Name of the Dam: Badanalla (NRLD No: OR10HH0139)

River Basin: Bansadhara River Sub-Basin: Bansadhara Constructed over: Badanalla River
Year of Commencement:1980 Year of Completion:1995

Salient Feature:
1. Location 2. Hydrology 3. Reservoir
Latitude 19°-19'-15" N Catchment Area 352 sq.km FRL 176 m
Longitude 83°-52'-30" E Design Flood 4328 cumecs MWL 176 m
village Kenduguda Free Board 3m DSL 163.8 m
Block/ Tahasil Padmapur Gross storage 7564 Ha.m
District Rayagada Dead storage 850 Ha.m
65 M/15,
Reference Toposheet Live storage 6714 Ha.m
65M/16
Nearest Railway station/Airport Gunupur Top Level of Dam 179 m
Distance from District Head Qrs. 80 km Water Spread Area 9.3 sq.km
Deepest bed level of river 131 m

4. Main Dam 5. Spillway 6. Ayacut Area


Concrete ogee
Homogenous
Type of Dam Type shaped with GCA 13065 Ha
earth fill
radial gate
Length of Dam 325 m Position of spillway Left CCA 9874 Ha
Maximum Height 48 m Length of Spillway 110 m Intensity of Khariff Irrigation 88.13%
Deepest Foundation Level of Dam 129 m Crest Level of Spillway 168 m Intensity of Rabi Irrigation 46.84%
8 Nos. of 12 M X 135%
Top Width of Dam 6m Type, No and Size of gates Annual Intensity of Irrigation
8 M size
Seismic Zone II Design discharge of Spillway 4328 cumecs

7. Distribution System 8. Purpose of the Project


Right Main Canal Left Main Canal Irrigation Yes
Head discharge 13.80 cumecs Head discharge N/A Hydro Power N/A
3 Nos & size: 2
No. and size of H.R. vents No. and size of H.R. vents N/A Flood Control N/A
Mx2M
Sill level of HR 161.85 m Sill level of HR N/A Multi Purpose Yes(Fishery)
Assessment of the Health Status of the Dam by: DSRP on 06.02.2019

Dam Component Observation Remedial Measures Suggested Action Taken Remarks


The hydrology was reviewed during It is recommended to rework the same considering
1988 and the revised design flood the updated rainfall-runoff data. The spillway
has been computed using Clerk’s capacity seems to be quite adequate for such a
model and a sensitivity analysis was catchment. However, the dam, spillway and its
Hydrology done to account for lack of data and appurtenant structures may be checked for the
the same is found to be 4793 m 3/s. revised flood, if found to be more than that may be
Accordingly, the spillway has been considered for the design.
constructed considering the routed
design flood of 4328.70 m3/s.
The dam site shows presence of Provision of concrete barrier towards right bank of
partially weathered to fresh, hard spillway is to be considered for proper channelizing
Geo-Technical granite ferrous granite gneiss at the water to avoid scouring of divide wall.
aspect both the abutments. Spillway is
working properly. Apron is in good
To be
condition.
rehabilitated
The d/s slope is disturbed at most of Re-sectioning of the d/s slope may be done.
under DRIP II.
the places.
The longitudinal drains and cross It is recommended that the slope may be re-
drains are covered with debris fallen sectioned and brought to the original shape. The
from the slope due to which the rain longitudinal and toe drain should clear off bushes
water falling on the top of the dam and be cleaned periodically and wherever the drains
Earth Dam
and d/s slope is not getting are damaged, these should be repaired.
discharged suitably which is
resulting in erosion of slope. The toe
drain is also profusely covered with
vegetation. At few places stagnant
water is seen in the toe drain which
was reported to be due to the rain
which has occurred a few days
back.
Difficulties were encountered in It is therefore very urgent to chip off the excess 2nd
lowering of stop logs in the grooves. stage concrete from the stop log gate grooves in the
Subsequently three sets of grooves balance five bays. The underwater concrete cutting
out of eight were rectified and the may be carried out wherever it is not possible to
operation of stop logs in these ensure dry area above the stop log sill. This may be
grooves was possible. However, the taken up on priority basis.
balance five sets of grooves are yet
to be rectified and the project
authorities are facing difficulties in
attending to the repairs etc. to the
upstream components of the radial
gates.
The gate components like lifting It is strongly recommended that necessary
brackets, pins, turn buckles, ropes rectification may be carried out in the gate groove to
with sockets; equalizer plates etc. lower stop log on the upstream of the radial gates
have not been overhauled. one by one and take up the necessary overhauling of
the vital components.
It is recommended that the project authorities should
Hydro-
install remote control systems for the operation of the
Mechanical works To be
radial gates by using SCADA system. It is also
rehabilitated
recommended that action may be taken for supply of
under DRIP II.
Installation of SCADA system. electricity through a dedicated 11 KV Transmission
Line for supply of power to the project site. Action
may also be taken for installation of a standby DG
set.
It has been observed that there are These items should be repaired / replaced
many problems associated with the immediately before monsoon so that all the gates are
electrical components of the rope operational.
drum hoists such as EM brakes,
cables, starters, volt meter, Ampere
meter, MCB, change over switches,
motors etc.
Profuse leakage is taking place Action should be taken to seal the leakage by
through gate no.2 of the head carrying out epoxy grouting or cement mixed with
regulator. quick setting admixture or any other suitable
Head Regulator compounds.
The structural components like HR gates need
painting. Routine lubrication of the moving parts of
the gates and the hoisting arrangements should be
carried out periodically as per norms.
Instrumentation Three piezometers may be installed one at top of
dam at the deepest section on the road on the
upstream of the d/s parapet wall and second at the
berm level and the third before the rock toe.
O&M Manual Not prepared O&M Manual on the pattern of Manuals are already
available. It may be prepared and implemented
Emergency Not prepared Dam owners are required to prepare the EAP within
Action Plan (EAP) 5 years from the date of enactment of the Dam
Safety Act, 2021.
It is observed that the road over Keeping in view the importance of the structure and
spillway is used by local people for leftwing extremism activities, it is strongly
Security vehicular movement. Gates on both recommended that the services of a specialized
Arrangement side of the spillway may be provided security agency may be utilized for security and
to restrict vehicular movement on safety of the dam and its components.
the spillway. At present there is no
dedicated security arrangement
existing on the dam and its
appurtenant structures. As reported,
the security at present is being
managed by the work-charged staff.
Basic dam facilities viz. approach roads to dam,
access roads to dam top as well as road to
downstream still basin arrangement are in good
Basic Facilities condition. Guest House facility is available. No public
convenience is available. No signage or guide map
available. Staff quarters for the dam site employees
are available.
Sources of The dam is located in very remote place, far from
Secondary major towns of Gajapati & Rayagada districts. Also,
Revenue this area is affected by left wing extremism. Tourism
Generation development may not be feasible. A hydro electric
structure was constructed, but not in operation. So,
possibility of secondary revenue generation through
hydro electric generation may be examined in
details.