PREAMBLE:
The Sri Ramaraju Vidyasagar Rao Dindi Lift
Irrigation Project (SRVR DLI Project)
envisages to provide irrigation and
drinking water to the most severely
affected areas by fluoride and the drought
prone areas of Devarakonda and
Munugodu constituencies of Nalgonda
District.
COMPONENTS
The project consists of Main Canal from km 0.000 to km 66.300 starting from
Ulpara Barrage and ends at Shivannagudem Reservoir.
Four offline reservoirs viz. Dindi Reservoir (Existing & Addl ayacut)
Singarajpally, Gottimukkala, Chinthapally and
Five online reservoirs viz. Ulpara Barrage, Yarrapally-Gokaram, Irwin,
Kistarampally and Shivannagudem Reservoirs.
The main canal starts at km 0.000 from Ulpara Barrage and outflows
into Shivannagudem Reservoir at km 66.300.
Land Acquisition
Total Land Land Balance Land to
S.No. Name of the Project required procured be acquired
Yerrapally-Gokaram
8 1673.40 321.80 1351.60
Reservoir
Expenditure details:
The total expenditure incurred towards works, LA, R&R etc is for an
amount of Rs.1506.51 Crs.