Professional Documents
Culture Documents
C116-10EMD-001 - Rev C - BASIS OF DESIGN
C116-10EMD-001 - Rev C - BASIS OF DESIGN
BASIS OF DESIGN
FOR
NITRIC ACID RELOCATION PROJECT
LOW DENSITY AMMONIUM NITRATE PLANT,
EMULSION PLANT, OFF SITES AND UTILITIES
TABLE OF CONTENTS
2 PRODUCTS ……………………………………………………………………………………. 14
2.1 Nitric Acid ………………………………………………………………………………. 14
2.2 Low Density Ammonium Nitrate Capacity ………………………………………….. 15
4 UTILITIES ………………………………………………………………………………. 17
4.1 Conditions at Battery Limit …………………………………………………………… 17
4.2 Utilities Supplies Specification ……………………………………………………. 18
6 EFFLUENTS …………………………………………………………………………………… 26
6.1 Liquid Effluent ………………………………………………………………………….. 26
6.2 Gaseous effluent ………………………………………………………………………. 28
7 WORKING CONDITION ……………………………………………………………………………
29
7.1 Noise Level (to be confirmed and completed by IKPT) …………………………... 29
7.2 Standard workers position and exposure time ……………………………………... 29
ANNEXURE I 31
UNITS 31
………………………………………………………………………………………………
ANNEXURE II 32
Dust and Saline Data ………………………………………………………………………..
ANNEXURE III
8.5.9.4 General 42
Conditions…………………………………………...
8.5.10 Non Mechanical Equipment ………………………………………………... 43
8.5.11 Fans and Blowers …………………………………………………………… 42
8.5.12 Mechanical Conveying Equipment ………………………………………… 43
8.5.12.1 Standards …………………………………………………... 43
8.5.12.2 Specific Design Requirements …………………………… 43
8.5.13 Cranes, Derricks and Hoist ………………………………………………… 45
8.5.14 Gearing and Gear Units ……………………………………………………. 45
8.5.15 Materials ……………………………………………………………………… 45
8.5.16 Noise ………………………………………………………………………….. 45
8.5.17 Effluent ……………………………………………………………………….. 45
8.5.18 Piping Loads …………………………………………………………………. 46
8.5.19 Tests ………………………………………………………………………….. 46
8.5.20 Inspections …………………………………………………………………… 47
8.5.21 Preparation for Shipment …………………………………………………… 47
8.5.22 Other Codes …………………………………………………………………. 49
8.5.23 Design for “Abnormal” Condition …………………………………………... 49
8.5.24 Non Code Equipment ……………………………………………………….. 49
8.5.25 Unproven, Protective of “First-off” Equipment ……………………………. 50
8.5.26 Miscellaneous Provisions …………………………………………………... 50
9.0 General System ……………………………………………………………………….. 51
9.1 Electrical ………………………………………………… 51
9.1.1 Reference ………………………………………………………... 51
9.1.2 Language and System of Units ………………………………... 51
9.1.3 Basic Design Consideration ……………………………………. 51
9.1.3.1 Safety ……………………………………………….. 52
9.1.3.2 Reliability ……………………………………………. 52
9.1.3.3 Simplicity of Operation …………………………….. 52
RECORD OF AMENDMENTS
It is certified that the amendments listed below have been incorporated in this copy of the publication
DOCUMENT TITLE: Design Basis for Multi Nitrotama Kimia Plant Document No.
Uprate
AMDT PARA
AMENDED SECTION DESCRIPTION OF CHANGES
NO NO
1 Sub section 3.1 Delete average values of ammonia liquid pressure to
LDAN and NA Plant BL
5 Sub subsection 1.4.5 The water table found inside the bore hole was
approximately 3.0 to 7.0 meter below the existing
ground surface
6 Sub subsection 1.4.5 Liquid limit (wL) 53 – 114
Plasticity Limit ( wP) 29 – 47
Plasticity Index 19 – 68
Bulk Density(γm) in g/cm3 1.53 – 1.79
Dry density (γd) in g/cm3 0.92 – 1.26
Equipment Design
7 Equipment Design (1) - Design Pressure &
Subsection 4.6
Temperature
ABBREVIATION
AN Ammonium Nitrate
LDAN Low Density Ammonium Nitrate
CEMA Conveying Equipment Manufacturers Association
API American Petroleum Institute
ASTM American Standard Testing Material
ASME American Society of Mechanical Engineer
ANSI American National Standard Industry
MTPD Metric Ton Per Day
NA Nitric Acid
SNI Standar Nasional Indonesia
UBC Uniform Building Code
AGMA American Gear Manufacturer Association
TEMA Tubular Exchanger Manufacturer Association
NEMA National Electrical Manufacturer Association
IEC International Electrical Code
PUIL Peraturan Umum Instalasi Listrik
ANSOL Ammonium Nitrate Solution
NFPA National Fire Protection Association
NAFM National Association of Fan Manufacturer
IP Insulation Protection
Tropical cyclones occur, but are not frequent. Except for temporary
squalls, strong winds are rare. Fog is also rare. Some actual tropical
cyclone tracks through the Indonesian Archipelago. It never snows in
this region.
The Seasonal Data for Temperature, Dry bulb and Wet bulb
temperature as follows:
Soil Lithostratigraphy:
Two types of soil are found in the project site at Cikampek,
• Fine grained soils ( CH, MH) medium stiff to stiff silt,
tuffaceous silt
• Fine grained soils ( CH, ML) very stiff to very hard silt,
tuffaceous silt
Ground water condition:
The water table found inside the bore hole was approximately
3.0 to 7.0 meter below the existing ground surface.
Engineering properties:
Grain size: Percent finer by weight passing No. 200 sieve
ranged from 81 percent to 100 percent
Item
Test Unit Property
No
1 Atterberg Limit
1.1 Liquid limit (wL) percentage 53 - 114
1.2 Plasticity Limit ( wP) percentage 29 - 47
1.3 Plasticity Index percentage 19 - 68
2 Normal Test
Natural water content (wn) on
2.1 percentage 53.9 - 75.3
undisturbed sample
2. PRODUCTS
The relocated nitric acid plant was originally designed for a capacity of
250 short ton per day by Chemico of USA.
Capacity:
Quality:
HNO3 : 57.5 wt% min
Dissolved nitrous oxides as NO2 : ≤ 100 ppm.w
Iron as Fe : ≤ 6 ppm.w
Chloride as Cl : ≤ 10 ppm.w
Capacity
Quality:
Parameter Quality
Moisture 0.12% max by weight
pH (measured as 10% solution) 4.7 minimum, 5.7 maximum
3
Bulk Density Between 720 and 770 kg/m
Coating agent 0.1% max by weight
Fuel Absorption 8% minimum
Mean Particle Size 95% between 1.0 mm and 2.36 mm
Crushing Strength 0.7 kg minimum (with additive) on 2 mm diameter prills
ANSOL
Parameter Quality
Ammonium Nitrate 84% ±1 wt%
Concentration
pH (measured at 10% 5.5 ±0.5
solution)
Ammonia Composition:
The Nitric Acid will be a raw material for the LDAN plant. The B/L
condition for Nitric Acid is as below:
o 2
Temperature ( C ) Pressure ( Kg/cm )G
Min Max Avg Min Max Avg
Nitric Acid 34.0 36.4 35.1 7.0 8.0 7.5
(At LDAN Plant B/L)
Chemical Composition
Sl Chemical Composition
no
1 HNO3 57.5 wt% min
2 Dissolved nitrous oxides as NO2 Max 0.01% w NO2
3 Iron as Fe < 10 ppm.w
4 Chloride as Cl < 20 ppm.w
4. Utilities
max 92,8122 4,2335 2,46144 0,5781 0,4510 0,1097 0,2481 0,1808 0,1070 0,0111 0,0082
Sl
Constituent Units Range
No
1 pH - 7.8 – 6.7
2 Turbidity NTU 5-2
3 Colour (Pt/Co) Unit 5
4 Conductivity µmhos 557 - 410
Calcium
5 ppm, CaCO3 87 – 37.3
Hardness
6 Total - Hardness ppm, CaCO3 109 – 22.3
7 M Alkalinity ppm, CaCO3 102 - 78
8 Bicarbonate ppm 169 -97
Total Chlorine,
9 ppm 0.9 – 0.00
Cl2
Sl
Constituent Units Range
No
10 Chloride, Cl ppm 32.2 - 17
11 Free- OH- ppm 4.04 – 1.29
12 Free-CO2 ppm 10.89 – 2.61
13 Nitrate, NO3 ppm 4.35 - 0
14 Sulfate, SO4 ppm 45.67 - 17
15 Sodium, Na ppm 51 - 28
16 Potassium, K ppm 10.36 - 3
17 Total Iron, Fe ppm 0.2 - 0
18 Total Silica, SiO2 ppm 75 – 11.9
19 Organic Matter ppm 7.39 - 0
Fault
Freq. Level in Motors Offsite NA &
Voltage Phase Remarks
(Hz) KA for 1 (kW) & Utility LDAN
sec.
HV 20000 3 50 40 >1000 Yes Yes -
MV 6000 3 50 30 150 Yes Yes
LV 380 3+N 50 50 ≤ 150 Yes Yes
1. For non process services less than 0.2 KW, Lighting, Heating below
Notes: 3KW, Electrical control, Convenience socket etc.
2. UPS 110 VAC 50Hz shall be provided for Instrument circuit
3. Power for Switchgear control, control circuit for HV equipment,
emergency lighting
4. Power for field Instrument
The main power supply is 20,000 V and step down transformer(s) has to be
considered for having the supply at required voltage.
Recommended Velocity
Design Maximum
Remark
No. Service Velocity Velocity
m/sec m/sec
UTILITIES
1 Steam ( 0 - 300 Kpa a ) 10 18
2 Steam ( 300 - 5000 25 40
3 Steam Vapor under vacuum 35 40
4 Steam Vent 15 20
5 Vent on Tanks 20 22
6 Air Ducts 22 25
7 Air Filter Suction 4
8 Compressed Air 15 25
Design Maximum
No. Service Remark
Velocity Velocity
m/sec m/sec
9 Gas till 2atm 4 20
C Update changes CP SK YM 14.08.09
B Issued for re-use CP SK YM 17.07.09
A Up date CP SK YM 07.07.09
2 Issued for Design CP SK YM 25.06.09
1 Issued for Review CP SK YM 22.05.09
0 Preliminary Issue CP SK YM 12.05.09
REV DESCRIPTION PREPARED CHECKED APPROVED DATE
This document has been prepared by PT MNK, INDONESIA. This document is exclusive property of MNK. Unauthorized communication or reproductions not
permitted.
PT MULTI NITROT AM A KIMIA
PREPARED CP Doc. No. C116-10EMD-001
CHECKED SK Contract No. C116
BASIS OF DESIGN APPROVED YM Sheet No. 25 of 122
LIQUIDS
1 Cooling Water
pump suction 0,6 0,8
pump discharge 1.5 4
2 Boiler Feed Water
pump suction 0,5 1
pump discharge 1,5 4,5
3 Potable water installation 1 2
4 Potable water distribution 0.9 2
5 Piping for Condenser 1 2
6 Condensate Discharge Line 1 4
7 Condensate Suction Line 0.5 1
8 Filtered Water Suction Line 0.6 1.3
9 Filtered water discharge line 1.2 4
10 Fire Water Line 1.2 2.5
11 Oil 1 2
12 Fuel Oil 0,5 2
13 Demin Water Suction Line 0.6 1.3
14 Demin Water Discharge Line 1.2 4
PROCESS FLUID
1 Gaseous Ammonia 10 30
2 Liquid Ammonia 1 3
3 Ammonium Nitrate
Pump Suction 0,8 1
Pump Discharge 1,5 2,5
No. Maximum
Service Design Velocity Remark No.
Velocity
m/sec m/sec
4 Nitric Acid
Pump Suction 0,8 1
Pump Discharge 1,2 2,5
5
Minimum values
Fluid m² K / W
Boiler feed water 0.000086
Demin. water 0.000086
Steam 0.000086
Steam condensate 0.000086
Cooling water 0.0005
Note 1: Pressure vessels mean metallic vessels with a maximum operating pressure ≥ 50
kPa g
Note 2: The maximum operating pressure shall be the highest possible pressure during
normal operation, start-up or shutdown of the plant / unit.
Note 3: The design pressure shall be regarded as acting at the top of a pressure vessel.
Note 4: In general, vessel shall be designed for an external pressure of 110 % of the
maximum operating pressure in the jacket space.
Note 5: Whenever the enclosed fluid may reach temperatures at which the vapour
pressure is lower than the atmospheric pressure, the possibility of uncontrolled
vacuum condition in the vessel shall be investigated.
Note:
For equipment having two different design temperatures and a common wall
(intermediate head, jacketed or half-tube-coil equipped vessels, etc.) the design
temperature of the wall shall be unfavourable temperature.
Oversize and undersize . All oversize and undersize prill to be recycled back to
10 Remelt Tank
Sl.
Plant facility Size ( m2 )
No.
1 Work Shop 216
2 Chemical Warehouse 480
3 Guard Room 25
4 SHE Room 50
5 Office Building 600
6 Control Building 520
7 Incoming Power Station 50
8 Technical and Mechanical Store 300
9 Maintenance Office 400
10 Lube Oil Store 144
11 Weighbridge 160
Shelters to be Provided in Plant Area
12 Compressor Shed 120
Sl.
Plant facility Size ( m2 )
No.
13 Boiler Area 100
14 Demin Plant 160
6. EFFLUENTS
The Nitric Acid Plant and The Low Density Ammonium Nitrate Plant shall
comply with the following limits of liquid effluent. The effluent standards as per
the ministry of state for development control and living extracts No. KEP-
051/MENLH/10/1995 and SK Gubernur Jabar No 06/1999 is in the table at this
section.
I. Physical Condition
0
1.Temperature < 38 C
2.Dissolved Solid < 2,000 mg/l
3.Suspended Solid < 200 mg/l
PH 6-9
Iron no more than 5 mg/l as Fe
Manganese ″ 2 mg/l as Mn
Barium ″ 2 mg/l as Ba
Copper ″ 2 mg/l as Cu
Zinc ″ 5 mg/l as Zn
Chrome ″ 0.1 mg/l as Cr
Hexavalent
Total Chrome ″ 0.5 mg/l as Cr
Cadmium ″ 0.05 mg/l as Cd
Mercury ″ 0.002 mg/l as Hg
Lead ″ 0.1 mg/l as Pb
Tin ″ 2 mg/l as Sn
Arsenic ″ 0.1 mg/l as As
Selenium ″ 0.05 mg/l as Se
Nickel ″ 0.2 mg/l as Ni
Cobalt ″ 0.4 mg/l as Co
Cyanide ″ 0.05 mg/l as CN
Sulfide ″ 0.05 mg/l as H2S
Fluorine ″ 2 mg/l as F
Free Chlorine ″ 1 mg/l as Cl2
Ammonia ″ 1 mg/l as NH3
Nitrate “ 20 mg/l as NO3
Nitrite ″ 1 mg/l as NO2
Biological Oxygen ″ 50 mg/l
Demand (BOD)
Chemical Oxygen ″ 100 mg/l
Demand (COD)
1. Notes: The wastewater which complies with the effluent standards shall not
be diluted.
The Nitric Acid Plant and the Low Density Ammonium Nitrate Plant will comply
with the following Gaseous effluent standard within the plant area.
Please refer to Regulatory Review Goverment Regulation PP N0.41/1999.
Gaseous Pollutant
Sl
Chemical Concentration
No.
3
Mist sulfuric acid and/ Not more than 150 mg/Nm :
1
or SO3 or both (as SO3) -From gaseous effluent
3
Not more than 200 mg/Nm :
2 Nitrogen Oxide (as NOX)
-Gas effluent shall be colorless
3
3 Solid Particles Not more than 350 mg/Nm
3
4 Hydrogen Sulfide (as H2S) Not more than 35 mg/Nm
3
5 Ammonia (as NH3 ) Not more than 0.5 mg/Nm
3
6 Chlorine Gas (as HCL) Not more than 5 mg/Nm
3
7 Hydrogen Chloride (as HCl) Not more than 5 mg/Nm
Fluor, Hydro Fluoride Acid or 3
Not more than 10 mg/Nm
8 inorganic fluor compound
-From gas effluent
(as Hydro fluoride acid)
3
9 Lead (as Pb) Not more than 12 mg/Nm
3
10 Zinc (as Zn) Not more than 50 mg/Nm
3
11 Mercury (as Hg) Not more than 5 mg/Nm
3
12 Cadmium (as Cd) Not more than 8 mg/Nm
3
13 Arsenic (as As) Not more than 8 mg/Nm
3
14 Antimony (as Sb) Not more than 8 mg/Nm
15 Radio Nuclide Nil
7. WORKING CONDITION
The following noise level shall be complied within the Nitric Acid Plant and Low
Density Ammonium Nitrate Plant.
As regulation noise level at the boundary of the plant will not exceed 70 dBA in
accordance with Ministry of Environment No. 48/MEN-LH/1996
Intensity of
Hours of Stay in a day in working area
noise in dBA
8 Hours 85
4 Hours 88
2 Hours 91
1 Hours 94
30 Minutes 97
15 Minutes 100
7,5 Minutes 103
3,75 Minutes 106
1,88 Minutes 109
0,94 Minutes 112
28,12 Seconds 115
14,06 Seconds 118
7,03 Seconds 121
3,52 Seconds 124
ANNEXURE – I: UNITS
Piping Nominal
inches (inches)
Diameter
Piping Thickness Schedule (Sch)
Insulation
millimeters (mm)
Thickness
Temperature Centigrade (°C)
Capacity cubic meters (m3)
Linear Dimensions meters and millimeters (m, mm)
Pressure kg/cm2
Weight kilograms (kg)
kilogram per hour or cubic meter per hour
Flow
(kg/h, m3/h)
Surface Area square meters (m2, cm2, mm2)
Density kilograms per cubic meter (kg/m3)
Energy kilowatt hours or kilojoule (kWh or kJ)
Power Watts (W, kW, MW)
Heat Watts (kW, MW)
Heat Transfer Watts per meter square per degree
Coefficient centigrade (W/m2/°C)
Velocity Meters per second (m/s)
Noise Decibels (dBA)
Time h – hour, mt – minute, s - second
ANNEXURE – II
2 Carbon Monoxide (CO) Micro g/Nm3 2.520 2.520 2.520 2.520 2.520
ANNEXURE – III
8.1 Introduction
This basis of design shall guide the Detail Engineering Company (DEC) to
evolve detailed design criteria which should be followed the detail engineering
stage.
In such cases the tender must clearly indicate the source of such
alternative standards and, if not easily available, copies of the codes
and standards proposed must be included in the tender.
8.2 Standardization
8.4.1 Layout
The DEC will be responsible for producing the Process Plant, Utilities
and off site layout with the area allocated by MNK.
8.4.1 Access
Headroom 9 Meters
Main access aisles indoors : Width 3 Meters
Headroom 3.5 Meters
Access to pump zones : 2.0 Meters
Access to heat Exchangers for
tube bundle removal
: Tube bundle length
+1.5 meters
General equipment spacing to : Min. 1.5 meters
be
Sources of ignition to : 4.5 meters
equipment
8.5.1 Scope
The term mechanical equipment for the purpose of this specification
refers to the following units:
vi. All water and effluent treatment equipment including Force Draft and
Induce Draft cooling towers, but excluding natural draft cooling towers
and works, e.g. ponds, etc.
vii. Packaged Equipment e.g. water treatment plant, etc.
viii. Filtration and separation equipment.
8.5.2.2. The following listing of codes and standards shall be used, but
is not intended to be a complete list of such codes and
standards.
Where alternatives are shown within these codes, then the higher
quality alternative shall apply.
ASME Standards
AGMA Standards
NEMA Standards
TEMA Standards
Heat Exchangers
8.5.3 General
8.5.3.2. For all rotating and reciprocating machines, the tensional and
flexural critical speeds shall be calculated and communicated to
MNK except as otherwise specially started, no critical speed
shall lay within 15% of the operating speed; nor, in the case of
variable speed machines, within the operating speed range nor
within 15% of maximum and minimum operating speeds.
8.5.3.3. Drive Units (prime mover plus power transmission) shall have a
rated output at least 10% greater than the power requirement at
design operating conditions of the driven machine.
In all cases, the DEC shall ensure that equipment is suitable not only
for maximum operation conditions, but for start-up and any abnormal
conditions which may be foreseen.
8.5.4 Turbine
8.5.12.2.1. The following standard shall be adopted for the design and
fabrication of heat exchangers.
For air coolers, the following standard shall be adopted for their
design and fabrication: API 661.
8.5.7 Documentation
The DEC shall supply in his Tender process and mechanical data relating to
each piece of equipment. This shall be given on a data sheet and shall include
a minimum, the process duty, operating and design conditions, material of
construction and equipment configuration, including a sketch, and shall also
include overall efficiency and utility consumption figures as appropriate.
The general standard for centrifugal pump shall conform to ASME B 73.1
8.5.9.1. Vessels
8.5.9.2. Towers
8.5.9.3. Tanks
8.5.12.1. Standards
8.5.12.2.7. The DEC must ensure that all unit parts of any
conveying system are in accordance with all other
applicable standards and codes of practice as
given in this volume.
8.5.15 Materials
8.5.16 Noise
8.5.17 Effluent
The effluent disposal, which emitted from the equipment, shall comply
with the effluent and environmental requirements as specified in
section 2.3.7.
8.5.19 Tests
8.5.20 Inspections
Wherever possible, sub-units with a main unit e.g. conveyor belts for a
conveying system, shall be supplied to a Code or Standard detailed in
Bidders Tender.
9. General System
9.1 Electrical
9.1.1 Reference
9.1.3.1. Safety
9.1.3.2. Reliability
9.1.3.4. Maintenance
9.1.3.5. Interchangeability
9.1.4 Design
• Classification of Area
Plant areas, in which the formation of gases, vapor, mist or dust may
occur in such quantities, that explosive mixtures with air are likely, shall
be classified as hazardous areas in accordance with the respective
regulations.
• Basic of Design
• Distribution System
The main electrical power supply for MNK-2 Project will be fed from 20
kV public grid / PT. PLN (Electrical State Own Company). PLN will
provide 20kV switchgear inside PLN substation for tie-in purpose.
20kV voltage will be derived to 6 kV through 20kV/6.3kV transformers.
380V supply will fed from 6 kV switchgear through 6kV/0.4kV
transformer.
For emergency power supply to the plant will be fed from the diesel
engine generator 400V.
Utilization Voltages
The following (Table 1) is the voltage system which are utilized for
MNK-2 Project.
UTILIZATION
CONSUMER EARTHING
VOLTAGE
Main supply from PLN 20kV, 3ph, 50Hz Low-
resistance
Motors – Less than 0.37 380V 3ph or 220V Solid
KW 1ph+N, 50 Hz
Motors – 0.37 KW up to 149 380V, 3ph, 50 Hz Solid
KW
Motors –150 KW and above 6000V, 3ph, 50 Hz Low-
resistancee
Process Heaters 380V, 3ph, 50 Hz Solid
Welding Sockets 380V, 3ph, 50 Hz Solid
Convenience Sockets (field) 220V, 1ph+N, 50 Hz Solid
Indoor Receptacle 220V, 1ph+N+E, 50 Solid
Hz
Lighting (normal + 220V, 1ph+N, 50 Hz Solid
emergency)
UTILIZATION
CONSUMER EARTHING
VOLTAGE
Anti-condensation Heaters 220V, 1ph+N, 50 Hz Solid
Diesel Engine Starter & 24V DC, 2 wire Solid/Floatin
Controls (Supplier/Vendor) g
MV and LV Switchgear 110V ,1ph+N, 50 Hz Floating
Closing and control circuits
MV & LV Switchgear 110V DC, 1ph+ N, 50 Floating
Tripping Hz
MV MCC Contactor 110 V, 1ph+N, 50 Hz Floating
Controls
LV MCC Contactor Controls 220V, 1ph+N, 50 Hz Solid
Communications systems 220V, 1ph+N, 50 Hz Floating
Fire & Gas System 110 V, 1ph+N, 50 Hz Floating
DCS 110 V, 1ph+N, 50 Hz Floating
ESD 110 V, 1ph+N, 50 Hz Floating
Voltage Profiles
The maximum permissible voltage drop along the length of the cable
with reference to the nominal supply voltage shall be as follows:
Feeders 5% at full load between the MCC and the load terminals
2% between MCC and a distribution board
• Electrical Equipment
Power Transformer
20 kV Switchgear
Electric Motor
In, general electric motors will have the voltage supply as follows:
Special Motors (Fractional motor) may be 220V, 50 Hz 1 phase
Motors below 150 kW shall be 380V, 50 Hz 3 phase
Motors 150 kW and above shall be 6 kV, 50 Hz 3 phase
The VSD will be part of MCC or separate, fed from MCC. Control &
monitoring are microprocessor-based. The input panel serves for
entering control parameters and structure pattern and installed in the
front panel of the cabinet.
Stationary Batteries
Distribution board
Bus Duct
• Lighting
General
Lighting Fixtures
Street Lighting
Wiring for lighting system, socket outlet street lighting and flood lighting
system shall be armored type if fastened to adjacent supported
structures or installed underground, or non armored cables supported
by cable tray/conduit. Wire in conduit shall be used for building lighting
system.
Grounding System
9.2 Instrumentation
9.2.1.2. The overall concept of the instrument system that the choice
will be microprocessor based distributed process control installed in the
Process Plant, Service Unit and control room.
9.2.1.4. The basic requirements of the design shall conform to the latest
edition of the following:
• Instrument Society of America (ISA)
9.2.1.6. The Contractor shall submit the following documents with the
final design including but not limited to:
• P and I diagram
• Operating and maintenance manuals for each type of
instrument
9.2.2 Suppliers
The chosen supplier must be able to show that the can provide a
suitable range of electronic digital instrument, but more than one
supplier can be used of it is known that each suppliers has a premier
position in a particular area of measurement, e.g. flow measurement.
Reliability of operation availability of spare parts and not first cost must
decide the supplier(s) chosen.
9.2.3 Training
9.2.4.1. All standards and Code used in the design of instruments and
referred to in this specification shall be the latest issue including any
revisions and additions at the date of Tender.
The system shall make maximum application of data highway and local
area network (LAN) communication concepts to link all plant information
handling and operations data gathering and processing into one highly
accessible, coordinated system.
9.2.4.4. In all cases the instrument supplier and the main Contractor are
to select the best instrument for the particular task to be performed.
MNK reserve the right to reject a particular type of instrument or an
instrument vendor without having to give reasons for their action.
9.2.5.3. The system provided shall contain the capability for process
simulation and calculation without disturbing the normal plant operation.
This feature will be used for operator training and engineering purpose
such as process optimization, etc.
9.2.5.6. Algorithms
Operator Console
Using the Operator Station, the operator will monitor and control the
process, and handle process and alarm system. The operator will use
the Operator Station to display and print process history, trends, and
averages; to print reports, logs, and journals; to archive historical data
on floppy diskettes; and to monitor and change the status of equipment
system.
The process engineer will use the Operator Station to provide the
means to set-up the process database, custom display, and reports,
and to load software system from floppy diskettes.
Operator Station shall have 3 (three) operator consoles for Nitric Acid
Unit, Ammonium Nitrate Unit and Service Unit, which shall include the
following items:
In principle, all LCD should have access to all plant parameters, and
their function should be the same. This allows the operator to bring up
on different screen the same display, or to interchange function among
LCDs.
All displays should be of pre-format type and linked to actual process
parameters with fill in the blanks programming procedure.
Display operation update shall not be greater than two second.
Each Operator Console shall be capable of accessing all data on the
communication bus. Each console shall operate independently of the
other.
Failure of any Operator Console shall not interfere with the operation of
any other device on the communication bus.
Printer
The color ink jet printer shall print hard copy ay text and graphic, in
display images in support of high quality, high speed workstation
display imaging.
Paper width shall be minimum of 420 mm.
Trend Recorder
History Module
A history module shall also provide storage for up to 300 custom LCD
displays, in additional to all operation displays. It will also store the
databases of other modules and boxes to be used for reloading after
power failures.
Application Module
9.2.5.11. Controllers
9.2.5.12. Gateways
The Contractor system shall have the ability to alter or configure loops
without affecting other loops on automatic control. Likewise, the
modifications or creations, or graphic displays show not effect loops on
automatic.
The software system shall be based on UNIX standard operating
system which capable of using the third party software.
Mathematics Library
• NO
• NO2
• N2O
• Hydrogen
• Equilibrium data
• Solubility
• Thermal expansion
• Joule Thomson effect
• Critical constants
• Compressibility’s
• Latent Heats
• Specific Heats
• Reaction Constants
Spreadsheet
Data Validator
1. Hardwired Annunciators
• Important alarm, such as shutdown, shall be
generated by the hardwired annunciator units, and
not by the DCS.
• Annunciator indicators shall be grouped on the
auxiliary console, close to their associated
operator station.
4. Analog Instrument
5. Others
9.2.5.23. Wiring
9.2.5.6. Analyzers
Rotameters
Level Transmitters
Control valve shall be furnished with plugs seating from the top in
order to facilitate removal in the field. Actuator shall be either “direct”
or “reverse” acting to satisfy “fail safe” requirements.
Pressure Switches
Flow Integrator
manually reset latching device, which shall hold the valve in the
normal reenergized position unless it is electrically tripped.
Manual resetting of the solenoid valve will not be possible unless
it is restored to its “normal” (reenergized) position.
Pressure Gauge
Temperature Transmitter
Thermo well material shall be 316 Stainless Steel for C.S, and SS
lines services, unless otherwise specified.
EMF to Converter
The Bidder must allow for all piping, valves and fittings to accord with
the American standards are given below but not limited to:
- ANSI B.1.1 Unfired inch screw threads (UN and UNR thread form)
API 594
Check valves
- API 598 Valve inspection and testing
9.3.2 Specifications
9.3.3 Documentation
9.3.2.5. All line designation list indicating each line with its route,
design and normal operating pressure and temperatures.The
fluid, line size, schedule and specification insulation if any.
9.3.4.1. These design criteria shall apply when situations are not
covered by the latest issue of codes and standards quoted in
section 3.7.3.1. above.
9.4.1 General
The color of the final coat, where large surfaces are concerned,
should take account of the possibility of minimizing the Sol-air
temperature.
9.4.2 Concrete
The site for the Project was prepared along with the Existing Plant.
Based on the soil investigation conducted by MNK necessary cut and
fill and compactness will be done by Contractor in accordance with
ASTM D-1557-70.
Contractor shall provide within its Lump Sum Fixed Price for site
preparation including, but not limited to the following items:
Designs
Foundations
Structural Steel
Connection bolts for main framing members shall be high strength bolt
conforming to ASTM A 325 or equivalent. Connection bolts for
secondary member (joist, purling, girt, etc.) shall be ordinary structural
bolt conforming to ASTMA A 307 or equivalent.
Concrete
Detailed Requirements
Steel Structures
Detail design calculation where standard design is not used for each
platform/attachment which shall clearly show design assumption
Specific Requirements
a. Flooring for process structures shall be galvanized open grate
type steel.
b. Bar thickness and depth shall be suitable for its intended services
and loads with acceptable deflections.
c. Stair treads shall be standard type open grating with non-slip
nosing and galvanized.
d. All steel work shall be adequately protected by suitable paint
system to resist corrosion from urea dusting in humid
environment and corrosive atmosphere.
Siding for all buildings shall be extended to a practical level above the
operating floor(s) to provide good protections to the operating floor and
operators against heavy driving rains.
Siding all extend from 2.0 m above floor level to the eaves.
The lower 0.5 m above plant level shall be made of bricks.
Width of plant roads shall be 10 meters for primary and 7.5 meters for
the secondary roads minimum.
The process sewer lines shall be PVC, Coal tar epoxy and C.I pipe
depending on the type of service.
Toilets should be provided with two kinds of eastern and western type.
Seismic Loads
Design for wind loads shall be in accordance with UBC and ANSI 58.1.
Basic design wind velocity shall be 120 Km/Hour.
Inspection Requirements
9.7 Safety
9.7.1 General
The Contractor must show that every part of the design of the Project
with regard to safety of operation for both personnel and equipment is
in accordance with the requirements laid down by the Occupational
Safety and Health Administration (OSHA) of the United State of
America or the Health and Safety Organization of the United Kingdom
of such other codes of practice of internationally recognized bodies
concerned with safety in the chemical industry.
MNK requires that “Hazard and Operability Studies” on all parts of the
Project as may be required by Project or by any Local or National
Authorities having the right to require such studies.
The noise level is so controlled that the noise level at the boundary of
the Project will not exceed 55 dB (A) for more than 10% of any hourly
time period.
9.6.4 Documentation
The Bidder shall include on his Tender, a site layout plot plan giving
the estimated noise level continuous at intervals of 10 dB (A) between
85 dB (A) and 55 dB (A) for the whole of the site of the Project.
9.7.1 Telephone
The Contractor shall prepare and supply paging system including but
not limited to amplifier, microphone, cable, load speaker, alarm and
other equipment.