The 4 first steps Step 1 Step 2 Step 3 Step 4

Upstream

Sizing of Terminal distribution protections Sizing of Terminal distribution busbar Sizing of Power distribution busbar Sizing of Main distribution busbar
- Rated current of Terminal distribution busbar by - Rated current of Power distribution busbar by - Rated current by addition of consumptions (or
- Rated current and curve of protective devices addition of consumptions
addition of consumptions accorded to the rated power transformer)
- Calculation of conductors up to loads - Calculation of conductors (up to Power distribution
- Calculation of conductors (up to Terminal Sizing of Power transformer
distribution enclosure systems and up to loads) enclosure systems and up to loads) - Rated power of transformer using correction factors
Downstream Sizing of Power distribution protections Sizing of Main distribution protections - Power factor correction to be calculated for power
- Rated current and curve of protective devices - Rated current and curve of protective devices optimization (global or individual compensation)

At the beginning of a study:


- Geographical location of distribution switchboards and loads is defined
- Informations concerning loads are known (characteristics, consumptions)

The 4 last steps Step 5 Step 6 Step 7 Step 8

Upstream

Choice of Main protection accorded to the selected - For the sizing of distribution busbar, correction
power transformer Sizing of Power distribution enclosure system Sizing of Terminal distribution enclosure system factors ku and ks have to be used
Calculation of Main conductor up to Main distribution - Mechanical withstand of busbar accorded to local - Mechanical withstand of busbar accorded to local - For each cable, the voltage drop, the maximum
enclosure systems length and the thermal constraint have to be checked
Ik3 Ik3
Sizing of Main distribution enclosure system - Discrimination has to be checked to ensure service
Downstream - Mechanical withstand of busbar accorded to local Ik3
- Breaking capacity of protective devices - Breaking capacity of protective devices
continuity
- Breaking capacity of protective devices
- Cascading can be implement

Colours caption
Supply source
: grey colour = not defined
Main : green colour = fully defined and sized
protection

Main
distribution

Power
distribution

Terminal
distribution

Loads PARTNER Academy - Grenoble (France)