2. Particulars Details
A. Source Main Dam Pick Up Weir
River Tillari West Kharari Nalla & Tail
B. Location flowing river race water of Tilari Hydro
Electric Project.
1 State Maharashtra Maharashtra
2 Zone Western Western
3 District Sindhudurg Sindhudurg
4 Taluka Dodamarg Dodamarg
5 Topo Sheet No. 48 I / 1,2,5 & 6 48 I / 1 & 2
6 Latitude 150 45’ 30” (N) 150 46’ 54” (N)
7 Longitude 740 05’ 30” (E) 740 05’ 21” (E)
H. Controlling levels
i. Top of Dam 118.50 m. 67.40 m.
ii. H.F.L. 117.52 m. 65.60 m.
iii. F.R.L. 113.20 m. 65.00m
iv. M.D.D.L. 64.00 m. 64.10m
v. C.B.L. 58.00 m. 61.00m
vi. River Bed level 46.00 m. 54.88m
I. Length Total
i Masonry ------ 278.50 m. 175 m. .
ii Earthen 1035 m. ------- 99 m.
J. Free Board 2.80 m. 2.80 m. 2.40 m.
K. Spillway
i. Type Gated having 4
Gated ogee having 7
Nos. radial
----- Nos. radial gates of
gates of size 12
size 12m. x 5m. each.
x 6.5 m. each
ii. Design flood at F.R.L. ----- 7270 cumecs 1307 cumecs.
and @ M.W.L. ----- 3233 cumecs
for 4 gates.
iii. Depth over crest. ----- 6.50 m. 5.00 m.
iv. Length ----- 57 m. 99 m.
7. Canals :
Total length
Length Discharge
in Km. as per
Name of Canal after cumecs
Project
Survey (Cusecs)
Report
1. Left Band Canal
32.56
a. Maharashtra 33.00 18.799
(1150)
b. Goa 48.80 37.400
Total....
81.80 56.199
7. Crop Pattern :
A. For Maharashtra State: (6676 ha.)
Particulars Existing Proposed (%)
i. Sugarcane -- 10
ii. Coconut -- 10
iii. Pineapple -- 5
iv. Banana -- 10
Kharif Seasonal
a. Paddy : 58 50
b. Wari, Nagli, Barik : 5 --
Rabi Seasonal :
a. Paddy : -- 10
b. Chilli’s (Vegetable) -- 5
c. Pulses : 2 10
d. Hybrid Jawar : -- 5
e. Water Melon : -- 5
Hot Weather Seasonal :
a. Ground Nuts : 1 25
b. Cashew Nuts : 14 --
c. Culturable Folow: 15 --
d. Waste Land : 5 --
Grand Total..... : 100% 145%