed!
A kit for the fixing on the floor is foreseen in Sécheron’s scope of supply. This kit contains an
insulated washer to be necessarily used to avoid a fortuitous earthing of the cubicles.
Sécheron’s reference: SG806195R5.
Refer to the appropriate electric diagram to identify the earthing connections between all the
equipment.
*1: The cubicles type SECUB-2 are not equipped with earth bar, the connection is made within
the frame.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
22 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Preliminary information

F.2. Before starting any work


Before starting any work, please control:
• Tools needed for this work are ready to be used (refer to F.5. Tools needed).
• Material needed (parts, screws, washers, nuts, etc.) is checked and closed to the cubicle to
be erected (refer to F.6. Installation material).
• People know and understand what they have to do.
• The place where the installation will be carried out must be ready before the beginning of the
installation operations.
• The necessary works for the routing of the power and control cables (drilling, channels, etc.)
must be completed (always refer to the layout drawings).

F.3. Important mechanical general rules


• Each time an alignment, a levelling or a mechanical setting is required, use systematically an
air level to guarantee the best result possible.
• Each time a part or a screw, a nut, etc. is loosen, please put it back in its place.
• Each time a screw or a nut is tighten at a mentioned torque range (refer to H.2.8. Checking
tightening, use a torque (Dynamometric) wrench and mark the bolt (e.g. with a red marker).
• Pay attention to the orientation for spring washer.

ff FIXING TWO PARTS TOGETHER

Connections (copper bars) Mechanical parts


1. Screw 1. Screw
2. Spring washer 2. Flat washer
3. First part 3. First part
4. Second part 4. Second part
5. Spring washer 5. Spring washer
6. Nut 6. Nut

3 4
2 5
1 6

ff TIGHTENING TORQUES
Refer to H.2.8. Checking tightening.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
23
Preliminary information Installation recommendations

F.4. Consumable parts


The following products are recommended for the installation and maintenance of the equipment
(not exhaustive list).

Item Designation
Bearing grease for moving mechanical Retinax LX2.
parts + bolts and nuts. Sécheron’s reference: NBT400344P0003.
Spray Silicon, Scotch 1609.
Sliding surfaces.
Reference: 10000417 (or similar).
Contact grease for fixed electrical Penetrox A13.
contact surfaces. Sécheron’s reference: SG800857P1.
Contact grease for moving electrical Aseol Litea 2 806-12.
contact surfaces. Sécheron’s reference: NBT400344P0090.
Antistatic solution, antistatic spray
Thermoplastic cleaner.
(i.e. cleaning product for glasses).
Duroplastic cleaner. White Spirit. (*)
Grease solvent. Acetone pure or industrial alcohol. (*)
Linen cloth.
Cloth.
Brush, cotton waste.

DANGER!
(*) Class A1, Highly inflammable.
All these products are harmful for the environment, particularly for the ground and water.
Their elimination must be carried out only by the authorized organizations.
Respect the local regulations as environment regard!
Carefully read and follow manufacturer’s precautions and directions for use when handling
cleaning solvents.

F.5. Tools needed


Basic standard tools:
• 2 sets of open end wrenches.
• 1 set of racket wrench with sockets.
• 1 torque wrench.
• 1 set of Allen keys.
• 1 set of Torx keys.
• 1 set of Flat head screwdrivers.
• 1 set of Pozidriv screwdrivers.
• 1 mallet.
• 1 hand drilling machine.
• 2 air levels (1 x ~500 mm, 1 x ~1500 mm).
• 1 Megohmmeter (Megger) max 1000 VDC.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
24 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Preliminary information

F.6. Installation material


Provided by Sécheron depending on the type and quantity of cubicles (refer to the packing list).
Example of typical delivery:
• Kit for fixing on floor.
• Crank handle for trolley.
• Key EMKA (for cubicle doors).
• Special screw driver for terminal block type WAGO.
• Insulating plates (where applicable).

F.7. Opening cases


Refer to D.4. Taking delivery of goods

ff GENERALITIES
IMPORTANT!
Before opening the cases, verify with the packing list that the material has been transported
to the right place of installation!
Transportation of unpacked material is more difficult and should be reduced to minimum!
• Do not open the cases if you do not intend to proceed with installation on the final site.
• The packing protects the equipment. Do not open the sealed aluminum bag (if present) around
the equipment if you can’t guarantee correct indoor conditions around cubicles.
• The heating of the cubicles (if present) should be connected and switched on at least 48
hours after opening the aluminium bag. The heating will protect the electric, electronic and
mechanical equipment against condensation.
• Use supplementary heaters to maintain a dry air if necessary.
• Power supply of the appropriate voltage must be available in the neighbourhood of the
equipment.

ff OPENING
1. Make sure that the cases are opened in the right place of installation in a protected, dry and
clean location.
2. Identify the cases to open them in the order of installation (refer to the packing list and the
layout drawings).
IMPORTANT!
If the equipment must be unpacked outdoors, have some covers ready to protect the
equipment in case of bad climatic conditions!
3. If an aluminium bag is present, cut it carefully to remove it. Be careful not to damage the
cubicle surfaces (i.e. with a sharp knife) when removing the aluminium bag.
4. Check immediately the content of the cases with the detailed packing list.
–– The material is identified with labels or stickers.
–– Verify that all parts of the same substation are present.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
25
Preliminary information Installation recommendations

F.8. Handling
INFORMATION!
Never try to move the equipment by using tools under cubicles!
Risk of deformation of side or bottom cubicles!
DANGER!
Weight up to 700 kg, use appropriate lifting slings!
Follow the instructions for safe handling of heavy equipment!

ff CUBICLES HANDLING

ff Applicable to all cubicles


The cubicles can be lifted:
A. With a crane and hooks into the four removable rings (1) or the lifting bars (2) after having
removed the top duct (3) if need be. Close all the doors before lifting the cubicles.
B. On a pallet with secured straps (4).

4
A
1
3

3
2

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
26 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Preliminary information


ff MBS HSCB TROLLEYS HANDLING

ff Applicable to the HSCB trolleys of cubicles type MBS


The MBS HSCB trolleys are equipped with wheels to be easily moved. They are also equipped
with four lifting rings (1) to lift them. Be careful not to damage the circuit breaker (2) or its arc
chute (3) by lifting the trolley, choose the appropriate slings.

IMPORTANT!
Risk of damage to equipment!
Never try to raise the HSCB trolley by the handles of the arc chute!

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
27
Installation recommendations

This page intentionally left blank.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
28 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Installation


G. Installation
G.1. Cubicles preparation
ff DC circuit breaker cubicles
Extract the HSCB trolley / drawer according to the instructions given in chapter H.3. Racking in
and out of the MBS HSCB trolley and in the corresponding cubicle user guide:
• Cubicles type MBS: SG822234TEN ----- Cubicles type SECUB-2 / SG820660TEN

ff Top duct all cubicles


Remove the top duct (1) and keep it on a safe place for later installation (screw 4 x M6 Hex).

ff Rear closing plates all cubicles


If present, remove the rear closing plates (2) (screws M6 Torx). Do not remove the two screws
and items that fasten the two plates together (3).

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
29
Installation Installation recommendations


G.2. Example of installation layout
For information purpose only.

3
3

1 1 1 1

1. DC circuit breaker cubicles 3. Customer cable trench (where applicable)


2. DC panel

G.3. Insulation sheet tips


The insulation sheets supplied by Sécheron measure 2 meters by 1 meter, and are 1 mm thick.
Cut the proper sheet dimension before placing of cubicles, by exceeding 25 mm at each side.
For cutting, use a sharp knife or cutter. One of the insulating sheet can serve as a ruler .
1. Cut it.
2. Bend it for separation.
3. 25 mm overlap between each sheet.

1 2

3 3

25 mm 25 mm

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
30 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Installation


G.4. Positioning
G.4.1. First unit
• Place the insulation sheet (1) onto the floor.
Tip: Secure the insulation sheet using Scotch tape to prevent it from moving when placing the
cubicle.
• Place the first unit (2) in place according to the layout drawing.

1
25 mm

3
2

25 mm

The cuts for the customer cable trench access are made once the cubicle is in place.

G.4.2. Levelling
Check the level of the cubicles (plumb line or air level) and correct it if necessary by means of
spacers placed between the cubicles and the insulation sheet.
Use the cutouts of the insulating sheets as spacers for the levelling.

1
3
4
2

1. Cubicle 3. Insulation sheet


2. Floor 4. Spacer for levelling (maximum 1 mm)

Practically it is better never use levelling plates in front, only at the rear. In front it may difficult the
proper insertion and extraction of the trolley.

G.4.3. Following cubicles


Place the second unit in place according to the layout drawing and repeat above procedure for
each adjacent cubicle.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
31
Installation Installation recommendations


G.5. Attachment of the cubicles together
The DC cubicles can be fixed to each other by means of 6 fixing points, as shown below.
The principle is the same regardless of the type of cubicle, MBS or SECUB-2, the following
examples are taken from MBS cubicles.
The same principle applies to fixing a DC cubicle to a DC circuit breaker cubicle.

G.5.1. “Standard” variant


• Align all cubicles at front bottom.
• Fix bottom bolt in front.
• Carefully balance cubicles to have aligned the front-top.
• Now fix the middle and top bolts in front.
• Insert the three rear bolts.

A B

1 2
2 1

4 5 6

1. Cubicle n°1 4. Screw M6 (Allen)


2. Cubicle n°2 5. Spring washer M6
3. Fixing points (6 x M6x16) 6. Rivet nut M6 (fixed on the cubicle)

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
32 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Installation


G.5.2. Variant with separation sheet between the cubicles
The principle is the same as described in previous chapter (G.5.1. “Standard” variant) with an
additional separation sheet placed between the cubicles.

The separation sheet is shipped mounted on the first cubicle and must be removed first.
• Unscrew the fastening screws of the separation sheet.
• Let the separation sheet in place and approach the second cubicle.
• Proceed then as described in previous chapter (G.5.1. “Standard” variant).

3
1
2

1. Cubicle 1 3. Separation sheet


2. Cubicle 2

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
33
Installation Installation recommendations


G.5.3. Variant with insulation sheet between the cubicles
The principle is the same as described in previous chapter (G.5.1. “Standard” variant) with an
additional insulation sheet placed between the cubicles.

The insulation sheet is shipped mounted on the first cubicle and must be removed first.
• Unscrew the fastening screws of the insulation sheet.
• Let the insulation sheet in place and approach the second cubicle.
• Proceed then as described in previous chapter (G.5.1. “Standard” variant).

3
1 4 5 3 6
2

1. Cubicle 1 4. Screw M6 (Allen)


2. Cubicle 2 5. Insulating insert for screw M6 - POM
3. Insulation sheet 6. Rivet nut M6 (fixed on the cubicle)

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
34 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Installation


G.6. Fixing on floor (principle)
IMPORTANT!
Risk of damage to equipment!
Failure to observe this information could result in damage to equipment!
Refer to the layout drawings to identify the fixing points specific to each cubicle type.

Use the following Sécheron’s fixing kit to fix the enclosure into the floor: SG806195R5.

ff For each enclosure:


• Insert the plastic washer (1) into the centre of the Ø16 mm fixing holes.
• Pre-drill Ø 6 mm.
• Remove the plastic washer and drill:
–– Use a Ø 7.4 mm drill when drilling into a metal frame (2).
–– Use a Ø 10 mm drill when drilling into concrete (3).
• Use a vacuum cleaner.
• Insert the plastic washer (1), the washer (4) the screw and tighten.
–– Use the M8x25 self-tapping screw (5) into a metal frame (2).
–– Use the M8x80 screw (6) and screw plug (7) into concrete (3).
• Check the insulation.
• Proceed with next fixing point.

1 4 1 4

7
1
2 5
3 80

Ø7.4 6

Ø6
Ø10

IMPORTANT!
Check the insulation after each fixing point in order to avoid unnecessary work in case of
insulation problem.
Recommended insulation value: > 100 kΩ.
Refer to F.1.3. Floor insulating principle and H.2.5. Insulation resistance test!

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
35
Installation Installation recommendations


G.7. Busbar and earth bar connection
IMPORTANT!
The contact between the different copper plates has to be correct. The number and the
surface of the different copper plates have been carefully designed. Therefore, follow
these instructions carefully!

ff Main busbar - by-pass busbar


The transmission of the traction current through the Sécheron cubicles is done by means of
busbar, generally made of copper. The connection of the busbar sections between each cubicle
is made by means of fish-plates. The dimensioning of the busbar and the fish-plates depends
on the installation specifications. Below are two examples representative of the majority of
installations.

5 6 5 6

4 5 4 5

2
2
3
3
1
1 8 x M12

16 x M12

1. Busbar cubicle n°1 4. Screw M12


2. Busbar cubicle n°2 5. Spring washer M12 (x2)
3. Fish-plates 6. Nut M12

ff Earth busbar (where applicable)


Connect the earth bar by means of the fish-plate supplied with the equipment.

3
2 x M10

5 1

4 5 6

1. Earth bar cubicle n°1 4. Screw M10


2. Earth bar cubicle N° 2 5. Spring washer M10 (x2)
3. Fish-plate 6. Nut M10

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
36 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Installation


G.8. Earth connection
Connect the main substation earth (2) to the output of the low impedance relay (1).
Refer to electrical diagrams to locate the earthing point.

DANGER!
The minimal cross section of the earthing conductor must be of 50 mm2 (defined according
to the customer specifications)!

1
“64”
I>

Refer to F.1.3. Floor insulating principle.

G.9. High-voltage connections


The design of high-voltage connections (1) depends on the type and quantity of cable lugs
used by the customer. This information must be supplied by the customer during the design of
cubicles.
Input/output cables entry can be through the top or the bottom, this is to be defined by the
customer during the design of cubicles.
A plexiglass plate (2) is delivered and the holes have to be made by the customers depending on
their needs regarding the input or output cables (3).

ff Example with output cables through the bottom

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
37
Installation Installation recommendations


G.10. Low-voltage connections
The customer low-voltage connections (1) can be located either on the roof of the MBS cubicles,
when low-voltage connections are made individually for each cubicle (A), or on the interface/
negative panel (B).
In the case of low-voltage connections located on the interface or negative panel (B), the
connections between the MBS cubicles and the interface/negative panel must be reconnected,
by means of connectors (2). During the transportation, these connectors are located on the
interface or negative panel.

1 A

1 B

In both cases, refer to electrical diagrams to identify the connections.

Use the special screwdriver for terminal block type WAGO supplied with the installation material.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
38 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


H. Service and maintenance
H.1. Safety precautions
DANGER!
Before starting any maintenance, ensure that no remote control is possible.
Proceed with the earthing of de-energized live parts so that work may be performed
without danger of electric shock.
Observe the instructions in B. Safety precautions section and comply scrupulously with
the applicable local regulations.

H.2. Maintenance plan


H.2.1. Periodicity and controls
The recommendations concerning the periodicity of interventions for maintenance and control
features (according to Table 1) apply to Sécheron’s equipment in normal operating conditions.
In cases of more severe conditions (humidity, condensation, air pollution such as dust, smoke or
corrosive gas), the periodicity must be adapted to the real conditions.

ff Table 1: Periodicity and controls

Maintenance interval for


Operations to be done
normal ambient conditions
Full visual control of the cubicles (in order to detect any
contamination, condensation and damaged materials, e.g. 2 x / year
electrical arcing).
2 x / year (depending on the
Cleaning of the cubicles (if necessary).
pollution degree)
Racking in and out of the trolley (if necessary). 2 x / year
Check the manual release of the DC circuit breakers. 1 x / year
Check the tightening torque of bolted busbar. 1 x / year
Clean and grease the power fingers and power block contact 2 x / year (depending on the
surfaces. pollution degree)
Carry out a test run and check the locks and position indicators. 1 x / year
Insulation resistance test. 1 x / year
Final check: Check that the enclosure is operational. After every maintenance

For maintenance of DC circuit-breakers, disconnectors, contactors or other components, please


refer to the corresponding manual.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
39
Service and maintenance Installation recommendations


H.2.2. Visual control
Carefully check for marks of burn or moisture which can lead to a serious defect.

H.2.3. Cleaning
Accumulation of dirt and dust on components acts as an insulating blanket preventing efficient
heat dissipation. Dust on circuit boards and wires can cause arcing and short-circuits, resulting
in damage to components or even cause equipment failure. Your equipment should be cleaned
to prevent it!
Dust can be removed using a dry rag, a soft brush or a vacuum cleaner.
To ensure the insulating power, it is necessary that the parts of insulating material are clean and
dry.
When cleaning, make sure that the lubrication of control mechanisms is maintained. If mechanisms
are not lubricated enough, lubrication must be renewed.

ff Slight soiling
Clean with a dry rag (non-fibrous), replace the rag quite often depending on the contamination.

ff Heavy soiling
Use of a cleaning product.
• Carefully read and follow manufacturer’s precautions and directions for use when handling
cleaning products.
• The operator must wear gloves and eye protection.
• Moisten the cloth and wipe shortly the parts of insulating material.

H.2.4. Greasing instructions


ff Table 2: Greasing

Sécheron’s
Greasing points Grease Method of greasing
reference
Clean using a non-fibrous rag; in the
Moving electrical Aseol Litea 2 case of heavy soiling, use detergent.
NBT400344P0090
contact surfaces. 806-12 Spread a thin and uniform coat of
grease.
Clean the greasing points using a
non-fibrous cotton rag or a soft brush;
Moving if necessary by means of a cleaning
mechanical parts Retinax LX2 NBT400344P0003 product (use sparingly and lightly coat
+ bolts and nuts. the lubrication points).
Spread a thin and uniform coat of
grease (e.g. by means of a brush).
Spray Silicon, Reference: 10000417 Apply a thin coat on the sliding surface
Sliding surfaces.
Scotch 1609 (or similar) with the spray.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
40 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


H.2.4.1. MBS cubicles
ff HSCB TROLLEY

ff Greasing points
1. Power fingers.
2. Power block contact for negative reference (in case of optional Line Test Device type C).
3. Leadscrew (trolley insertion device).

ff Type of grease (according to Table 2)


A. Moving electrical contact surfaces: Aseol Litea 2 806-12.
B. Moving mechanical parts + bolts and nuts: Retinax LX2.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
41
Service and maintenance Installation recommendations


ff HSCB CUBICLE

ff Greasing points
1. Power block contacts.
2. Power finger for negative reference (in case of optional Line Test Device type C).
3. Earth pad for HSCB trolley earthing.

ff Type of grease (according to Table 2)


A. Moving electrical contact surfaces: Aseol Litea 2 806-12.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
42 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


ff HSCB COMPARTMENT DOOR

2 1

B B

3 1

ff Greasing points
1. Manual release of the HSCB. Press on the red button to grease the axis behind the door.
2. Mechanical device for blocking the door when the HSCB trolley is in service position.
3. Mechanical device to authorize or avoid the insertion of the manoeuvring lever.

ff Type of grease (according to Table 2)


B. Moving mechanical parts + bolts and nuts: Retinax LX2.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
43
Service and maintenance Installation recommendations


H.2.4.2. SECUB-2 cubicles
ff HSCB DRAWER

A
1

3 B

2
A

[SECUB-2 046]

ff Greasing points:
1. Power fingers.
2. Earthing copper bar.
3. Locking mechanism (on both sides).

ff Type of grease (according to Table 2)


A. Moving electrical contact surfaces: Aseol Litea 2 806-12.
B. Moving mechanical parts + bolts & nuts: Retinax LX2.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
44 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


ff HSCB CUBICLE

A
1

B
3

2
A

[044]

ff Greasing points:
1. Power block contact.
2. Power finger for negative reference (in case of Line Test Device option).
3. Sliding surface between cubicle and drawer (on both sides).

ff Type of grease (according to Table 2)


A. Moving electrical contact surfaces: Aseol Litea 2 806-12.
B. Bearing grease for sliding surfaces: Spray Silicon Scotch 1609, reference 10000417, 1609
(or similar).

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
45
Service and maintenance Installation recommendations


H.2.5. Insulation resistance test
ff TEST PURPOSE
This test is aimed at verifying the quality of the isolation of cubicles compared to a ground as part
of equipment installed in the arrangements (a) and (b) of EN 50123-7 with monitoring by current
relay (earth fault) with low impedance.

ff PROCEDURE
DANGER!
First, make sure that equipment to be tested as well as the work area is safe, that
equipment is turned off and disconnected and that all safety measures have been taken!

a. Open all the mini circuit breakers of the auxiliary circuits of the equipment to be tested.
b. Disconnect the connection between the substation earth (2) and the earth of the equipment
(3) at the output of the low impedance relay (1).
c. Connect the insulation resistance meter (4) between the earth of the equipment (3) and the
substation earth (2), through the low impedance relay (1).
d. Apply the test voltage (at least during 60 seconds to allow the measured current to stabilize)
and check the value of the insulation resistance.
e. If the result is incorrect, look for the cause of the insulation problem, fix it and repeat the test.
It is better to connect the positive to the substation earth and the negative onto the cubicles, in
order to help prevent polarization of the earth.

1 MΩ 4
“64”
I>

ff Table 3: Test voltage and results

Maximum test voltage to be applied Recommended insulation resistance


1000 VDC > 100 kΩ

ff POSSIBLE CAUSES OF A POOR INSULATION RESISTANCE


• Connection of an another part of the panels to the earth.
• Accidental earthing of the cubicle when fixing to the floor (use of the insulating washer).
• Presence of liquid around the cubicle: sweep it.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
46 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


H.2.6. Prevent condensation
To ensure the insulation properties, the cubicle must be free from condensation.

ff Measures in case of condensation


• If condensation is detected in a cubicle, the cubicle should be cleaned (refer to H.2.3. Cleaning).
• Check the proper operation of the heating of the cubicle, check the value of the thermostat
and/or hygrostat of the heating.
• If the cubicle has no heating, consider the installation of a heater to prevent condensation.

H.2.7. Treatment of screwed contact surfaces


Only in case of disassembly of the busbars.

Clean the contact surfaces just before to reassemble them (according to Table 4). Immediately
after the treatment, spread a thin and uniform coat of contact grease.

ff Table 4: Treatment of screwed contact surfaces

Material of the Sécheron’s


Treatment Grease
contact surfaces reference
Copper Clean1, polish2 (gloss) Penetrox A-13 SG800857P1
or or
Silvered Clean 1
Electrical Joint SC204008
Aluminium Clean1, polish2 (gloss) Compound BX1-225

1. Clean using a non-fibrous rag; in the case of heavy soiling, use detergent.
2. Polish (metallically gloss):
–– By machining, using abrasive cloth or a rotary grinding wheel (grits 80 or 100).
–– By means of a steel wire brush for a specific use on copper or aluminium.

H.2.8. Checking tightening


Proceed with tightening all electrical connections, such as busbars, circuit breakers, disconnectors,
switches, cables, measuring devices, etc., using the proper tightening torques. The screws and
bolts that need to be tightened with a specific torque are marked with a red mark.

ff Table 5: Tightening torque

Screw Torque range Nm


M8 15
M10 35
M12 45
M16 60

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
47
Service and maintenance Installation recommendations


H.2.9. Replacement of components
The replacement of individual parts or assemblies is possible.

ff REFERENCES
The references of the components are located in the last pages of the electric drawings.

5 6 7 8 9 10 11 12 13
Item Sheet Localisation ID Number Designation Data Type Manufacturer Qty
72F 19 COMPARTMENT 6 AUR0981E1471J380 HIGH-SPEED CIRCUIT BREAKER 900 VDC / 4000 A / 4-15 kA / 60 VDC UR40E-81S SECHERON 1
A00 12 COMPARTMENT 4 SG824300R0100000 CONTROL & PROTECTION UNIT 60-220 VDC / 50 W / 1I/O / BASIC SEPCOS-2 SECHERON 1
E91-L 21 COMPARTMENT 4 SC204683 LUMINAIRE 110-230 VUC / 1.2 W / LED LL10-W PEAKS 1
F21 10 COMPARTMENT 6 SG806643P00032 FUSE 2000 VDC / 32 A CC 20 SRC 120 QF 0032 MERSEN 1
10 COMPARTMENT 6 SG806651P0002 MICROSWITCH 1REV MCR3E1-5NBS MERSEN 1
KA03-F 18 COMPARTMENT 4 SC200726 PLUG-IN RELAY 60 VDC / SUPPRESSOR C7-A20D/DC60V COMAT 1
18 COMPARTMENT 4 COMATCS-18 SOCKET / CS-18 COMAT 1
KA74-W 18 COMPARTMENT 4 SC200726 PLUG-IN RELAY 60 VDC / SUPPRESSOR C7-A20D/DC60V COMAT 1
18 COMPARTMENT 4 COMATCS-18 SOCKET / CS-18 COMAT 1

E
KA85-O 18 COMPARTMENT 4 SC200726 PLUG-IN RELAY 60 VDC / SUPPRESSOR C7-A20D/DC60V COMAT 1
18 COMPARTMENT 4 COMATCS-18 SOCKET / CS-18 COMAT 1

L
KM21 17 COMPARTMENT 6 SC201953 CONTACTOR 60 VDC / SUPPRESSOR C193 A/ 60EV-U1 SCHALTBAU 1

P
KM72-C 17 COMPARTMENT 6 SC200727 CONTACTOR 60 VDC / SUPRESSOR LC1 D093 ND SCHNEIDER ELECTRIC 1
KM72-R 17 COMPARTMENT 6 SC200727 CONTACTOR 60 VDC / SUPRESSOR LC1 D093 ND SCHNEIDER ELECTRIC 1

M
KM75-S 17 COMPARTMENT 4 SC200727 CONTACTOR 60 VDC / SUPRESSOR LC1 D093 ND SCHNEIDER ELECTRIC 1
KM75-T 17 COMPARTMENT 4 SC200727 CONTACTOR 60 VDC / SUPRESSOR LC1 D093 ND SCHNEIDER ELECTRIC 1

A
M75 8 COMPARTMENT 3 SC350006P00001 MOTOR 24 VDC / 150 W RE40 MAXON 1

X
P60 13 COMPARTMENT 3 SG824390R00001 LCD DISPLAY 8 " / 8 LED / LDVS SEPCOS-2 DISPLAY SECHERON 1

E
P72 19 COMPARTMENT 6 SG800290P1 PULSE COUNTER 60 VDC / 6 DIGITS 552.5135 WISAR 1
Q72 9 COMPARTMENT 4 SC204305P0003D MINI CIRCUIT BREAKER 415 VAC / 125 VDC / 2 POLES / 3 A / D iC60H 2P 3A D SCHNEIDER ELECTRIC 1
9 COMPARTMENT 4 SC204306P00001 AUXILIARY CONTACT 1REV iOF SCHNEIDER ELECTRIC 1
Q75 20 COMPARTMENT 4 SC201200 MOTOR CIRCUIT BREAKER 415 VAC / 220 VDC / 1.6-2.5 A GV2 ME 07 3 SCHNEIDER ELECTRIC 1
20 COMPARTMENT 4 SC200792 AUXILIARY CONTACT 1NO 1NC GV AN11 3 SCHNEIDER ELECTRIC 1
Q90-C 9 COMPARTMENT 4 SC204305P0003D MINI CIRCUIT BREAKER 415 VAC / 125 VDC / 2 POLES / 3 A / D iC60H 2P 3A D SCHNEIDER ELECTRIC 1
Q90-M 9 COMPARTMENT 4 SC204305P0003D MINI CIRCUIT BREAKER 415 VAC / 125 VDC / 2 POLES / 3 A / D iC60H 2P 3A D SCHNEIDER ELECTRIC 1
9 COMPARTMENT 4 SC204306P00001 AUXILIARY CONTACT 1REV iOF SCHNEIDER ELECTRIC 1
Q91-L 9 COMPARTMENT 4 SC204305P0003D MINI CIRCUIT BREAKER 415 VAC / 125 VDC / 2 POLES / 3 A / D iC60H 2P 3A D SCHNEIDER ELECTRIC 1
R01-C 8 COMPARTMENT 6 GMN961705P0019 SHUNT 4000 A / 60 mV / CLASS 0.5 DIN 43703 WEIGEL 1
R21 10 COMPARTMENT 6 SC350003P00001 RESISTOR 30R / 600 W / -10+10% / FIXED FW60-400 30R K WIDAP 1
R72 19 COMPARTMENT 6 SC200101 RESISTOR 100R / 250 W / 0+15% / ADJUSTABLE VAW 30x265 100 WIDAP 1
S75-S 16 COMPARTMENT 6 SC350008P00001 POSITION SWITCH 1NO 1NC S800 B SCHALTBAU 1
S75-T 16 COMPARTMENT 6 SC350008P00001 POSITION SWITCH 1NO 1NC S800 B SCHALTBAU 1
S91-L 21 COMPARTMENT 4 SC200462 POSITION SWITCH 1NO 1NC XCK P2118P16 SCHNEIDER ELECTRIC 1

This document is the sole property of Secheron SA and may Drawn Drawing Title Drawing No. Revision
not be copied, duplicated, used or given to third parties
without the written permission from Secheron.
24/06/2015 P. ALTIERI OSLO FEEDER HSCB SCHEMATIC SG832802SEN C00
Misuse is subject to penalities and will be legally pursued. Modified CAD File Name Sheet
Copyright Secheron SA A3 Classification SG832802SEN 01/09/2015 P. ALTIERI ITEMS LIST SG832802SEN_28_C00.dwg 28

3 1 2 4

1. Drawing number (Sécheron’s codification)


2. Revision number
3. Drawing title
4. Page number
5. Item number
6. Page where the component is located
7. Location of the component in the cubicle
8. Identification number (Sécheron’s codification)
9. Designation (short description)
10. Data (short technical data)
11. Item designation (Sécheron’s codification or manufacturer’s codification)
12. Manufacturer
13. Quantity

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
48 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


ff COMMON EQUIPMENT
Most of the components are mounted on a DIN rail and are easily removable using a screwdriver
(2) as shown below.
Installation is done by clipping on to the DIN rail (1).

1 2

The cables are numbered. Refer to the appropriate electric drawings for connection.

ff ISOLATED AMPLIFIERS, MEASURING RELAYS


Isolated amplifiers – such as current measuring relay MIU10 (1) and voltage measuring relays
VM10 and VM12 (2) – are mounted on a DIN rail (3).

For replacement of these components, refer to Common equipment.


The isolated amplifiers MIU10, VM10 and VM12 are configured according to the characteristics
of the measuring circuits. Before installing a new amplifier, it is necessary to set it according to
the data given in the appropriate electric drawings and according to the instructions given on the
corresponding instructions manual.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
49
Service and maintenance Installation recommendations


ff SEPCOS
• Disconnect the auxiliary power supply.
• Remove all connectors from the SEPCOS.
• Disassemble the SEPCOS: 4 screws / washers (1).
• Proceed in reverse order to mount the new SEPCOS.

The SEPCOS is configured according to the customer specifications. Configure the new SEPCOS
accordingly.

ff DISPLAY
• Disconnect the connection between the SEPCOS and the Display (1).
• Disassemble the Display: 4 nuts / washers (2).
• Proceed in reverse order to mount the new Display.

The Display is configured according to the customer specifications. Configure the new DISPLAY
accordingly.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
50 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


H.2.10. Protection against corrosion
The chassis and the unpainted sheet metal parts are protected against corrosion (Aluzinc). Steel
parts are galvanized.
IMPORTANT!
Of paint damage, scratches or other damage must be repaired immediately to avoid
corrosion!

H.2.11. Once maintenance works are completed


• Remove all tools and aids used.
• Reinsert the corresponding trolleys into their cubicles.
• Reassemble the panels, close the doors, check the operating functions.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
51
Service and maintenance Installation recommendations


H.3. Racking in and out of the MBS HSCB trolley
WARNING!
Before to rack in or out the trolley, the circuit breaker must be switched OFF according to
your operating rules!

H.3.1. Procedure to rack-in the HSCB trolley


a. Check that all power circuits are OFF and that the circuit breaker is ready to operate accurately.
b. Check that the locking mechanism is in “unlocked” position (1) on both sides.
c. Push by hands the trolley into the cubicle until it stops into its place (2).
d. Pass the locking mechanism in “locked” position (3) on both sides.
e. Plug the umbilical chord onto the circuit breaker connection (4).
f. Close the door and lock it.
g. Push the red manual trip push button (5), move the lever (6) to the left and release the red
button.
h. Insert the crank handle into the mask (7).
i. Turn the crank handle counter clockwise (8) until it stops (without forcing).
j. Check the correct position (service) through the control window (9).
k. Remove the crank handle from the mask.
l. Push the red manual trip push button (5), move the lever (6) to the right and release the red
button.
m. The trolley is now in service position and is ready to be switched ON. The door cannot be
opened.

4
2

1 3

6
9

5
8
7

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
52 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


H.3.2. Procedure to rack-out the HSCB trolley
a. Check that the circuit breaker is switched OFF according to your operating rules.
b. Push the red manual trip push button (1), move the lever (2) to the left and release the red
button.
c. Insert the crank handle into the mask (3).
d. Turn the crank handle clockwise (4) until it stops (without forcing).
e. Check the correct position (test) through the control window (5).
f. Remove the crank handle from the mask.
g. Push the red manual trip push button (1), move the lever (2) to the right and release the red
button.
h. The trolley is now in test position. The door can be opened.
i. Unlock the door and open it.
j. Unplug the umbilical chord from the circuit breaker connection (6).
k. Pass the locking mechanism in “unlocked” position (7) on both sides.
l. Pull by hands the trolley out of the cubicle (8).
m. The trolley is now in removed position.

2
5

1
4
3

6
8

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
53
Service and maintenance Installation recommendations


H.4. Insertion-extraction HSCB drawer SECUB-2
DANGER!
Always refer to safety instructions before to work on the equipment!

H.4.1. Extraction
Before starting the extraction of the drawer, make sure the circuit breaker is open

Starting point, drawer in SERVICE position.

ff ACCESS TO THE HSCB DRAWER


• Open the circuit breaker compartment door using the square key or key according to the
options.
Opening the door causes the opening of the circuit breaker and prevents closure thereof as the
door is opened.

[032]

1. Front insulation

DANGER!
The front insulation shall be removed only when the HSCB drawer is in test position!

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
54 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


DANGER!
Although the circuit breaker is open, high voltages remain inside the circuit breaker
compartment! The arc chute and heatsinks (1) of the HSCB and the drawer of the line test
device (2) may be energized.

[050]

HSCB drawer LTD drawer Arc chute & heatsinks (1) LTD device (2)
Service position Connected Voltage present Voltage present
Service position Disconnected Voltage present Voltage present
test position Connected No voltage Voltage present
test position Disconnected No voltage No voltage

ff DRAWER EXTRACTION
• Depending on option chosen, the drawer can be locked with a key or a lock, make sure the
drawer is unlocked.

[033]

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
55
Service and maintenance Installation recommendations


• Lift the locking mechanism (1) and, simultaneously, move the drawer slightly toward you to
release it. Once the drawer free, continue until you reach the stopper.
• The drawer is now in TEST position.

[034]

ff SETTING UP THE MAINTENANCE TROLLEY


The maintenance trolley allows to extract the drawer out of the cubicle.
The fixing of maintenance trolley on the drawer is done by means of the 4 knurled nuts (1) fixed
on the trolley.
4x

[035]

• Remove the front insulation

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
56 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


[051]

• Remove the drawer out of the cubicle.


• Insert the trolley under the drawer.
–– Pay attention to the mounting direction, the central wheel forward.
• Fix the trolley by means of the knurled nuts fixed on either side of the trolley.
Properly tighten the knurled nuts to avoid inadvertent unscrewing when moving the trolley.

[036]

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
57
Service and maintenance Installation recommendations


ff EXTRACTION OF THE TROLLEY WITH THE DRAWER
The drawer is mechanically locked in the cubicle by means of a device consisting of a removable
stopper (1) fixed on the left side of the cubicle and by a fixed stopper (2) fixed on the drawer.

2
[037]

Push the drawer (A) to release the removable stopper. Lift the removable stopper (B) and pull the
drawer out of the cubicle (C). The drawer is now in MAINTENANCE position (D).

A B

[038]

Do not to apply too much traction on the umbilical of auxiliaries (line test device and circuit
breaker).

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
58 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations Service and maintenance


H.4.2. Insertion
ff INSERTION OF THE TROLLEY WITH THE DRAWER
• Place the drawer in front of the cubicle.
• Partially insert the trolley into the cubicle enough to move the stopper (see Extraction of the
trolley with the drawer).
• Pull the trolley towards you to check if it is locked in the cubicle, if it is not, repeat the above
procedure of inserting the trolley further into the cell.

ff MAINTENANCE TROLLEY
• Remove the maintenance trolley by proceeding inversely to the instructions described in
chapter Setting up the maintenance trolley.
• Replace the knurled nuts on the trolley.
• The drawer is now in TEST position.

ff DRAWER INSERTION
• Replace the front insulation.

[042]

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.
59
Service and maintenance Installation recommendations


• Push the drawer into the cubicle with two hands until it is completely inserted.
Be careful when inserting the drawer, DO NOT pull the locking mechanism as described in section
Extraction of the trolley with the drawer.

[040]

• Depending on option chosen, the drawer can be locked with a key or a lock, make sure the
trolley is locked in accordance with your operating rules.

[033]

• Close the door.


• The drawer is now in SERVICE position.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
60 This document is not contractual and contains information corresponding to the level of technology at the date of release.
Installation recommendations



This page intentionally left blank.

Document number: SG840230TEN    |    Revision: #01    |    Issue date: 01.03.2017


Copyright© 2017 Sécheron SA
This document is not contractual and contains information corresponding to the level of technology at the date of release.